AGENDA MEMORANDUM                        Item No.          6f 
ACTION ITEM                            Date of Meeting        May 8, 2018 
DATE:     April 30, 2018 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Ralph Graves, Senior Director Capital Development 
SUBJECT:  Parking Garage Elevators Modernization Project (CIP #C800789) (Short Form) 
Amount of this request:                 $595,000 
Total estimated project cost:         $23,276,000 
ACTION REQUESTED 
Request  Commission  authorization  for  the  Executive  Director  to  prepare  design  and
construction bid documents for the initial phase of the Parking Garage Elevators Modernization
project at Seattle-Tacoma International for $595,000. 
SUMMARY 
The initial phase of this project will weatherize the 8th floor Parking Garage Section B and C
elevator cores, and eliminate slip/trip hazards in Section B, C, D, and E elevator lobbies on all
eight floors. This work is being carried out in advance of the next phase of the project, replacing
the elevators in the Section B and C cores, expected to begin during the last quarter of 2019
pending Commission approval. 
Specifically, this initial phase of the project will re-roof, replace leaking doors, repair and seal
porous exposed walls, and install employee safety aparatus in the Parking Garage Section B and
C elevator cores. The initial phase of the project will also include flooring safety and aesthetic
improvements to improve the customer experience in the Section B, C, D, and E garage elevator
lobbies. Elements of the project scope will provide opportunities for small and minority- and
women-owned business enterprises (MWBEs) to participate in both design and construction. 
This project was included in the 2018-2022 capital budget and plan of finance with a budget of
$23,276,000 for all phases. The total estimated cost of the initial phase is $2,649,000, which
represents an increase of $240,000 over the original budget amount of $2,359,000.  Staff
anticipates returning to Commission for design authorization of the next phase in Q3 2018. Any
revisions to the project budget to account for both phases will be addressed at that time. 
This project is categorized as a non-aeronautical cost center, which does not impact the airline
rate base. 
There are no attachments to this memo. 

Template revised September 22, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.