8d. Third Gateway MOU

Puget Sound Gateway Program 
SR 167 and SR 509 Completion Projects 

Local Funding and Phasing 
Memorandum of Understanding 

1.   Participating Parties 
In addition to the Washington State Department of Transportation (WSDOT), the following Local
Agency Partners constitute those parties currently participating in this Memorandum of
Understanding pertaining to the local contribution requirement for the Puget Sound Gateway
Program (Gateway Program): 
Port of Seattle                 City of Des Moines             City of Pacific 
Port of Tacoma               City of Edgewood             City of Puyallup 
King County                 City of Federal Way           City of SeaTac 
Pierce County                City of Fife                   City of Sumner 
City of Algona                 City of Kent                   City of Tacoma 
City of Auburn                City of Milton 
2.   Background and Purpose of MOU 
In July 2015, the Washington State Legislature and Governor Inslee acted to fund the Gateway
Program through the Connecting Washington revenue package. The Gateway Program is
comprised of two projects: the State Route 167 Completion Project and the State Route 509
Completion Project. These projects provide essential connections to the ports of Tacoma and
Seattle and will help ensure people and goods move more reliably through the Puget Sound
region. 
WSDOT is the lead project sponsor and is responsible for the planning, design and construction
of the Gateway Program, as well as for its overall financial management. The program has been
guided from its beginning by a Joint SR 167/SR 509 Executive Committee (Executive Committee),
comprised of elected and appointed representatives of local jurisdictions served by the Gateway
Program (Algona, Auburn, Burien, Des Moines, Edgewood, Federal Way, Fife, Kent, Milton,
Pacific, Puyallup, SeaTac, Sumner, Tacoma, King County, Pierce County, Port of Seattle, and Port
of Tacoma) as well as Federal Highway Administration, Washington State Transportation
Commission, Washington State Department of Transportation, Puget Sound Regional Council,
Sound Transit, Pierce Transit, and the Freight Mobility Strategic Investment Board. 
Funding for the Puget Sound Gateway Program has been approved to come from the state gas
tax, tolls, local contributions, and potential federal and state grants. Total funding for the
Gateway Program, from the 2015 Connecting Washington transportation funding package, is
$1.875 billion, which includes local contributions of $130 million. The program has been funded

THIRD DRAFT Funding and Phasing MOU          1                                      5/2/2018

over a 16-year timeline. Based on the legislative funding plan, major construction for a first
stage would occur from 2019 through 2025, and a second stage from 2026 through 2030. Local
contributions will be needed to construct both stage one and stage two projects.
In the 2017 Legislative session new language was enacted (Engrossed Senate Bill 5096  
306(20)(b)) requiring development of a Memorandum of Understanding (MOU) between the
Local Agency Partners and WSDOT. The legislature directed that: 
The secretary of transportation must develop a memorandum of understanding with
local project stakeholders that identifies a schedule for stakeholders to provide local
matching funds for the Puget Sound Gateway project. Criteria for eligibility of local
match includes matching funds and equivalent in-kind contributions including, but not
limited to, land donations. The memorandum of understanding must be finalized by July
1, 2018. The department must submit a copy of the memorandum of understanding to
the transportation committees of the legislature and report regularly on the status. 
To this end, the Executive Committee of the Puget Sound Gateway Program convened a Funding
and Phasing Subcommittee (Subcommittee) to develop a MOU that summarizes their planned
future commitments and planned timing of those commitments to contribute to the SR 167 and
SR 509 projects.
The Subcommittee goals include: 
Support efforts to build the Gateway projects on or ahead of schedule 
Create successful local partnerships 
Obtain sufficient local funding to build the Puget Sound Gateway projects 
Time grant-funding projects to support the project delivery schedule 
The construct of local funding participation, when authorized by the legislative bodies of the
relevant agencies through a series of forthcoming interlocal agreements, is based on the
following projections: 
SR 167                 SR 509                 TOTAL 
Port contributions           $30 million             $30 million             $60 million 
Federal INFRA grant         $10 million             $10 million             $20 million 
Local agency partner        $10 million             $10 million             $20 million 
match 
Other Grants (PSRC,        $20 million             $10 million            $30 million 
FMSIB, TIB) 
Total                         $70 million              $60 million             $130 million 

3.   Local Funding Strategy 
A key element of the local funding strategy, is to identify projects within the Gateway Program
that provide clear and measurable benefits to local jurisdictions. In the Gateway Program, these
are called "Local Nexus Projects," designed to: 

THIRD DRAFT Funding and Phasing MOU          2                                      5/2/2018

Create a positive business case for Local Agency Partners by focusing on the parts of the
program that are most relevant and important to local jurisdictions 
Leverage the potential to access significant grant funding to support local funding
assumptions 
In support of the local funding strategy, Local Agency Partners shall: 
Participate, co-fund match, and submit grant applications with support from
Subcommittee staff, as identified in Section 6 of this MOU 
Combine local monetary and in-kind contributions and project funds to ensure fully-
funded applications, as identified in Section 6 of this MOU 
Support the grant effort and avoid competition with the local projects in the year of
application 

The following Local Nexus Projects have been identified within the north (SR 509) and south (SR
167) segments of the Gateway Program: 
Gateway North (SR 509)                     Gateway South (SR 167) 
188th South Ramps                            Meridian West Ramps 
SeaTac Access, with Ramps to 28th/24th          54th Avenue East Ramps 
Avenue South 
Veterans Drive Extension                       Interurban Trail 
Lake to Sound Trail                              Valley Avenue West Ramps 
Port of Tacoma Access/SR 509 Spur 
70th Avenue E Bridge Relocation 
If Local Nexus, INFRA, and any other pending grant projects become fully funded, these projects
will contribute substantially toward the Legislative requirement for local match. Funding
commitments will be achieved via an interlocal agreement from each signing party up to the
amounts presented in MOU. Local Agency Partner signatories to this MOU understand that once
the local contribution requirements set forth in ESB 5096 ($130 million) is achieved, that Local
Agency Partners will not be required to commit to additional funds beyond what is outlined in
this MOU. If additional grant funding or additional funds from other sources are obtained that
fulfill the $130 million local contribution requirement, the Secretary of Transportation and the
Executive Committee will review and determine to either reduce local agency partner match
payments, or recommend expanding scope of the Gateway Program, and amend each signing
party's interlocal agreement accordingly . 

4.   Local Participation Policy 
The Joint Executive Committee has agreed to a funding and phasing policy that structures local
agency partner match requirements to be commensurate with the benefits accrued from the
project at a local level. This policy states that: 

THIRD DRAFT Funding and Phasing MOU          3                                      5/2/2018

All local agency partners accrue some benefit from the Puget Sound Gateway Program.
Partners receiving fewer benefits, however, are not expected to contribute as much as
partners who receive more benefits. Direct benefits are those that most quantifiable, but
there are other components of value that include indirect, strategic and policy/social
benefits. Both direct and indirect benefits will be assessed as part of the consideration of
local contributions, because they are more easily quantifiable than strategic and
policy/social benefits. 
All Local Agency Partner signatories of this MOU expect to seek approval of interlocal
agreements to contribute a match to be applied to Local Nexus Projects at a level that reflects
their respective anticipated level of benefit, as identified in Section 6 of this MOU.
5.   Benefit Assessment Methodology 
The proposed financial participation by each partner is based on a general, qualitative
assessment of the net benefits expected to be received by full completion of the Gateway
Program. The assessment includes the following metrics, based on available project data and
transportation modeling outputs: 
Direct transportation linkages. The location of direct access points for new limited
access highways or other transportation infrastructure that benefits the community. 
Effects on local sales taxes. The impacts of the projects to sales tax receipts, both in
terms of one-time construction sales taxes for the project, and ongoing sales taxes from
impacts to commercial uses. 
Travel time savings. Overall travel time savings for local car and truck traffic associated
with the projects. 
Traffic diversion from local streets. The diversion of, or increase in, traffic on local
arterials due to the project, with associated positive impacts to traffic safety and local
road maintenance. 
Effects on local employment. The potential effects of improved accessibility are
reviewed, particularly in the context of access to new or potential employment uses. 
Effects on developable residential lands. The potential impacts of changes in traffic
flow and accessibility on residential land development, with a focus on areas within the
jurisdiction that are available for redevelopment. 
Effects on developable employment lands. The potential impacts of changes in traffic
flow and accessibility on the development or redevelopment of commercial and
industrial lands. 
Achievement of local policy goals. The alignment of the WSDOT Gateway Program with
local plans and policies. 
Environmental and social benefits. Environmental and social benefits specifically linked
to these projects, including upgrades to pedestrian and cycling infrastructure, and
wetlands and riparian restoration. 
The approach and findings of the benefits assessments have been provided to the Local Agency
Partners. 

THIRD DRAFT Funding and Phasing MOU          4                                      5/2/2018

6.   Local Jurisdiction Anticipated Contributions to the Program 
Based on results from the benefit assessment described in Section 5, contributions for each of
the Local Agency Partners were determined by project stage in the tables below. Following
execution of this MOU, interlocal agreements will be drafted for subsequent approval.
Anticipated contributions only become binding commitments when embedded in interlocal
agreements, and the conditions therein are approved by the proposed funding entity. Interlocal
agreements between WSDOT and the respective Local Agency Partner must be in place for a
project prior to issuance of the Request for Proposals (RFP) for any proposed construction
contract. The Interlocal agreements will become binding commitments, within the statutory
authority of the Local Agency Partner, and will define the schedule of local match payments
expected over the duration of each construction project stage. 
WSDOT will exercise due diligence to develop and construct each project on schedule within the
Gateway Program to the best of its abilities. Local Agency Partners will participate in project
development reviews and project meetings in support of the Gateway Program. 
If grant pursuits identified in the Stage 1 and Stage 2 tables below are not achieved sufficient to
meet the $130 million local contribution, additional grants will be pursued from the funding
programs listed or from other funding programs that may become available over the life of the
Gateway Program. If Local Nexus Projects go to construction without planned grants, the Local
Agency Partner match funds will still be provided by agreement with WSDOT. If it is determined
that a Local Nexus Project cannot be fully funded, WSDOT will review options with the Executive
Committee. If an official decision is determined by the Executive Committee and the Secretary
of Transportation that the Local Nexus Project is not to be included in a construction project, the
Local Agency Partner match may be withdrawn. 
Stage 1 Grant Pursuits for Local Nexus Projects 
Project         Estimated      Funding    Grant Target   Target Due    Anticipated    Local Agency   Partner Nexus 
Construction   Program      Amount       Mo/Year    Construction      Partner
Cost                                                    Expenditure       Match 
th
70  Avenue      $32,245,600    FMSIB      $5,000,000    Mar 2018     2019-2021        $800,000   Fife 
E/Interurban                                                                                $500,000   Tacoma 
Trail                                                                                              $3,000,000   Port of Tacoma 
TIB         $5,000,000    Aug 2018      2019-2021       $1,000,000   Fife 
State       $1,400,000    Mar 2018      2019-2021                    Fife 
Capital & 
Transpor
tation 
Veterans         $33,800,000     PSRC       $4,500,000    Apr 2018      2021-2025       $1,000,000   Kent 
Drive/ SR516                       TIB        $5,000,000    Aug 2020      2021-2025       $1,000,000   Kent 
Interchange 
SeaTac Access    $176,883,500     PSRC        $4,500,000    Apr 2018      2021-2025       $2,000,000   SeaTac (ROW
in lieu) 
Port of Tacoma   $323,042,000     PSRC        $4,500,000    Apr 2018      2021-2025       $1,500,000   Tacoma 
Access/509                                                                            $3,000,000   Port of Tacoma 
Spur                               FMSIB       $5,000,000    Mar 2020      2021-2025 

THIRD DRAFT Funding and Phasing MOU          5                                      5/2/2018

All Gateway                      INFRA     $20,000,000*    Nov 2017     2019-2021 
Program 
SR 167 Stage 1                     Port of                      Jan 2021      2021-2025       $9,000,000   Port of Tacoma 
Tacoma 
SR 509 Stage 1                     Port of                      Jan 2021      2021-2025      $15,000,000   Port of Seattle 
Seattle                                                                     (expected in
2023-2025) 
$500,000   Des Moines 
Total Stage 1                                    $54,900,000                                    $38,300,000      $93,000,000 
Stage 2 Future Grant Pursuits for Local Nexus Projects 
Project         Estimated     Funding    Grant Target   Target Due    Anticipated    Local Agency   Partner Nexus 
Construction   Program      Amount       Mo/Year    Construction      Partner
Cost                                                    Expenditure       Match 
Meridian                         TBD        $3,000,000      2022       2026-2030      $2,000,000   Puyallup 
Avenue 
Interchange 
Valley Avenue                      TBD        $3,000,000      2022        2026-2030       $2,000,000   Pierce County 
Interchange 
th
188  Street                     TBD         TBD         2023       2026-2030        TBD 
Interchange 
improvements 
SR 167 Stage 2                       TBD         $4,000,000      2022        2026-2030         $500,000   Edgewood
(ROW in lieu) 
Sumner 
Port of                      Jan 2026      2026-2030      $15,000,000   Port of Tacoma 
Tacoma 
SR 509 Stage 2                       TBD         $4,000,000       2024        2026-2030 
Port of                      Jan 2026      2026-2030      $15,000,000   Port of Seattle 
Seattle 
Total Stage 2                                   $14,000,000                                    $34,500,000      $48,500,000 
Total Stages 
$68,900,000                                 $72,800,000    $141,700,000 
1 & 2 
*  If no INFRA, apply for FHWA BUILD grant for Port of Tacoma Access (SR 509 Spur) 
TBD  grant funding program pursuit to be determined in future
7.   Terms and Termination 
7.1. Amendments 
This MOU shall be periodically reviewed and evaluated regarding the need for modifications or
amendments by mutual determination of WSDOT and Local Agency Partners. Amendments to the
MOU shall be required if program funding assumptions need to be adjusted that affect the ability to
construct the identified Local Nexus Projects or the ability to achieve the $130 million local
contribution. Such amendments shall only be binding if they are in writing and signed by authorized
personnel from all of the Local Agency Partners. Except as set forth in an amendment, the MOU will be
unaffected and shall continue in full force and effect in accordance with its terms. If there is conflict
between an amendment and the MOU or any earlier amendment, the terms of the most recent
amendment will prevail. 

THIRD DRAFT Funding and Phasing MOU             6                                        5/2/2018

If there is a conflict between subsequent Interlocal Agreements and the MOU or any earlier
amendments, the terms of the Interlocal Agreements will prevail. 
Changes that do not affect the ability to construct the identified Local Nexus Project or achieve the
$130 million local contribution shall be addressed through the Interlocal Agreement between WSDOT
and the relevant Local Agency Partner. 
7.2. Dispute Resolution 
Should any signatory to this MOU object at any time to any actions proposed or the manner in
which the terms of this MOU are implemented, the Executive Committee shall hear the dispute
first and if the disputant(s) is/are not satisfied with the Committee's proposed decision, the
Committee will send to the Secretary of Transportation its proposed solution and all
documentation relevant to the dispute. The Secretary of Transportation shall provide the
Executive Committee with his/her advice on how to resolve the dispute within thirty (30)
calendar days of receiving adequate documentation. Prior to reaching a final decision on the
dispute, the Executive Committee shall prepare a written response that considers any timely
advice or comments regarding the dispute from the Secretary of Transportation, signatories
and other interested parties, and provide them with a copy of this written response. WSDOT 
will then proceed according to this final decision.
7.3      Conditions for Termination of Participation 
Subject to legislative appropriation and all applicable laws, each signatory shall ensure that the
Gateway Program is carried out in accordance with the terms of the MOU and subsequent 
Interlocal Agreements. A signatory may terminate its participation in this MOU if its terms
cannot be met and by providing written notice to the Secretary of Transportation and the
Executive Committee a minimum of 180 calendar days before a project issues an RFP that relies
on that local agency partner funding. Prior to providing written notice terminating
participation, however, the signatories shall consult with WSDOT to determine whether an
amendment to the MOU might be feasible. If a signatory terminate its participation, WSDOT
will then consult with the Executive Committee to determine if project scope elements need to
be removed if contributions are not realized in accordance with this understanding.
8.   Period of Agreement.
This MOU will commence on (July 1, 2018 proposed date) and will dissolve when the $130
million of local contribution have been secured, or when the Local Nexus Projects have been
constructed and are complete. 





THIRD DRAFT Funding and Phasing MOU          7                                      5/2/2018

9.   Signatories 

_______________________________________ ________________________________ 
Stephen Metruck                                         Date 
Executive Director 
Port of Seattle 

_______________________________________ ________________________________ 
Dick Marzano                                               Date 
Commissioner 
Port of Tacoma 

_______________________________________ ________________________________ 
Dow Constantine                                           Date 
County Executive 
King County 

_______________________________________ ________________________________ 
Bruce Dammeier                                         Date 
County Executive 
Pierce County 

_______________________________________ ________________________________ 
David E. Hill                                                           Date 
Mayor 
City of Algona 

_______________________________________ ________________________________ 
Nancy Backus                                               Date 
Mayor 
City of Auburn 

_______________________________________ ________________________________ 
Matt Mahoney                                          Date 
Councilmember 
City of Des Moines 


THIRD DRAFT Funding and Phasing MOU          8                                      5/2/2018

_______________________________________ ________________________________ 
Daryl Eidinger                                                     Date 
Mayor 
City of Edgewood 

_______________________________________ ________________________________ 
Jim Ferrell                                                            Date 
Mayor 
City of Federal Way 

_______________________________________ ________________________________ 
Pat Hulcey                                                     Date 
Councilmember 
City of Fife 

__________________________________ ________________________________ 
Dana Ralph                                                 Date 
Mayor 
City of Kent 

_______________________________________ ________________________________ 
Shanna Styron-Sherrell                                                         Date 
Mayor 
City of Milton 

_______________________________________ ________________________________ 
Leanne Guier                                                Date 
Mayor 
City of Pacific 

_______________________________________ ________________________________ 
Kevin Yamamoto                                         Date 
City Manager 
City of Puyallup 

_______________________________________ ________________________________ 
Joseph Scorcio                                                  Date 
City Manager 
City of SeaTac 

THIRD DRAFT Funding and Phasing MOU          9                                      5/2/2018

_______________________________________ ________________________________ 
William L. Pugh                                                  Date 
Mayor 
City of Sumner 

______________________________________ ________________________________ 
Victoria Woodards                                           Date 
Mayor 
City of Tacoma 

_______________________________________ ________________________________ 
Roger Millar                                                     Date 
Secretary of Transportation 
Washington State Department of Transportation 













THIRD DRAFT Funding and Phasing MOU          10                                     5/2/2018

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.