9b Low Voltage presentation

Item No. 9b supp 
Meeting Date: June 12, 2018 
Main Terminal Low Voltage
System Upgrade 
C800061 

1

Main Terminal Low Voltage
System Upgrade 
What is the Main Terminal?    Concourse B    Concourse C 
What is Low Voltage? 
What is being Upgraded? 
Concourse A                          Concourse D 

MTLV System Upgrade 
2

High Voltage Distribution System 


3

Low Voltage Distribution System
Power Centers 


4

STIA Main Terminal 


The Main Terminal and Work Area 
5

Passenger Experience Video 


Passenger Experience 
6

Justification for Project 
Genuine risk to airport/airline operations 
Aged equipment, risk of failure/fire (water damage), extended
outages to repair 
Loss of power to ticket counters and kiosks, baggage claim,
communications, airline offices, elevators/escalators, HVAC. 
Existing system has limited capacity 
Negates new equipment/circuits or increased loads 
Unsafe working conditions  risk of injury or death 
Inability to meter/monitor power usage 
Risks of Delay 
7

Typical Main Terminal Electrical Room 
28" FROM PANEL TO
RAILING 
MECHANICAL
VALVES IN
WORKING SPACE 

DANGER! ASBESTOS! 

Safety issues in typical old Main Terminal electrical space. 
8

Typical Main Terminal Electrical Room 


Safety issues in typical old Main Terminal electrical space with worker. 
9

Another Electrical Room 
6" CLEARANCE                 23" CLEARANCE 




18" CLEARANCE 
Working space does not comply with National Electrical Code. 
10

Typical Power Panels in Main Terminal 
Manufacturer no longer in business. 
All breakers in use. 
Replacement circuit breakers not available. 
Unsafe condition. 




Obsolete electrical panels. 
11

Recent Power
Outage in the News 
Aging equipment was scheduled
for replacement. 
"Equipment failed before we
could get to it." 

Failure of Aging Electrical Equipment Results in Power Outage 
12

Project Work 


Electrical Rooms 
Electrical Panels 
Conduit Runs 
13

Overview Budget 
Est. Final Construction Costs: $70,546,000 
Est. Design Costs: $29,754,000 
Est. Program Total: $100,300,000 

Estimated Program Total: $100,300,000 
14

Scope Item Costs 
Scope Item           2014 Estimate         2018 Estimate 
Normal Power        $20 Million           $61 Million 
Emergency Power     $0                  $5 Million 
Central Power        $0                    $14 Million 
Center 
Branch Metering      $0                    $7 Million 
Regulated Materials    $0                     $13 Million 
Abatement 
Scope item cost by line item. 
15

Overview Schedule 
Commission Authorization for Design: Q3 2018 
Design Team and GCCM Begin: Q1 2019 
Design Complete: Q4 2021 
Commission Authorization for Construction: Q3 2021 
Construction Start: Q4 2021 
Construction Complete: Q1 2025 

Construction Complete 2024 
16

Questions? 

17

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.