6a Memo

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA                   Item No.         6a 
Date of Meeting      August 3, 2010 
DATE:      July 12, 2010 
TO:       Tay Yoshitani, Chief Executive Officer 
FROM:     Michael Burke, Director, Cargo and Container Operations 
Ticson Mach, Capital Project Manager 
SUBJECT:   Fender Piling Replacement at Terminal 18 
Amount of This Request:   $741,000           Source of Funds: General Fund 
Estimated Total Project Amount: $5,738,000 
ACTION REQUESTED:
Request Commission authorization for the Chief Executive Officer to prepare design,
permit applications, and bid documents for the replacement of the damaged fender piling 
at Terminal 18 (T-18) in the amount of $741,000, for a total authorization to date of
$1,014,000, and a total estimated project cost of $5,738,000. 
SYNOPSIS:
The project consists of replacement of the fender piles and supporting members at T-18.
The fender system is designed to protect the main apron structure of the dock from the
initial impact made by a berthing barge/vessel. The fender system for this portion of
T-18 was replaced in 2003/2004, but, in January 2009, it was found to have a latent
defect which exposes the apron structure to possible damage during normal berthing
activities.  On April 6, 2010, the Commission authorized replacing 30 broken piles,
approximately 15% of the fender system. Since that time, an additional 31 broken piles
have been discovered, and staff now recommends replacing the entire fender system.
The estimated cost of the project is $5,738,000. Staff will return to Commission later for
authorization to pre-purchase material, and advertise for construction.
Port staff determined that replacing the fender piles is a lease obligation, which maintains
the Port's competitiveness by keeping T-18 container berthing area active, and helps
protect the dock revenue that the Port receives.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 12, 2010 
Page 2 of 6 
PROJECT DESCRIPTION AND JUSTIFICATION: 
The project is located within bent 62 to 162 (approximate footmark 2900 to 4900) at T-18
along the waterside of the concrete apron. The timber fender system is designed to
absorb the initial impact from a berthing vessel/barge to protect the main apron structure.
Periodic repair and replacement of fender piles is typical during the life of the system.
However, the damages discovered in this case are outside of the typical wear and tear.
The scope of work consists of replacement of the fender piles and their supporting
members. The cost estimate for the project is $5,738,000. It is projected to be completed
in 2012. 
The fender system for this portion of the T-18 dock was replaced by the Port as part of
the berth deepening project in 2003/2004. This deepening to -50 feet was an obligation
of the port per the T-18 lease. 
The fender system damages were first discovered in January 2009 during the T-18
Maintenance Dredging Project. Port Engineering conducted a detailed inspection of the
damages in August 2009, and concluded that the damages may be attributed to a
combination of design, construction and operational issues as described in the following: 
1)  Excessive notching at the back of fender piles. 
2)  Restricted movement between the timber walkway and the concrete bullrail. 
3)  Fender piles out of alignment.
4)  Excessive vessel or barge berthing force.
The broken fender piles created a void in the fender system. With barges or small vessels
berthing at an angle, the front corners of the barges or vessels could reach and hit the
structural/bearing concrete piles. Split piles will also have less fendering capacity in
keeping the vessels from going underneath the dock. The apron structure is exposed to
possible damage with ongoing berthing activities. Staff therefore recommends
proceeding with the work immediately. The Port Design Errors and Omissions Team met
and reviewed the case on April 14th, 2010. The team concluded that the case has
exceeded time frame of the Statute of Limitations and Statute of Response under the State
Legislation even if cause could be shown. Therefore, the team recommended the Port not
to pursue the designers or the contractors for E&O or latent defect. Port Engineering has
contacted and met with the designers to discuss lessons learned and ways to prevent
similar damage in the future. 
Prior to the conclusion to replace all of the piling, and in an effort to minimize further
fender pile damages, the trimming of the supporting members was completed and steel
bands were installed in some of the piles. 
After the approval of the Commission on April 6, 2010, staff has proceeded with the
design and permitting for the replacement of 30 broken piles and its associated

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 12, 2010 
Page 3 of 6 
supporting structures. However, the design team has discovered an additional 31 broken
piles during the May 6, 2010, field inspection.  Staff now believes all the fender piles
will eventually fail and the Port should replace the entire fender pile system to minimize
cost and operational disruptions.
PROJECT SCOPE OF WORK AND SCHEDULE: 
The scope of work consists of replacement in-kind of 202 timber fender piles and their
supporting members. With this authorization, staff will proceed to complete design phase 
and seek modified permit authorizations for the project. An existing Docks IDIQ
contract will be utilized for these services. 
The construction will be phased in two in-water work windows in order to minimize the
impact on terminal operation, to accommodate limited in-water work window, and long
lead time for piles purchase.
Tentative Project Schedule: 
Commission Authorization for Design                          April 06, 2010 
Procure Engineering Services                                   April 23, 2010 
Permit Submitted                                             May 23, 2010 
Commission Authorization for Additional Design Funding       August 12, 2010 
100% Design Completed                                   August 23, 2010 
Commission Authorization for Construction                    September 7, 2010 
Estimated Begin Construction                                  February 01, 2011 
Estimated Construction Complete                              March 15, 2012 
STRATEGIC OBJECTIVES: 
This project supports the Port's strategies to "Ensure Airport and Seaport Vitality", by: 
Replacing the fender piles in this area is a renewal and replacement project for the
Seaport. It will help protect dock revenue the Port currently receives. 
Meeting lease obligation. 
Maintaining our ability to remain competitive by keeping all of Terminal 18 container
berthing area active.
Meet Environmental Obligations 
The project will meet environmental obligations by: 
Acquiring all necessary and required permits from appropriate agencies prior to start
of construction; 
Complying with all conditions stipulated by permit authorizations

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 12, 2010 
Page 4 of 6 
Using best management practices during construction to limit water quality impacts. 
Using vibratory impact pile driving to limit noise impacts to endangered species.
BUSINESS PLAN OBJECTIVES: 
The purpose of the project is to maintain the use of berth. 
FINANCIAL ANALYSIS: 
Budget/Authorization Summary 
Previous Authorizations (authorized by Seaport Division Director)                  $273,000 
Current request for authorization                                               $741,000 
Total Authorizations, including this request                                  $1,014,000 
Remaining budget to be authorized (estimated construction costs)                 $4,724,000 
Total Estimated Project Cost (pending final design)                            $5,738,000 
Project Cost Breakdown 
Design                                                                  $448,000 
Project Management                                                    $256,000 
Permitting                                                                     $183,000 
Construction Management (Contracts Admin)                               $61,000 
Interim Repair Work (Maintenance)                                         $66,000 
Subtotal  this request:                                                $1,014,000 
Estimated Construction Costs (remaining budget to be authorized)               $4,724,000 
Total Estimated Project Cost (pending final design)                            $5,738,000 
Source of Funds 
The approximately $66,000 cost of the interim repair work (banding of select piles to
deter further splitting) was recorded as an operating expense in 2009 ($22,000) and 2010
($44,000). 
The fender replacement project was not anticipated in the 2010 Plan of Finance, as the
full extent of the fender damage was not known when the 2010 Capital Plan was
prepared. The project cost will be offset by delays or deferrals of other projects included
in the 2010 Plan of Finance, such as C800142 Carnitech (new bldg). This project will be
funded from the general fund.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 12, 2010 
Page 5 of 6 
Financial Analysis Summary 
CIP Category             Renewal/Enhancement 
Project Type              Renewal & Replacement 
Risk adjusted Discount    7.0% 
rate 
Key risk factors             Key risk factors include potential cost overruns due to project
complexity/timeframe and permitting delays. 
Construction costs may increase if unknown obstructions are
encountered during piling installation. 
Procurement of treated timber piling is a long lead item. Delays
in delivery may adversely impact planned construction timing. 
Project cost for analysis    $5,738,000 (preliminary cost estimate based on 90% design) 
Business Unit (BU)         Container Operations 
Effect on business         Fender system replacement will preserve existing revenue from
performance             Terminal 18 container operations.
At completion, incremental depreciation expense from the fender
replacement project is estimated at $567,000/year, based on a 10
year asset life.
IRR/NPV              No incremental revenue. NPV is present value of project cost. 
NPV
($5,202)
(in $000's)
SUSTAINABILITY AND LIFE CYCLE COSTS: 
Due to premature failure of the fender piling, the Port will replace the broken piles with
in-kind material to fulfill lease obligation. Port tenant is obligated to perform future
maintenance of the fender system. This is a temporary repair to maintain terminal
operation. Value Engineering will be conducted at the end of the system design life to
determine best fender system for current and future use of the terminal.
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1: Proceed with the design, bid package and in-kind replacement of the 61
identified damaged timber fender piles and the supporting system, and include allowance
to replace an additional 31 broken piles for the cost of $2,790,000. Inspect and replace
36 piles in each of the following three years as needed to a total of all 200 piles. A
potential total project cost ranges from $1,830,000 for the replacement of 61 broken piles
to $6,995,000 for all 200 piles in the period of four years.
Alternative 2: Proceed with the design, bid package and replacement of all 202 timber
fender piles with steel piling and the damaged supporting structures for the preliminary

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 12, 2010 
Page 6 of 6 
total project cost estimate of $11,656,000. This will provide a steel fender piling system
in all of the container berth area. 
Alternative 3: Do Nothing: Continue monitoring of the timber fender system. The apron
structure is exposed to possible damage with ongoing berthing activities, creating a safety
hazard for the operation, significant cost for repair, and lengthier impact to operation. 
Alternative 4: Proceed with the design, bid package and in -kind replacement of all
202 timber fender piles and the damaged supporting structures for the total project
cost of $5,738,000. This is the recommended alternative.
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
On April 6, 2010, Commission authorized design and permitting for the repair of the
damaged fender system at Terminal 18.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.