6d Change Order to Contract-0319157 Memo

COMMISSION 
AGENDA MEMORANDUM                        Item No.          6d 
ACTION ITEM                            Date of Meeting     November 13, 2018 
DATE:     October 5, 2018 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Ralph Graves, Senior Director, Capital Development 
Janice Zahn, Assistant Engineering Director, Construction Services 
SUBJECT:  Stage 3 Mechanical Energy Conservation Project (CIP #C800658) 
Amount of this request:                    NONE 
Total estimated project cost:           $7,121,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to execute Change Order 1 to
Contract MC-0319157, at Seattle-Tacoma International Airport, to extend the contract duration
by 116 calendar days to correct an administrative error in the calculation of the contract
duration. No additional funds are being requested, nor does the requested time extension
represent a delay to the project. 
EXECUTIVE SUMMARY 
This project is the third phase of the Airport's mechanical energy conservation program 
reducing energy usage throughout SeaTac Airport.   On July 25, 2017,  the Commission
authorized  the  design  and  construction  of  the  project  through  the  Washington  State
Department of Enterprise Services (DES) Energy Services Contractor (ESCO) program. An
administrative error by DES caused the contract duration to be issued incorrectly. 
The Stage 3 project directly supports the Century Agenda Goals to meet future energy needs
through conservation and to reduce greenhouse gas emissions. It also advances the accelerated
goals in the Energy and Sustainability Policy (E&S Policy) recommendations by adding electrical
sub-metering to 35 motors that serve large mechanical system loads.
DETAILS 
Background 
After Commission approval of the project in July 2017 DES amended an existing contract with 
the ESCO on January 20, 2018, to provide design, construction and other services on the Stage 3
Mechanical Upgrades project. In that amended contract, DES stated a Time of Completion of
295 calendar days after Notice to Proceed was issued by DES to the ESCO. This was a calculation 

Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. 6d                                 Page 2 of 3 
Meeting Date: November 13, 2018 
error by DES in which working days rather than calendar days were counted. Upon recognizing
this error, the ESCO requested that DES make an adjustment of 116 days to correct this
administrative error.  On August 16, 2018, DES notified the Port and requested that an
administrative change in the contract duration be approved. This Commission action corrects
the contract duration by adding 116 days for a total duration of 411 consecutive calendar days 
from NTP which was issued by DES on March 5, 2018. The DES contract end date then becomes
April 20, 2019. 
Scope of Work 
This project will improve the efficiency of the Airport's mechanical systems, replace equipment 
that has exceeded its useful life and reduce energy usage. Energy savings will be achieved for
both electricity and natural gas, with a resulting reduction in carbon emissions. 
The project work includes: 
(1)   Optimize chilled water production and distribution network 
(2)   Remove non-performing heat exchanger in the chilled water system 
(3)   Replace direct expansion refrigeration units with chilled water units and install duct
work in the main data center to improve cooling at the server racks 
(4)   Optimize chilled water pumping 
(5)   Monitor indoor air quality in the airport Main Terminal to improve efficiency and
reduce energy consumption 
(6)   Install air curtains at public doors on baggage and ticketing levels to reduce the
amount of conditioned air leaving the building 
(7)   Replace older constant volume terminal boxes with variable volume boxes 
(8)   Insulate condensate tanks 
(9)   Add electrical submetering. 

ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Do not award the additional days. 
Cost Implications: 
Pros: 
(1)   None. 
Cons: 
(1)   The contractor would be unable to complete the work within the contract time and
would therefore be unduly subjected to liquated damages due to this administrative
error.  The Port and DES may be subject to litigation or be unable to close out the
contract with the ESCO. 


Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. 6d                                 Page 3 of 3 
Meeting Date: November 13, 2018 
Alternative 2  Award the 116 days requested. 
Cost Implications: None. 
Pros: 
(1)   ESCO will be allowed to complete the contracted work within the corrected number of
contracted days. 
Cons: 
(1)   None. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
There is no additional funding being requested in this memo.
ATTACHMENTS TO THIS REQUEST 
None 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
July 25, 2017  The Commission authorized executing the Interagency Agreement 
July 11, 2017  The Commission was briefed on Stage 3 Mechanical Energy Conservation 
June 24, 2014  The Commission authorized Stage 3 Mechanical Energy Conservation Audit 
March 11, 2014  The Commission was briefed on Stage 3 Mechanical Energy Conservation 









Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.