6d Passenger Loading Bridge September Memo

A
of Seattle'

COMMISSION
AGENDA MEMORANDUM                      Item No.         8b

ACTION ITEM                           Date of Meeting    September 10, 2019

DATE:    September 3, 2019
TO:       Stephen P. Metruck, Executive Director
FROM:   Jeffrey Brown, Director Aviation Facilities and Capital Programs C_ Fe Jeberey Bri
Wayne Grotheer, Director, Aviation Project Management Group Aud)
SUBJECT:  Passenger Loading Bridge Renewal & Replacement Phase 2 - Budget Increase
Request (CIP #C800793)

Amount of this request:              $3,000,000
Total estimated project cost:         $13,000,000

ACTION REQUESTED

Request Commission authorization for the Executive Director to (1) increase the project budget
for the Passenger Loading Bridge (PLB) renewal & replacement project in the amount of
$3,000,000; (2) use Port of Seattle crews, and small and major works on-call contracts to
perform the construction work; and (3) advertise, bid, and execute a major works construction
project. This request is $3,000,000 for a revised total estimated project cost of $13,000,000.

EXECUTIVE SUMMARY

Critical structural failures, unforeseen site conditions, and addition of new systems since the
project was scoped have increased the cost to replace the PLBs. This request will provide the
necessary funding to complete the replacement of the nine PLBs and fixed walkways. Reliable,
well-operating PLBs are critical to airline and airport operations. Port staff has created a
prioritized list of PLBs, whose age and condition indicate a need for replacement. Three of the
nine PLBs and associated fixed walkways (S6, S11, and C15) have already been replaced and the
others (B10, C9, C11, C18, D4, and D11) are at the highest risk for failure.

JUSTIFICATION

The PLBs at Sea-Tac have high utilization compared to airports with comparable annual
enplanements. In 2018, Sea-Tac processed approximately 312,000 passengers per bridge, well
above the average of the top 20 airports of approximately 209,000 passengers. Any unplanned
downtime due to PLB or fixed walkway failure impacts airlines and customer service. PLBs have
a service life of approximately 25 years before replacement is required. Many of the parts for
25+ year old PLBs are no longer available; as a result, repair time is extended while parts are
fabricated or re-manufactured or used parts are located from other PLB owners. Unplanned
downtime caused by failure of obsolete parts can extend for several weeks, seriously disrupting

COMMISSION AGENDA - Action Item No. _8b_                               Page 2 of 7
Meeting Date: September 10, 2019

airline operations. This has occurred with Gate C15, December 2017, being inoperable for
almost a month because of a failed, obsolete motor generator set. Another failure occurred at
Gate S12, May 2019, after a quarterly inspection found the structure to be critical; which
required the PLB shut down for a significant amount of time to make temporary repairs until
the PLB can be replaced.

Diversity in Contracting
The major works contract has a five percent aspirational goal for women- and minority-owned
business enterprise (WMBE). No specific diversity in contracting goals were originally set for
this project, however, the SWMBE achievements to date are 23.8 percent.

DETAILS

Aviation Project Management has worked in conjunction with AV Operations, AV Planning, AV
Facilities and Infrastructure, and AV Maintenance to create a prioritized list of PLBs whose age
and condition are cause for replacement or refurbishment. The additional funds will be used to
complete the replacement of nine bridges covered under CIP# C800793.

Several factors, as detailed below, have driven the increased cost to replace the PLBs and fixed
walkways:

e   Gate S6 failed  before  it was scheduled to be  replaced. The  expedited  replacement
incurred  additional  costs  and  impacted  the  other  PLB  schedules.  Other structural
modifications, seismic upgrade requirements, telecommunications upgrades, and 400
Hz aircraft power modifications resulted in design and construction changes. This PLB is
complete.

e   Gate S11 had a severely damaged anchor bolt for one of the foundations requiring a

new foundation. Other structural modifications, differing site conditions, utility conflicts,
and seismic upgrade requirements resulted in design and construction changes. This PLB
and fixed walkway are complete.

e   The foundation for Gate C15 needed to be redesigned and constructed differently with

a deeper foundation. This resulted from unknown utilities and differing site conditions.
This PLB is installed and in close-out.

e   The foundation for Gate C11 needs to be redesigned and constructed differently with a
deeper foundation. This resulted from unknown utilities and differing site conditions.

e   Gate D4 has an issue with the Pre-Conditioned Air hydronic piping not having isolation
valves that allow for the replacement of the PLB. The lack of isolation valves requires the
system to be drained and valves installed prior to bridge replacement.

COMMISSION AGENDA  Action Item No. _8b_                               Page 3 of 7
Meeting Date: September 10, 2019

Gate D11 has two fixed walkway foundations, and one rotunda foundation that will
need to  be  upgraded to meet seismic  code.  There  is  limited  area  to  expand  the
foundations due to interference from other buildings and utilities resulting in changes to
design and construction.

Gate B10 foundation is surrounded by industrial wastewater system lines that will need
to be relocated prior to adding a new foundation that meets current seismic code. Three
manholes  (two  48  inch  and  one  60  inch)  will  be  installed  to  meet  drainage
requirements. These modifications to design and construction were a result of differing
site conditions. Additionally, an abandoned fuel line will need to be remediated and
removed prior to any foundation work.

Gate C9 currently has all the 400Hz aircraft power system routed along the fixed walk -
way which will have to be re-routed prior to replacing the PLB. This bridge has three
foundations that will need to be upgraded to meet the seismic requirements.

Gate C18 has two fixed walkway sections with three individual foundations that will
need to be modified to meet current seismic code. Differing site conditions, utility
conflicts,  and  seismic  upgrade  requirements  resulted  in  design  and  construction
changes.

Scope of Work
(1)    Design  services  for this scope of work  will  be  provided  under existing  indefinite
delivery, indefinite quantity (ID!Q) design services contract.
(2)    Purchase  and  installation  of new  PLBs,  associated  fixed  walkway,  and  related
components at Gates B10,  C9, C11,  C18,  D4, and  D11 along with  necessary
architectural, electrical, data, and mechanical infrastructure upgrades to meet new
PLB standards and current code requirements. Three of the nine PLB's have already
been replaced - S6, S11, and C15.
(3)    Port  Construction   Services  will   perform   work  associated   with   preparing  the
foundations upgrade or replacement and provide construction management services
for PLB installations at all gates.
(4)    The new bridges will be connected to the Port's Facility Monitoring System so any
malfunction that shuts the bridge down will be promptly reported to Maintenance for
faster response.

Schedule
Replacement Schedule:
1.  4Q 2019: D4 & B10
2   1Q 2020: D11
3.  4Q 2020: C11 & C18
4  1Q 2021: C9

COMMISSION AGENDA  Action Item No. _8b_                               Page 4 of 7
Meeting Date: September 10, 2019

*This schedule is tentative and can change due to changing conditions and priorities.

Activity
Commission design authorization               2018 Quarter 1
~
Design start                                      2018 Quarter 2
Commission construction authorization         2018 Quarter 1
Construction start                               2018 Quarter 4
In-use date                                      2021 Quarter 1

Cost Breakdown                                    This Request         Total Project
Design                                                  $500,000           $2,100,000
Construction                                            $2,500,000          $10,900,000
Total                                                      $3,000,000           $13,000,000

ALTERNATIVES AND IMPLICATIONS CONSIDERED

Alternative 1  Complete only the bridges that the current funding allows (7 bridges of 9
planned)
Cost Implications: $0, No additional funds would be required.

Pros:
(1)    This  alternative  minimizes the  capital  input by only replacing  7  of the  9  planned
bridges.
Cons:
(1)   This alternative would significantly degrade the quality of passenger experience at
Sea-Tac.
(2)   This alternative would potentially lead to airlines insisting on  processing departing
passengers in severely congested hold rooms on other concourses already being used
for other flights.
(3)    This alternative does not provide reliable gate capacity for the increasing number of
flights.
(4)    This alternative does not give airlines, tenants, and passengers a reliable gate system
to provide customer service and process guest for arrivals and departures.
(5)    This alternative does not address the need to replace the aging bridges that could lead
to a significant failure causing increased cost and downtime to replace.
(6)    This alternative does not address the need to update the bridge foundations to meet
the current seismic regulations.

This is not the recommended alternative.

COMMISSION AGENDA  Action Item No. _8b_                               Page 5 of 7
Meeting Date: September 10, 2019

Alternative 2  Delay replacement of the two (2) planned bridges to a later project.

Cost Implications: $3,000,000 plus escalation costs added to a future project to re-start the
replacement effort. Replacement timeline would be pushed out approximately 1.5 years for a
new project to be created and approved.

Pros:
(1)    This alternative delays the capital requirement.
Cons:
(1)    This alternative will delay the replacement of the walk ways and bridges that have
been identified as critical.
(2)    This alternative does allow for efficient use of PCS construction crews during the dry
season for foundation work.
(3)    This alternative carries a risk of a premature failure of a bridge leading to extended
closure time and increased cost for expedited replacement.
(4)    This alternative does not provide reliable gate capacity for the increasing number of
flights.
(5)    This alternative does not give airlines, tenants, and passengers a reliable gate system
to provide customer service and process guest for arrivals and departures.
(6)    This alternative does not address the need to replace the aging bridges that could lead
to a significant failure causing increased cost and downtime to replace.
(7)    This alternative will increase the cost of future replacement projects.
This is not the recommended alternative.

Alternative 3  Increase the funding to complete the scope of work for all nine bridges.

Cost Implications: $3,000,000

Pros:
(1)    Complete the planned bridge replacements and upgrade the foundations to meet the
seismic code.
(2)    Relocate added equipment from the bridge to a permanent location and off the bridge
structure.
(3)    The replaced bridge will have a new service life.
(4)    This alternative will give the airlines, tenants, and passengers a reliable gate system to
provide customer service and process guest for arrival and departures.
(5)    This alternative will keep the bridge replacement on the existing timeline.
(6)    This alternative allows for construction flexibility with the PCS crews to complete the
more complicated foundation work.

Cons:
(1)    None
This is the recommended alternative.

COMMISSION AGENDA - Action item No. _8b_                               Page 6 of 7
Meeting Date: September 10, 2019

FINANCIAL IMPLICATIONS

The Passenger Loading Bridges Project CIP #C800793 is included in the 2019-2023 capital
budget and plan of finance with a budget of $10,000,000. A budget increase of $3,000,000 was
transferred from the Aeronautical Reserve CIP C800753 resulting in zero net change to the
Aviation capital budget. The funding sources would be the Airport Development Fund and
revenue bonds. This project was approved by the airlines through a Majority-in-interest (Mil)
vote in 2017. Due to the cost increase, the project will require additional MI! approval.

Cost Estimate/Authorization Summary              Capital        Expense           Total

COST ESTIMATE
Original estimate                               $10,000,000              SO    $10,000,000
Current change                                $3,000,000             SO     $3,000,000
Revised estimate                              $13,000,000              SO    $13,000,000

AUTHORIZATION
Previous authorizations                         $10,000,000              SO    $10,000,000
Current request for authorization                $3,000,000              SO      $3,000,000
Total authorizations, including this request      $13,000,000               SO    $13,000,000
Remaining amount to be authorized                    SO             SO             SO

Annual Budget Status and Source of Funds

Financial Analysis and Summary

Project cost for analysis                        $13,000,000
Business Unit (BU)                            Passenger Loading Bridges
Effect on business performance (NOI after    NOI after depreciation will increase
depreciation)
IRR/NPV (if relevant)                           N/A
CPE Impact                                $0.04 in 2022

Future Revenues and Expenses (Total cost of ownership)

This is a renewal and replacement program that replaces existing equipment that is old and
dated.  Replacement of the equipment will require a similar level of maintenance and an
anticipated reduced level of repairs and does not have a material impact on current Aviation
Maintenance O&M costs.

ADDITIONAL BACKGROUND

PLBs were historically predominantly owned by airlines. Over the past fifteen years or so, the
Port has increasingly taken over ownership of PLBs when they needed to be replaced to provide
a consistent level of maintenance and level of service for all PLBs. Currently, Alaska is the only

COMMISSION AGENDA - Action Item No. _8b_                               Page 7 of 7
Meeting Date: September 10, 2019

airline owning PLBs at Sea-Tac. Upon the completion of this project and the North Satellite
Expansion project, the Port will own and maintain all the PLBs at Sea-Tac.

ATTACHMENTS TO THIS REQUEST
(1)    Presentation slides

PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
February 27, 2018  The Commission approved $7,700,000 for the design, construction, and
purchase of PLBS at gates C15, C9, D11, C11, C18, S6, D4, and the fixed walkways at C9,
D11, C18, and D4.
February 28, 2017  The Commission approved $2,300,000 for the design, construction, and
purchase of PLBs at gates S11 and B10 and the fixed walkway at S11.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.