6j Memo Video Management System

COMMISSION 
AGENDA MEMORANDUM                        Item No.          6j 
ACTION ITEM                            Date of Meeting       April 14, 2020 
DATE:     March 10, 2020 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Stuart Mathews, Director, Aviation Maintenance 
Ryan Pazaruski, Senior Manager, Aviation Maintenance 
SUBJECT:  Support services for the Genetec video management system 
Amount of this request:              $1,200,000 
Total estimated project cost:          $1,200,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to execute a contract for Video 
Management System (VMS) technical support services at Seattle-Tacoma International Airport 
for a term of up to five years, with an estimated cost of $1,200,000. 
EXECUTIVE SUMMARY 
Genetec is the software and hardware system that supports Video Management at the Seattle-
Tacoma International Airport (Airport). The approval of this request will provide maintenance
support services for the VMS. The system allows  monitoring of a large array of cameras and
provides services for several stakeholders at the Airport to include Security, Operations and
Maintenance. The Genetec system provides a platform to coordinate all these cameras and video
functions. This support services contract will provide technical support during the upgrades to
the existing system. 
JUSTIFICATION 
Security cameras and video information are critical to Airport Security and Operations. The Video
Management System provides critical camera and video footage of Airport spaces assisting in
resolving security breaches, injuries, accidents, etc. Port staff is proposing to continue to use
service providers to perform technical support service for the VMS to supplement internal
resources. This will aid Port staff in providing the level of service necessary for the Airport. 
This maintenance service agreement is necessary to ensure software updates and system
upgrades are implemented in a timely and secure fashion. Technical support for these systems
in  the  form  of  software  and  hardware  maintenance,  trouble  shooting,  and  root  cause
investigation will be included in the deliverable services. These are critical to ensure the Genetec
VMS remains fully capable. 

Template revised January 10, 2019.

COMMISSION AGENDA  Action Item No. 6j                                    Page 2 of 3 
Meeting Date: April 14, 2020 
DETAILS 
It is anticipated that the contract will be structured with an initial two-year duration and
incorporate 3 one-year extension options. T he existing system includes over 1,500 cameras
and several  federal agencies  sites and is growing rapidly. Due to facilities currently in
construction, it is anticipated the system will have approximately 3,000 cameras in the near 
future. 
Federal agencies sites are utilized to share some, but not all, camera views with non-Port entities
such as Airlines and Government partners. Approval of this request will also include video system
utilized by CBP in the IAF as Aviation Maintenance staff will be maintaining the system on behalf
of the CBP. 
Currently, the Airport utilizes Genetec's Mission Control System. Genetec  authorizes
approximately seven unique service providers for this system. If approved, the preferred
alternative will allow for a competitive process amongst these multiple service providers. 
Scope of Work 
(1)   Provide software upgrades as they are released by the developer. 
(2)   Provide download services for patching, bug fixes and enhancements. 
(3)   Provide technical service remotely via telephone as necessary in support of on-site staff
24/7. 
Schedule 
Activity 
Issue Solicitation                                    2020 Quarter 2 
Award Contract                               2020 Quarter 2 
In-use date                                       2020 Quarter 3 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Execute annual one-year contracts. 
Cost Implications: $280,000 estimated average annually over 5 years. 
Pros: 
(1)   This alternative allows staff to switch between service providers. 
Cons: 
(1)   Additional work is required for staff to perform a competitive process every year. 
(2)   Annually re-competing the process can lead to cost uncertainty year over year. 
(3)   Pricing may be higher than a multi-year contract due to the lack of a long-term
commitment. 
This is not the recommended alternative. 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. 6j                                    Page 3 of 3 
Meeting Date: April 14, 2020 
Alternative 2  Procure a two-year contract with three one-year renewals. 
Cost Implications: $1,200,000 
Pros: 
(1)   Costs may be lower due to the security of a longer-term commitment. The two-year
contract with up to 3 option-years provides the Port with some flexibility if the service
being provided is unsatisfactory, yet provides for a longer term of service if the Port is
satisfied. 
Cons: 
(1)   This alternative commits the Port financially for a longer period of time. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Annual Budget Status and Source of Funds 
These service contract costs are included in Aviation Maintenance's annual operating budget.
The amount of $196,400 was included in the 2020 operating budget, suggesting there will be an
annual increase going forward. This is due primarily to the large number of cameras being added
to the system as new facilities are brought on line, and the associated licensing and maintenance
fees. The funding source will be the Airport Development Fund. 
ATTACHMENTS TO THIS REQUEST 
None 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None 







Template revised June 27, 2019 (Diversity in Contracting).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.