6c Memo Concourse C Power Center

COMMISSION 
AGENDA MEMORANDUM                        Item No.          6c 
ACTION ITEM                            Date of Meeting       April 28, 2020 
DATE:     April 16, 2020 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Eileen Francisco, Acting Director Aviation Facilities and Capital Programs 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Concourse C New Power Center Project (CIP #C800724) 
Amount of this request:               $8,525,000 
Total estimated project cost:         $10,500,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to (1) advertise and award a
major works construction contract for the Concourse C New Power Center Project at Seattle-
Tacoma International Airport, 2) use Port of Seattle crews and small works contracts for
preconstruction activities. The amount of this request is $8,525,000 for a total estimated
project cost of $10,500,000. 
EXECUTIVE SUMMARY 
This project will install a new power center and new electrical distribution panels in Concourse
C near the C10/12 gates in a new electrical room. The project will rectify three problems in
Concourse C. 
1)  The existing Power Center on Concourse C is close to maximum capacity. Additional
capacity is needed on Concourse C to support future projects. 
2)  The Fire Zones (each power center serves a separate geographic area of the concourse) 
in Concourse C will be restored by re-feeding existing equipment located in the north
end from the new Power Center. This will provide a safer environment for emergency
responders in the event of a fire within a specific geographic area, as the power center
serving that area can be shutdown. 
3)  Obsolete equipment on Concourse C will be replaced with new, serviceable equipment.
Some existing equipment is no longer maintainable (no spare parts) and is also not
expandable to allow for power for new projects. 
This project was submitted to the airlines for a majority-in-interest vote. The project was
approved. 


Template revised January 10, 2019.

COMMISSION AGENDA  Action Item No. __6c__                              Page 2 of 5 
Meeting Date: April 28, 2020 
JUSTIFICATION 
Concourse C is near maximum capacity for electrical power. This can result in reduced asset life
and power outages due to overloaded equipment, causing a disruption in operations.
Additionally, the Airport will be unable to implement any project on Concourse C that will
require the installation of new equipment with electrical requirements. 
Staff expects that the existing Concourse C power center will not be able to meet operational
requirements within the next three years. Electrical installations of this type typically take two
years to complete and that is our project schedule. This project will install a new power center
that will allow the Airport to provide reliable electrical power on the north end of Concourse C
and meet current and future electrical power needs for this area. 
Diversity in Contracting 
The project staff, in coordination with the Diversity in Contracting department, have set a 7%
woman and minority-owned business enterprise (WMBE) aspirational goal for the major works 
construction contract. 
Scope of Work 
1)  Renovate existing space for a new electrical room on the north end of Concourse C. 
2)  Install a new 3200A rated electrical power center in the new electrical room. Install two
1600A 480V distribution switchboards, and multiple 208V panelboards. Provide HVAC
and fire protection for the new electrical room. 
3)  Replace two (2) 600A tenant distribution panels in the 41D electrical room. 
4)  Refeed three (3) existing electrical panels in the 41D electrical room from the new
power center. 
5)  Install electrical required metering for new distribution feeders and panels, per Port
standards and per State of Washington energy code requirements. 
Schedule 
Activity 
Construction start                             2021 Quarter 1 
In-use date                                    2022 Quarter 4 
Cost Breakdown                                      This Request           Total Project 
Design                                                           $0             $1,975,000 
Construction                                             $8,525,000             $8,525,000 
Total                                                          $8,525,000             $10,500,000 


Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. __6c__                              Page 3 of 5 
Meeting Date: April 28, 2020 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Maintain the status quo. Do nothing 
Cost Implications: An estimated $1,355,235 in costs to date will need to be expensed if this
option is pursued. 
Pros: 
(1)   No additional capital cost. 
Cons: 
(1)   This alternative does not provide electrical power for capacity growth of Concourse C. 
(2)   If no action is taken, the existing power center will operate at maximum electrical
power capacity, increasing the risk of system overloading and power outages. 
This is not the recommended alternative. 
Alternative 2  Install a new power center on the north end of Concourse C. This will meet the
current needs of the Airport and allow for future growth on Concourse C. 
Cost Implications: $10,500,000 
Pros: 
(1)   This alternative will provide the best solution in providing additional electrical power
capacity for future growth on all of Concourse C. 
(2)   This alternative will provide the following: 
o  Capacity for future growth on all of Concourse C. 
o  A robust and reliable distribution system on Concourse C. 
o  Infrastructure to support future tenant projects and airline utilization equipment
at the north end of Concourse C. 
o  Re-establish the fire zones and eliminate a hazardous situation in the event of an
emergency. 
Cons: 
(1)   Large capital project required to build out this new electrical infrastructure facility. 
This is the recommended alternative. 

FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary               Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                 $9,850,000        $250,000     $10,100,000 
Previous changes  net                            $595,000      ($195,000)        $400,000 
Revised estimate                               $10,445,000         $55,000     $10,500,000 
AUTHORIZATION 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. __6c__                              Page 4 of 5 
Meeting Date: April 28, 2020 
Previous authorizations                          $1,975,000                0      $1,975,000 
Current request for authorization                $8,470,000         $55,000      $8,525,000 
Total authorizations, including this request      $10,445,000         $55,000     $10,500,000 
Remaining amount to be authorized                    $0             $0             $0 
Annual Budget Status and Source of Funds 
This project, CIP C800722, was included in the 2020-2024 capital budget and plan of finance
with a budget of $10,445,000. The funding sources will be the Airport Development Fund and
existing revenue bonds. 
Financial Analysis and Summary 
Project cost for analysis              $10,500,000 
Business Unit (BU)                  Terminal Building 
Effect on business performance     NOI after depreciation will increase due to inclusion of
(NOI after depreciation)             capital (and operating) costs in airline rate base 
IRR/NPV (if relevant)                N/A 
CPE Impact                        $.03 in 2023 
Future Revenues and Expenses (Total cost of ownership) 
This project will increase electrical power capacity for Concourse C, increase availability of
electrical  power  for  future  loads,  reduce  power  outages,  improve  the  electrical  system
reliability and will not appreciably increase the number of preventative maintenance activities
performed on the electrical system. 
ADDITIONAL BACKGROUND 
The existing Concourse C power center is nearly at capacity and does not have adequate
remaining reserve capacity for projected future electrical power loads on Concourse C. The
existing electrical distribution on Concourse C is not in compliance with fire zones defined by
the Port Fire Department. This could result in delays and complications in responding to a fire.
In addition, some of the distribution equipment at the end of Concourse C is outdated and
obsolete. There are no parts available to repair the equipment in the event of a failure, and as
the equipment approaches end of life, the likelihood of failure increases. 
This project will install a new power center in the North end of Concourse C. This will support
future projects on Concourse C including increased utilization and deployment of 400Hz Aircraft
ground power, Pre-Conditioned Air, Electric Ground Service Equipment (eGSE) charging
stations, future airline tenant utilization of mezzanine space, increased operational needs
including ramp level hold rooms, and new retail and dining needs to meet growing traveler
demand. 


Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. __6c__                              Page 5 of 5 
Meeting Date: April 28, 2020 
Existing distribution equipment will be re-fed from the new Power Center, thus re-establishing
the Fire Zones. The purpose of the fire zones is to have all electrified equipment within a zone
fed from a single source within that zone. Currently several distribution panels are fed from the
C1 building. This project will remove the feeds from the C1 Power Center and re-route them to
the new Power Center (which will also free up capacity on the C1 power center for the Baggage
Optimization Project and for future C1 building expansion.) This will create a new fire zone for
all power derived from the Concourse C new power center providing a means to readily isolate
all  normal  electrical  power  and  therefore  minimize  a  hazardous  condition  for  the  Fire
Department in the event of a fire in this fire zone. 
The existing electrical distribution equipment at the North end of Concourse C is also near rated
capacity and some of the equipment is obsolete. This project will add new distribution
equipment and will replace the obsolete equipment. The obsolete equipment is of concern 
because parts are no longer manufactured and if there is a failure with this equipment, we
could face an extended power outage as we scramble to find alternate sources of power for the
equipment and tenants it serves. The new distribution equipment will provide electrical
infrastructure to support new projects at the north end of Concourse C. 
The project design phase was extended due to the following. 
The project schedule was originally developed based on an established location for the new
power center on the west side of the concourse. When the project preliminary design was
nearly complete, the project was directed by Aviation Management to move the new power
center to the east side of the concourse. This required significant redesign and delayed the
completion of the project. 
The Port determined standardization of major electrical equipment including programmable
logic controllers, meters, and switchgear was required via an RFP process. Because this
project included all  the  equipment  proposed for the standardization memo,  it was
determined the project would benefit from this, therefore the design schedule was delayed
until completion of the RFP process. 

ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
September 22, 2015  The Commission authorized $1,900,000 to execute a design contract,
prepare design and construction bid documents, and authorized the use of Port crews
for preliminary work in support of this project. 


Template revised June 27, 2019 (Diversity in Contracting).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.