8c Presentation Phase 4 Restroom Upgrades
Item No. 8c supp Meeting Date: September 9, 2020 Restroom Renovation Project Commission Presentation September 8, 2020 1 PROJECT BASICS 2 Restroom Design Objectives Increased accessibility Ambulatory stalls Adult changing tables Increased maintainability Maintenance chases Janitorial closets and dumpster storage Durable materials Infrastructure to support janitorial tracking 100% touchless fixtures Consistent architectural look & feel Incorporating daylighting All-gender restroom integration New Mother's Rooms New Service Animal Relief Areas Improved wayfinding & signage 3 Restroom Renovation Project: Overview PHASE 1 Enabling project, relocate tenants to free up space for new public restrooms. Completed PHASE 2 Enabling project, relocate tenants to free up space for new public restrooms. Completed PHASE 3 First new public restroom on Concourse D. In Construction Scheduled Completion | Q3 2020 In Design Provides new & expanded restrooms on concourses B, C & D. PHASE 4 Requesting funding & Includes All-Gender implementation. authorization for re-design & construction Renovates remaining existing restrooms on concourses B, C & D. Requesting funding & PHASE 5 Includes Adult Changing Tables, Mother's Room and Service Animal Relief Area. authorization for design 4 Project Details Total= 20 Restrooms, 45% more fixtures N 5 Changes Requiring Additional Budget Recent bid experiences tells us the market has changed since first estimating the project (2016). Cost increases associated with building in spaces that are not currently restrooms (holdrooms, office spaces, ADR, etc.). Incorporated initiatives: all-gender restrooms, accessibility, mother's rooms, touchless fixtures, janitorial and maintenance improvements. Design standard improvements. COVID-19 added changes during construction. 6 ALL GENDER RESTROOMS 7 All Gender Restrooms Background May 2018 Commission adopted motion 2018-08 to develop a gender-inclusive restroom plan. SEA executive response to all-gender restroom implementation was received by the Commission in September 2019. Signage iconography and language was finalized by staff in April 2020. Signage 8 All Gender Restrooms These restrooms include full height doors on all of the stalls for safety and privacy. Design below "Greenfield" will be implemented on the D Concourse as part of phase 4, and is scheduled to open in Q1 2022. "Greenfield Design" 9 COST-CUTTING ALTERNATIVE 10 ORIGINAL DESIGN 11 PROGRESS PHOTOS 12 NORTHSTAR RESTROOMS BUDGET & AUTHORIZATION REQUEST 14 Estimated Budget Increase Current Required 2017 Estimate 2018 Budget Add New Total Budget Budget Mod Phase 1 $2,109,000 $1,500,000 ($831,000) $2,778,000 Phase 2 $4,849,000 $1,830,000 $1,550,000 $8,229,000 Phase 3 $1,938,000 $2,002,000 $1,781,000 $5,721,000 Phase 4 $10,660,000 $15,440,000 $26,100,000 Phase 5 $13,491,000 $4,997,000 $18,488,000 Expense $41,000 $41,000 Sub-Total $38,088,000 $5,332,000 $22,937,000 $61,357,000 COVID-19 Estimated Costs $643,000 $643,000 Total Budget Required $23,580,000 $62,000,000 15 Requested Revised Project Budget Project Budget Original Budget (2016 Capital + Expense) $33,088,000 Previous Budget Addition (2018) $5,332,000 Current Authorized Budget (Capital + Expense) $38,420,000 Today's Budget Request(2020) $23,580,000 Total Budget for CIP (including COVID est. costs) $62,000,000 16 Federal Funding Federal Funding Phase 3, $2M out of $5.7M total Phase 4, $6M out of $26.1M total Phase 5, $6M out of $18.5M total Contractor photo if we have one including all PPE including COVID. 3% DBE goal for construction in Phase 3 Review with CM to confirm okay to use. 2% DBE goal for construction in Phase 4 17 Schedule Complete Phase 3 Q3 2020 Complete redesign and advertise Phase 4 Q1 2021 Begin design Phase 5 Q2 2021 Complete construction Phase 4 Q3 2022 Request construction authorization Phase 5 Q2 2022 Complete construction Phase 5 Q4 2023 18 LESSONS LEARNED, RISKS AND OPPORTUNITIES 19 Lessons Learned Invest in preliminary design (10-15% design) before finalizing a project's budget. The Airport has now adopted the use of Project Definition Document (PDD) for this purpose The PDD can include more thorough site investigation where needed. Employ Change Management to address budget impacts of initiatives inclusion The Airport has now adopted a more formalized change management process. Budget issues Design to budget Calculate, communicate, seek approval before implementing 20 Risks & Opportunities Risks Constructing in a constrained environment. Delays could impact FAA funding. Continued impact of COVID-19. Opportunities Changing market conditions. Investing in needed infrastructure improvements. Increasing the number of available fixtures for passengers, improving the passenger experience. Providing the first all-gender restrooms at a U.S. airport. 21 QUESTIONS? 22
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.