8c. Presentation - Communication Enhancement Project

Item No. 8c
Meeting Date: July 27, 2021
Communication Enhancement
Tyler Salisbury  AV-PMG
C801161
July 27, 2021

Project Overview
The Airport is expanding to support the returning travelers and
prepare for the continued growth.
New systems and services are being offered to improve the
experience of the travelers, tenants, and port employees. Many of
these systems require high speed and capacity data connections.
WIFI access points, People counter sensors for check points, airline check
in and gate operations, security cameras, ADR business transactions.
This project will add new connections to the airport to support the
continued growth and improve the customer experience.

2

Background
In early 2000's, the port established the
Communication Infrastructure Backbone
System (CIBS). This created the Main
Distribution Rooms (MDR) and the outlying
communications equipment rooms (ER).
Dedicated cable trays were also installed
between the MDR's and the ER that contain
the Airport current fiber connections.

This system established a data network that
connects service providers to users
throughout the airport.

3

Project Scope
Add connections to 35 comm rooms that are:
23 Out of connections (100% full)
12 Nearly full (85% or greater)
Use existing cable tray for new fiber connection
New fiber runs between the MDRs to equipment rooms
located in:
Main Terminal
South Satellite
Administration building (AOB)
Concourse B
4

Budget and Authorizations
Budget                                                 Project Budget
Design                                                              $3,200,000
Construction                                                           $7,800,000
Total                                                                            $11,000,000

Authorizations                                                 Project Budget
Previous authorization                                                      $200,000
This request                                                               $3,000,000
Total authorized amount (Including this request)                            $3,200,000
Remaining to be authorized                                             $7,800,000


5

Schedule
Commission Authorization for Design: 3Q 2021
Design Start: 3Q 2021
Commission Authorization for Construction: 2Q 2023
Issue Notice to Proceed: 4Q 2023
Construction Complete: 3Q 2025


6

Cost and Schedule Project Estimating Certainty
We are here
Degree of Uncertainty   3
DIVISION APPROVED      4
AUTHORIZED
Managing Director
Commission authorized design    5
approved
Refine cost and schedule estimates up to
Staff level authorization for cost                         100%                                     IN PROGRESS               6
and schedule estimates                                                         Commission Authorization
COMPLETE
Construction
Commu nication
Enhanc ement




7

Risks and Operational Impacts
RISK                       DESCRITPITON                            PROBABILITY     IMPACT       MITIGATION PLAN
CIBS Tray Space              Other projects have added fiber as needed        Medium         Medium     During the design phase additional
and the spare tray space needs to be                                             time is being allocated to conduct
evaluated.                                                                      field surveys of the existing tray
space to verify fill percentages.
CIBS tray access               Most of the trays are run in the ceiling               High            Medium     The project team will identify the
space of the bag well and can be difficult to                                         location where fiber installed from,
access. Challenges: Tug operation, floor to                                          evaluate the impact to operations,
ceiling access, working hours, social                                                 and provide access plan
distancing requirements, and changing                                          recommendations that can be
pathways.                                                                 shared with the construction team
and operations.
Multiple project              Project team will need to work closely with        Medium         Medium     Critical reviewers are being
coordination                 other projects and evaluate changing                                           identified from other surrounding
environments. Baggage optimization, Main                                     projects to reduce the impact of the
Terminal projects, and Tenant projects                                            projects overlap.



8

Opportunities
Multiple Fiber Pulls
Pull fiber strands in bundled cables (24-144 fibers per cable). Evaluate
pathways to maximize innerduct pathways.
Optimizing connections by room for known future needs.



9

Questions?

10

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.