8c. Memo - P69 Wifi Refresh

COMMISSION 
AGENDA MEMORANDUM                        Item No.          8c 
ACTION ITEM                            Date of Meeting      August 10, 2021 

DATE:     July 30, 2021 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Matt Breed, Chief Information Officer, Information & Communication Technology 
Jim Dawson, Dir. Infrastructure Services, Information & Communication Technology 
SUBJECT:  Port Headquarters WIFI Replacement (CIP #C801063) 
Amount of this request:                 $820,000 
Total estimated project cost:          $2,500,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to (1) proceed with the Wireless
Network (WIFI) Replacement project; (2) prepare design and construction bid documents for the
replacement of WIFI technology and supporting equipment at the Port of Seattle Headquarters
(P69); and (3) procure required hardware, vendor services, licensing, and maintenance services
in support of WIFI and network services at P69. The amount of this request is $820,000. The total
estimated project cost is $2,500,000. 
EXECUTIVE SUMMARY 
This project will replace the current P69 wireless network to ensure continuity of WIFI service,
deploy technology that adheres to Port security protocols, and provide full coverage of work and
public spaces. The Port WIFI is used extensively throughout P69 by employees, customers, and
visitors to access internal Port systems or external internet. The network, deployed over a decade
ago, is at end-of-life, no longer receives security updates, and doesn't provide the coverage or
bandwidth needed to meet modern connectivity requirements. 
This authorization includes the design of electrical and communication infrastructure to support
new wireless access points and the procurement of equipment to minimize schedule risks from
long-lead time items that will be installed by the construction contractor as well as Port labor 
respectively. Authorization for construction will be sought in a subsequent request. 



Template revised January 10, 2019.

COMMISSION AGENDA  Action Item No. __8c__                              Page 2 of 4 
Meeting Date: August 10, 2021 
The capital project is included in the 2021-2025 capital budget and plan of finance for $2,500,000.
Recurring costs estimated at $11,600 per year will be budgeted in the ICT operating budget
beginning in 2022. 
JUSTIFICATION 
Replacing end-of-life hardware supports the Century Agenda goal of being a highly effective 
public agency by proactively maintaining technology critical for Port operations. 
(1) The current wireless infrastructure is old, at risk of failure, and most components no longer
receive security updates. 
(2) Requirements for wireless access have changed over the last decade and the current wireless
infrastructure is not able to accommodate the number and types of devices used by
employees and visitors, as well as the bandwidth required for more sophisticated
applications. 
(3) As our workforce becomes more mobile, expectations for connectivity throughout P69
increase. The upgraded WIFI  will include  better coverage in areas without adequate
connectivity. 
Diversity in Contracting 
Design work is being performed in-house. Project staff will work with the Diversity in Contracting
Department to identify WMBE opportunities. 
DETAILS 
This project will replace the current WIFI at P69 with better coverage and bandwidth to meet
requirements for modern and emerging technology, install equipment that adheres to the Port's
security protocols, and minimize the risk of failure due to age. Following is the scope of work for
this authorization. 
Scope of Work 
(1) Utilize existing IDIQ for a site survey to determine best wireless access point locations to
provide full coverage at P69. 
(2) Utilize in-house communication infrastructure Design Engineer to develop designs for
installation of WIFI equipment and electrical and communication infrastructure. 
(3) Procure WIFI equipment as needed to meet schedule expectations. 
(4) Installation of communication room equipment by Port labor. 
There are other Port sites with aging or insufficient wireless connectivity that may require 
attention during this project. They will be addressed separately with operating funds or small
capital projects. More comprehensive needs at other sites will be evaluated for future projects. 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. __8c__                              Page 3 of 4 
Meeting Date: August 10, 2021 
Schedule 
Design Start                                   2021 Quarter 4 
Commission Construction Authorization      2022 Quarter 2 
Construction start                             2022 Quarter 4 
In-use date                                    2023 Quarter 3 
Cost Breakdown                                     This Request           Total Project 
Equipment & Vendor Services                             $585,000              $585,000 
ICT and Information Security Labor                          $115,000               $395,000 
Design/Construction                                       $120,000             $1,520,000 
Total                                                           $820,000              $2,500,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Delay Replacing the WIFI Infrastructure at P69 
Cost Implications: $0 
Pros: 
(1)  Capital funds are available for other projects. 
Cons: 
(1)   The existing WIFI is at risk of failure. This alternative will delay upgrades that may be
more costly to the business if service is disrupted. 
(2)  The existing WIFI is unable to have the latest security remediations installed resulting in
a security risk that is currently manually managed by Information Security personnel. 
(3)  The current WIFI infrastructure does not fully support an increasingly mobile workforce. 
This is not the recommended alternative. 
Alternative 2  Replace the WIFI Infrastructure at Port Headquarters 
Cost Implications: $2,500,000 
Pros: 
(1) The wireless technology will adhere to the latest security protocols and the burden on
Information Security to manually monitor the WIFI will be reduced. 
(2) WIFI will be available throughout the facility for employees and public and will not fail
due to aged hardware.
(3) Mobile business applications and devices will not experience degraded, interrupted, or
slow functionality. 
(4) New cabling infrastructure will support modern WIFI equipment and future initiatives
precluded by current cable. 
Cons: 
(1) Capital funds are not available for other projects. 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. __8c__                              Page 4 of 4 
Meeting Date: August 10, 2021 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary              Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                 $2,500,000               $0      $2,500,000 
AUTHORIZATION 
Previous authorizations                             $40,000                0         $40,000 
Current request for authorization                  $820,000                0        $820,000 
Total authorizations, including this request         $860,000                0        $860,000 
Remaining amount to be authorized            $1,640,000               0     $2,500,000 
Annual Budget Status and Source of Funds 
This project was included in the 2021 plan of finance under committed CIP #C801063 in the
amount of $2,500,000. The project will be funded 81.3% with the Airport Development Fund and
18.7% General Fund. 
Financial Analysis and Summary 
Project cost for analysis              $2,065,000 (Airport's cost) 
Business Unit (BU)                  AV division wide with 62.3% included in airlines rate 
Effect on business performance     NOI after depreciation will increase due to inclusion of
(NOI after depreciation)             capital (and operating) costs in airline rate base. 
IRR/NPV (if relevant)                NA 
CPE Impact                       Less than $.01 in 2024 
Future Revenues and Expenses 
Annual recurring license and maintenance fees, estimated at $11,600 per year, will be budgeted
in the ICT annual operating budget beginning in 2022. 
ATTACHMENTS TO THIS REQUEST 
None 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None 



Template revised June 27, 2019 (Diversity in Contracting).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.