8d. Memo - Airfield Utilities Infrastructure Improvements

COMMISSION 
AGENDA MEMORANDUM                        Item No.          8d 
ACTION ITEM                            Date of Meeting      August 10, 2021 

DATE:     July 7, 2021 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Eileen Francisco, Acting Director, Aviation Facilities and Capital Programs 
Wayne Grotheer, Director, Aviation Project Management 
SUBJECT:  Airfield Utility Improvements (AUI) Design (CIP #C801177) 
Amount of this request:               $6,300,000 
Total estimated project cost:         $46,200,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to (1) complete design and
prepare construction documents for  the Airfield Utilities Infrastructure (AUI) project (CIP
C801177) at Seattle-Tacoma International Airport  (SEA)  and (2) enter into  reimbursable
agreements with the Federal Aviation Administration. This  design authorization is  for an
amount of $6,300,000 out of a total estimated project cost of $46,200,000. 
EXECUTIVE SUMMARY 
The Facilities and Infrastructure (F&I) group at SEA  have identified a variety of capital
improvements required to replace and amend aging, failing, and over-capacity utility systems
serving the existing terminal and apron areas. These utilities are located on the airside of the
terminal and include sanitary sewer, domestic water, power, communications, and the
industrial wastewater system (IWS). This AUI project will minimize operational impacts, achieve
soft cost efficiencies, and enhance airfield construction safety management by sequencing the
work to align with two existing programs: The Airfield Pavement and Supporting Infrastructure
Replacement Program and the South Satellite Renovation Program. Construction of the utility
improvements will begin in 2023 and conclude in 2025. 
JUSTIFICATION 
The Airfield Sanitary Sewer trunk-line serving the terminal and the South Satellite (SSAT) is in
poor condition. F&I has identified deteriorating joints, sagging pipe and structural damage as
part of their Closed-Circuit Television (CCTV) pipe condition assessment program. Now over 60 
years old, this sewer trunkline is also exceeding current conveyance capacity and cannot take

Template revised January 10, 2019.

COMMISSION AGENDA  Action Item No. _8d_                                Page 2 of 6 
Meeting Date: August 10, 2021 
additional sewer loads from the main terminal. The new sewer trunk-line will also support the
C1 Building expansion and South Satellite renovation. 
The existing cast iron water main that runs underneath Concourse B was built in the 1960's and
has exceeded its 50-year life span resulting in a high risk of failure. This water main is serving
both domestic and fire for Concourse B and the SSAT. Concurrent to replacement of the
sanitary sewer trunk line described above, the AUI project will install a new ductile iron water 
main outside of the footprint of Concourse B allowing for access for maintenance or repairs. 
A recent CCTV condition assessment of the IWS pipe revealed that portions of the system in the
vicinity of the sewer and waterline work are also in poor condition and need to be relined or
replaced to prevent failures and impacts to operations, as well as prevent infiltration of
contaminated runoff. 
There is a need for a power and communication ductbank that will run from the SSAT power
station to the NSAT power station to create redundancy to the airport's terminals. These
ductbanks are part of the Utility Master Plan. Where the AUI project is removing pavement and
impacting operations to install the sewer and waterlines, it will use the opportunity to install
significant portions of this ductbank system. 
This  project  contributes  to  the  Port's  Century  Agenda  goal  to  meet  the  region's  air
transportation needs at Sea-Tac Airport for the next 25 years. It supports current and future 
Airport capacity by improving the efficiency of utility systems and extends their useful life. 
Diversity in Contracting 
Project staff is working with the Diversity in Contracting Department to include inclusion plans 
and the establishment of women and minority business enterprise (WMBE) aspirational goals 
for this project. 
DETAILS 
The project involves installing new ductile iron sewer pipe to replace under capacity, failing and
aging sewer pipe; installing new ductile iron water pipe to replace aging cast iron water pipe
that is currently located within the footprint of Concourse B; renewing aging and damaged IWS
pipe through a combination of trenchless pipe relining and replacement with new pipe where
pipe damage prohibits use of lining techniques; finally, installing new concrete-encased power
and communication ductbanks running roughly parallel with the SS trunkline from the SSAT to
roughly 100 feet past the north end of Concourse C. The excavation and replacement of existing
pavements that are associated with the utility scope described in this section are part of the
project scope.


Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. _8d_                                Page 3 of 6 
Meeting Date: August 10, 2021 
Scope of Work 
The AUI Project elements described above will be aligned with the Airfield Pavement and
Supporting Infrastructure Program to capitalize on concurrent operational impacts and similar
airfield work. 
(1)   Replacement of the sanitary sewer trunk line serving the main terminal 
(2)   Rerouting of the Concourse B water main around Concourse B 
(3)   IWS repairs and replacements 
(4)   Power ductbank from SSAT to north of Concourse C 
(5)   Communications ductbank from SSAT to north of Concourse C 
Schedule 
This work will be phased  over three years  with the 2021-2025 Airfield Pavement and
Infrastructure Replacement program for years 2023-2025 to minimize operational impacts,
lower soft costs, and promote airfield safety risk mitigation. 
Activity 
Design start                                           2021 Quarter 3 
Commission construction authorization Phase 1     2022 Quarter 4 
Construction start                                    2023 Quarter 1 
Commission construction authorization Phase 2     2023 Quarter 4 
Construction start                                    2024 Quarter 1 
Commission construction authorization Phase 3     2024 Quarter 4 
Construction start                                    2025 Quarter 1 
In-use date                                           2025 Quarter 4 
Cost Breakdown                                      This Request          Total Project 
Design                                                   $6,300,000            $6,300,000 
Construction                                                      $0           $39,900,000 
Total                                                          $6,300,000            $46,200,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
When this project was originally scoped the Utility Master Plan was underway and since then
has discovered additional utility deficiencies, this project is seeking to focus on those which
align with the sewer trunk line installations. 
Alternative 1  Only replace the sanitary sewer trunk line. 
Cost Implications: $23,200,000 
Pros: 
(1)   Avoids the risk of a failed sewer system to Main Terminal and SSAT operations. 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. _8d_                                Page 4 of 6 
Meeting Date: August 10, 2021 
(2)   Sewer capacity will meet current and future needs of the Main Terminal, C1 Building, 
and SSAT. 
(3)   Minimizes level of investment by focusing on highest risk infrastructure. 
Cons: 
(1)   Does not address other utility repair and replacement needs. 
(2)   Will cause future operational impacts to repair, replace, or install other utilities in the
same areas. 
(3)   If emergency repairs are needed for other failed utilities the costs will be much higher. 
(4)   Does not support the Utility Master Plan for water, IWS, power and communication
needs. 
This is not the recommended alternative. 
Alternative 2    Replace the sanitary sewer  lines, the water line at Concourse B, and
repair/replace adjacent IWS infrastructure. 
Cost Implications: $32,800,000 
Pros: 
(1)   Avoids the risk of both a failed sewer and water system to Main Terminal and SSAT 
operations. 
(2)   Sewer and water service will meet current and future needs of the Main Terminal, C1
Building, and SSAT. 
(3)   Adding  IWS  and  waterline  work  reduces  amount  of  pavement  replacement  and
operational impacts for future work on these utilities. 
Cons: 
(1)   Does not complete the work to install the power and communications ductbanks 
while pavement and operational impacts are occurring. 
(2)   Will  not  support  the  Utility  Master  Plan;  postpones  redundancy  for  power  and
communications from the main terminal to the South and North Satellites. 
This is not the recommended alternative. 
Alternative 3    Replace the sanitary sewer trunk line, the water main  at Concourse B,
repair/replace  adjacent  IWS  infrastructure. Install  parallel    power  and  communication
ductbanks. 
Cost Implications: $46,200,000 
Pros: 
(1)    Avoids the risk of both a failed sewer and water system to Main Terminal operations. 
(2)   Sewer and water service will meet current and future needs of the terminal. 
(3)   Adding  IWS,  waterline,  power  and  communications  work  reduces  amount  of
pavement replacement and operational impacts for future work on these utilities. 
(4)    The power and communications ductbank will provide parallel pathway for redundant 
feeds from the Main Terminal to the South and North Satellites. 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. _8d_                                Page 5 of 6 
Meeting Date: August 10, 2021 
Cons: 
(1)   Requires additional cost for utility and pavement restoration up front. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary              Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                $34,592,000               $0     $34,592,000 
Current change                                 11,608,000               0      11,608,000 
Revised estimate                                46,200,000                0      46,200,000 
AUTHORIZATION 
Previous authorizations                             295,200                0         295,200 
Current request for authorization                  6,300,000                0       6,300,000 
Total authorizations, including this request         6,595,200                0       6,595,200 
Remaining amount to be authorized           $39,604,800             $0    $39,604,800 
Annual Budget Status and Source of Funds 
This project, Airfield Utility Improvements (AUI) Design (CIP #C801177), was included in the
2021-2025 capital budget and plan of finance with a budget of $34,592,000. A budget increase
of $11,608,000 will be transferred from the Aeronautical Reserve C800753 resulting in zero net
change to the Aviation capital budget. The funding sources would be Airport Development Fund
(ADF) and revenue bonds. 
Financial Analysis and Summary 
Project cost for analysis                         $46,200,000 
Business Unit (BU)                            Terminal Building 97% and IWS 3% 
Effect on business performance (NOI after    NOI after depreciation will increase due to
depreciation)                                 inclusion of capital (and operating) costs in
airline rate base 
IRR/NPV (if relevant)                           N/A 
CPE Impact                                 $.13 in 2026 
Future Revenues and Expenses (Total cost of ownership) 
This  project  will  not  have  an  impact  on  annual  Aviation  Maintenance  operating  and 
maintenance (O&M) costs for mechanical or electrical systems and may lead to a reduction in
the amount of time currently spent by the field crew on pipe inspections due to the current
condition of the water and sewer systems. After implementing the project, the improved 
portions of the water and sewer systems will have a renewed 50-year asset life and a greatly
reduced risk of failures, emergency repair and maintenance work, and impacts to operations. 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. _8d_                                Page 6 of 6 
Meeting Date: August 10, 2021 

ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None 
















Template revised June 27, 2019 (Diversity in Contracting).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.