8e. Presentation - 2022 Airfield Pavement and Supporting Infrastructure Rep

Item No. 8e_supp             _
Meeting Date: November 16, 2021
2021-2025 Airfield Pavement and Supporting
Infrastructure Replacement Program
(CIP #C800930)
Seattle-Tacoma
International Airport

2021-2025 Program Justification
The 2021-2025 Airfield Pavement and Supporting Infrastructure Replacement
Program replaces distressed airfield pavement, joint sealant, related and
supporting infrastructure at the Airport to provide safe and efficient conditions
for aircraft operations and meet FAA requirements.




2

2021  2025 Program Map



3

2021 Airfield Construction



4

2022 Project Locations



5

2022 Project Scope
Work Area N - Portland Cement Concrete Pavement (PCCP) and supporting
infrastructure replacement on portions of the ramp and taxilane serving the
southeast side of the North Satellite.
Work Area C  IWS channel drain upgrade and Cargo 2 Taxilane PCCP replacement.
Work Area B  Replacement of a portion of Taxiway B PCCP; near the intersection of
Taxiway S and Taxiway B.
Work Area H  Installing over height vehicle clearance bar protection system on
Perimeter Road leading to RW 16R-34L Approach Lighting System bridge.
Work Area J - Replacement of PCCP joint sealant materials and pavement markings
on portions of Taxiways M, N, P and Q.


6

2022 Project Schedule
Commission construction authorization            2021 Quarter 4
Construction start                                   2022 Quarter 2
In-use date                                         2022 Quarter 4




7

2021-2025 Program Budget
Cost Breakdown                        This Request      Total Project
Design                                          $0      $16,000,000
Construction                               24,000,000     $137,500,000
Total                                           24,000,000      $153,500,000



8

Communication & Outreach
Developed a Communication Plan for the 2022 Airfield
construction season to ensure Air Traffic Tower/Ramp Tower
planning, Tenant and Air Carrier awareness.
Included:
AAAC Meetings and MII Process
Safety Risk Management Panel
Separate meetings with impacted air carriers


9

2022 Project Risks
RISKS                 DESCRIPTION            PROBABILITY   IMPACT   MITIGATION
FAA funding application        For projects with FAA              Low                High          Close coordination with the FAA Region and ADO.
discretionary funds applied to                                          Postpone construction work until receiving FAA
majority of work, the grants                                            discretionary funds
need to be received prior to
issuing NTP. Any delay by FAA
could delay the overall project
Labor Action                  There is a potential that labor      Med               Med          Contingency dollars could be used to implement
and supplier agreement                                            targeted acceleration, as necessary
negotiations might impact
construction if there is a strike
Weather delays               Potential delay to the overall      Low               Med          Contingency dollars will be used for targeted
construction project due to                                            acceleration when weather is favorable
inclement weather




10

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.