11c. Presentation
C Concourse Expansion Project Briefing
Item No. 11c_supp Date of Meeting April 12, 2022 C Concourse Expansion Project Briefing April 12, 2022 Agenda Briefing Purpose Project Purpose Project Location Expansion Renderings Sustainability Initiatives Budget and Schedule 2 Briefing Purpose Update Commission on design, sustainability, and budget status. 3 Project Purpose Increase airport revenue through Increase Airport Dining and Retail offerings Increase leasable office space Increase airline lounge capacity Improve Customer Service by: Increase C3 holdroom size Add passenger amenities (restrooms, meditation room, nursing rooms) Increase economic opportunities 4 Project Location Concourse D Concourse C Building C1 5 Expansion Status and Renderings 6 Project Status The CCE Program consists of the main C Concourse Expansion (CCE) design package and three accelerated design packages: Main CCE package: 30% complete, 60% due late Q3 2022 Civil and Structural foundation package: 100% designed and bid Tenant relocation design package: 90% complete Structural Steel design package: 60% complete 7 Building Exterior 8 Performance Stair 9 Mezzanine 10 Public Lookout 11 Sustainability Initiatives 12 Budget and Framework Sustainable Evaluation Framework: Airport's first Tier 3 Estimated environmental sustainability impacts from project Brainstormed reduction strategies, and evaluated costs and benefits Presented recommendations to SEA leadership, and the Commission Sustainability, Environment, and Climate Committee (SEAC) Costs to implement initiatives not included in original budget 13 CCE: Baseline Sustainability Impacts Without intervention or sustainability strategies: Energy increases by 21,000 MMBTU/year Carbon increases by 620 tonnes/year Solid waste increases by 488 tons/year Increased transportation demand for employees No adverse impacts on equity but project could provide opportunities to support tenant employees 14 Recommendations Carbon/Energy Strategies Tenant all electric hot water and cooking Fossil-fuel free heating (heat pumps) Rooftop photovoltaics Reduce carbon 90% Meet 47% of new energy load with low carbon sources and renewables Equity Strategies Employee break room New food donation storage reduces waste by ~3% First cost: $11M and TCO: $13M 15 Budget and Schedule 16 Budget Overview Original Estimate $340M-$510M MII Approved Budget $340M Spent to Date $9.2M Estimate Trends Sustainability Initiatives (includes soft costs) $10.4M Non-Discretionary Scope Changes $24M Escalation and Scope Definition $32.6M Current Range $340M $420M 17 Program Contingency Status Available Program Contingency is $30 Million Project team is assessing how much of this contingency can be allocated against Estimate Trends Evaluating Risk Register against available contingency 18 Schedule Milestones 2022 Commission Dates April 26: Authorization for Baggage Transfer Line Budget Transfer June 14: Authorization for Structural Steel Package Funding September 27: Project Briefing Construction Milestones Q2 2022: Start structural foundations and civil work Early Q4 2022: Start TSA relocation from existing C1 Building Q2 2023: Start building structural steel Early Completion Q1 2026 Late Completion Q2 2027 19 Questions? 20 Cone of Certainty W e are here 21
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.