8i. Memo

Sanitary Pipe Replacement

COMMISSION 
AGENDA MEMORANDUM                        Item No.          8i 
ACTION ITEM                            Date of Meeting      March 14, 2023 

DATE:     March 3, 2023 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Keri Stephens, Director, Aviation Facilities and Capital Programs 
Eileen Francisco, Director, Aviation Project Management 
SUBJECT:  Sanitary Pipe Replacement (CIP# C801239) – Design Authorization 
Amount of this request:                 $600,000 
Total estimated project cost:          $3,000,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to (1) increase the project budget
by $1,000,000 for a revised total budget of $3,000,000; (2) prepare design and construction bid
documents for the Sanitary Pipe Replacement project. The amount of this request is $600,000
for an estimated total project cost not to exceed $3,000,000. 
EXECUTIVE SUMMARY 
Sanitary waste pipes serving multiple SEA areas are at or near end-of-life (typically 30 years). This
project replaces or relines waste pipes. Failures result in unscheduled shutdown of airport
restrooms, restaurants, and tenant spaces which will directly impact passenger experience and
tenant operations. Leakage and spills from failed pipes may result in health hazards to the public
and airport workers as some waste pipes are routed over occupied spaces. 
Since the preliminary budget was developed (2020) we have seen rising material costs, increased
labor rates, increased abatement scope, and escalation, resulting in an additional $1,000,000
needed to complete the work.
JUSTIFICATION 
Failure of sanitary waste piping is often sudden, unexpected, and impossible to predict. Sanitary
waste pipe failures result in unscheduled emergency repairs which cause unscheduled
shutdowns of airport restrooms, restaurants, and tenant owned spaces. This directly impacts
customer experience and tenant operations. This project replaces the sanitary waste piping
identified as a risk if not replaced. 

Template revised January 10, 2019.

             COMMISSION AGENDA – Action Item No. 8i                                   Page 2 of 4 
Meeting Date: March 14, 2023 
Diversity in Contracting 
The design services will be completed using an existing IDIQ contract that was established in 2022
which has a 16% WMBE participation utilization requirement.
DETAILS 
Scope of Work 
Replace, or reline failing sanitary waste piping on Concourse A, Main Terminal, and Central
Terminal (2 locations). 
(1)   A Concourse - Work will result in temporary closures to restrooms and tenant spaces 
on concourse level. Scope includes approximately 350 linear feet of sewer pipe work.
210 linear feet will replace existing cast iron pipe with new stainless-steel piping and
150 linear feet of buried pipe will be cast-in-place pipe linear. 
(2)   Main Terminal – Pipe located in mechanical room 4 (under baggage claim 15 area).
Approximately 250 linear feet pipe will be replaced from cast iron to stainless-steel. 
(3)   Central Terminal South – Approximately 250 linear feet of sanitary pipe serving TSA
locker rooms (Men/Women) with some central terminal concourse concessions. 55
linear feet of this will be replacing cast iron piping with stainless-steel, and 200 linear
feet of this will be cast-in-place pipe. 
(4)   Central Terminal North – Approximately 230 linear feet of Sanitary pipe serving
concourse level restrooms and concessions. 30 linear feet of this will be replacing cast
iron piping with stainless-steel, and 200 linear feet of this will be cast-in-place pipe. 
Schedule 
Activity 
Design complete                              Q2 2024 
Commission construction authorization          Q2 2024 
Construction award                            Q4 2024 
Substantial completion                          Q2 2026 
Cost Breakdown                                     This Request           Total Project 
Design                                                    $600,000               $650,000 
Construction                                                     $0             $2,350,000 
Total                                                           $600,000              $3,000,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1 – Status Quo. Do not proceed with project. 
Cost Implications: Expense approximately $35,000 for notebook development costs. 
Pros: 
(1)   Delays or defers capital investment. 

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 8i                                   Page 3 of 4 
Meeting Date: March 14, 2023 
Cons: 
(1)   Sanitary pipe failures could occur at any time resulting in large expense costs for
emergency repairs and shutdowns to restrooms, concessions and other tenant owned
spaces. 
(2)   Potential for additional increase in costs for materials, labor, and/or inflation. 
This is not the recommended alternative. 
Alternative 2 – Replace, or reline failing sanitary waste piping on Concourse A, Main Terminal,
and Central Terminal (2 locations). 
Cost Implications: $2,935,000 in capital costs and $65,000 in expense costs 
Pros: 
(1)   Provides an additional 15-50 years of sanitary pipe life, resulting in less unexpected
shutdowns and emergency repairs. 
(2)   Reduces potential negative risk to passenger experience by limiting shutdowns of
concessions and restrooms. 
(3)   Replaces aging infrastructure in a timely manner. 
Cons: 
(1)   Capital and expense costs. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary              Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                 $2,000,000               $0      $2,000,000 
Current change                                   $935,000         $65,000      $1,000,000 
Revised estimate                                $2,935,000         $65,000      $3,000,000 
AUTHORIZATION 
Previous authorizations                             $50,000               $0         $50,000 
Current request for authorization                  $600,000               $0        $600,000 
Total authorizations, including this request         $650,000               $0        $650,000 
Remaining amount to be authorized            $2,285,000        $65,000     $2,350,000 



Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 8i                                   Page 4 of 4 
Meeting Date: March 14, 2023 
Annual Budget Status and Source of Funds 
This project C801239 was included in the 2023-2027 capital budget and plan of finance with a
budget of $2,000,000. The capital budget increase of $935,000 was transferred from the
Aeronautical Allowance CIP C800753 resulting in no net change to the Airport capital budget. The
funding sources will be the Airport Development Fund and future revenue bonds. 
Financial Analysis and Summary 
Project cost for analysis              $3,000,000 
Business Unit (BU)                  Terminal Building 
Effect on business performance    NOI after depreciation will increase due to inclusion of
(NOI after depreciation)             capital (and operating) costs in airline rate base. 
IRR/NPV (if relevant)                N/A 
CPE Impact                       $0.01 in 2026 
Future Revenues and Expenses (Total cost of ownership) 
As a result of this project, Aviation Maintenance may see a small increase in preventative
maintenance support. 
ATTACHMENTS TO THIS REQUEST 
(1) Presentation Slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None 








Template revised June 27, 2019 (Diversity in Contracting).



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.