10e. Memo
T91 Trail Bridge Removal and Widening
COMMISSION AGENDA MEMORANDUM Item No. 10e ACTION ITEM Date of Meeting September 12,2023 DATE: July 26, 2023 TO: Stephen P. Metruck, Executive Director FROM: David McFadden, Managing Director, Economic Development Division Kyra Lise, Director of Real Estate Development Stefan Wynn, Capital Project Manager IV SUBJECT: T91 Trail Bridge Removal and Segment Widening (CIP# C801192) Amount of this request: $1,475,000 Total requested project cost: $1,525,000 ACTION REQUESTED Request Commission authorization for the Executive Director to proceed with design and construction for the T91 Trail Bridge Removal and Segment Widening. This single authorization is for $1,475,000 of a total estimated project cost of $1,525,000. EXECUTIVE SUMMARY This project will remove the existing pedestrian/bicycle bridge and replace with an on-grade path, widen the existing pinch point south of the pedestrian/bicycle bridge and upgrade the existing rail crossing. JUSTIFICATION 1) Improve Public Safety - This project improves public safety by upgrading these trail segments to American Association of Highway and Transportation Officials (AASHTO) design standards where applicable to allow for two-way traffic and reduce risk of collisions. 2) Improve Accessibility - This project addresses accessibility challenges at the pedestrian/bicycle bridge and the rail crossing to expand the number of users who can enjoy and utilize this unique non-vehicular route between Interbay and Downtown. Diversity in Contracting Design is being executed through an existing IDIQ with preestablished contracting goals of 25%. With the small nature of this project, it presents a great opportunity to have high WMBE Template revised January 10, 2019. COMMISSION AGENDA – Action Item No. 10e Page 2 of 4 Meeting Date: September 12, 2023 participation. The Diversity in Contracting Department will be engaged as part of the Bid Document preparation to establish these goals. DETAILS Scope of Work Work included to widen the two trail segments, about 750 feet of trail in total. (1) Remove the existing pedestrian/bicycle bridge and replace with an on-grade path to meet standard design criteria of a ten-foot paved trail (10’-0”) with two-foot (2’-0”) buffers areas consistent with existing tree planting wherever possible. (2) Widen the existing pinch point south of the pedestrian/bicycle bridge to a paved width of 8-feet 6-inches (8’-6”) with no buffer by moving the east fence per an easement with BNSF railroad. This is an acceptable alternate when existing fixed elements like train tracks and buildings exist. (3) Upgrade the rail crossing in the south pinch point segment to AASHTO or National Association of Transportation Officials (NACTO) design standards address safety and accessibility issues, which ever is the higher standard. (4) Revise grading to direct flow to existing stormwater conveyance system. Coat new and existing fences within the project boundary to reduce zinc runoff. (5) Install new fencing where required and paint existing fence in segment areas to remain. (6) Install conduit sleeves under the trail for future lighting opportunities. Schedule Activity Commission design authorization 2023 Quarter 3 Design start 2023 Quarter 3 Commission construction authorization 2023 Quarter 3 Construction start 2024 Quarter 3 In-use date 2024 Quarter 4 Cost Breakdown This Request Total Project Design $525,000 $575,000 Construction $950,000 $950,000 Total $1,475,000 $1,525,000 Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA – Action Item No. 10e Page 3 of 4 Meeting Date: September 12, 2023 ALTERNATIVES AND IMPLICATIONS CONSIDERED Alternative 1 – Maintain the current condition. Cost Implications: None. Pros: (1) No additional cost to the Port. (2) No trail closure during construction. Cons: (1) Existing safety issues remain which could present the Port with potential Liabilities. (2) Existing accessibility issues remain which limit usability and access to some users. This is not the recommended alternative. Alternative 2 – In addition to the proposed alternative, move the west fence three feet six inches (3’-6”) at the southern pinch point to achieve a full 10-foot (10’-0”) paved width with 2-foot (2’-0”) buffers on each side. Cost Implications: $4,000,000 - $7,000,000 Pros: (1) Trail segments will meet minimum design standards to the full extent, including at the southern pinch point. Cons: (1) The rail spur would need to be shifted which would add considerable cost, extend the construction duration, and cut off all rail access to the Port during construction. This is not the recommended alternative. Alternative 3 – Remove the existing pedestrian/bicycle bridge and replace with an on-grade path meeting minimum design standards and widen the existing pinch point south of the pedestrian/bicycle bridge as much as feasible per an easement with BNSF Railways. Cost Implications: $1,525,000 Pros: (1) Improves safety and accessibility. (2) Limited project scope will facilitate a shorter construction period and impact to daily users from the trail closure. Cons: (1) Due to the existing constraints of the existing rail lines on both sides of the trail, the full standards design width with buffers cannot be achieved at the southern pinch point and therefore tree planting is limited. (2) Does not include time-intensive sustainability and equity elements, lighting installation, or waste receptacles. This is the recommended alternative. Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA – Action Item No. 10e Page 4 of 4 Meeting Date: September 12, 2023 FINANCIAL IMPLICATIONS Cost Estimate/Authorization Summary Capital Expense Total COST ESTIMATE Original estimate $1,525,000 $0 $1,525,000 AUTHORIZATION Previous authorizations $50,000 0 $50,000 Current request for authorization $1,475,000 0 $1,1475,000 Total authorizations, including this request $1,525,000 0 $1,525,000 Remaining amount to be authorized $0 $0 $0 Annual Budget Status and Source of Funds This project was included in the 2023 Capital Plan under C801192 T91 Trail Improvements with a total estimated cost of $1,200,000. The current total project estimate is $1,525,000. The additional cost will be covered by management reserves. The project will be funded by the General Fund. A separate easement deal with BNSF includes a land transfer that will net cash proceeds to the Port. Financial Analysis and Summary Project cost for analysis $1,525,000 Business Unit (BU) Portfolio Management/Parks Effect on business performance This project is expected to increase annual depreciation (NOI after depreciation) by approximately $50K. IRR/NPV (if relevant) NA CPE Impact NA ATTACHMENTS TO THIS REQUEST (1) Presentation PREVIOUS COMMISSION ACTIONS OR BRIEFINGS None Template revised June 27, 2019 (Diversity in Contracting).
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.