8k. Presentation

Maritime Industrial Center Electric Equipment Procurement

Item No. 8k supp
Meeting date: November 14, 2023
Maritime Industrial Center
Electrical Infrastructure Replacement
Electric Equipment Procurement
Authorization for Additional Funding
Kelly Purnell – Capital Project Manager
Jennifer Maietta – Director, Real Estate Asset Management (Sponsor)
Kenneth Lyles – Director, Fishing and Commercial Operations (Sponsor)

CIP # C801241
Project # N06470

                   Overview
• Action Requested
• Current Condition
• Project Scope and
Equipment Purchase
• Risks and Opportunities
• Schedule
• Funding

2

                Action Requested
Request Commission authorization for the Executive Director to:
1. Approve additional funding in the amount of $1,810,000 for
the procurement of long-lead major electrical equipment for
the Maritime Industrial Center Electrical Infrastructure
Replacement project.
Project Estimated Cost: $8,590,000
Procurement Authorization Request: $1,810,000

3

                 Current Condition
•   Significant corrosion
•   Stormwater intrusion
•   Degraded protective coatings
•   Decaying structural pads




4

                Current Tenant Mix
•  Building A-1:
– Mix of storage, warehouse, repair and maintenance shops, silk screen
printing
• Building A-2, yard and moorage:
– Boat yard and marine services (metal fabrication, woodwork, heating
and cooling, electronics)
• Building A-3, A-4, A-5, yard and moorage:
– Fishing vessel support operations

5

                   Project Scope
Project Work:
•  Demolition of (5) existing switchboards and associated equipment
•  Install new switchboards and associated equipment
•  New ducts, vaults, and electric cables
Electrical Equipment Purchase:
•  Location 1: At Main Electrical – Switchgear, switchboards, transformer
•  Location 2: At Mooring Pier – Switchgear, switchboard, transformer
•  Location 3: At Wharf – Switchboards, transformer


6

              Risks and Opportunities
•  Risks
– Failure of the existing electrical equipment
– Safety risks to maintenance personnel due to degradation of equipment
– Schedule risks
• Supply chain constraints causing very long lead times for equipment
procurement
• Seattle City Light delays
– Materials and equipment price volatility
– High escalation in current construction market
•  Opportunities
– Upgraded and safe equipment with higher load capacities for future site
upgrades (EV chargers, shore power, tenant changes)
7

        Project Status/Authorization Request
•  30% design complete on overall project
•  Equipment procurement advertised and bids opened 10/06/2023
• Three bids received; low bid 82% over the Engineer’s Estimate​
•  Requesting additional funding to allow for execution of procurement
contract including WSST ​
•  Total amount of this request: $1,810,000
•  Total project budget: $8,590,000


8

                  Preliminary Schedule

Commission design authorization                  2022 Quarter 4
Design start                                         2022 Quarter 4
Commission authorization for major electrical       2023 Quarter 1
equipment procurement
Commission authorization for additional       2023 Quarter 4
funds for electrical equipment procurement
Commission construction authorization             2024 Quarter 3
Construction start                                   2024 Quarter 4
In-use date                                         2025 Quarter 3

9

                    Funding
Cost Estimate/Authorization Summary        Capital        Expense            To ta l
COST ESTIMATE
Current estimate                             $8,590,000              0    $8,590,000
AUTHORIZATION
Previous authorizations                       $2,650,000              0    $2,650,000
*Current request for authorization             $1,810,000               0    $1,810,000
Total authorizations, including this             $4,460,000               0    $4,460,000
request
Remaining amount to be authorized          $4,130,000            $0    $4,130,000

*Additional funding will be covered by the Maritime Management Reserve C800002


10

               Questions?

11



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.