8g. Presentation
Bell Street Garage Guardrail Upgrade
Item No.: 8g_Supp Date: March 26, 2024 Bell St. Garage Railing Repair PN: N10381, CIP: C801406 March 26, 2024 Rod Jackson/ Susie Archuleta Overview • Project Information • Project Location • Project Scope • Summary Recommendation • Preliminary Schedule 2 Project Information • Sponsors: Jennifer Maietta, and Susie Archuleta • Project Estimated Cost: $4.85M • Estimated Construction Cost: $3.86M • Current Authorization: $300,000 Seed money Request Commission authorization for the Executive Director to direct staff to advertise and execute a Public Works Building Engineering Systems (BES) Contract to upgrade the Bell St. Garage guardrail system in the central parking garage and bring railing up to current code. This Life Safety guardrail replacement project has an estimated total project cost of $4,853,000. 3 Project Location Bell St. Parking Garage 4 Project Scope: Bring railing up to current code The project will Replace or Retrofit to bring the garage railing up to current code: • The Bell St. Central Garage Railing that was previously damaged and to upgrade all central garage railings. 5 Project Scope: Bring railing up to current code The project will Replace or Retrofit to bring the garage railing up to current code: • The Central Garage Railing that was previously damaged, plus a Replacement or Retrofit at forty railing openings. 6 Project Scope: Bring railing up to current code The project will Replace or Retrofit to bring the garage railing up to current code: • Forty (40+) Bell St. Central Garage Rail openings between column bays on our (4) floors adjacent to the BNSF railroad tracks. 7 Sustainability and Community • The project team will endeavor to reduce embodied carbon through re-using the existing railings in design. • The project area is visible from the P66 cruise terminal and the Bell Street overpass. To support the community, the project will improve the aesthetic appearance of the P66 parking garage through railing color and design. 8 Summary Recommendation Request Commission authorization for the Executive Director to direct staff to advertise and execute a Public Works Building Engineering Systems (BES) Contract to replace the Bell St. Garage guardrail system in the central parking garage and bring railing system up to current code. 9 Project Schedule Acquisition Planning December 7, 2023 Commission Authorization – Design and Construction 2024 Quarter 1 Notice to Proceed 2024 Quarter 4 In-use date 2026 Quarter 2 10 Questions? Questions? 11
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.