4c

COMMISSION 
AGENDA MEMORANDUM                Item No.       4c 
October 25, 2016 
ACTION ITEM                   Date of Meeting 
DATE:    September 19, 2016 
TO:     Ted Fick, Chief Executive Officer 
FROM:   Michael Tasker, Senior Manager, Facility and Infrastructure 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Cargo 2  400 Hz In-ground Power Station Retrofit (CIP #C800247) 
Cargo 6  400 Hz In-ground Power Station Retrofit (CIP #C800390) 
2017 Airfield Pavement Project (CIP #C800483) 
Amount of this request:          $1,280,000 
Total estimated project cost:       $2,800,000 
ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to advertise and execute a
single construction contract to: (1) retrofit five existing 400 Hz in-ground power stations at
Cargo Area 2 (CIP #C800247), and Cargo Area 6 (CIP #C800390), and (2) reconstruct a portion of
the existing pavement at Cargo Area 2 (2017 Airfield Pavement Project  CIP #C800483). 
EXECUTIVE SUMMARY 
This project will improve safety conditions for in-ground power stations at Cargo Areas 2 and 6
and improve aircraft operating conditions at Cargo Area 2. Specifically, the construction
contract will retrofit two 400 Hz in-ground power stations located at Cargo Area 2 and three
located at Cargo Area 6; and replace a section of distressed asphalt pavement and adjacent
broken concrete panels with Portland cement concrete pavement (PCCP) at Cargo Area 2. 
The retrofit of five existing 400 Hz in-ground power stations with pop-up systems eliminates the
potential for personnel to inadvertently step into an open vault and improves safety. The use of
400 Hz in-ground power stations to power aircraft while on the ground, rather than having air
carriers run their auxiliary power units (APUs) reduces the emission of greenhouse gases and
other pollutants and creates significant fuel savings for the airlines. 
As part of an ongoing Pavement Management and Maintenance Program (PMMP), the 2017
Airfield Pavement Project will replace the pavement deteriorating from repeated use at Cargo
Area 2. The replacement with PCCP will provide more structural support for safe and efficient
aircraft operations. The pavement replacement program was included in the 2016  2020 
capital budget and plan of finance. 

Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. 4c                        Page 2 of 9 
Meeting Date: October 25, 2016 
The total value of this authorization request is $1,280,000 of an estimated total cost of
$2,800,000. Savings from previously authorized Cargo 2 and 6 projects have been returned to
fund the design and construction of the 400 Hz in-ground power stations retrofit. $220,000 was
previously authorized for 2017 Airfield Pavement design. 
JUSTIFICATION 
The five existing 400 Hz in-ground power stations located at Cargo Area 2 and Cargo Area 6
were installed as a part of projects completed in 2015. Safety concerns have emerged since the
stations were installed due to the vaults being open when in use and creating a risk of falls.
Alternatives were evaluated during the design phase for these power stations which included
hatch systems and pop-up systems. The hatch system was the recommended option at the time
as it was perceived to have a lower risk of being hit by vehicles and had a lower cost. The
existing 400 Hz in-ground power stations have not been placed into operation based on these
safety considerations. Retrofits to the existing systems are needed to ensure safe operations. 
This is the first installation of such systems at Seattle-Tacoma International Airport. 
For the hatch system, an operator needs to step into the vault and onto a grate in order to
make cable connections to the receptacle. The grate was installed lower than the surrounding
surface to provide space for the receptacle when the hatch system is closed. After the hatch
systems were installed, Port Safety and Maintenance raised concerns about the potential for
personnel to inadvertently step into the vault. The system will be operated by staff employed
by the airlines or their contractors, which historically have a high rate of personnel turnover.
Port Safety, Facilities & Infrastructure, Maintenance and Operations have determined that it
would be impractical to institute training or operational measures and expect them to have
long term effectiveness. Staffs' recommendation is to retrofit these power stations. 
Retrofit alternatives were evaluated including other hatch systems and the pop-up system. The
pop-up system was the recommended alternative based on the coordination with Port Facilities
& Infrastructure, Safety, Maintenance and Operations, discussion with the industry and review
of a similar system at King County Airport which has 400 Hz in-ground power systems installed.
The pop-up system would have a beacon safety light installed to help prevent the system from
being hit when it's extended. Since the pop-up system requires larger vaults than the existing
vaults, one concrete panel at each location will need to be replaced for the retrofit. 
Since the 400 Hz pop-up power stations are long-lead items, advanced procurement would
facilitate the early start of construction so that the installation could be complete before the
peak season for Cargo traffic to minimize the impact to operations. Five power stations will be
procured by the Port and furnished to the contractor for installation. 
The project will also replace a section of existing asphalt pavement and adjacent broken
concrete panels with PCCP at Cargo Area 2. Additional aircraft parking positions have been
added at Cargo Area 2. This resulted in aircraft parking on asphalt pavement not designed for
such a load. The pavement is deteriorating from the repeated use and the replacement with

Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. 4c                        Page 3 of 9 
Meeting Date: October 25, 2016 
PCCP will provide the needed structural support. The 2017 Airfield Pavement Project is part of
an ongoing pavement management program. Distressed panels that are deemed critical by
Airport Operations and need urgent replacement could be added to this project. 
Maintaining critical airfield assets supports the Port's Century Agenda objective to meet the
region's air transportation needs at the Airport  for the next 25 years. The pavement
management program maintains the integrity of airfield pavements and efficient airport
operations. 
Three individual projects have been combined into a single construction project because of the
similarity, proximity, and the timing of the work at Cargo 2 and 6 areas. The combined project
results in a more efficient design, economies of scale, lower administrative costs and will
minimize impacts to airfield operations from construction activities.
One of the Century Agenda goals is to use the Port's influence as an institution to promote
small business growth and workforce development. Although some of this work may be
specialized, Port staff will coordinate with Economic Development Division's Small Business
Group to identify potential opportunities within the scope of work for small business utilization. 
Given the location and limited magnitude of the combined project, a Project Labor Agreement
(PLA) is not recommended. 
DETAILS 
Project Objectives 
(1) Provide for safe operations 
(2) Reduce the emission of greenhouse gases and other pollutants 
(3) Maintain pavement on the airfield. 
Scope of Work 
(1) Retrofit two existing 400 Hz in-ground power stations located at Cargo Area 2 and three
in-ground power stations at Cargo Area 6 with pop-up systems 
(2) Replace distressed asphalt pavement and adjacent broken concrete panels with PCCP at
Cargo 2 area. 
Schedule 
Activity 
Construction start                      2017 Quarter 1 
In-use date                          2017 Quarter 2 


Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. 4c                        Page 4 of 9 
Meeting Date: October 25, 2016 
Cargo 2 - 400 Hz In-ground Power Station Retrofit (CIP C800247) 
Cost Breakdown                         This Request       Total Project 
Design                                       $0           $80,000 
Construction                                    $0          $440,000 
Total                                             $0           $520,000 
Cargo 6 - 400 Hz In-ground Power Station Retrofit (CIP C800390) 
Cost Breakdown                         This Request       Total Project 
Design                                       $0          $120,000 
Construction                                    $0          $660,000 
Total                                             $0           $780,000 
2017 Airfield Pavement Project (CIP C800483) 
Cost Breakdown                         This Request       Total Project 
Design                                    $37,000          $235,000 
Construction                              $1,243,000         $1,265,000 
Total                                      $1,280,000          $1,500,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternatives related to the Cargo 2 and 6- 400 Hz In-ground Power Station Retrofit 
Alternative 1  The Port would not retrofit the existing 400 Hz in-ground power system. 
Cost Implications: $0 
Pros: 
(1) No additional cost. 
Cons: 
(1) Based on the decisions from Safety and Operations, the existing systems that use hatch
vaults are not being used due to safety concerns. Air carriers will need to run their APUs
to power aircraft while on the ground. The airport would not be able to reduce the
emission of greenhouse gases and other pollutants by the installation of 400 Hz pop-up
power stations. Air carriers would not be able to have significant fuel savings. 
(2) If the existing 400 Hz in-ground power systems were to be used, there would be risks of
fall incidents of workers operating the system and potential back injuries of workers
connecting the cable to the receptacle. 
This is not the recommended alternative. 


Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. 4c                        Page 5 of 9 
Meeting Date: October 25, 2016 
Alternative 2  Retrofit the existing 400 Hz in-ground power system with other hatch assembly. 
Cost Implications: $779,000 
Pros: 
(1) Lower cost than the recommended Alternative 3. 
(2) Eliminate safety concerns of fall incidents with a platform at the ground level. 
Cons: 
(1) Increase potential of back injuries with a platform at the ground level since the elevation
of receptacles is relatively low. The cable is very stiff and heavy, which makes it difficult
for connecting to the receptacle. 
This is not the recommended alternative. 
Alternative 3  Retrofit the existing 400 Hz in-ground power system with pop-up system. 
Cost Implications: $1,300,000 
Pros: 
(1) Receptacles are installed at a higher elevation, which facilitates the connections to the
power and future maintenance. 
(2) Beacon safety lights would be installed for protection of the pop-up system when it's
extended. 
(3) Eliminates safety concern. 
Cons: 
(1) Highest cost of final alternatives considered. 
This is the recommended alternative. 
Alternatives related to the 2017 Airfield Pavement Project 
Alternative 1 The Port would not replace the section of asphalt pavements at Cargo 2 with
PCCP. 
Cost Implications: $0 
Pros: 
(1) No additional cost. 
Cons: 
(1) Continued use of the pavement could result in potential Foreign Object Debris (FOD),
and/or closure of the area to aircraft use. 
(2) Potential impacts to aircraft operations 
This is not the recommended alternative. 

Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. 4c                        Page 6 of 9 
Meeting Date: October 25, 2016 
Alternative 2  Delay the project beyond 2018. 
Cost Implications: $1,600,000 
Pros: 
(1) No additional construction cost for 2017. 
(2) No construction impacts to aircraft operations at Cargo 2 area in 2017. 
Cons: 
(1) Continued use of the pavement could result in foreign object debris (FOD), and/or
closure of the area to aircraft use. 
(2) This project would likely become a stand-alone project if it's delayed beyond 2018; this
would result in contracting inefficiencies (higher total cost) and potential impact to
aircraft operations. 
This is not the recommended alternative. 
Alternative 3  Replace the section of asphalt pavements at Cargo 2 with PCCP. 
Cost Implications: $1,500,000 
Pros: 
(1) Provide more structural support to aircraft parking at Cargo 2 for safer operations. 
(2) Combining with Cargo 2 400 Hz In-ground Power Station Retrofit will benefit from a
more efficient design, lower cost and less impact to operations. 
Cons: 
(1) Construction impacts to aircraft operations at Cargo 2 area in 2017. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Financial implications of Cargo 2 - 400 Hz In-ground Power Station Retrofit C800247 
Cost Estimate/Authorization Summary          Capital      Expense        Total 
COST ESTIMATE 
Revised budget                      $7,047,875     $797,125    $7,845,000 
Total cost to date                       $6,410,972      $284,064    $6,695,036 
Retrofit estimate                        $520,000          $0      $520,000 
Estimated savings after retrofit               $116,903      $513,061      $629,964 
AUTHORIZATION 
Previous Authorizations                 $11,747,875     $797,125   $12,545,000 
Current request for authorization                 $0          $0          $0 
Total Authorizations, including this request    $11,747,875      $797,125   $12,545,000 

Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. 4c                        Page 7 of 9 
Meeting Date: October 25, 2016 

Annual Budget Status and Source of Funds 
Cargo 2 west hardstand project C800247 was completed in 2015 with total cost to date of
$6,410,973. The additional costs will be funded with the Airport Development Fund. 
Financial Analysis and Summary 
Project cost for analysis         Revenue/Capacity Growth 
Business Unit (BU)            Airfield Commercial Area 
Effect on business performance   NOI after depreciation will decrease 
(NOI after depreciation) 
IRR/NPV (if relevant)           N/A 
CPE Impact                None 
Financial implications of Cargo 6 - 400 Hz In-ground Power Station Retrofit C800390 
Cost Estimate/Authorization Summary          Capital      Expense        Total 
COST ESTIMATE 
Revised budget                      $6,345,486          $0    $6,345,486 
Total cost to date                       $5,278,817           $0    $5,278,817 
Retrofit estimate                        $780,000          $0      $780,000 
Estimated savings after retrofit               $286,669          $0      $286,669 
AUTHORIZATION 
Previous Authorizations                 $6,345,875     $132,125    $6,478,000 
Current request for authorization                 $0          $0          $0 
Total Authorizations, including this request     $6,345,486      $132,125    $6,477,611 
Annual Budget Status and Source of Funds 
Cargo 6 hardstand improvements C800390 was completed in 2015 with a total project spending
of $5,278,817. The additional costs will be funded with the Airport Development Fund. 
Financial Analysis and Summary 
Project cost for analysis         Revenue/Capacity Growth 
Business Unit (BU)            Airfield Commercial Area 
Effect on business performance   NOI after depreciation will decrease 
(NOI after depreciation) 
IRR/NPV (if relevant)           N/A 
CPE Impact                None 


Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. 4c                        Page 8 of 9 
Meeting Date: October 25, 2016 

Financial implications of 2017 Airfield Pavement Project C800483 
Cost Estimate/Authorization Summary          Capital      Expense        Total 
COST ESTIMATE 
Program budget                    $32,500,000         $0   $32,500,000 
2017 cost estimate                     $1,500,000          $0    $1,500,000 
Remaining program budget             $31,000,000         $0   $31,000,000 
AUTHORIZATION 
Previous authorizations                   $220,000          $0      $220,000 
Current request for authorization           $1,280,000          $0    $1,280,000 
Total Authorizations, including this request     $1,500,000          $0    $1,500,000 
Remaining amount to be authorized       $31,000,000         $0   $31,000,000 
Annual Budget Status and Source of Funds 
The Airfield Pavement Program for C800483 was included in the 2016-2020 capital budget and
plan of finance with a budget of $32,500,000. This CIP will have an average annual budget of
$6.5 million based on past pavement replacement expenditures. The design and construction
for the 2017 work will be funded with future revenue bonds, to be issued in 2017. 
Financial Analysis and Summary 
Project cost for analysis         $1,500,000 
Business Unit (BU)            Airfield Apron Area 
Effect on business performance   NOI after depreciation will increase 
(NOI after depreciation) 
IRR/NPV (if relevant)           N/A 
CPE Impact                $0.01 CPE in 2017 
Future Revenues and Expenses (Total cost of ownership) 
The estimated life expectancy for this project is 20 years for pavements, 30 years for 400 Hz
pop-up power stations and 30 years for transformers. Replacing pavement will result in
maintenance cost avoidance. 
ADDITIONAL BACKGROUND 
Utilizing 400 Hz power, versus APUs, supports the Port's Century Agenda Goal to be the
greenest, and most energy efficient port in North America. Reduce air pollutants and carbon
emissions, specifically: -- Reduce air pollutant emissions by 50% from 2005 levels. -- Reduce
carbon emissions from all Port operations by 50% from 2005 levels and reduce aircraft-related
carbon emissions at Sea-Tac by 25%. Using 400 Hz power at aircraft parking positions is
consistent with previous decisions to reduce noise and emissions. 

Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. 4c                        Page 9 of 9 
Meeting Date: October 25, 2016 

The estimated annual emission savings of utilizing 400 Hz power versus APUs for a cumulative
360 hours of 747 or MD11 freighter aircraft operations is: 
(1) Hydrocarbon             0.1 tons/yr. 
(2) Carbon Monoxide         2.0 tons/yr. 
(3) Nitrous Oxides             0.5 tons/yr. 
(4) Carbon Dioxide            325 tons/yr. 
ATTACHMENTS TO THIS REQUEST 
Presentation slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
February 24, 2015  Commission authorized the Chief Executive Officer to design, prepare
construction documents, and implement advanced measures as necessary to replace
distressed pavement and joint sealant for the 2016 Airfield Pavement portion of the
2016-2020 Airfield Pavement Program at the Seattle-Tacoma International Airport in the
amount of $200,000. 
October 8, 2013  Commission authorized the Chief Executive Officer to advertise and
execute a single construction contract comprised of Cargo 2 Hardstand Expansion (CIP
#C800247), Cargo 5 Hardstand Construction (CIP #C800254), Cargo 6 Hardstand
Improvements (CIP #C800390), and Airfield Pavement Replacement-Cargo 6 Apron (CIP
#C102583). 
September 25, 2012  Commission authorized the Chief Executive Officer to design and
prepare construction documents for the Cargo 6 Enhancements at Seattle-Tacoma
International Airport. Commission also separately authorized the Chief Executive Officer
to design and prepare construction documents for the demolition of a cargo building
(Building 2) and for the enlargement of the hardstand in the Cargo 2-West area in the
amount of $830,000. 






Template revised September 22, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.