4b supp

Item No.      4b_Supp 
Date of Meeting: September 13, 2016 
Electric Ground Support Equipment
(EGSE) Charging Stations 


1

LEGEND 
GSE CHARGER DEMONSTRATION PROJECT (COMPLETED - RELOCATED BY NORTH STAR PROJECT)
GSE CHARGER PHASE 1 CHARGING CORALS PROJECT (INSTALLATION COMPLETED)
CONCOURSE D - GSE PHASE 1 - POWER CENTER (MODIFICATIONS COMPLETED)
GSE CHARGER PHASE 2 CHARGING CORRALS PROJECT (DESIGN 85% COMPLETE)
GSE CHARGER PHASE 2 PROJECT - NEW POWER CENTERS (DESIGN 85% COMPLETE)
CONCOURSE C - NEW POWER CENTER (NOTEBOOK 85% COMPLETE)
EGSE Locations & Power Centers 
2

Project Scope of Work 
Summary of Work Phase 1 & 2 (Bold Items Phase 2 Work) 
Upgrade Concourse D existing Power Center - install controls to automate existing bus transfer scheme.
Reduce electrical load on Concourse C power center by re-routing sub-feeder circuits to C1 power center. 
Install electrical GSE chargers throughout AOA ramp area that includes approx. 500 charge ports at: 
Concourses A, B, C and D 
North and South Satellites 
Add two new power centers to support the additional GSE Charger electrical loads at: 
Concourse C (Separate Project C800724 ) 
Concourse B 
South Satellite 
Install a distributed data collection network that will collect metered power consumption charger log data
for billing & other historical system reports. 
Develop reporting system to provide various system historical, trend and GSE vehicle maintenance reports. 
Simplified overview of project scope of work 
3

GSE Phase 1 Installation Summary 
GSE CHARGER PHASE 1 LOCATIONS       TOTALS 
Concourse C 
Total Corrals 
16 
Total Charger Ports                        114 
Concourse D 
Total Corrals                            16 
Total Charger Ports                        72 
North Satellite 
Total Corrals                            14 
Total Charger Ports                        92 
CTE BAGWELL 
Total Corrals                            4 
Total Charger Ports                        8 
Grand Totals 
Grand Total Corrals Installed                  50 
Grand Total Charger Ports                   286 

Summary of Charger Ports for Phase 1 
4

GSE Phase 2 Installation Summary 
GSE CHARGER PHASE 2 LOCATIONS     TOTAL 
Concourse A 
Total Corrals                          17 
Total Charger Ports                     76 
Concourse B 
Total Corrals                        19 
Total Charger Ports                     70 
South Satellite 
Total Corrals                        11 
Total Charger Ports                     72 
Grand Totals 
Grand Total Corrals Installed               47 
Grand Total Charger Ports               218 

Summary of Charger Ports for Phase 2 
5

Accomplishments 
6

Typical GSE Charger Corrals 
The electrical charging system allows the airlines at the Airport to use electrically
powered ground service equipment. 




Two Charger Ports       Four Charger Ports       Ten Charger Ports 
Multiple Charging Ports can be Derived from One Branch Circuit  Reduces Costs 
7

Charger Technical Specifications 
The Fast Charge GSE system consists of a PowerServer, multiple Power Stations and a Battery Monitor Identifier
(BMID) installed in each GSE vehicle. The BMID communicates with the Battery Charger 
Rated for outdoors. 
Automatic start/stop. 
Anti-arcing disconnect. 
High power factor. 
Ultra-low harmonic distortion. 
Branch circuit 480VAC, 3 Phase input. 
Charger ratings 30kW, 40kW & 80kW DC output. 
Eliminates the need for battery changing. 
Electric GSE Tugs running on one battery all day. 

Multiple Charging Ports can be Derived from One Branch Circuit  Reduces Costs 
8

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.