7e Supp reduced

Item No.          7e_supp
Date of Meeting     April 26, 2016 
Seattle-Tacoma International Airport
International Arrivals Facility (IAF)
1Q2016 Program Update

Perspective of Overall IAF Project
22

Contract Status-at-a-Glance
Negotiate
Today Guaranteed Maximum Price
(GMP)

Validation    GMP Development         Post-GMP
Period          Period               Period 

4Q16
Commence Design,
Preliminary Construction, and
Long Lead Time Item Procurement

Design has Begun
33


1Q2016 Accomplishments 
Advanced design of automated passport control (APC) with
Customs and Board Protection (CBP).
Reached agreement with the artist, Robert Maki, on
relocation of the Airport's Canary II sculpture 
Engaged an independent contract compliance firm
Began work on the Narrow Body Configuration Project
Initiated small contractors and suppliers outreach: Clark/SOM
attended the 2016 Regional Contracting Forum (RCF) held
April 5, 2016. See www.clarkseataciaf.com for other upcoming
events 

First Quarter Focus  Start of Design
4

Key Activities Planned for 2Q2016
Continue to advance design
Execute enabling works and long-lead materials/systems
procurement packages
Continue working with US Customs & Border Protection (CBP)
to develop innovative passenger processing procedures for
implementation in the IAF



Progressing to GMP 
5

Budget-at-a-Glance
$650
Millions  $600
$550
$500     Estimate $608.4M       Additional Funding
Required
$450
$308.4M
$400
$350
$300
$250
Approved Budget
$200
$300M 
$150
$100
Spent $19.4M
$50
$0
Additional Funding Required 
6

Financial Metrics
Overall Program Progress                              Actual       Planned/Forecast 
(Millions)             (Millions)
Cash Flow  First Quarter 2016             $6.75M          $9.7M
Expenditures to Date                    $19.4M          $22.1M
Current Authorizations                    $300.0          $608.4



Design-Builder is Fully Engaged 
7

SCS & Small Business
Small Contractors & Suppliers (SCS)                             Participation    Contract Requirement 
Participation                               Level to Date       (Percent of Total)
Program Management                          17%            20% 
($0.9M/$5.7M)         ($3.4M/$17M)
Design-Build Team                    4%             12% 
($0.2 M/$5.4M)*     (GMP yet to be Negotiated)
Small Business Participation           Actual to Date         Target
(Including Small Contractors & Suppliers)        (Percent of Eligible Work)    (Percent of Eligible Work) 
Design-Build Team                    7%            17.5%
($0.3M/$4.2M)*     (GMP yet to be Negotiated)
* Design-Build Team included 8 registered SCS firms in this period, 1Q2016


SCS Participation Will Increase as Construction Commences 
8

Future Commission Briefings & Actions IAF Program
Negotiate
GMP
4Q2016 
2015 Fourth      First Quarter     Second Quarter     Third Quarter
2016   Quarter Briefing    Briefing      Briefing      Briefing
1Q2017 GMP     First Quarter    Second Quarter    Third Quarter
2017    Amendment     Briefing      Briefing      Briefing
Authorization

2017 Fourth      First Quarter     Second Quarter     Third Quarter
2018   Quarter Briefing    Briefing      Briefing      Briefing

2018 Fourth      First Quarter     Second Quarter     Third Quarter
2019   Quarter Briefing    Briefing      Briefing      Briefing

2019 Fourth      First Quarter     Second Quarter     Third Quarter
2020   Quarter Briefing    Briefing      Briefing      Briefing

Commission Participation Critical to Project Success 
9

Perspective of IAF Building
10 10

Look Ahead
Target
Milestone
Schedule  Forecast 
Schematic Design Completion   2Q 2016  2Q 2016 
Ceremonial Ground Breaking  4Q2016  4Q 2016 
60% Design Completion    1Q 2017  1Q 2017 
Negotiate GMP        4Q2016  4Q2016 
90% Design Completion    2Q 2017  2Q 2017 
Transport and Place Bridge   3Q 2018  3Q 2018 
Bridge Completed      2Q 2019  2Q 2019 
IAF Completed       3Q 2019  3Q 2019 
Sterile Corridor Complete   3Q 2019  3Q 2019 
Facility Open        3Q 2019  3Q 2019 
Close-Out         4Q 2019  4Q 2019 

Milestones: Design Packages Release Construction
11 11

Airport Growth Creates Nexus Between
IAF & Baggage Program



Relationship of Gate, Make-up and Airport Layout
12 12

Current Baggage Make-up 


142                                180 


Space Constraints Limit Options for Expansion
13 13

Maximum Baggage Make-up 
in Existing Footprint


201                                230 


Shortage Remains After Bag Opt, NorthStar & IAF
14 14

Baggage Make-up Expansion Opportunity


201                                230 

+48
Outside of IAF Scope, Within Time to Capture
15 15

IAF Initial Basis of Design

CBP   CBP   Re-Check
Parking Offices    BHS




IAF Programmed Space 
16

Need to Create a Mezzanine
13,200SF




Change IAF Program to Provide CBP Offices on Mezzanine 
17

IAF Initial Basis of Design

CBP       Re-Check
Parking          BHS




IAF Programmed Space 
18

Need to Reconfigure CBP Parking



CBP           Re-Check
Parking              BHS
IAF Programmed Space 
19

Need to Consolidate/Stack IAF Re-Check



Re-Check
BHS
IAF Programmed Space 
20

New Useable Area




Yields Additional Capacity in 2023 
21

Baggage Make-up & IAF: Same Footprint

CBP OFFICES

CBP SECONDARY PROCESSING

RE-CHECK SCREENING

OUTBOUND BHS

Section 
22

Seizing This Opportunity 
Path forward
Finalize Cost Estimate
Issue MII Ballot to Airlines
Present for Commission Authorization in May



Quick Action Required to Not Delay IAF 
23

Future Action 




Continuing Growth Warrants Reconsideration of Two
Additional Gates           24

Program Background
Key Objectives
Program Goals




Why is a New IAF Needed? 
25

Key Objectives
Develop a facility that meets federal regulatory requirements
Deliver a facility that improves the level of service and
enhances the passenger experience
Create a signature identity that is both memorable and
welcoming to our international arriving passengers
Increase competitiveness with peer Airports by shortening
processing time through our facility


Optimize Airline Operations & Improve Passenger Experience 
26

Program Goals
Replace the Airport's existing over-burdened Federal
Inspection Services (FIS) facility with a modern and efficient
passenger processing facility
Reduce passenger wait and connect times, streamline baggage
connections and ensure international arrivals processing
capacity keeps pace with growing regional needs 
Contribute to achieving the Port Commission's Century Agenda
objective of making the Airport the West Coast's "Gateway of
Choice" for international travel
Provide 18 widebody FIS connected gates
Deliver 1,900 peak hour passenger capacity expandable to
2,600
Keeping Up with Regional Growth
27 27

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.