4g

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA              Item No.      4g 
ACTION ITEM             Date of Meeting   December 8, 2015 

DATE:    December 1, 2015 
TO:      Ted Fick, Chief Executive Officer 
FROM:   Kathy Bahnick, Manager, Seaport Environmental Programs 
Catherine Chu, Capital Project Manager 
SUBJECT:  Terminal 91 Agreed Order Amendment 
Amount of This Request:            $0   Source of Funds:  General Fund (Ops)
and Tax Levy
Estimated Total Project Cost:          $ 
(Environmental
Remediation Liability
[ERL] Non Ops) 
ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to execute (1) an amendment to
Agreed Order No. DE 8938 with Washington State Department of Ecology (Ecology); and (2) a
three year contract for consulting services to perform sediment investigation at T-91 for an
estimated value of $900,000.
SYNOPSIS 
Terminal 91 (T-91) is located in an industrial area in the Interbay neighborhood of Seattle. The
two piers located at Terminal 91were built by the Port soon after its establishment in 1911. In
1941 the U.S. Navy took ownership, consolidating multiple parcels into T-91 as it exists today.
The Port reacquired the facility in the 1970s. A former tank farm located at the terminal was used
as a dangerous waste treatment and storage facility under a Resource Conservation and Recovery
Act (RCRA) permit from the 1970s until 1995.  The above-ground portion of the tank farm was
demolished by the Port in 2005.
Releases associated with the tank farm operations resulted in contaminated soils and groundwater
at T-91. Since 1991, the Port has been working with the Ecology on the investigation, assessment
and development of corrective/cleanup action to address the tank farm contamination. On April
10, 2012, Ecology and the Port entered into an Agreed Order (No. DE 8938) which obligated the
Port to implement the tank farm affected area cleanup. The tank farm cleanup has been completed
except for the long term compliance monitoring. The Order also applies to the Port-owned
submerged lands adjacent to T-91 (Submerged Lands), but it defers action with respect to any
contamination identified in the Submerged Lands for up to ten years (that is, no later than 2022).
The Order states that Ecology would re-evaluate the necessity and practicability of remediation in

Template revised May 30, 2013.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 1, 2015 
Page 2 of 7 
the Submerged lands meanwhile.  During sediment sampling for the Commission-approved
Terminal 91 Maintenance Dredging project located on the east side of Pier 91, sediments
exceeding the Washington state sediment standards were encountered. This led Ecology to request
additional investigation and that both the sediment investigation and the maintenance dredging
work be performed under an Order amendment.
BACKGROUND 
The T-91 site is regulated under both a RCRA permit and a Model Toxics Control Act (MTCA)
Agreed Order. The RCRA permit remains in place because a portion of the site (the tank farm)
was formerly permitted to operate as an RCRA-regulated dangerous waste treatment and storage
facility. Both the former RCRA facility, and the surrounding piers and terminal, are now being
cleaned up under the MTCA program. The Port, as the property owner, is required to hold the
RCRA permit until cleanup ("corrective action") is completed. The permit imposes corrective
action by incorporating a separate agreed order issued under the MTCA. 
Environmental investigations at the T-91 site have been ongoing since the early 1980s. The
primary area of contamination at the site is the tank farm and associated operations.
The Ecology-selected cleanup approach was identified in the December 15, 2010, final Clean up
Action Plan, which consisted of measures designed to prevent migration of contaminants to Elliott
Bay and to prevent direct contact with contaminants. In addition, long-term operation and
monitoring of the installed systems and compliance monitoring were included.
On April 10, 2012, the Port and Ecology entered into an Agreed Order, under which the Port
agreed to implement the work identified in the Cleanup Action Plan. The 2012 Agreed Order also
requires investigation and cleanup of discrete units in the upland area separate from the Tank Farm
area, and placement of a restrictive covenant on the property. Most of the work outlined in the
Cleanup Action Plan was completed earlier this year. As noted above, the Agreed Order deferred
action on any contamination identified in the Submerged Lands for up to ten years.
In addition to chemical contamination, discarded military munitions (DMMs) have been identified
in the Submerged Lands by the U.S. Army Corps of Engineers (USACE). These DMMs are a
result of former Naval operations at T-91. The USACE has performed a Remedial Investigation
under the Formerly Used Defense Site (FUDS) Military Munitions Response Program to
determine the nature and extent of DMMs and is currently working on a Feasibility Study to
identify cleanup options related to DMMs. In 2010 and 2011, FUDS performed a time critical
removal action, removing 25 DMMs that were at or near the surface of the seabed.
In 2013, the Port determined that the cruise ship berth area on the southeast side of Pier 91
required maintenance dredging to re-establish consistent water depth needed throughout the berth
area to accommodate calling cruise ships. Pre-dredging sediment sampling was performed in
September 2013. This sampling effort identified an area of elevated PCBs as well as exceedances
of metals and PAHs. In light of these sample results, Ecology has notified the Port that the time
has come to address the contaminants in the Submerged Lands under an amendment to the current
order.  As noted above, DMMs could be buried in the sediments.  This possibility triggers

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 1, 2015 
Page 3 of 7 
regulatory requirements that render conventional dredging (and disposal of dredged material)
infeasible. As discussed above, the USACE is now developing a Feasibility Study (FS) to evaluate
options for addressing any remaining DMMs. Those options will likely include dredging (which
would remove any remaining DMMs) of submerged lands adjacent to piers 90 and 91. Such
dredging, if it were to occur, would probably also be sufficient to achieve required navigation
depths in the long-term. In the meantime, the Port must pursue interim measures to maintain
consistent water depth in the area for cruise ship operations.
Because conventional dredging methods would risk bringing DMMs to the surface, staff evaluated
other methods to address the shoal. Underwater regrading was determined to be the most costeffective
and environmentally protective approach. Underwater regrading involves excavating the
shoal material with a digging bucket and moving it to adjacent deeper areas, entirely underwater.
The bucket would not break the water surface, thereby ensuring that DMMs potentially mixed-in
with the dredged sediment material would be relocated safely underwater away from construction
personnel. Similar regrading techniques, as alternatives to conventional dredging methods, have
been permitted and performed successfully at other Ports and USACE districts in California and
Oregon. 
Subsequent to pre-project sediment sampling, project boundaries for the regrading were revised to
exclude the area of elevated PCBs (to be addressed later). The total amount of material to be
regraded is very small, estimated at 280 cubic yards. Because the project is not using conventional
dredging methods, staff has been working with regulatory agencies and subject matter experts to
ensure that adverse environmental impacts will be mitigated. Ecology is requiring the work to be
performed under the Agreed Order and is included in the scope of this Order amendment. The y
also require the amendment to include steps to investigate sediment quality on and around the
project area. The funding for the regrading portion of this project has been approved in a previous
Commission action and the regrading action will be performed using an existing on-call
construction contract. The sediment investigation will require a new service agreement. 
PROJECT JUSTIFICATION AND DETAILS 
The T91 Site is under a RCRA permit and an Agreed Order which includes the Submerged Lands.
The current order states that "the Submerged Lands Area will be reevaluated by the agency as it
continues to monitor the site". Ecology has reevaluated the Submerged Lands Area based on the
recent sediment sample results and believes it is time to amend the Order to further investigate the
sediments. The sediment regrading is needed in order to remove an estimated 280 cubic yards of
shoaled material to ensure the -35' MLLW required minimum depth for cruise ships calling in the
east berth of Pier 91. Shoal material will be relocated to adjacent deeper areas using underwater
regrading methods.  Following regrading, sediments in the project site will be sampled and
analyzed. 
Project Objectives 
Perform the sediment regrading project to maintain required berthing depths for the Cruise
operations in a manner that will not adversely affect any future DMMs removal actions that
the USACE's FUDs would carry out in the future.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 1, 2015 
Page 4 of 7 
Investigate  the  site  history  and  identify  locations  that  warrant  additional
investigation/sampling to inform future sediment work 
Implement investigation of the sediment using a new service contract. 
Deliver project in a quality, cost-efficient manner and within schedule. 
Maximize cost recovery opportunities. 
Identify and consider community values and concerns and minimize construction impacts
to the community. 
Scope of Work 
The scope of work in the Order amendment would include: 
Implementation of the sediment regrading project, including relocation of approximately
280 CY of shoaled material located near the pier to deeper water. 
Preliminary research regarding sources of contamination to the T-91 sediments,
identification of available information on sediment quality, and development of a work
plan to investigate identified sediment contamination and performance of the work plan. 
Schedule 
1.  This Action: Obtain authorization to execute the Order amendment and to execute a
project specific services contract to perform the sediment investigation. 
2.  Perform the regrading project 1Q  2Q 2016 
3.  Implement the sampling once a contract is executed and the work plan is approved by
Ecology, expected by Q4 2016 
FINANCIAL IMPLICATIONS 
Terminal 91 Sediments Cleanup-up Lifecycle Project Estimate and Sources of Funding 
Previous Amounts Spent on Cleanup                      $102,000 
Cost Estimated Associated with work under the Agreed Order
amendment One                               $1,400,000 
Estimated Project Costs for ERL regrading and investigation       $1,502,000 
Estimated/Actual Sources of Funding: 
Past Amount Recovered (Settlement, Insurance, Grant)1               $0 
Committed Future Grant Funding2                           $0 
Port of Seattle3                                       $1,502,000 
Total Sources of Funding4                             $1,502,000 
Note 1: Amount already received. Staff will continue to seek additional recovery from insurance companies and other
responsible parties. 
Note 2: Staff is seeking Grant money related to this project

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 1, 2015 
Page 5 of 7 
Note 3: Remaining Port obligations if no other grants are received or funds obtained from insurance or other
responsible parties. 
Note 4: Cost estimate for the Agreed Order Amendment One includes the major construction contract for regrading,
soft costs and the investigation. Staff is actively seeking additional grant funding and additional recovery to help offset
these costs. This cost estimate does not include costs for the marine sediment portion of the site for a full remedial
investigation, feasibility study and cleanup. 
Cost Estimate Associated with the investigation work 
The actual cost for the investigation is expected to vary, depending on actual site conditions, and
any changed conditions or requirements established by the oversight agency (Ecology). However,
the current estimated cost range for the sediment investigation is approximately $900,000.
The estimated cost for the regrading work, including tax and contingency is to be under $500,000,
which was approved by the Commission on September 10, 2013, under the T-5 and T-91 
Maintenance Dredging project. 
Source of Funds 
The costs to implement the investigation were included in the Commission's 2016 Environmental
Remediation Liability (ERL) spending authorization and five-year plan. The ERL cost estimates
were also included in the 2015 plan of finance. Additional costs may be incurred if the historical
review identifies multiple areas requiring investigation or DMMs have to be addressed in the
sampling effort. Any additional investigation costs that may be required as the project moves
forward will be recorded as a liability and a non-operating expense in accordance with Port Policy
AC-9, Environmental Remediation Liability. These amounts will be reported annually to the
Commission via routine environmental remediation liability reports and spending authorization
requests. 
The Port's tax levy will pay the costs for the environmental investigation project that are not
ultimately covered by cost-sharing agreements, settlements, insurance, or other cost recovery
sources.  In addition, Port staff is pursuing additional grant funding from Ecology for the
investigation work. 
The source of funding for the regrading work is General Funds, and is included in the 2015 and
2016 Maritime Division Operating Budget. 
Potential Net Costs to the Port 
The cost summary table above presents a breakdown of all the paid, committed, and/or anticipated
total known costs and recoveries associated with the T-91 sediment investigation. As shown, the
Port cost is expected to be approximately $1,502,000. Staff is actively seeking grant funding and
additional recoveries to help offset this cost. This estimated cost does not include additional
investigation (Remedial Investigation, Feasibility Study) or cleanup if required for the marine
sediments. 
STRATEGIES AND OBJECTIVES 
In support of the Century Agenda strategy to be the greenest port in North America, this project
will accomplish environmental investigation of the Port's property, while assuring that other
responsible parties are paying their fair share. The sediment regrading project supports the asset
preservation objective and ensures the Port can maintain and grow the cruise business.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 1, 2015 
Page 6 of 7 
TRIPLE BOTTOM LINE 
State and federal laws require elimination of unacceptable environmental risks caused by the
presence of contaminants in soil, groundwater, and sediment.  From the perspective of the
surrounding communities and the customers that we serve, the Port's participation in site
remediation is the hallmark of responsible environmental stewardship.  Cleanup also returns
contaminated land to a more productive use. Regarding small business participation, the Office of
Social Responsibility (OSR) will provide analysis and recommend small business goals to be
included in the consulting contract. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1)  Do not enter into a new amendment to the Order to perform a historical
review and sampling of the T-91 sediments and to perform the sediment regrading project. 
Pros: 
Not entering into the Order amendment will delay spending. 
Cons: 
This alternative would result in the Port not being able to maintain the required water depth
at the cruise ship berth. 
This alternative could result in Ecology imposing the requirement for the sediment
investigation through a unilateral enforcement  order issued under the MTCA (and
incorporated into the RCRA permit). This is not the recommended alternative. 
Would not comply with Port's obligation to investigate the sediment portion of the site. 
Alternative 2)  Enter into an Agreed Order amendment for the sediment regrading portion
only.
Pros 
This would allow the Port to maintain the required water depth at the cruise ship berth. 
This approach would delay spending on sediment investigation 
Cons 
Ecology and the other agencies have indicated that they would not be willing to approve
the sediment regrading project unless the Port commits to the sediment investigation.
Alternative 3)  Enter into the Agreed Order amendment to perform a historical review and
sampling of the T-91 sediments, to perform the sediment regrading project; and to execute a
project specific contract for the sediment investigation. 
Pros 
Proceeding with this work ensures compliance and continued cooperation with Ecology 
Proceeding with this work would allow the Port to maintain adequate water depth at the
cruise terminal. 
Cons 
The investigation may lead to additional investigation and possible cleanup actions under
new order amendments. 
This is the recommended alternative.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 1, 2015 
Page 7 of 7 

ATTACHMENTS TO THIS REQUEST 
Agreed Order No. DE 8938 amendment 1 with the Washington State Department of Ecology 
Map of Site 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
December 1, 2014  Commission authorized a five-year spending plan of $64,088,000
for Environmental Remediation Liabilities and environmental remediation liability funds
for 2015 in the amount of $36,804,000, of which (a) $16,804,000 is forecast to be spent
in 2015 and (b) an amount estimated not to exceed $20,000,000 of the remaining funds
approved in the five-year plan will be obligated during 2015 to be spent in future years.
September 10, 2013  Commission authorized maintenance dredging at Terminal 5 and
Terminal 91 for the combined total of $4,800,000. 
March 27, 2012  Commission authorized the Chief Executive Officer to execute Agreed
Order No. DE 8938 with the Washington State Department of Ecology on the
implementation of a Cleanup Action Plan and to address contamination in the Upland
area of Terminal 91. 
May 4, 2010  Commission authorized the Chief Executive Officer to execute the 2010
agreed order with the Washington State Department of Ecology.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.