4i

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.       4i 
ACTION ITEM 
Date of Meeting    October 13, 2015 
DATE:    October 2, 2015 
TO:      Ted Fick, Chief Executive Officer 
FROM:   Bari Bookout, Northwest Seaport Alliance 
Anne Porter, Seaport Project Management 
SUBJECT:  Terminal 5 Berth Modernization Test Pile Program (CIP #C800132) 
Amount of This Request:             $0   Source of Funds:  General fund 
Est. Total Project Cost:        $230,000,000 
ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to execute a major public
works construction contract with the lowest responsible bidder for the Terminal 5 Berth
Modernization Test Pile Program, notwithstanding the low bid exceeding the engineer's estimate
by more than 10 percent.
SYNOPSIS 
The Commission authorized advertisement for bids for test pile installation as part of the design
of the Terminal 5 Berth Modernization project on July 14, 2015. However, when the four
contractor bids received were opened on October 1, 2015, the lowest responsive bid, from
Pacific Pile and Marine LP, exceeded the engineer's estimate by nearly 14%. This represents a
bid irregularity requiring further Commission action prior to contract award in accordance with
Section 4.2.3.4 of the General Delegation of Authority. The additional amount of $410,000,
including the resulting incremental increase in sales tax, construction contingency, and added
staff costs, can be covered by the remaining funds within the existing design funding
authorization of $10,000,000.
Port staff has carefully reviewed the test pile program scope in light of the increased bids and has
determined that the test pile program should continue as it remains critical to effective
management of the project. The requested action has been endorsed by the Northwest Seaport
Alliance leadership. 
BACKGROUND 
On June 3, 2014, the Port of Seattle Commission authorized design of the Terminal 5 Berth
Modernization project for an initial budget of $5,000,000. On July 14, 2015, the Commission
authorized additional design budget of $5,000,000, bringing the total project design budget up to

Template revised May 30, 2013.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 2, 2015 
Page 2 of 5 
a new total of $10,000,000, in addition to authorization to advertise for bids for the Terminal 5
test pile program. On September 11, 2015, the test pile installation contract was advertised for
construction bids with the intent to complete the in-water work during the latter part of the
allowed construction window that closes on February 15, 2016. A pre-bid meeting and site tour
was held on September 21, 2015, with several prime contractors in attendance. 
Four construction bids were received and opened on October 1, 2015, with Pacific Pile and
Marine LP identified as the apparent lowest responsive bidder with a bid of $2,374,955. The
Port's engineer's estimate for the project was $2,086,507. The difference between the engineer 's
estimate and the low bidder exceeds 10%, necessitating this Commission authorization request.
The remaining three bids received ranged from $2,392,000 to $3,977,150. Adding sales tax and
construction contingency to the difference between the engineer'sestimate and the low bidder
plus associated project management and construction management soft costs increases the
estimated costs by a total of $410,000. 
Port staff have reviewed the engineer's estimate and identified some factors that may have
contributed to the bid difference. One of the unique primary elements of this project is the Rapid
Load Testing of the piles, a procedure that has not been used previously in  this
region. Therefore, the coordination and performance of that work is new to the bidding
contractors.  In developing the engineer's estimate, contractors who have coordinated and
performed Rapid Load Test work in other parts of the country were used as resources for
developing estimated costs. The cost of the contractors' risk and uncertainty in performing this
work, which is new to them, was underestimated. The nature of this work as a test program
rather than production installation of piles also inherently involves additional coordination,
schedule restrictions, and work variability that are not typical of routine wharf construction,
which can lead to lower predictability of prices. 
In light of the number of bids received and the proximity of the two lowest bid prices, Port staff
believes the bid price received from Pacific Pile and Marine LP to be fair and reasonable. It is
believed that re-bidding would not result in any lower bid price. Staff also considered whether
any scope could be deleted or if all bids should be rejected, but has determined that all scope will
be critical to achieve the planned purposes of the test pile program and that the bids received
accurately reflect the cost of the work. Additional delay in the bidding process will jeopardize
the ability of the contractor to complete the work within the permitted time frame for in-water
work. 
PROJECT JUSTIFICATION AND DETAILS 
The test pile program has a potential estimated net savings of $5,000,000 to $7,000,000 in
construction costs. It will provide additional geotechnical information that may result in shorter
and fewer structural piles, improving habitat and fisheries and reducing noise from construction.
Additionally, information gathered from the program reduces design and construction
uncertainties and associated cost and schedule risks.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 2, 2015 
Page 3 of 5 
Project Objectives 
Project objectives have not changed since the July 2015 request and include ensuring the dock is
capable of handling two EEE class vessels by mid-2018 or 2019. The proposed capital
improvements will maintain the economic and job benefits from the cargo business at
Terminal 5. 
Scope of Work 
The scope of work remains unchanged and includes continued development of construction and
permitting documents, in addition to conducting a test pile program. 
Schedule 
Design and construction phases will vary for each element of the scope due to compliance
requirements, operational constraints, or availability of the terminal area. The team will evaluate
the scope of work to determine a cost-effective approach to efficiently implement the work. 
Lifecycle Cost and Savings 
Modernizing our existing assets readies them for current and future changes, extends their useful
service life, and preserves the economic vitality of our operations. The current T5 facility is
unable to generate revenue as a container terminal due to obsolete dock infrastructure. 
STRATEGIES AND OBJECTIVES 
This project will support the Port's Century Agenda Strategic Objective to grow Seaport annual
container volume to more than 3.5 million TEUs. 
TRIPLE BOTTOM LINE 
Modernizing Terminal 5 for larger vessels is key to the Port meeting its Century Agenda
strategies of increasing container volume in Seattle to 3.5 million TEUs and doubling the value
of exports from Seattle.  Environmental sustainability principles will be employed consistent
with Port policy. In addition, procedures set forth in the Port's Small Contractors and Suppliers
Program and other small business participation opportunities in support of the Century Agenda
goals or requirements will be established, accordingly. 
Economic Development 
Terminal 5 Modernization will allow the Port to keep pace with the evolution of vessel size in
the container shipping market. The improvements are critical to remain relevant as the shipping
industry changes.   The project represents an investment in effectively stewarding
competitiveness of the region for market share. 
Environmental Responsibility 
This project will provide the opportunity to apply environmental sustainability  principles
associated with the new improvements, including practices to avoid and minimize potential

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 2, 2015 
Page 4 of 5 
negative environmental effects.  Among anticipated benefits is the removal of the existing
creosote-treated timber piling. 
Community Benefits 
This project benefits the local community by preserving existing jobs and adding new living
wage jobs in construction and terminal operations. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1) Rebid test pile program.
Pros: 
Bidding climate and other factors may result in lower bids. 
Cons: 
Delay of test pile program likely results in missing in-water work window. 
Extending work into the 2016-2017 in-water work season will likely result in contractor
claims for additional mobilization and demobilization costs. 
This is not the recommended alternative. 
Alternative 2) Do not conduct test pile program. 
Pros: 
Would reduce estimated design costs by approximately $3,000,000.
Cons: 
Eliminates potential net savings from test pile program, which are in the $5 to $7 million
range. 
Eliminates the potential benefits to fisheries due to fewer piles. 
This is not the recommended alternative. 
Alternative 3) Proceed with action request to award construction contract for test pile
installation.
Pros: 
Realizes benefits of test pile program (fewer and shorter piles, reduced noise, improved
habitat and fisheries) and potential net savings in the $5 to $7 million range. 
Allows for completion in mid-2018 or 2019 if desired by prospective tenant and most
effectively supports Port strategy of speed to market. 
Cons: 
Moving forward with design without a committed tenant may result in project delays or
significant scope changes requested by future tenant that will result in additional design
work and expense. 
This is the recommended alternative.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 2, 2015 
Page 5 of 5 
ATTACHMENTS TO THIS REQUEST 
None 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
On July 14, 2015, Commission authorized request for continued design and test pile
program in the amount of $5,000,000 for a new total authorization of $10,000,000. 
On June 3, 2014, Commission authorized request for $5,000,000 to begin T-5 Facility
Modernization design and permitting. 
On May 13, 2014, briefed Commission on the T5 Facility Modernization project.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.