7c attach

Item Number:   7c _Report
Meeting Date: June 9, 2015


Commission Staff Brieng
Capital Improvement Projects
First Quarter Report 2015

This page intentionally left blank









ii  Port of Seattle 1Q 2015 Report

Port of Seattle
Capital Improvement Project Report
First Quarter 2015
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2015, the Port plans to invest $373,800,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 2 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, budget transfers, and cost growth of construction if it exceeds 10% of contract. The
report may include graphics that report project costs compared to authorization, construction costs (including change
orders (CO)) compared to the construction contract, location maps, and photographs. The Port implements a number
of different types of projects and not all information may be relevant to a specific project; as such, the reports may vary
in detail and content. Project types may range from construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (substantial completion). This section also includes "Project Status" illustrating at a
glance if the project is on schedule, and within budget, and the date Construction authorization received.
x  Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x  Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x  Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
x  Change Orders provides information on current quarter's COs and total project COs including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
x  Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x  Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x  Budget Transfers reports any transfers between authorized projects during the reporting period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports intend to meet the reporting requirements of Port of Seattle Commission Resolution 3605, as amended by
Resolution No. 3628, and the Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 1Q 2015 Report  1

Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C101107 ................160th GT Lot ..........................................................6 ...........
C102032 ...............Sanitary Sewer Pump Station Upgrade ................7 .........................................
C102112 ................Hennelly Service Tunnel Renewal Rep .................8 ...........
C102573 ...............Aireld Pavement Replacement ............................9 ...........
C800019 ...............Gate Utilities Improvement ...................................10 ..........
C800034 ...............North Expressway Relocation ..............................11 ..........
C800061 ...............Main Terminal South Low Voltage ........................12 ..........
C800107 ...............C4 UPS System Improvements ............................13 ........................................ 
C800168 ...............C60-C61 BHS Modications ................................14 ........................................
C800218 ...............Security Exit Lane Breach Control Phase I ..........15 ........................................ 
C800230 ...............Emergency Lighting Parking.................................16 .......... 
C800238 ...............Central Plant Pre-Conditioned Air ........................17 ..........
C800247 ...............Cargo 2 West Hardstand ......................................18 ........................................
C800251 ...............Vertical Conveyance Modernization.....................19 ..........
C800253 ...............Parking System Replacement ..............................20 ........................................
C800254 ...............Aircraft RON Parking Post Ofce Site..................21 ........................................
C800274 ...............8th Floor Weather Proong ..................................22 .......... 
C800324 ...............Long-Term Cell Phone Lot ................................. 23-24 .....................................
C800334 ...............Two new CTE Freight Elevators ...........................25 ........................................
C800335 ...............EGSE Electrical Charging Stations ................... 26-27 ....... ..............
C800368 ...............Refurbish Bag Claim Device 8..............................28 ..........
C800390 ...............Cargo 6 Enhancements ........................................29 ..........
C800406 ...............RW 16C/34C Reconstruction ...............................30 ..........
C800426 ...............FIS Improvement - Short Term .............................31 .......... ..............
C800451 ...............Doug Fox Site Improvement .................................32 .......... .............. ..................
C800464 ...............Fiber Infrastructure to Gate Backstands ..............33 ........................................
C800479 ...............Fire Station Electrical Upgrades ...........................34 ..........
C800483 ...............Aireld Pavement Program ..................................35 ..........
C800495 ...............Facility Monitoring System Renewal ....................36 ........................................
C800497 ...............Airport Wide Mechanical Controls System ..........37 ..........
C800543 ...............Replace PLBs at S7, S9, B4 .................................38 ..........
C800544 ...............NorthSTAR Program.............................................39 ..........
C800545 ...............NorthSTAR Main Terminal Improvements............40 ..........
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............41 ..........
C800549 ...............SSAT Interior Renovations ...................................42 ..........
C800550 ...............Concourse D Roof Replacement..........................43 ........................................


2  Port of Seattle 1Q 2015 Report

Aviation, cont.
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800551 ...............Grease Interceptor Augmentation ........................44 ........................................
C800555 ...............NorthSTAR Refurbish Baggage Systems ............45 ..........
C800556 ...............NorthSTAR North Satellite Lobbies ......................46 ..........
C800560 ...............MT Mezzanine Tenant Relocation ........................47 ..........
C800576 ...............Known Crew Member Employee Bypass .............48 ........................................
C800581 ...............Parking Garage Lights ..........................................49 ..........
C800583 ...............International Arrivals Facility ................................50 ..........
C800585 ...............Wi-Fi Enhancement for Ramp and Terminal ........51 ........................................
C800612 ...............Checked Baggage Recapitalization/Optimzation.52 ..........
C800615 ...............Second Floor Mezzanine Infra Upgrade ..............53 ........................................
C800629 ...............S1 Ramp ...............................................................54 ..........
C800637 ...............2014-15 Roof Replacement ..................................55 ........................................
C800638 ...............Dining and Retail Infrastructure Modernization ....56 ..........
C800642 ...............CCTV Camera Data Improvements ....................57 ..........
C800653 ...............Passenger Loading Bridge Renew .......................58 ..........
C800657 ...............Domestic Water Piping .........................................59 ..........
C800658 ...............Mech Energy Conservation ..................................60 ..........
C800659 ...............North Utility Tunnel Steam Pipe ...........................61 ..........
C800662 ...............S4 and S6 IC Connection .....................................62 ........................................
C800667 ...............Automated Passport Control ................................63 ..........
C800688 ...............Construction Logistics Expansion ........................64 ..........
C800692 ...............2016 Fuel System Modications...........................65 ........................................ 
Other Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................66 ........................................
C200042 ...............Highline Community College Noise Insulation .....67 ..........
C200048 ...............Home Insulation Retrot .......................................68 ..........
C200093 ...............Single Family Home Sound Insulation .................69 ..........
C800146 ...............RMU/Kiosk Concession Program ........................70 ........................................
C800154 ...............Tenant Reimbursement ........................................71 ..........



Port of Seattle 1Q 2015 Report  3

Maritime
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C102554-U00050 Terminal 46 Development....................................72 ..........
C102554-U00175. Container Dock Upgrade .....................................73 ..........
C102858 et al ....... Street Vacations T-5/18/105.................................74 ........................................
C800090 ...............Pier 34 Mooring Dolphins .....................................75 ..........
C800132 ...............T-5 Berth Modernization .......................................76 ..........
C800137 ...............FT C15 HVAC Improvements ...............................77 ........................................
C800160 ...............T-91 Lighting Upgrade ..........................................78 ........................................
C800314 ...............P69 Built-up Roof Replacement ...........................79 ..........
C800344 ...............FT C-2 Nordby Roof and HVAC ..........................80 ..........
C800356 ...............Shilshole Tenant Service Buildings .....................81 ..........
C800430 ...............T-91 Building C175 Roof Replacement ................82 ..........
C800439 ...............T-91 Substation Upgrades ....................................83 ..........
C800527 ...............FT Net Shed 9 Roof Replacement .......................84 ..........
C800546 ...............Argo Yard Truck Roadway ....................................85 ........................................
C800603 ...............T-46 Dock Rehabilitation ......................................86 ........................................
C800689 ...............T-115 Stormwater Separation ...............................87 ..........
C800691 ...............P69 Carpet Replacement .....................................88 ........................................
C800698 ...............P69 Beam Rehab .................................................89 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................90 ..........
E104324 ................Viaduct Construction Coordination ......................91 ..........
E104838................FT Net Shed Code Compliance ...........................92 ..........
E104840................T-5, T-18 and T-91 E. Maintenance Dredging ......93 ........................................
U00033 .................T-18 Maintenance Dredging .................................94 ..........
U00099 .................IHI Cranes Removal .............................................95 ........................................







4  Port of Seattle 1Q 2015 Report

Corporate
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800162 ...............ID Badge Replacement ........................................96 ........................................
C800323 ...............Network Switch Replacement ...............................97 ..........
C800436 ...............Terrminal 91 Visitor Management .........................98 ..........
C800519 ...............Contractor Data System Upgrade.........................99 ..........
C800520 ...............Computer Dispatch System Upgrade ..................100 .........
C800521 ...............Construction Document Management ................101 .......................................
C800586 ...............Radio Systems Upgrade......................................102 .........
C800693 ...............Noise Monitoring System Replacement ..............103 .........
C800694 ...............Expense Project Authorizations ..........................104 .........
C800728 ...............Parking System Replacement .............................105 .........
C800745 ...............HCM Upgrade ......................................................106 .........


Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date







Port of Seattle 1Q 2015 Report  5

FIRST QUARTER REPORT, 2015
So. 160th GT Lot Expansion 
Project: C101107              Improve lot drainage, underground    Project Status:
Budget: $3,559,000             existing overhead utility lines, fencing   Schedule: Within or Ahead
Phase: Design                 and landscaping. Renovation of       Budget: On or Under
Start: 2/1/2013                 layover facility is being re-evaluated.   Status Reset: 11/22/2013
Schedule Completion: 9/30/2015                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design for building renovation and site improvements is complete and Airport     4         3.6
Building Department has reviewed. Negotiations with utility companies to
underground existing overhead utility lines along S. 160th are in progress.        3
Schedule
2
1.0
Project scope is being re-evaluated, this may impact final product and schedule.   Dollars in Millions 1               0.4
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                               None at this time 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project scope is being reviewed. Complications in executing agreements with
utilities for underground lines are a schedule risk.
Budget Transfers
Amount       From         To
$0




AIRPORT 
6  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Sanitary Sewer Pump Station Upgrade 
Project: C102032             Upgrade the aging control systems of 22  Project Status:
Budget: $1,133,000           sanitary sewer lift stations.            Schedule: Delayed
Phase: Construction                                       Budget: On or Under
Start: 3/1/2013                                            Status Reset: N/A
Schedule Completion: 6/30/2015                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Nineteen (19) of the 22 panels have now been installed.                        1.1     1.1
1.2
1
Schedule
0.8                      0.7
The project is behind schedule due to changes to the control panels and         0.6
installation challenges. We are carefully proceeding forward in a manner that    Dollars in Millions 0.4                                                          minimizes risk during and after system switchover.                      0.2
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2015 Report  7

FIRST QUARTER REPORT, 2015
Service Tunnel Renewal/Replace 
Project: C102112              Project will seismically retrofit and    Project Status:
Budget: $27,586,000            structurally strengthen the airport      Schedule: Within or Ahead
Phase: Design                 Service Tunnel that resides between    Budget: On or Under
Start: 11/4/2012                the Main Terminal and Airport       Status Reset: 8/5/2014
Schedule Completion: 6/1/2018    Garage.                      (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
Commission authorized procurement of a design team. Design procurement is    30        27.6
nearly complete. Discovery and design work will begin immediately thereafter.   25
20
Schedule
15
Project is underway and on schedule.                              Dollars in Millions 10
4.6
5
0.1
Budget                                      0
Authorized Forecasted   Costs
The project is within budget.                                                     Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       None at this time 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
8  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Airfield Pavement Replacement 
Project: C102573              This is a multi-year program to      Project Status:
Budget: $24,602,213            replace distressed pavement and joint   Schedule: Within or Ahead
Phase: Design                 seal on the airfield.                Budget: On or Under
Start: 5/2/2010                                             Status Reset: 4/1/2014
Schedule Completion: 10/31/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Beneficial Occupancy was granted on October 22, 2014 for the 2014 contract.    30   27.9
24.6
Authorization for design on 2015 Apron Panel Replacement was received       25              20.8
November 11, 2014.                                      20
Schedule
15
10
Q3 2014 report showed "Delayed" due to the 2014 project which is in closeout.   Dollars in Millions 5
Current status identifies the 2015 contract scheduled to be advertised or          0
Authorized Forecasted   Costs
included in other work by change order in May 2015 with construction
Incurred
beginning in August 2015.
Construction Costs
Budget
The project forecast is within the approved budget.                        20  17.1       16.8
15
Change Order
10
Current Quarter     Project Total
Number of COs           0             13           Dollars in Millions  5
Amount of Cos           $0           $100,024                 0.1
0
Justification for COs: None at this time.                                  Initial Change Spent
Orders
Risks
None at this time.                                            Photo
Budget Transfers
Amount       From         To
$0


AIRPORT
Port of Seattle 1Q 2015 Report  9

FIRST QUARTER REPORT, 2015
Gate Utility improvements 
Project: C800019              Upgrade the Concourse B loading    Project Status:
Budget: $15,648,312           bridges to the standard 400Hz power.    Schedule: Within or Ahead
Phase: Design                 This will reduce aircraft emissions and   Budget: On or Under
Start: 6/28/2007                noise and improve energy efficiency    Status Reset: N/A
Schedule Completion: 10/16/2017  and save money for the airlines.       (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
South Satellite 400Hz construction and project closeout completed.            20
Final phase of CIP; Concourse B 400Hz project 30% design submitted 20 days             15.6
13.2
ahead of schedule. MUST, PEST, and START meetings completed with       15
positive feedback/comments from reviewers. 60% design submittal due 2nd      Dollars in Millions                9.2
10
quarter 2015
5
Schedule                                       0
Design for Concourse B 400Hz is on schedule.                          Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project is within design budget.
6
5.1          5.2
Change Order                                  5
Current Quarter     Project Total          4
Number of COs           2             46             3
Amount of COs         $14,369         $299,867         Dollars in Millions  2
1
Justification for COs: Changes to existing conditions - Substantial Completion             0.3
0
date for South Satellite 400Hz was extended by 40 calendar days in order to
Initial  Change  Spent
complete designer and owner requests, additional room for switchboard at               Orders
South Satellite requested by owner and required by state L &I.
Risks
None
Budget Transfers
Amount       From         To
$0


AIRPORT 
10  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
North Expressway Relocation 
Project: C800034             Reconstruct the Northern Airport      Project Status:
Budget: $102,564,300         Expressway, support the extension of    Schedule: Within or Ahead
Phase: Construction          light rail to the Airport, and construct    Budget: On or Under
Start: 7/1/2004                improvements to Wall 14.            Status Reset: 2/20/2014
Schedule Completion: 11/26/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Reconstruction of the Northern Airport Expressway and the light rail transit     $115.00
components are complete. The construction of the Wall 14 Improvements is          110.2
complete and beneficial occupancy was issued November 26, 2014. The      $110.00
replacement of a damaged power conduit on S 170th St is also complete. The   $105.00   Dollars in Millions           102.6   102.0
project is in closeout and the final contract payment is anticipated next quarter.
$100.00
Schedule                                      $95.00
Authorized Forecasted   Costs
The Wall 14 improvements and the replacement of the damaged power conduit
Incurred
on S 170th St are both complete.
Construction Costs
Budget
Project forecast is within the approved budget and authorization. The total     $120.00           107.8
99.4
budget for the Wall 14 Improvements is $1,529,000 and $120,000 for the      $100.00
replacement power conduit.                                   $80.00
$60.00
Change Order                                $40.00  Dollars in Millions
Current Quarter     Project Total        $20.00      8.3
Number of COs           2            239           $0.00
Initial  Change  Spent
Amount of Cos         ($52,759)        $8,329,600                Order
Justification for COs: Varying site conditions and disputes (liquidated
damages).                                           Photo
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0


AIRPORT
Port of Seattle 1Q 2015 Report  11

FIRST QUARTER REPORT, 2015
Main Terminal Low Voltage 
Project: C800061             Renewal and replacement of low      Project Status:
Budget: 20,730,000           voltage (600 volts and below) electrical   Schedule: Within or Ahead
Phase: Design               distribution equipment in the Main       Budget: On or Under
Start: 6/28/2007              Terminal.                      Status Reset: N/A
Schedule Completion: 7/31/2019                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Due to project deferral and the possibility of changes in site conditions and
25
building codes, the design phase changed from 100% to 0% complete.                   20.7
Commission re-approved the project in Q3 2014. Procured a design consultant    20
and began the detailed design process.                               15
10    8.1
Schedule                                      Dollars in Millions 5
0.7
The scope of work, schedule and final design budget finalized. The 100%
0
design documents scheduled for completion by the end of December 2015.         Authorized Forecasted  Costs
Incurred
Budget
The forecast is within the approved budget.                          Construction Costs
Not Applicable 
Change Order
Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
In order to reduce regulated materials management (RMM) abatement impacts
to the project schedule, the RMM contractor will be required to add additional
crews to complete work in a timely manner. This area is a 24/7/365 operation.
Sequencing of this work is critical and electrical power has to be maintained
without interruptions.
Budget Transfers
Amount       From         To
$0


AIRPORT 
12  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
C4 UPS System Improvement 
Project: C800107             Replace existing Uninterruptible Power  Project Status:
Budget: $4,555,238           Supply (UPS) System, including       Schedule: Delayed
Phase: Planning             batteries, with a new system located in   Budget: On or Under
Start: 4/14/2015               the Airport Combined Communications  Status Reset: 4/14/2015
Schedule Completion: 2/15/2017  and Command Center (C4).          (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Due to project deferral, changes to site conditions, and building codes, the       $5          4.6
design phase changed from 100% to 30% complete. Approval of the project
$4
Notebook received.                                        Dollars in Millions $3   2.3
Schedule                                      $2
Project reactivated. Preliminary Schedule shows Substantial Completion as      $1               0.5
February 2017.                                          $0
Authorized Forecasted   Costs
Incurred
Budget
New estimate has been developed based on new design concept.           Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total       Photo
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The C4 center is a 24/7/365 operation. Sequencing of this work is critical and
electrical power has to be maintained without interruptions.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2015 Report  13

FIRST QUARTER REPORT, 2015
C60 - C61 BHS Modifications 
Project: C800168             This work represents a critical        Project Status:
Budget: $11,084,991          component to providing improved       Schedule: Within or Ahead
Phase: Construction          operational baggage in-line screening at   Budget: On or Under
Start: 6/1/2012               the South end of the Airport and more    Status Reset: 4/14/2014
Schedule Completion: 6/30/2015  baggage make-up capacity for airlines.    (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Automatic Tag readers (ATR's) and upper level controls installation is
15
ongoing. The project team will be doing satisfactory acceptance testing on the         11.9
11.1
ATR's and upper level controls. High volume baggage testing completed
8.5
during the period. We are working with the contractor on enhanced reporting
10
for the airlines.                                                     Dollars in Millions 5
Schedule
0
Original scope of work was completed April 27, 2015. The additional EDS is       Authorized Forecasted  Costs
Incurred
expected to complete prior to Q3.
Budget                                    Construction Costs
The project forecast is within the approved budget and authorization.            6  5.2       5.0
5
Change Order                                  4
Current Quarter     Project Total          3
Number of COs           7             16             2
Amount of Cos         $120,634         $173,937          Dollars in Millions  1      0.2
0
Justification for COs: The change order issued was due to varying site
Initial  Change  Spent
conditions and added reporting                                          Orders
Risks
None
Budget Transfers
Amount       From         To
$0


AIRPORT 
14  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Security Exit Lane Breach Control Exit B  Phase II 
Project: C800218              Procure and extend new automated exit  Project Status:
Budget: $1,562,000            land breach control equipment at the      Schedule: Delayed
Phase: Design                 Concourse B exit.                   Budget: On or Under
Start: 3/1/2012                                               Status Reset: N/A
Schedule Completion: 6/30/2015                                (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Equipment received for post-construction work to convert the twin door lanes     2
to triple door lanes. Additional authorization received January 6, 2015.              1.6     1.5
Procure contract through Small Works Contracting. The design is 100%        1.5
complete and the next step is to have the consultant to provide contract         Dollars in Millions                 0.9
1
specifications for bidding.
0.5
Schedule                                       0
Construction delayed until September 2015 after the busy passenger summer       Authorized Forecasted  Costs
Incurred
season.
Budget                                    Construction Costs
Not Applicable 
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No major risks at this time
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2015 Report  15

FIRST QUARTER REPORT, 2015
Emergency Lighting - Parking 
Project: C800230             Provide electrical infrastructure for a    Project Status:
Budget: $2,683,179           new source of emergency power to feed   Schedule: Within or Ahead
Phase: Closeout              the parking garage emergency lighting    Budget: On or Under
Start: 7/24/2012              circuits and ensure that code required     Status Reset: N/A
Schedule Completion: 7/16/2014  level of egress illumination is provided   (Commission Construction Auth.)
for safety.
Significant Developments                             Budget/Costs Incurred
Received and accepted the Final Monitoring and Verification report.           5   4.7
Received and submitted As-builts to Engineering to archive.                      4
3
Schedule                                      Dollars in Millions        2.3    2.1
2
Construction contract is to be closed. Contractor O&M submittals have not
1
been accepted.
0
Authorized Forecasted   Costs
Budget
Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
2
Current Quarter     Project Total            1.7
1.5
Number of COs           0             0            1.5
Amount of Cos           $0             $0
1
Justification for COs: N/A                                       Dollars in Millions 0.5
Risks                                                 0.0
0
None                                          Initial Change Spent
Orders
Budget Transfers
Amount       From         To
Click here to enter text.




AIRPORT 
16  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Central Plan Pre-Conditioned Air 
Project: C800238             Provide a centralized pre-conditioned   Project Status:
Budget: $55,140,463          air (PC-Air) plant (PCAP), associated    Schedule: Within or Ahead
Phase: Construction          heating and cooling piping systems,     Budget: On or Under
Start: 6/15/2009               and jet bridge terminal air handling     Status Reset: 2/25/2014
Schedule Completion: 8/31/2013  units to serve airplanes with heating     (Commission Construction Auth.)
and cooling while at the gates.
Significant Developments                             Budget/Costs Incurred
The major-works Contractor's construction is complete. PC-Air is operating at
56    55.3     55.1
71 gates. Work on the three of the four remaining gates is complete. Waiting
for delivery of controls equipment for the remaining gate and will be complete    54
early 2Q 2015. Design to replace the chilled water insulation, anchor and       Dollars in Millions 52
guides on Concourse A, and the anchors and guides on Concourse B, C and                      50.6
South Satellite is on schedule.                                      50
48
Schedule
Authorized Forecasted   Costs
Three of the four gates completed in the first quarter of 2015. Completion of                      Incurred
the last gate delayed, waiting for replacement control valves. Completion
expected in 2Q 2015.                                      Construction Costs
Budget                                      40        36.6
35
The major works contract is complete. Work for completing the remaining four     30  27.0
gates and anchors and guides is within the budget.                         25
20
Change Order                                Dollars in Millions 15     9.9
10
Current Quarter     Project Total          5
Number of COs           0            230             0
Initial  Change  Spent
Amount of Cos           $0          $9,886,034                Orders
Justification for COs: None this quarter
Risks
None at this time
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 1Q 2015 Report  17

FIRST QUARTER REPORT, 2015
Cargo 2 West Cargo Hardstand 
Project: C800247             Enlarge the western cargo hardstand in the  Project Status:
Budget: $7,890,000           Cargo 2 area. Includes buyout of two      Schedule: Delayed
Phase: Construction          cargo buildings and tenant relocations;      Budget: On or Under
Start: 9/5/2012               relocation of FAA antenna, security gate,    Status Reset: 10/8/2013
Schedule Completion: 4/30/2015  and guard shack; and installation of 400Hz   (Commission Construction Auth.)
in-ground power.
Significant Developments                             Budget/Costs Incurred
Cargo 2 Hardstand pavement is complete. IWS Control Panel (DDC          15
12.5
connection) has been installed and E190 Security Guard Shelter construction
has been completed tested and is now active. Final work includes demolition of   10         7.9
existing E185 Security Guard Shelter and Gate E185 reconfiguration.                          6.4
5
Schedule                                      Dollars in Millions
Partial Beneficial Occupancy reached on August 11, 2014 with the completion     0
Authorized Forecasted   Costs
of the hardstand portion of the work. Completion expected by the end of the 2st
Incurred
Quarter 2015. Delay is due to long lead in procurement for IWS Controls in
addition to Building Department approval of new guard shelter. Final delay
Construction Costs
due to demolition and gate reconfiguration could not be completed until new
E185 Guard Shelter and Gate activation. Additional modification to the 400Hz     6
5.0
electrical vaults to address fall protection will be completed outside of the          5
4.1
contract schedule.                                              4
3
Budget                                      2
The project forecast is within the approved budget and authorization.          Dollars in Millions  1
0.0
0
Change Order                                   Initial Change Spent
Orders
Current Quarter     Project Total
Number of COs           3             5          Photo
Amount of Cos          $32,109          $34,521
Justification for COs: 1) Minor AOA Gate, Guard Shelter and electrical
modifications; 2) Minor Security Gate electronic modifications; 3) Minor
modifications to Secuity Guard Shelter.
Risks
None 
Budget Transfers
Amount       From         To
$0
AIRPORT
18  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Vertical Conveyance Modernization Program -
Aeronautical 
Project: C800251             Perform modernization on 9 existing    Project Status:
Budget: $24,556,408          elevators and 4 escalators: SSAF, MT-2,   Schedule: Within or Ahead
Phase: Construction          MT-3, MT-4, MT-5, MT-6, MT-7, SSB,   Budget: On or Under
Start: 10/25/2011             SSC. Install new elevators SSM and     Status Reset: 11/11/2013
Schedule Completion: 10/30/2016 SSN. Install cooling packages on 12     (Commission Construction Auth.)
existing hydraulic elevators throughout
Main Terminal.
Significant Developments                             Budget/Costs Incurred
Construction continued with the contractor working on first three elevators.
20
16.4
Schedule                                      15       13.2
Construction is underway with partial substantial completion of portions of the    10
first phase of construction in Q3 2015.                               Dollars in Millions                 4.8
5
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within the approved budget and construction is                         Incurred
underway. Project has returned budget upon deferral of second phase of work.
Construction Costs
Change Order
5   4.6
Current Quarter     Project Total
Number of COs           5             16             4
Amount of Cos          $15,872          $80,225            3
Justification for COs: Differing site conditions, sequencing of work, and        Dollars in Millions              1.8
2
administrative changes.
1
0.1
Risks                                           0
Initial  Change  Spent
Contractor is projecting missing delivery milestones and is in danger of failing            Orders
to complete work on time in 2016.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 1Q 2015 Report  19

FIRST QUARTER REPORT, 2015
Parking System Replacement 
Project: C800253              Replace the previous Parking Revenue  Project Status:
Budget: $5,577,364             Control System, which manages       Schedule: Delayed
Phase: Closeout                parking access and revenue collection   Budget: On or Under
Start: 4/6/2010                 in the Airport's Main Parking Garage.   Status Reset: 3/8/2011
Schedule Completion: 8/31/2012                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Scheidt & Bachmann (S&B) system is operational and exhibits accuracy     12
and availability rates above 99.99%. However, the Port continues working with       9.8
10
S&B to correct a limited number of outstanding system certification issues.       8
Ports' Legal and ICT departments are also involved.                     Dollars in Millions           5.6
6                   5.1
4
Schedule                                       2
The system is complete and in use. However, critical Payment Card Industry      0
Authorized Forecasted   Costs
(PCI) certification issues remain to be resolved prior to closing the project.
Incurred
Budget
Construction Costs
The project forecast is within the approved budget and authorization.         None this quarter 
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             9
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The Port is working with the contractor to address outstanding PCI and unique
transaction identifier issues.
Budget Transfers
Amount       From         To
$0



AIRPORT 
20  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Aircraft RON Parking USPS Site 
Project: C800254              Prepare the site for the construction of  Project Status:
Budget: $41,456,350            hardstands for use as Remain         Schedule: Delayed
Phase: Construction            Overnight (RON) parking of aircraft at  Budget: On or Under
Start: 8/26/2008                the Cargo 5 area.                Status Reset: 10/8/2013
Schedule Completion: 5/31/2015                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Hardstand construction is complete. New Security Gate E125 and related Guard   50   45.6
41.5
Shelter construction complete  waiting on Commissioning and Building
40                  34.7
Department approval and final electrical approval from Facilities and
30
Infrastructure.                                                 Dollars in Millions 20
Schedule                                      10
Hardstand completed and in use. Security Gate and Guard Shelter construction     0
Authorized Forecasted   Costs
completed. Complete final security testing and punch list items in second
Incurred
quarter 2015.
Construction Costs
Budget
27.8
The project forecast is within the approved budget and authorization.            30
24.4
25
Change Order                                 20
15
Current Quarter     Project Total
10
Number of COs           3             6           Dollars in Millions  5
Amount of Cos         $102,544         $154,861                 0.2
0
Justification for COs: 1) Modification to ramp lighting, security camera            Initial Change Spent
mountings, electrical and interior enhancements at E125 Guard Shelter; 2)               Orders
Modification of grading around building and height of soldier wall; 3)
Incorporation of Building Department revisions to E125 Guard Shelter.       Photo
Risks
A significant amount of contaminated soil at Cargo 5  contract bid quantity
was 13,500 total TNs, 21,500 TNs to date. Overrun managed through
construction contingency. E125 Guard Shelter security testing still needs to be
completed and need TSA approval before Guard Shelter is occupied.
Budget Transfers
Amount       From         To
$300,473         C800254         C800404

AIRPORT 
Port of Seattle 1Q 2015 Report  21

FIRST QUARTER REPORT, 2015
8th Floor Weatherproofing 
Project: C800274              Removal and replacement of the floor  Project Status:
Budget: $9,324,000             covering system on the eighth floor of   Schedule: Within or Ahead
Phase: Closeout                the STIA parking garage and of the     Budget: On or Under
Start: 3/23/2010                expansion joints and flashing.        Status Reset: 5/27/2014
Schedule Completion: 7/31/2014                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Ordered PCL, the Port's contractor, to install deck coating in areas where        15   13.1
defective coating had been identified and removed. PCL completed the work
but it is now the subject of a claim action by the contractor. Port staff                      9.3
10                  8.2
participated in a Level I claim resolution meeting with PCL. The portions of the
project not impacted by the claim are in the closeout process.                Dollars in Millions 5
Schedule                                       0
Authorized Forecasted   Costs
Project complete
Incurred
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
7   6.1         6.1
Change Order                                  6
5
Current Quarter     Project Total          4
Number of COs           0             30             3
Amount of Cos           $0           $84,555          Dollars in Millions  2
1
Justification for COs: None this quarter                                        0.1
0
Initial  Change  Spent
Risks                                                Orders
Contractor claim
Budget Transfers
Amount       From         To
$0



AIRPORT 
22  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Long-Term Cell Phone Lot 
Project: C800324              Construct a new cell phone waiting lot  Project Status:
Budget: $3,293,100            to replace the existing lot that is being   Schedule: Delayed
Phase: Construction            displaced, including permanent access   Budget: On or Under
Start: 12/31/2012               control on South 170th Street.         Status Reset: 5/6/2014
Schedule Completion: 4/1/2014                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction of the Cell Phone Lot and interim traffic signal under the first       6          5.2
phase of the project is complete. Staff has coordinated with the City of SeaTac     5
and determined that a traffic signal, and associated roadway improvements, is     4   3.1
the likely permanent access solution. Given the uncertainty of scope and timing    3               2.5
of future development associated with the Sustainable Airport Master Plan,       2
staff is continuing to evaluate options in order to minimize the overall          Dollars in Millions 1
investment.                                               0
Authorized Forecasted   Costs
Incurred
Schedule
Expect a recommendation on the permanent traffic control solution considering
Construction Costs
the scope and timing of future development in Q4 2015.
0.8                     0.7
0.7
Budget
0.6
The current authorized budget for the Cell Phone Lot is $2,650,100. Additional
authorization approved in Q2 to maintain the interim traffic signal and in        Dollars in Millions 0.4
support of the recommended solution by year-end. The total budget forecast is
0.2             0.2
at $5,200,000, which includes the permanent access solution.
0
Change Order                                    Initial  Change  Spent
Orders
Current Quarter     Project Total
Number of COs           1             5          Photo
Amount of Cos          $900          $151,305
Justification for COs: Three-month time extension.
Risks
Displacement of completed improvements by future development in 5-10 years.
Continued congestion and complaints during summer months until the
permanent access solution is implemented. Completion of the permanent
access solution improvements to satisfy State Environmental Protection Agency
and roadway standard requirements.


Port of Seattle 1Q 2015 Report  23

Budget Transfers
Amount       From         To
$0














AIRPORT
24  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Two New CTE Freight Elevators 
Project: C800334             Provide two new freight elevators to    Project Status:
Budget: $8,315,100         support concession operations in the     Schedule: Delayed
Phase: Construction          Central Terminal/Pacific Marketplace.     Budget: On or Under
Start: 8/5/2011                                            Status Reset: N/A
Schedule Completion: 11/19/2014                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction is complete. Delivered As-Builts and project is in the closeout
8.5     8.3
process. 
8           7.8
Schedule                                      Dollars in Millions             7.4
7.5
Construction complete
7
Budget                                     6.5
Authorized Forecasted   Costs
The project forecast is within approved budget and authorization.                            Incurred
Change Order                               Construction Costs
Current Quarter     Project Total
5   4.3         4.5
Number of COs           5             41
Amount of Cos          $29,562         $314,638           4
Justification for COs: Differing site conditions and code compliance             3
2
Risks                                         Dollars in Millions  1     0.3
No new risks identified this quarter.
0
Initial  Change  Spent
Budget Transfers                                        Orders
Amount       From         To
$0                                     Photo




AIRPORT 
Port of Seattle 1Q 2015 Report  25

FIRST QUARTER REPORT, 2015
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations 
Project: C800335             Airport-wide electrical charging system Project Status:
Budget: $30,700,000          for electrical ground support equipment   Schedule: Delayed
Phase: Construction          at the Concourses and the North and     Budget: On or Under
Start: 10/26/2010              South Satellites.                  Status Reset: 10/23/2012
Schedule Completion: 6/30/2017                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
EGSE Phase 1 Project: Major contract completion and closeout is underway.     40
Test data collection and historical reporting. Record drawings are completed.               30.7
30    25.7
EGSE Phase 2 Project: Complete final design service directive once Sole
Source Competition Waiver is approved that will allow use of PosiCharge       20              15.4
Chargers for this Phase of the EGSE Program.
10
FAA, via the VALE grant process, has awarded the Port of Seattle a total of      Dollars in Millions
$5,500,000 for the EGSE Charger Phase 2 Project.                      0
Authorized Forecasted   Costs
Washington State Department of Revenue has approved sales tax exemption for                 Incurred
the construction phase of the EGSE Charger Phase 2 Project.
Construction Costs
Schedule
5
Phase 1- Record Drawings received and archived 3/15.                               4.0
4   3.6
Phase 2- Construction scheduled for late -2017.
3
Budget                                      2
The project forecast is within the approved budget. Request the remaining       Dollars in Millions         0.8
1
authorization for the construction funding and authority to advertise for
0
construction when the design and bid documents are completed for EGSE           Initial Change Spent
Charger Phase 2 Project.                                               Orders
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             56
Amount of Cos           $0           $804,166
Justification for COs: None this quarter
Risks
Coordinate with other airfield projects and Airline Gate Realignment program.
Budget and schedule may affect project implementation and completion of the
EGSE Phase 2 Project.


26  Port of Seattle 1Q 2015 Report

Budget Transfers
Amount       From         To
$0
Cost Growth During Construction:
Airline Realignment contributed to cost increase; varying site conditions related
to equipment installation; scope change for providing back-up power to
concourse D.












AIRPORT
Port of Seattle 1Q 2015 Report  27

FIRST QUARTER REPORT, 2015
Refurbish Bag Claim Device 
Project: C800368             Refurbish Claim Device 8 and replace   Project Status:
Budget: $303,730            the current door to a more secure type.    Schedule: Within or Ahead
Phase: Closeout                                            Budget: On or Under
Start: 6/24/2014                                           Status Reset: N/A
Schedule Completion: 11/24/2014                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Completed the project early and turned back over to Operations.             0.4
0.3
Schedule                                      0.3
The Project is on schedule and completed.                           Dollars in Millions           0.2     0.2
0.2
Budget                                     0.1
The forecast is within the approved budget and authorization.                0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos           $0             $0
Justification for COs: N/A                                      Photo
Risks
None
Budget Transfers
Amount       From         To
$0




AIRPORT 
28  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Cargo 6 Enhancements 
Project: C800390             Enlarge the Cargo 6 off-gate hardstand  Project Status:
Budget: $6,428,000           to allow simultaneous nose-loading of    Schedule: Delayed
Phase: Construction          wide-body freight aircraft as well as     Budget: On or Under
Start: 9/25/2012               provide fuel hydrant and ground power   Status Reset: 10/8/2013
Schedule Completion: 6/30/2015   capabilities.                    (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Cargo 6 Enhancements combined with Cargo 2, 5 and 6 Panel Replacement as    8
a single construction contract was successfully bid and awarded. Partial             6.5     6.4
occupancy granted when positions 1, 2 and 3 were turned over for beneficial      6
use the week of December 22, 2014.                                             3.8
4
Schedule                                      Dollars in Millions 2
Construction of the Cargo 6 hardstand enhancements began in the 3rd quarter      0
Authorized Forecasted   Costs
2014. Completion delayed to the end of the 2nd quarter due to Fuel Hydrant
Incurred
System design issues, long lead procurement items, and electric connection
design changes. New Fuel System has been connected and flushed. Permanent
Construction Costs
electrical connections scheduled for May 9th along with final electrical settings
for the fuel system. Additional modification to the 400Hz electrical vaults to       4  3.7
address fall protection will be completed outside of the contract.                            2.9
3
Budget                                      2
The project forecast is within the approved budget and authorization.
1   Dollars in Millions           0.5
Change Order                                  0
Initial  Change  Spent
Current Quarter     Project Total               Orders
Number of COs           3             5
Amount of Cos         $317,426         $455,000        Photo
Justification for COs: 1). Modify fuel system control valves; 2) Modification
to Fuel System surge suppression; 3) Provide, install and program additional
emergency fuel shut off switches for fuel system; Provide and install an IWS
run.
Risks
None
Budget Transfers
Amount       From         To
$0
AIRPORT
Port of Seattle 1Q 2015 Report  29

FIRST QUARTER REPORT, 2015
RW16C/34C Design and Reconstruction 
Project: C800406              Produce final design and reconstruct   Project Status:
Budget: $113,095,000           the existing RW 16C/34C in its       Schedule: Within or Ahead
Phase: Construction            existing location, replace TW C and    Budget: On or Under
Start: 5/4/2010                 N, reconfigure TWs H and J, install    Status Reset: 12/2/2014
Schedule Completion: 8/31/2016    FOD detection equipment, and install   (Commission Construction Auth.)
LED lighting system.
Significant Developments                         Budget/Costs Incurred
Project advertised in December 2014 and bids opened in January 2015.              113.1
120   110.2
Contract executed with joint venture of Scarsella/Acme in March        100
2015. FAA contracts to address impacts to their navigational aids and     80
fiber optic transmission system are underway. Design started for the SR   60
518 Interchange Restoration project used as a haul route for the runway    Dollars in Millions 40
reconstruction.                                          20               5.1
0
Schedule                                    Authorized Forecasted  Costs
Incurred
The project is on schedule. Runway closure occurred in May 2015 as
planned. Plan to reopen the runway in Q4 2015.
Construction Costs
Budget
70
57.3
There was a Capital increase of approximately $7,000,000 and a          60
$3,200,000 Expense increase.                               50
40
Change Order
30
20
Current Quarter     Project Total     Dollars in Millions 10     0.0  0.0
Number of COs          0            0          0
Initial  Change  Spent
Amount of Cos          $0            $0
Orders
Justification for COs: N/A
Photo
Risks
At the SR 518 Interchange, local agencies have expressed a desire for
changes. These changes are not part of the Port's commitment to
WSDOT for restoration, and require funding and agreement between
multiple agencies. 
Budget Transfers
Amount       From        To
$0

AIRPORT 
30  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Federal Inspection Services Short Term
Improvements 
Project: C800426             Short Term Improvements to the      Project Status:
Budget: $1,912,000           Federal Inspection Service area at S.     Schedule: Delayed
Phase: Construction          Satellite to improve through put and     Budget: On or Under
Start: 4/1/2012               conditions for passengers waiting in the   Status Reset: 12/10/2013
Schedule Completion: 8/8/2014   International Corridor prior to Primary    (Commission Construction Auth.)
Inspection.
Budget/Costs Incurred
Significant Developments
Major Contract work is complete. Project completed adjacent to the wall panel    2.5
1.9       1.9
replacements for visual continuity.                                  2
1.6
Schedule
Adjacent wall panel replacements are extending project closeout but do not
impact project beneficial use.                                     Dollars in Millions 1.510.5
0
Authorized Forecasted   Costs
Budget                                                Incurred
The project forecast is within the increased, approved budget and authorization.
Construction Costs
Change Order
0.7   0.6          0.6
Current Quarter     Project Total         0.6
Number of COs           4             7            0.5
Amount of Cos          $24,699          $56,123           0.4
Justification for COs: Include delays for late flight activity and varying site
0.3
0.2
conditions.                                                 Dollars in Millions 0.1       0.1
0
Risks                                             Initial Change Spent
Orders
None
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2015 Report  31

FIRST QUARTER REPORT, 2015
Doug Fox Lot Service Upgrades 
Project: C800451              Construct a new drainage system,     Project Status:
Budget: $6,909,000            asphalt resurfacing, improved lot       Schedule: Delayed
Phase: Construction            lighting, new building, and road       Budget: Forecast Overrun
Start: 2/29/2012                signage to improve lot appearance,     Status Reset: 10/8/2013
Schedule Completion: 2/27/2015   function, and revenue generation .     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission authorized completion of the project in January. Overall project         6.9     6.9
$7.00
construction is now complete and beneficial occupancy achieved on February
27, 2015. The Port received two protests (claims) from the contractor totaling   $6.50
$266,917. Port Construction Services to complete the two minor items of work                  5.9
$6.00
remaining that support tenant operation.
$5.50  Dollars in Millions
Schedule                                     $5.00
Authorized Forecasted   Costs
The overall project delayed with project beneficial occupancy occurring on
Incurred
February 27, 2015. 
Construction Costs
Budget
The original budget revised by the January Commission action forecasted for       5
4.0              4.0
completion, including the resolution of the two claims, within the revised          4
budget.
3
2
Change Order                                Dollars in Millions 1
Current Quarter     Project Total                 0.1
Number of COs           9             33             0
Initial    Change    Spent
Amount of Cos         ($99,688)         $59,931                   Orders
Justification for COs: Changes related to errors and omissions (scope gap),
varying site conditions (unknown utilities), tenant requested changes, and      Photo
regulatory requirements (egress lighting).
Risks
Project is complete  no risks identified.
Budget Transfers
Amount       From         To
$0


AIRPORT 
32  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Fiber Infrastructure to Gate Backstands 
Project: C800464             Extend airport provided           Project Status:
Budget: $3,195,000           communications infrastructure to       Schedule: Delayed
Phase: Design               additional gates, gate information       Budget: On or Under
Start: 7/9/2013                displays to all gates and Wi-Fi antennas  Status Reset: 5/26/2015
Schedule Completion: 6/1/2016   throughout Concourses A and B.       (Commission Construction Auth.)
Significant Developments
100% Design complete. Investment Committee approved additional budget.    Budget/Costs Incurred
2.5             2.3
Schedule
2
Schedule affected by design issues uncovered at 90% Review and procurement
of a Wi-Fi designer.                                          Dollars in Millions 1.51   0.8
0.4
Budget                                     0.5
0
The project cost estimate at 100% Design approved by the Investment
Authorized Forecasted   Costs
Committee.                                                       Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Bid may come in high during the contractor procurement process. This risk is
mitigated by evaluating the cost estimate.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2015 Report  33

FIRST QUARTER REPORT, 2015
Feeder 101 Taps Replacement/Fire Station
Electric Upgrades 
Project: C800479              Replace the existing 208V transformer  Project Status:
Budget: $4,775,400             and 12.47 KV feeder, and add a 500    Schedule: Within or Ahead
Phase: Construction            KVA generator and a 1000KVA       Budget: On or Under
Start: 4/1/2013                 transformer. Replace the electrical     Status Reset: 7/1/2014
Schedule Completion: 10/31/2016  feeds to 13 locations along Air Cargo   (Commission Construction Auth.)
Road. Also, replace the electrical
transformer and associated switchgear
for Air Cargo #4.
Significant Developments                             Budget/Costs Incurred
The Contractor completed pre-construction submittals; however, they lost key     6
members of the project team prior to starting construction. They submitted on a        4.8     4.8
5
new project team.                                          Dollars in Millions 4
3
Schedule
2
0.9
The Contractor provided a recovery plan. Their plan recovers the two months     1
they lost. Substantial completion still scheduled for Q3 2016.                0
Authorized Forecasted   Costs
Incurred
Budget
The project is on budget.                                      Construction Costs
Change Order                                 2.5  2.3
Current Quarter     Project Total          2
Number of COs           0             0            1.5
Amount of Cos           $0             $0             1
Justification for COs: N/A                                       Dollars in Millions 0.5
0.0    0.0
0
Risks                                             Initial Change Spent
Orders
Unplanned electrical shut downs could affect the schedule.
The current schedule is aggressive. We will monitor progress carefully.
Budget Transfers
Amount       From         To
$0


AIRPORT 
34  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Airfield Pavement Program 
Project: C800483               This is a multi-year program to    Project Status:
Budget: $32,500,000            replace distressed pavement and     Schedule: Within or Ahead
Phase: Design                  joint seal on the airfield starting in    Budget: On or Under
Start: 5/5/2011                  2016 through 2020.             Status Reset: 2/24/2015
Schedule Completion: 6/30/2021                             (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
Scope for 2016 work is under way. Design expected to begin in 2nd Quarter.
40000          32,500.
0
Schedule                                     30000
Projects will occur annually through 2020.
20000
Budget                                    10000 Dollars in Millions    0.2        0.1
Within budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total
Construction Costs
Number of COs           0             0
None at this time 
Amount of Cos           $0             $0
Risks
None at this time
Budget Transfers
Amount       From         To
$0





AIRPORT 
Port of Seattle 1Q 2015 Report  35

FIRST QUARTER REPORT, 2015
Facility Monitoring System Renewal 
Project: C800495             Provide a system upgrade that will allow Project Status:
Budget: $3,423,500           the system to maintain and expand       Schedule: Delayed
Phase: Construction          monitoring of critical systems such as    Budget: On or Under
Start: 10/23/2011             elevators, escalators, moving walks,     Status Reset: 12/10/2013
Schedule Completion: 4/11/2015  passenger boarding bridges and baggage  (Commission Construction Auth.)
systems.
Significant Developments                             Budget/Costs Incurred
Kolkay has been on site performing work throughout the Concourses.          4   3.4    3.4
Schedule                                       3
Project completed in Q2 2015                                   2              1.7
Budget                                     Dollars in Millions 1
The forecast is within the approved budget and authorization.                0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           1             2
Amount of Cos          -$1,020          -$1,020
0.4
Justification for COs: Change orders were due to errors and omission, varying         0.3
site conditions, and scope change. Change order No. 1 was a credit to the Port.                     0.3
0.3
0.2
Risks
None identified at this time.                                       Dollars in Millions 0.1          0.0
0
Budget Transfers
Initial    Change     Spent
Amount       From         To        -0.1     Orders
$0




AIRPORT 
36  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Airportwide Mechanical Controls System 
Project: C800497             Upgrade the Mechanical Control System Project Status:
Budget: $3,500,000           for Concourse A at the Airport. This     Schedule: Within or Ahead
Phase: Design               includes adding a wireless connection to   Budget: On or Under
Start: 5/1/2013               the Logistics area to the south of the     Status Reset: 12/9/2014
Schedule Completion: 3/11/2016  Airport.                       (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Ready to bid documents submitted to the Central Procurement Office.          4   3.5    3.5
Schedule                                          3
The project schedule was updated to reflect the delivery time for system        Dollars in Millions 2
components. Bid date set for June 6, 2015.
1
0.2
Budget                                      0
Authorized Forecasted   Costs
The budget increased to $3,500,000 with the added scope.                                Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Unplanned electrical shut downs could affect the project schedule increased
control component costs. An allowance added to the estimate.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2015 Report  37

FIRST QUARTER REPORT, 2015
Replace PLBs at S7, S9 and B4 
Project: C800543             Replace the Passenger Loading Bridges  Project Status:
Budget: $2,950,000           at S7 and S9 and install a new bridge at   Schedule: Within or Ahead
Phase: Construction          B4                           Budget: On or Under
Start: 12/21/2014                                          Status Reset: 1/21/2014
Schedule Completion: 12/31/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
All three gates are operational. PC Air installation on the new B4 gate is         3   3.0     3.0
scheduled to be completed during 1Q 2015.                          2.9
Schedule                                      Dollars in Millions 2.82.7            2.6
Project is on schedule.                                          2.6
2.5
Budget                                     2.4
Authorized Forecasted   Costs
No issues                                                             Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None at this time
Budget Transfers
Amount       From         To
$0




AIRPORT 
38  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
NorthSTAR Program 
Project: C800544             Includes programmatic project        Project Status:
Budget: $18,764,150          management and project controls costs    Schedule: Within or Ahead
Phase: Design               for the NorthSTAR program; consisting   Budget: On or Under
Start: 4/5/2012               of 5 capital projects that represent a      Status Reset: N/A
Schedule Completion: 7/27/2020  unique partnership between the Port and   (Commission Construction Auth.)
Alaska Airlines.
Significant Developments                             Budget/Costs Incurred
Updated the Communication Plan, Organization Charts, Roles and           20        18.8
Responsibilities matrix. Created and implemented NorthSTAR programmatic
"Dashboard" on the Project SharePoint site.                            15
Schedule                                          Dollars in Millions 10
5    3.6             3.0
Continue programmatic linkage coordination to assure airport-wide gate
availability is not compromised during construction.                      0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is inclusive of Programmatic Management Reserve and is   Construction Costs
within the approved budget. Transferred $1.8M from Management Reserve to   Not Applicable 
C800547  Concourse C Vertical Circulation.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Communication and coordination across multiple teams and stakeholders along
with identification/monitoring of all "linked" Capital projects outside of
NorthStar.
Budget Transfers
Amount       From         To
$1,835,850         C800554         C800547


AIRPORT 
Port of Seattle 1Q 2015 Report  39

FIRST QUARTER REPORT, 2015
NorthSTAR Main Terminal Improvements 
Project: C800545             Renovate the North Main Terminal    Project Status:
Budget: $29,200,000          security checkpoint, curbside and       Schedule: Within or Ahead
Phase: Design               ticketing lobby areas incorporate self-    Budget: On or Under
Start: 12/3/2013              operated technologies and improve      Status Reset: N/A
Schedule Completion: 11/29/2018 aesthetics.                      (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Began passenger check-in processing, time modeling and checkpoint          40
distribution study.                                                         29.2
30
Schedule
20
Project is continuing on track with passenger forecasts for sizing of checkpoint    Dollars in Millions 10
and alternatives for passenger processing, circulation and checkpoint               1.5           0.2
configuration.                                                0
Authorized Forecasted   Costs
Incurred
Budget
Project forecast is within the approved budget. Commission Authorization for   Construction Costs
construction funding and authority to advertise for construction is anticipated    Not Applicable 
Q1 2017, when the bid documents are completed.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project scope definition could increase scope and budget.
Budget Transfers
Amount       From         To
$0



AIRPORT 
40  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
NorthSTAR Concourse C Vertical Circulation 
Project: C800547              Construct exterior, weather protected  Project Status:
Budget: $17,938,950            sloped walkways with elevators at      Schedule: Within or Ahead
Phase: Construction            Gates C2/4, C10/12, and C14 to       Budget: On or Under
Start: 11/6/2012                provide enhanced access from        Status Reset: 10/22/2013
Schedule Completion: 6/17/2015   concourse to aircraft ramp for        (Commission Construction Auth.)
Alaska/Horizon regional operations.
Significant Developments                             Budget/Costs Incurred
Beneficial Occupancy for Sloped Walkways occurred on schedule.           25
19.3
20           17.9
Schedule
Dollars in Millions 15                      11.6
Construction effort proceeded as planned for sloped walkways. Delay in
10
completion of elevators was due to the workforce availability in the elevator
industry.                                                    5
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project is within approved budget. $1.8M out of the $3.2M previously
transferred to the Program Reserve was returned to complete current effort.     Construction Costs
Change Order                                 10  8.7
Current Quarter     Project Total          8
6.5
Number of COs           8             28             6
Amount of Cos         $156,446         $710,968           4
Justification for COs: Overtime Premium; Panel Joint sealant; Expansion Joint    Dollars in Millions  2       0.7
mods and Replace storefront glazing system.
0
Initial  Change  Spent
Risks                                                Orders
Further delays in Elevator completion.
Budget Transfers
Amount       From         To
$1,835,850         C800544         C800547



AIRPORT 
Port of Seattle 1Q 2015 Report  41

FIRST QUARTER REPORT, 2015
SSAT Interior Renovations 
Project: C800549             Modify the mezzanine and concourse   Project Status:
Budget: $5,167,000           levels of the South Satellite to improve   Schedule: Within or Ahead
Phase: Construction          the passenger experience.           Budget: On or Under
Start: 11/4/2012                                           Status Reset: 12/9/2014
Schedule Completion: 6/1/2016                              (Commission Construction Auth.)
Significant Developments
NTP issued for Phase One Carpet Replacement on April 16. Phase One       Budget/Costs Incurred
construction will be complete by end of May.                          6
5.0
5
Schedule                                       4
On schedule                                           3
1.9
2
Budget                                     Dollars in Millions 1           0.3
0
Within budget
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
42  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Concourse D Roof Replacement 
Project: C800550              Remove and replace the roofing      Project Status:
Budget: $3,946,000             systems on Concourse D of the        Schedule: Delayed
Phase: Construction            Airport; install ladders, stairs and fall   Budget: On or Under
Start: 7/1/2013                 protection on the penthouse sections;    Status Reset: N/A
Schedule Completion: 11/24/2014  and make repairs and where required,   (Commission Construction Auth.)
replacements to the KalWall window
system.
Significant Developments                             Budget/Costs Incurred
All construction on this project is complete.                            3.6
3.4
3.4
Schedule                                              3.2
Substantial completion reached in January 2015.                       Dollars in Millions 3.2
3                   2.9
This will be the final report.
2.8
Budget                                     2.6
Authorized Forecasted   Costs
The project is within the approved budget.                                           Incurred
Change Order                               Construction Costs
Current Quarter     Project Total
3   2.75
Number of COs           0             5
2.5
Amount of Cos           $0           $47,910                     1.86
2
Justification for COs: None this quarter                              Dollars in Millions 1.5
1
Risks                                          0.5
0.05
None at this time                                               0
Initial  Change  Spent
Orders
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2015 Report  43

FIRST QUARTER REPORT, 2015
Grease Interceptor Augmentation 
Project: C800551             Install one underground 9,000 gallon   Project Status:
Budget: $1,484,200           grease interceptor and one 6,000 gallon   Schedule: Delayed
Phase: Permitting            above ground interceptor to service the   Budget: On or Under
Start: 5/1/2013                South Satellite, as well as hooking up    Status Reset: N/A
Schedule Completion: 3/1/2016   an existing interceptor to concessions at  (Commission Construction Auth.)
Concourse C.
Significant Developments                             Budget/Costs Incurred
Project advertised and bids received. Low bid 40% above engineer's estimate.         1.5     1.5
1.6
Decision made to reject all bids, redesign utilizing an above ground interceptor    1.4
1.2
in one of the locations to avoid conflict with the S1 ramp project and rebid.      Dollars in Millions 1
Revised design is complete and being reviewed by Airport Building
0.8
Department for permit. Rebid project this summer and construction will begin     0.6
0.4
0.4
in September to avoid disrupting operations during the summer peak.
0.2
0
Schedule                                        Authorized Forecasted  Costs
Incurred
Unacceptable bids and subsequent design revision has caused project schedule
to slip.                                                           Construction Costs
Not Applicable 
Budget
The project forecast is within the approved budget. 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Construction impacts Delta Operations at S. Satellite.
Budget Transfers
Amount       From         To
$75,000         C800551         C800547


AIRPORT 
44  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
NorthSTAR Refurbish Baggage Systems 
Project: C800555             Refurbish existing baggage systems in   Project Status:
Budget: $20,002,500          support of AAG operation at North      Schedule: Within or Ahead
Phase: Construction          Satellite and Concourse D. The work    Budget: On or Under
Start: 11/6/2012              will extend the service life of part of the   Status Reset: 9/24/2013
Schedule Completion: 6/15/2015  C92 systems, C88 North Satellite       (Commission Construction Auth.)
systems, and C88 tunnel systems.
Significant Developments                             Budget/Costs Incurred
C92 system is commissioned and operating. C88 system began operating with    25   22.0    21.7
limited capacity and schedule on March 15, 2015 while construction continues    20
until commissioning of entire system is complete. Maintenance access to C88    Dollars in Millions 15               12.4
conveyor systems and Port staff training is in progress.
10
Schedule                                       5
0
Project completion slipped one month to address added scope from BSO/MCP
Authorized Forecasted   Costs
relocation and construction phasing. Change orders executed to mitigate                       Incurred
schedule risk.
Construction Costs
Budget
14
The project forecast is within the approved budget.                           11.8
12
9.5
10
Change Order                                  8
Current Quarter     Project Total          6
4
Number of COs          10            22           Dollars in Millions       1.4
2
Amount of Cos         $656,211        $1,437,661
0
Justification for COs: Revised Construction Phasing & Acceleration; C1 ATR        Initial Change Spent
Orders
Replacement;
Risks
Project schedule has no float remaining.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 1Q 2015 Report  45

FIRST QUARTER REPORT, 2015
NorthSTAR North Satellite Renovation and
NSTS Lobbies 
Project: C800556             Renovation and expansion of the North  Project Status:
Budget: $421,612,944         Satellite (NSAT), including NSAT      Schedule: Within or Ahead
Phase: Design               Satellite Transit System (STS) stations    Budget: On or Under
Start: 7/24/2012              "refresh", ramp level, Concourse level,    Status Reset: N/A
Schedule Completion: 7/27/2020  and new rooftop airline lounge.        (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Issues NTP to Hensel Phelps as the General Contractor/Construction Manager    500
421.7
(GC/CM) and began solicitation process for Electrical & Mechanical CM firms.
400
Conducted AAAC briefing and MII ballot. Approval received for NSAT
300
baggage handling system expansion design. Decision finalized to pursue
Leadership in Environmental and Energy Design (LEED) certification. Safety    200
Risk Assessment (SRA) for tri-taxilane completed.                     100  Dollars in Millions    62.7
12.4
0
Schedule                                        Authorized Forecasted  Costs
Incurred
Continue to evaluate construction phasing options in collaboration with the
GC/CM contractor and AAG. Design progressing for a June 30th 60%
Construction Costs
deliverable.                                                Not Applicable 
Budget
The forecast is within the approved budget.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0


AIRPORT 
46  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Main Terminal Mezzanine Tenant Relocations 
Project: C800560             Construct new tenant leased spaces in   Project Status:
Budget: $2,025,000           order to move existing tenants and       Schedule: Within or Ahead
Phase: Construction          provide new leasable office space for     Budget: On or Under
Start: 3/26/2013              airlines on the mezzanine of the main    Status Reset: 11/19/2013
Schedule Completion: 3/30/2015  terminal.                      (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction of all leased spaces completed with a few punch list items to       2.5
complete. Delta occupied the Credit Union's new office, as the Credit Union         2.0     2.0
2                   1.7
will no longer need the space.
1.5
Schedule                                      Dollars in Millions 1
On schedule                                           0.5
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
1   0.9         0.9
Current Quarter     Project Total
Number of COs           5             9            0.8
Amount of Cos         $19,295.34        $29,380.34          0.6
Justification for COs: Design changes and varying site conditions.            Dollars in Millions 0.4
0.2
Risks                                                 0.0
0
None identified at this time.                                            Initial Change Spent
Orders
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2015 Report  47

FIRST QUARTER REPORT, 2015
Known Crewmember Employee Bypass 
Project: C800576             Construct two Known Crew Member    Project Status:
Budget: $780,000            points of entry and employee bypass     Schedule: Delayed
Phase: Closeout              portals with Airport access control       Budget: On or Under
Start: 12/11/2012             equipment at each end of the main      Status Reset: 9/30/2014
Schedule Completion: 1/15/2015  terminal.                       (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Portal is in operation and project is in close out.                          0.8   0.8     0.8
Schedule                                         0.75
Project completed.                                          0.7               0.7
0.65
Budget                                     Dollars in Millions
The project forecast is within approved budget and authorization.             0.6
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
48  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Parking Garage Lights (CA) 
Project: C800581             Use current technology to replace all    Project Status:
Budget: $6,235,000           normal lighting in the Airport Parking    Schedule: Within or Ahead
Phase: Design               Garage on all 8 floors and in the helices.   Budget: On or Under
Start: 1/31/2014              This will reduce energy consumption     Status Reset: N/A
Schedule Completion: 12/31/2019 over 60%.                     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission has approved construction funds, to execute a major public works    8
contract and authorized Port Maintenance to purchase and install LED retrofit         6.2     6.2
kit.                                                                    6
Design completed and the building permit received. Advertisement for the       4
major works phase I anticipated in April.                             Dollars in Millions 2
0.2
Schedule                                       0
Authorized Forecasted   Costs
The Project is on schedule.
Incurred
Budget
Construction Costs
The forecast is within the approved budget and authorization.              Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No risks at this time.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2015 Report  49

FIRST QUARTER REPORT, 2015
International Arrivals Facility (IAF) 
Project: C800583              Planning, Design, Construction of new Project Status:
Budget: $608,365,000           Federal Inspection Services (FIS)      Schedule: Within or Ahead
Phase: Planning               facility, including connector between    Budget: On or Under
Start: 6/25/2013                South Satellite and FIS and sterile     Status Reset: N/A
Schedule Completion: 11/9/2019    corridors between Concourse A and   (Commission Authorization  to  start 
FIS.                       Design & Construction)
Significant Developments                             Budget/Costs Incurred
Request for Proposal issued to four shortlisted finalists on February 13, 2015     800
for the IAF, Port's first Progressive Design Build project.                             608.4
600
Schedule
400
Project schedule revised to account for reconciliation. Next schedule revision
200
will be after the Validation Period and receipt of Design-Builder's Target       Dollars in Millions     24.5           7.3
Schedule commitment (anticipated in 1Q 2016).                       0
Authorized Forecasted   Costs
Incurred
Budget
The IAF Project Notebook Status II Budget approval granted subject to       Construction Costs
amendment after Validation Period and receipt of Design-Builder's Target     Not Applicable 
Budget commitment (anticipated in 1Q 2016).
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Program budget may increase due to additional scope development.
Budget Transfers
Amount       From         To
$0



AIRPORT 
50  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Wi-Fi Enhancement 
Project: C800585              Upgrade Wi-Fi system in the public   Project Status:
Budget: $9,880,000             and ramp operational areas of the      Schedule: Delayed
Phase: Design                 Airport.                       Budget: On or Under
Start: 11/4/2012                                            Status Reset: 5/13/2014
Schedule Completion: 6/5/2017                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Electrical infrastructure designer has executed service agreement. Wi-Fi signal    12
9.9
audits completed for the interior of the Airport. They will continue on to the      10
ramp, which will identify antenna locations.                            8
Schedule                                      Dollars in Millions 6
4
1.9
Schedule is trending late due to designer procurement period.                2
0.1
0
Budget                                       Authorized Forecasted  Costs
Incurred
On budget
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2015 Report  51

FIRST QUARTER REPORT, 2015
Checked Baggage Recapitalization/Optimization 
Project: C800612             TSA approached the Airport in 2012    Project Status:
Budget: $320,550,000         with plan to replace all federally owned   Schedule: Within or Ahead
Phase: Design               and operated baggage scanning         Budget: On or Under
Start: 2/26/2013              equipment, known as Explosive        Status Reset: N/A
Schedule Completion: 12/31/2024 Detection System (EDS) equipment.     (Commission Construction Auth.)
The EDS equipment is approaching the
end of its life.
Significant Developments                             Budget/Costs Incurred
Design team submitted 70% documents for design review on April 22, 2015.
400
The design team is progressing toward 100% design due in 4th Quarter. The               320.6
team continues to refine the project phasing. Coordinate with all other programs   300
within the capital program. 
200
Schedule                                      100 Dollars in Millions    20.4        7.1
The project is currently on schedule. Overall schedule will be refined to reflect     0
a ten-year program.                                             Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project forecast is within the approved budget. When the bid documents are Not Applicable 
completed, request Commission Authorization for construction funding and
authority to advertise for construction.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0


AIRPORT 
52  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Second Floor Mezzanine Infrastructure Upgrade 
Project: C800615             Upgrade and extend the infrastructure   Project Status:
Budget: $2,666,000           (HVAC, Communications, Electrical,     Schedule: Delayed
Phase: Construction          Plumbing, WiFi) to 14,000sq ft of future  Budget: On or Under
Start: 8/1/2013               lease space on the 2nd floor, including    Status Reset: 6/25/2013
Schedule Completion: 2/13/2015  7,000 sq ft for a new USO.           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Major construction complete. Project received beneficial occupancy.
3    2.7      2.7
2.5                      2.1
Schedule
2
The delay is due to design challenges existing from the second floor to meet      1.5
egress code requirements and to determine the routing of the infrastructure,       1
primarily HVAC. Currently working on substantial completion and project      Dollars in Millions 0.5
closeout.                                                   0
Authorized Forecasted   Costs
Incurred
Budget
The forecast is within the approved budget and authorization.              Construction Costs
Change Order                                 1.2
1.0
Current Quarter     Project Total          1
Number of COs           8             11            0.8
Amount of Cos          $8,427          $14,427           0.6
Justification for COs: Design changes and errors.                        Dollars in Millions 0.4
0.2
0.0
0
Risks
Initial  Change  Spent
Large potential change orders on horizon due to aluminum jacketing of roof              Orders
duct and seismic changes to duct support.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2015 Report  53

FIRST QUARTER REPORT, 2015
Gate S1 Ramp 
Project: C800629             Install a ramp to facilitate travel       Project Status:
Budget: $1,405,000           between the ramp surface and the       Schedule: Within or Ahead
Phase: Construction          International arrivals facility for        Budget: On or Under
Start: 11/24/2013             passenger use.                    Status Reset: 12/9/2014
Schedule Completion: 6/1/2015                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Steel delivered to the site the last week of April and installation has begun.       1.5
1.2       1.2
Schedule
Dollars in Millions 1
On schedule
0.5
0.2
Budget
The project forecast is within approved budget and authorization.              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
With the delivery of steel arriving a week late, we have a tight schedule with a
critical time line, which does not leave much room for error. If the contractor
does not meet his scheduled deliveries, or if we find fault in any of the material
delivered, the in-use date of June 1st will not be met.
Budget Transfers
Amount       From         To
$0



AIRPORT 
54  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
2014-2015 Roof Replacement 
Project: C800637             Remove and replace the current roofing Project Status:
Budget: $4,416,000           system on the Alaska Hangar One and    Schedule: Delayed
Phase: Design               associated maintenance building, the     Budget: On or Under
Start: 4/1/2014                Air Cargo 6 facility, and the former     Status Reset: N/A
Schedule Completion: 10/31/2015 United Cargo Building.             (Commission Construction Auth.)

Significant Developments                             Budget/Costs Incurred
No significant developments this quarter.                             5         4.4
4
Schedule
3
Project is behind schedule while the project scope is reviewed against the
2
Strategic Airport Master Plan.                                    Dollars in Millions 1   0.5
0.1
Budget                                      0
Authorized Forecasted   Costs
Project forecast is within the approved budget.                                         Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Delay to schedule could impact construction by moving it into less favorable
weather conditions (from summer into fall).
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2015 Report  55

FIRST QUARTER REPORT, 2015
Dining and Retail Infrastructure Modernization 
Project: C800638             Project is to provide infrastructure     Project Status:
Budget: $13,953,000.00        modifications, redemise of spaces, two   Schedule: Within or Ahead
Phase: Design               new elevators, and two new Children's   Budget: On or Under
Start: 10/28/2014              Play Areas in support of the Airport     Status Reset: N/A
Schedule Completion: 6/30/2020  Dining and Retail concessions plan.     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Thirty percent design package 1 documents received. Job Order Contract        15         13.9
procurement started. Concepts for new elevator received.
10    8.8
Schedule
Currently on schedule                                       Dollars in Millions 5
0.4
Budget                                      0
Authorized Forecasted   Costs
Currently on budget                                                       Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Design and construction of elements related to the central terminal will be
critical to upcoming project milestone completion.
Budget Transfers
Amount       From         To
$3,400,000         C800638         C800612




AIRPORT 
56  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
CCTV Camera and VMS Enhancement 
Project: C800642             Add cameras and improve the video    Project Status:
Budget: $11,000,000          management system at the Airport.      Schedule: Within or Ahead
Phase: Design               Project funded by a TSA Other        Budget: On or Under
Start: 11/4/2012               Transaction Agreement (OTA)        Status Reset: N/A
Schedule Completion: 11/30/2016                            (Commission Construction Auth.)
Significant Developments
Infrastructure designer has executed their service agreement and a Service      Budget/Costs Incurred
Directive is being developed. Monthly meetings are being held with TSA and a    12         11.0
Port of Seattle Steering Committee. Commission authorized the video          10
management system improvements in March 2015.                    8
6
Schedule                                       4
The project is proceeding on schedule.                              Dollars in Millions 2   1.0
0.1
0
Authorized Forecasted   Costs
Budget
Incurred
Project continues to be within approved budget.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2015 Report  57

FIRST QUARTER REPORT, 2015
Passenger Loading Bridge Renew 
Project: C800653               Renewal/Replacement of Passenger  Project Status:
Budget: $7,250,000             Loading Bridges B6, B8, B14, C3    Schedule: Within or Ahead
Phase: Design                  and S15                      Budget: On or Under
Start: 7/18/2014                                           Status Reset: 10/7/2014
Schedule Completion: 12/31/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Thirty percent design completed for B14 and C3. Ordered all five passenger
8.00    7.25      7.3
loading bridges.
6.00
Schedule
4.00
Completion schedule for the loading bridges:
2.00  Dollars in Millions                       0.1
B14 and C3       June 1, 2015
0.00
B6          September 21, 2015                   Authorized Forecasted Costs
Incurred
B8          October 12, 2015
S15           November 2, 2015
Construction Costs
Not Applicable at this time 
Budget
NSTR 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Risks
Delivery of B14 and C3 Passenger Loading Bridges is very tight.
Budget Transfers
Amount       From         To
$0



AIRPORT 
58  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Domestic Water Piping 
Project: C800657             Replace domestic water piping       Project Status:
Budget: $1,950,000           branches and manifolds including       Schedule: Within or Ahead
Phase: Design               valves.                         Budget: On or Under
Start: 11/4/2012                                           Status Reset: 5/13/2014
Schedule Completion: 1/4/2016                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
90% design is complete.
$3
2.0
$2
Schedule
Dollars in Millions $2
Staff will request funding for construction in 2Q 2015. Substantial completion
$1
scheduled for January 4, 2016 per the project notebook schedule.                 0.6
$1
0.0
Budget                                     $0
Authorized Forecasted   Costs
The authorized amount is $558,000 to complete project design.                             Incurred
The remaining funding will be requested in 2Q 2015.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT
Port of Seattle 1Q 2015 Report  59

FIRST QUARTER REPORT, 2015
Mech Energy Conservation (CA) 
Project: C800658             Stage 3 Mechanical Energy          Project Status:
Budget: $3,500,000           Conservation to improve the efficiency    Schedule: Within or Ahead
Phase: Audit/Notebook        of portions of the mechanical          Budget: On or Under
Start: 8/25/2014              infrastructure system at the Airport.      Status Reset: N/A
Schedule Completion: 8/30/2016                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Investment Grade Audit Final report received on February 27, 2015. Service
4           3.5
directive issued to PBS Engineering for Asbestos RMM survey.
3
Schedule
2
Schedule for completing RMM survey and incorporating POS costs in funding
1
request is aggressive when considering scope of work due to diversity in scope    Dollars in Millions     0.3           0.2
and location of nine separate energy conservation measures.                 0
Authorized Forecasted   Costs
Incurred
Budget
Schedule future Commission authorization for additional funds after         Construction Costs
completion of Audit and with an updated construction schedule.            Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0



AIRPORT 
60  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
North Utility Tunnel Steam Pipe 
Project: C800659             Replace 45 year old steam piping      Project Status:
Budget: $1,250,000          expansion joints in the North Utility      Schedule: Within or Ahead
Phase: Closeout              Tunnel.                          Budget: On or Under
Start: 3/18/2014                                            Status Reset: N/A
Schedule Completion: 10/8/2014                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project is in Closeout Phase.                                      1.5
1.3
Schedule
1           0.9
0.7
Project is substantially complete.
0.5
Budget                                     Dollars in Millions
The project is on budget.                                         0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             5
0.5
Amount of Cos           $0           $19,915
0.4          0.4
0.4
Justification for COs: None this quarter
0.3
Risks                                          0.2
None                                       Dollars in Millions 0.1
0.0
0
Budget Transfers                                     Initial Change Spent
Orders
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2015 Report  61

FIRST QUARTER REPORT, 2015
S4 & S6 International Corridor Connection 
Project: C800662             Installation of a fixed bridge and      Project Status:
Budget: 4,850,000            corridor extension to connect gates S6    Schedule: Delayed
Phase: Design               and S4 to the International Corridor      Budget: On or Under
Start: 11/4/2012                                           Status Reset: 2/25/2014
Schedule Completion: 10/22/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project executed a construction contract with PCL Construction Services on
6
February 26th.                                                 4.9    4.8
5
4
Schedule
3
Project completion scheduled for October 2015.                       Dollars in Millions 2
1                   0.6
Budget
0
Project is on budget after some scope reductions for HVAC in corridor.           Authorized Forecasted  Costs
Incurred
Change Order
Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Discovery of PC Air wide body aircraft unit omitted from design. Review
budget/scope for inclusion. Possible budget increase.
Budget Transfers
Amount       From         To
$0




AIRPORT 
62  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Automated Passport Control 
Project: C800667              Install additional Automated Passport  Project Status:
Budget: $2,197,900            Control (APC) kiosks in the existing    Schedule: Within or Ahead
Phase: Construction            FIS at the South Satellite.            Budget: On or Under
Start: 10/31/2013                                           Status Reset: N/A
Schedule Completion: 6/1/2015                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Twelve additional APC Kiosks installed bringing the total to 26 APC Kiosks.     3   2.2     2.1
Four Global Entry Kiosks relocated and CBP has increased their number to 10.
2
Schedule
2                   1.2
The additional Global Entry and APC Kiosks installed and commissioned        1
before April 22, 2015 ahead of the May 1, 2015 target date.                Dollars in Millions 1
0
Budget                                       Authorized Forecasted  Costs
Incurred
Project remains within current budget.
Construction Costs
Change Order
Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2015 Report  63

FIRST QUARTER REPORT, 2015
Construction Logistics Expansion 
Project: C800688              The expansion and reconfiguration of   Project Status:
Budget: $7,400,000            the existing construction logistics        Schedule: Within or Ahead
Phase: Design                 facilities (including contractor parking)    Budget: On or Under
Start: 8/1/2014                 and the renovation of Port field offices.    Status Reset: N/A
Schedule Completion: Q4 2016                                (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Complete the design and opened bids for the relocation of the contractor       8.000         7.4
parking lot (small works contract). There was one bidder, Apply-A-Line, and
their bid was above the Engineer's estimate but within the overall budget.      6.000
Continued with the design for the renovation of the field offices, and began the   4.000
design for the expansion and reconfiguration of the construction logistics            2.5
2.000
facilities.                                                            Dollars in Millions                    0.1
0.000
Schedule                                        Authorized Forecasted  Costs
Incurred
The project is currently on schedule with the following completion dates:
x Contractor Parking Relocation  Q3 2015                      Construction Costs
x Construction Logistics  Q3 2016                          Not Applicable 
x Field Office Renovation - Q4 2016
Location
Budget
The project is within budget and additional funds are planned to be authorized
for construction in Q3 2015.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The completion of this project to accommodate the Aviation Capital Program.
Budget Transfers
Amount       From         To
$0

AIRPORT
64  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
2016 Fuel System Modifications 
Project: C800692               Airline activity growth at the      Project Status:
Budget: $2,069,000             Airport is requiring the installation   Schedule: Delayed
Phase: Design                  of a new fuel pits in 2016.         Budget: On or Under
Start: 11/6/2013                                           Status Reset: 11/11/2014
Schedule Completion: 6/30/2016                             (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
No change at this time. Anticipate beginning design with a consultant in 3rd
2.5
Quarter.                                                            2.1
2
Schedule                                      1.5
Project originally scheduled for completion in Q4 2015 postponed to 2016 to     1
allow time for new design of "hot tap" fuel connection, which reduces fuel
0.5     0.2
system down time during construction.                             Dollars in Millions                0.0
0
Authorized Forecasted   Costs
Budget                                                Incurred
N/A 
Construction Costs
Change Order                               None at this time 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Risks
Not Applicable
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2015 Report  65

FIRST QUARTER REPORT, 2015
Highline Schools Noise Insulation 
Project: C200007              Planning, Design, Construction of new Project Status:
Budget: $101,797,000           Federal Inspection Services (FIS)      Schedule: Delayed
Phase: Construction            facility, including connector between    Budget: On or Under
Start: 3/23/1999                South Satellite and FIS and sterile     Status Reset: N/A
Schedule Completion: 11/30/2021  corridors and walkways within       (Commission Construction Auth.)
Concourse A.
Significant Developments                             Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of Washington,    120   102.1    101.8
and the Highline School District (HSD) provide matching funds. HSD was      100
unable to pass a school bond vote in February. Project has an unknown        Dollars in Millions 80               63.4
timeframe until a bond passes.                                    60
40
Schedule                                      20
The schedule for state funds is unknown. The district's schedule is dependent     0
Authorized Forecasted   Costs
on obtaining general election bonds at various intervals. Construction may                      Incurred
resume in late 2015 if a future voter approved bond is secured, although it is
unknown when that will happen at this point.                        Construction Costs
Not Applicable 
Budget
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project delayed due to funding issues with HSD. There is a risk if there are no
bonds passed in the general election, and if FAA Airport Improvement Program
(AIP) Grant funding is not available.
Budget Transfers
Amount       From         To
$0


AIRPORT 
66  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Highline Community College Noise Insulation 
Project: C200042              Highline Community College       Project Status:
Budget: $7,970,266             Insulation Agreement will provide     Schedule: Within or Ahead
Phase: Construction            funding for up to 22 eligible buildings   Budget: On or Under
Start: 1/11/2005                that are impacted by aircraft noise     Status Reset: N/A
Schedule Completion: 12/31/2013  from Sea-Tac Airport.             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Fourteen of the original 22 eligible buildings have been sound insulated by the    8.3
college. The College sound insulation program has been dependent on receiving       8.2
8.2
funds from FAA grants. The FAA notified the Port that the Highline
Community College Campus is no longer located within the 65 DNL Noise
Contour and therefore is not eligible for any further grant funding. Without the
8.0       8.0
FAA's approval and funding, the remainder of the college buildings cannot be    Dollars in Millions 8.18 7.9
sound insulated.                                             7.8
Authorized Forecasted   Costs
Incurred
Schedule
The construction is complete on the last building (Building #4) and the Noise
Construction Costs
Office is working with FAA to Close Grant AIP 127. We have recently       Not Applicable 
received the Final Grant Closure letter from the FAA. The project is in the
process of being closed.
Budget
The project forecast is within the approved budget. No further authorization
anticipated.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The FAA will not allocate future grant funds to this project.
Budget Transfers
Amount       From         To
$0

AIRPORT 
Port of Seattle 1Q 2015 Report  67

FIRST QUARTER REPORT, 2015
Home Insulation Retrofit 
Project: C200048              Storm window retrofit of previously   Project Status:
Budget: $4,060,147             insulated homes.                  Schedule: Within or Ahead
Phase: Construction                                        Budget: On or Under
Start: 1/11/2005                                            Status Reset: N/A
Schedule Completion: 12/31/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of their         6   5.3
eligibility. The Port is continuing with storm window retrofit.                5
4.1
3.4
Schedule
4
3
The project is on hold until new eligible homes are identified.               Dollars in Millions 2
1
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within the approved budget and authorization.                          Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The ability to accomplish the retrofit is dependent on homeowner's schedules,
and structural integrity of the home. Ability to Identify future potentially
eligible homes.
Budget Transfers
Amount       From         To
$0




AIRPORT 
68  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Single Family Home Sound Insulation 
Project: C200093             Sound insulate remaining homes that are Project Status:
Budget: $13,747,395          within the 1998 65 decibel day night     Schedule: Within or Ahead
Phase: Construction          level (DNL) noise contour.            Budget: On or Under
Start: 3/27/2007                                           Status Reset: N/A
Schedule Completion: 12/31/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Sixty-five homes are complete; and 16 homes are in the process of receiving
15    13.7     13.7
sound insulation.
Schedule
10
Project is on schedule. Anticipate completion by 4th quarter 2015.            Dollars in Millions                 5.4
5
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within approved budget and authorization to complete all                  Incurred
homes currently in progress.
Construction Costs
Change Order
3.8
Current Quarter     Project Total          4
Number of COs           0             0             3
Amount of Cos           $0             $0
1.8
Justification for COs: N/A                                       Dollars in Millions  2
1
Risks                                                 0.0
0
The ability to accomplish the insulation is dependent on the homeowner's           Initial Change Spent
schedules, willingness to sign an aviation easement, obtain a subordination               Orders
agreement from their lender, and structural integrity of the home.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2015 Report  69

FIRST QUARTER REPORT, 2015
RMU/Kiosk Concession Program 
Project: C800146             Design and fabrication of Retail       Project Status:
Budget: $879,146            Merchandising Units (RMUs); power,    Schedule: Delayed
Phase: Construction          communications, and data to RMU      Budget: On or Under
Start: 11/20/2007             locations; and install floor-mounted      Status Reset: N/A
Schedule Completion: 2/5/2014   receptacles for the utilities to allow easy   (Commission Construction Auth.)
connection points as well as flexibility
for future utilization.
Significant Developments                             Budget/Costs Incurred
We are working with the vendor to complete the punchlist items.             1.5
1.2
Schedule
1           0.9
0.8
Waiting for corrected color of display arms.
0.5
Budget                                     Dollars in Millions
The project forecast is within the approved budget and authorization.           0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
70  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Tenant Reimbursement 
Project: C800154              Build-out of spaces for new and      Project Status:
Budget: $4,709,577             existing tenants. If more than a "basic   Schedule: Within or Ahead
Phase: Construction            finish", condition space is built for the   Budget: On or Under
Start: 8/14/2007                tenant. The tenant is required to       Status Reset: N/A
Schedule Completion: TBD      reimburse the Port for the cost of the    (Commission Construction Auth.)
work beyond the "basic finish.
Reimbursements allowed under the
guidelines in the "Tenant Reimb.
Policy:
Significant Developments                             Budget/Costs Incurred
In 2015, anticipate a reimbursement to TSA for build-out of the last unfinished        4.7     4.7
5
space on the concourse level of the C1 building, likely Q3 or Q4.
4
3
Schedule
2
Schedules vary to meet the tenant's needs.                            Dollars in Millions                 1.3
1
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within the approved budget and authorization.                          Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2015 Report  71

FIRST QUARTER REPORT, 2015
T-46 Lease Improvements  Stormwater
Improvements 
Project: U00050 (C102554)         Construct stormwater treatment    Project Status:
Budget: $8,000,000             system to comply with Ecology      Schedule: Within or Ahead
Phase: Construction             order.                      Budget: On or Under
Start: 4/12/2013                                          Status Reset: 5/7/2015
Schedule Completion: 2020                                 (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Contractor is working through punch list items. Change order work for the
10
outfall pipe replacement at Basin 6 is completed. Design team is now started         8.00    8.00
8
the commissioning of the three treatment vaults. Significant amount of
Dollars in Millions 6
sediment discovered during inspection of treatment vault #5, sts5, which will                      4.70
require complete cleaning, and replacement of all treatment filter media.         4
Significant amount of oil product found during inspection of sts8, which require    2
complete removal, cleaning of the vault, and inspect to determine the need to      0
replace the treatment filter media.                                      Authorized Forecasted  Costs
Incurred
Schedule
Construction Costs
The outfall pipe replacement is completed. Install the fourth treatment vault
once Washington State Department of Transportation (WSDOT) vacates the      2.5
lease area.                                                         1.9        2.0
2
1.5
Budget
1
Authorized budget of $8,000,000 for Stormwater Treatment System is currently
within budget.                                               Dollars in Millions 0.5       0.3
0
Change Order                                   Initial Change Spent
Orders
Current Quarter     Project Total
Number of COs           3             8
Amount of Cos         $-23,726         $259,264
Justification for COs: Reconciliation of previous lump sum change order.
Risks
Delay of completing the treatment vaults commission due to terminal operation.
Budget Transfers
Amount       From         To
$0

MARITIME 
72  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
T-46 Lease Improvements  Container Dock
Apron Upgrade 
Project: U00175 (C102554)         Upgrade 200 LF at existing T-46   Project Status:
Budget: $10,195,000            dock apron to increase load        Schedule: Within or Ahead
Phase: Design                  capacity to accommodate 100-foot    Budget: On or Under
Start: 4/12/2013                 gauge cranes. Upgrade electrical     Status Reset: 5/7/2015
Schedule Completion: 3/31/2017   power to support new cranes if      (Commission Construction Auth.)
requested by tenant.
Significant Developments                             Budget/Costs Incurred
Thirty percent design submittal developed. Completion scheduled for May 15,
3
2.50      2.50
2015. Design team is preparing Master Use Permit (MUP) submittal for City
2.5
Shoreline requirements. Draft JARPA and Biological Evaluation documents
Dollars in Millions 2
submitted for Port review.
1.5
1
Schedule
0.5
0.03
Schedule adjusted to tenant request. Construction scheduled to begin May       0
2016.                                                 Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Currently within budget                                       None at this time
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Permit review timeline uncertain. Meet federal funding procurement
requirements. Contractor's ability to procure long lead items on schedule.
Coordination and work perform by SCL on schedule. Meet tenant requests due
to change in operation.
Budget Transfers
Amount       From         To
$0


MARITIME 
Port of Seattle 1Q 2015 Report  73

FIRST QUARTER REPORT, 2015
Street Vacations T-5, T-18 and T-105 
Project: C102858, C102875,       Street vacation related real estate   Project Status:
E104366                   negotiations and agreements  T-5,  Schedule: Delayed
Budget: $1,500,000             T-18 and T-105 (complete).        Budget: On or Under
Phase: Permitting                                         Status Reset: N/A
Start: 6/1/2010                                            (Commission Construction Auth.)
Schedule Completion: 2016; T-18
end of 2015 
Significant Developments                             Budget/Costs Incurred
Draft Easement and Utility transfer documents prepared by the City and are     1.55
under Port Legal Department review for T-18. Discussion and Title work has         1.50    1.50
1.5
begun for Terminal 5.
1.45
Schedule                                      1.4            1.37
Current schedule has T-18 completed by end of 2015 (City Council action by    1.35  Dollars in Millions
end of September 2015) and T-5 by the end of 2016.                    1.3
Authorized Forecasted   Costs
Incurred
Budget
The budget revised for 2015 and beyond.                           Construction Costs
None at this time
Change Order
Current Quarter     Project Total       Photo
Number of COs           0             2
Amount of Cos           $0          $20,390.33
Justification for COs: None this quarter
Risks
Not applicable
Budget Transfers
Amount       From         To
$0



MARITIME
74  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Pier 34 Mooring Dolphins 
Project: C800090               Replacement of four existing failed  Project Status:
Budget: $1,800,000             timber mooring dolphins with four   Schedule: Within or Ahead
Phase: Construction             new steel dolphin structures located   Budget: On or Under
Start: 4/1/2014                  at Pier 34 at the head of the East     Status Reset: N/A
Schedule Completion: 3/30/2015   waterway by March 2015 for       (Commission Construction Auth.)
$1.8M.
Significant Developments                             Budget/Costs Incurred
Construction work is completed.                                  2   1.80
This will be the final report.                                                    1.61
1.5                      1.27
Schedule
1
Construction is completed and obtained beneficial occupancy March 31, 2015.    Dollars in Millions 0.5
Budget                                      0
Authorized Forecasted   Costs
Project is within the approved budget.                                                Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable
Number of COs           5             5
Amount of Cos          $44,921          $44,921
Justification for COs: varying site conditions; additional site demolition; and
additional cathodic protection anodes.
Risks
No significant known risks at this time
Budget Transfers
Amount       From         To
$0




MARITIME 
Port of Seattle 1Q 2015 Report  75

FIRST QUARTER REPORT, 2015
T-5 Berth Modernization 
Project: C800132               Improvements to support larger    Project Status:
Budget: $180,000,000-$250,000,000  vessels at T5, including crane rail    Schedule: Within or Ahead
Phase: Design                  strengthening, berth deepening, and   Budget: On or Under
Start: 6/3/2014                  electrical upgrades.             Status Reset: 6/3/2014
Schedule Completion: 6/30/2018                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Environmental review documents published and comments received.          6
5.00      5.00
Shoreline, land use, and in-water work permit applications submitted for         5
agency reviews and approvals.                                   4
Schedule
3                  2.29
2
Sixty percent design completion expected in May.                      Dollars in Millions 1
0
Budget                                       Authorized Forecasted  Costs
Incurred
Authorized budget is currently $5,000,000, which will cover 60% level design
and initial environmental review and permit process.                    Construction Costs
None at this time
Change Order
Current Quarter     Project Total       Photo
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Scope of work is subject to change depending on securing tenant and any
impacts of leasing requirements. Design and agency permit reviews are on
critical path. Schedule is partially dependent on Seattle City Light upgrades.
Pre-purchase of some piles may be necessary in order to deliver project in
2018.
Budget Transfers
Amount       From         To
$0


MARITIME 
76  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
FT C15 HVAC Improvement 
Project: C800137               Replace existing HVAC systems   Project Status:
Budget: $4,000,000             within Building C-15 that are at the   Schedule: Delayed
Phase: Construction             end of their service life.           Budget: On or Under
Start: 5/1/2010                                            Status Reset: 10/8/2013
Scheduled Completion: 6/30/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Although major HVAC equipment has been installed the systems were not
5    4.9      4.9
functioning correctly. Equipment manufacturer then discovered that heat
pumps had fabrication errors and the corrective work has been completed. The    4.8
equipment is going through the commissioning process and being fine tuned.
4.4
Schedule                                      Dollars in Millions 4.6 4.4
Contractor is behind schedule and substantial completion date has been further    4.2
delayed due to equipment manufacturing error. Notice of forbearance has been      Authorized Forecasted  Costs
Incurred
issued and Port will be collecting liquidated damages.
Budget                                    Construction Costs
Project is still within the October 8, 2013 Commission funding authorization.       3.5  3.0
3             2.6
Change Order                                 2.5
2
Current Quarter     Project Total         1.5
Number of COs           5             15             1
Amount of Cos          $6,554          $111,790          Dollars in Millions 0.5      0.1
0
Justification for COs: Mostly varying site conditions and some design error
Initial  Change  Spent
and omission.                                                    Orders
Risks                                        Photo
Some significant cost items have been raised by the contractor but Port
disagrees with their merits. These likely would result in claims and dispute
resolution/mediation may be necessary.
Budget Transfers
Amount       From         To
$0


MARITIME 
Port of Seattle 1Q 2015 Report  77

FIRST QUARTER REPORT, 2015
T-91 Lighting Upgrade 
Project: C800160               Lighting upgrade at Terminal 91    Project Status:
Budget: $1,160,000                                         Schedule: Delayed
Phase: Construction                                       Budget: Forecast Overrun
Start: 6/23/2014                                          Status Reset: 5/15/2015
Schedule Completion: 9/30/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
On April 14, 2015, Commission approved an additional $125,000. The
1.5
remainder of the fixtures are ordered and the final commissioning of the             1.16    1.16
controls is being scheduled.                                                       0.94
1
Schedule
0.5
Expect to finish the project in September of 2015.                       Dollars in Millions
0
Budget                                       Authorized Forecasted  Costs
Incurred
The budget was increased by $125,000; now totaling $1,160,000 total project
cost.                                                            Construction Costs
Not Applicable
Change Order
Current Quarter     Project Total       Photos
Number of COs           0             2
Amount of Cos           $0           ($23,000)
Justification for COs: None this quarter
Risks
If the project is not fully funded the benefit of the control system will not be
realized. It is important to complete the work prior to cruise season to have a
fully functional control system available to the users.
Budget Transfers
Amount       From         To
$0



MARITIME 
78  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
P-69 Built-up Roof Replacement 
Project: C800314               Replace 32,000SF of the 65,000SF  Project Status:
Budget: $3,418,000             Built-Up Roof at the P-69         Schedule: Within or Ahead
Phase: Construction             Headquarters Office Building.      Budget: On or Under
Start: 2/26/2012                                          Status Reset: 2/25/2014
Schedule Completion: 10/30/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The physical construction work was complete in Q4/2014. This will be the last
4    3.42     3.42
report on this project.
3
Dollars in Millions                        2.14
Schedule
2
Substantial completion was issued in Q4/2014 with the project preparing to
1
close-out.
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project is currently below budget 
Construction Costs
Change Order
Current Quarter     Project Total         3.5  3.1
3
Number of COs           4             9
2.5
Amount of Cos          $57,000          $57,000          Dollars in Millions           1.9
2
Justification for COs: Errors/Omission- Designer, Errors/Omission- Owner,       1.5
Varying Site Conditions, Scope Change.                             1      0.6
0.5
Risks                                           0
Initial  Change  Spent
No risks at this time.                                                      Orders
Budget Transfers                                 Photo
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2015 Report  79

FIRST QUARTER REPORT, 2015
FT C-2 Nordby HVAC and Roof Replacement 
Project: C800344               Replace 23,000SF of existing     Project Status:
Budget: $2,438,000             Roofing and roof top HVAC units.   Schedule: Delayed
Phase: Construction                                       Budget: On or Under
Start: 2/26/2012                                          Status Reset: 1/7/2014
Schedule Completion: 1/16/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The project is physically complete with construction. All HVAC units have
3
been Tested, Balanced and Commissioned. The contractor is finalizing             2.44    2.34
2.5
Operation and Maintenance submittals for the project. This will be the last
Dollars in Millions 2                      1.80
report on this project.
1.5
1
Schedule
0.5
The physical construction work was complete in Q1/2015.                 0
Authorized Forecasted   Costs
Incurred
Budget
Project is currently below budget                                  Construction Costs
Change Order                                 2.5  2.2
Current Quarter     Project Total          2         1.7
Number of COs           6             7            1.5
Amount of Cos          $7,726          $7,726
1
Justification for COs: Error/Omission- Designer; Error/Omission- Contractor;       Dollars in Millions 0.5
Varying Site Condition; Tenant Requested and Scope Change.                            0.0
0
Initial  Change  Spent
Risks                                                Orders
No risks at this time
Photo
Budget Transfers
Amount       From         To
$0



MARITIME 
80  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Shilshole Tenant Service Buildings 
Project: C800356               Replacement/rehabilitation of five   Project Status:
Budget: $5,500,000 to $6,500,000    restrooms and laundry facilities at    Schedule: Within or Ahead
Phase: Design                  Shilshole Bay Marina by June 2017   Budget: On or Under
Start: 1/6/2015                  for $5.5M.                   Status Reset: N/A
Schedule Completion: 6/30/2017                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design Authorization approved by Commission on January 6, 2015.
2
Selection of design consultant underway, public outreach for tenant feedback               1.61
and priorities started.                                              1.5
1    0.71
Schedule
0.5
Design completion by February 2016.                            Dollars in Millions               0.05
0
Budget                                       Authorized Forecasted  Costs
Incurred
Project is within the approved budget. 
Construction Costs
Change Order
None at this time
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant known risks at this time
Budget Transfers
Amount       From         To
$0




MARITIME 
Port of Seattle 1Q 2015 Report  81

FIRST QUARTER REPORT, 2015
T91, Bldg. C175 Roof Replacement 
Project: C800430               Replace roof on the C175 Building  Project Status:
Budget: $2,450,000             at Terminal 91                 Schedule: Delayed
Phase: Construction                                       Budget: On or Under
Start: 7/26/2011                                          Status Reset: 1/14/2014
Schedule Completion: 11/14/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The substantial completion date of April 22, 2015 is 51 days past the revised
3
substantial date of March 3, 2015. The added 51 days are a combination of          2.45
2.5             2.15
contractor inefficiencies, lack of urgency, and weather delays.
Dollars in Millions 2                      1.82
1.5
Schedule
1
The project should complete under budget by approximately $300,000.         0.5
0
Budget                                       Authorized Forecasted  Costs
Incurred
Project is within approved budget. 
Construction Costs
Change Order
Current Quarter     Project Total          2
1.7
Number of COs           6             8            1.5         1.3
Amount of Cos          $76,078          $82,949          Dollars in Millions  1
Justification for COs: Varying site conditions and weather delays
0.5
Risks                                                 0.1
0
None at this time                                                 Initial Change Spent
Orders
Budget Transfers
Amount       From         To        Photos
$0




MARITIME 
82  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
T-91 Substation Upgrades 
Project: C800439               Upgrade/replace existing        Project Status:
Budget: $2,058,000             substations/equipment at Substation   Schedule: Within or Ahead
Phase: Design                  Nos. 1, 14 and 15.               Budget: On or Under
Start: 11/4/2013                                          Status Reset: 3/10/2015
Schedule Completion: 4/30/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission authorized Completed major works construction contract
2.5
documents  contract advertised.                                      1.995   1.995
2
Schedule
On Schedule                                         Dollars in Millions 1.510.5             0.304
Budget                                      0
Authorized Forecasted   Costs
On budget                                                           Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable
Number of COs           0             0
Amount of Cos           $0             $0          Photo
Justification for COs: N/A
Risks
Equipment procurement duration could be very volatile due to demands.
Unable to verify As-built condition due to locations/accessibility issues -
differing site conditions may result.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2015 Report  83

FIRST QUARTER REPORT, 2015
FT Net Shed #9 Roof Overlay 
Project: C800527               Overlay 12,000SF of existing     Project Status:
Budget: $401,400               corrugated Roof at the FT Net Shed   Schedule: Delayed
Phase: Construction             Building.                    Budget: On or Under
Start: 2/26/2012                                          Status Reset: 1/7/2014
Schedule Completion: 1/16/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The project is physically complete with construction. The contractor is
0.42
finalizing Operation and Maintenance submittals for the project. This will be          0.40    0.40
0.4
the last report on this project.
0.38
Schedule                                      0.36            0.35
The physical construction work was complete in Q1/2015.                0.34 Dollars in Millions
0.32
Budget                                       Authorized Forecasted  Costs
Incurred
Project is currently at budget 
Construction Costs
Change Order
Current Quarter     Project Total         0.35         0.30
0.3   0.27
Number of COs           1             1
0.25
Amount of Cos          $1,706          $1,706
0.2
Justification for COs: Varying Site Condition                          0.15
0.1
Risks                                         Dollars in Millions 0.05     .001
0
No risks at this time                                                 Initial Change Spent
Orders
Budget Transfers
Amount       From         To        Photo
$0




MARITIME 
84  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Argo Yard Truck Roadway 
Project: C800546, E104751,       New Port of Seattle owned truck    Project Status:
E104754                   roadway between East Marginal    Schedule: Within or Ahead
Budget: $7,750,000             Way and Colorado Avenue South    Budget: On or Under
Phase: Construction             right-of-way.                 Status Reset: 4/22/2014
Start: 3/11/2012                                          (Commission Construction Auth.)
Schedule Completion: 4/15/2015 
Significant Developments                             Budget/Costs Incurred
Construction is underway.                                     10
7.75      7.75
8
Schedule
Construction to be substantially completed Q2 2015.                    Dollars in Millions 6
4
2.31
Budget                                      2
Project is currently within the budget authorized by Commission on April 22,     0
Authorized Forecasted   Costs
2014. This status may change depending upon the outcome of several                      Incurred
contractor claims currently being negotiated. 
Construction Costs
Change Order
6
Current Quarter     Project Total            5.05
5
Number of COs           8             8
4
Amount of Cos         $157,525         $157,525
3
Justification for COs: Construction requirements not addressed by design       Dollars in Millions  2
documents.
1        0.16   0.32
0
Risks
Initial  Change  Spent
Orders
No significant known risks at this time.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2015 Report  85

FIRST QUARTER REPORT, 2015
T-46 Dock Rehabilitation 
Project: C800603               Terminal 46 Dock Rehabilitation   Project Status:
Budget: $32,659,000            Project.                      Schedule: Delayed
Phase: Design                                             Budget: On or Under
Start: 11/6/2012                                          Status Reset: N/A
Schedule Completion: Q4 2018                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The project is at 90% design and is on hold. This project has been postponed
2    1.85
and will resume design upon completion of TIGER grant contract execution.
At this time this is the last report until the project is resumed.                 1.5
1.02
1
Schedule
0.44
0.5
The project has been postponed until completion of TIGER grant execution.     Dollars in Millions
Design work is scheduled to resume in February 2016, construction is          0
anticipated to start in 2016/2017.                                      Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project is on budget.                                        None at this time
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Container operation variation which can cause additional construction phasing.
Budget Transfers
Amount       From         To
$0



MARITIME 
86  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Terminal 115 Stormwater Separation 
Project: C800689               Separate stormwater originating    Project Status:
Budget: $548,000               from the Port leased area and the     Schedule: Within or Ahead
Phase: Construction             Common Use Area on T-115 from   Budget: On or Under
Start: 1/27/2014                 the area exclusively used by       Status Reset: 5/6/2014
Schedule Completion: 12/31/2014  Northland Services.             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction completed by PCS crews. As of September 30, 2014, 100% of
0.56
stormwater flow diverted to new outfall using temporary pumps. Final pump         0.55    0.55
0.55
force main system fully operational on February 17, 2015.
0.54
0.53
This will be the final report.                                                          0.52
0.52
0.51  Dollars in Millions
Schedule
0.5
All construction is completed.                                       Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Project is within approved budget.                                 Port Self Perform Construction
Change Order
Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
There are no significant known risks at this time.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2015 Report  87

FIRST QUARTER REPORT, 2015
P69 Carpet Replacement 
Project: C800691               Upgrade 200 LF at existing T-46   Project Status:
Budget: $1,200,000             dock apron to increase load        Schedule: Within or Ahead
Phase: Construction             capacity to accommodate 100-foot   Budget: On or Under
Start: 7/7/2014                  gauge cranes. Upgrade electrical     Status Reset: 5/15/2015
Schedule Completion: 9/30/2014   power to support new cranes if      (Commission Construction Auth.)
requested by tenant.
Significant Developments                             Budget/Costs Incurred
The Contractor has successfully completed 100% of the contract scope. The      1.5
hold-up on closing this project is ongoing labor determinations. There are            1.20    1.20
concerns regarding appropriate labor rates and application of small business       1
involvement.                                           Dollars in Millions               0.60
0.5
Schedule
Port legal counsel and CPO are working to resolve the mentioned issues.         0
Authorized Forecasted   Costs
Expectations are that resolution will linger into the first quarter of 2016 before
Incurred
documentation can be completed with Labor & Industries.
Construction Costs
Budget
Not Applicable
The project is anticipated to complete within the allotted budget. 
Change Order
Current Quarter     Project Total
Number of COs           1             3
Amount of Cos          $1,400          $4,700
Justification for COs: CO-03 was issued to add carpet replacement in a
corridor on the second floor.
Risks
None at this time
Budget Transfers
Amount       From         To
$0


MARITIME 
88  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
P69 Beam Rehabilitation Project 
Project: C800698               Rehabilitate five rows of concrete   Project Status:
Budget: $2,000,000 to $3,300,000   beams supporting top of clerestory   Schedule: Within or Ahead
Phase: Design                  windows at P69..               Budget: On or Under
Start: 7/1/2014                                            Status Reset: 10/27/2015
Schedule Completion: 10/18/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission authorization to proceed with design and preparation of bid
4
documents received on July 1, 2014.                                         3.30
3
Schedule
2
90 percent Design phase started with submittal scheduled for 06/16. Mock-up
installation and assessment complete.                               Dollars in Millions 1
0.33
0.05
0
Budget                                       Authorized Forecasted  Costs
Incurred
Design phase budget authorization is $330,000. Total project costs expected to
be between $2,300,000 and $3,300,000.                           Construction Costs
Change Order                               None at this time
Current Quarter     Project Total       Photos
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Scope of work and costs may escalate as design work and investigations
proceed.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2015 Report  89

FIRST QUARTER REPORT, 2015
East Marginal Way Grade Separation 
Project: E102007               FAST Corridor funded project;    Project Status:
Budget: $56,256,171            FHWA, State, City with Port       Schedule: Within or Ahead
Phase: Closeout                commitment of $22,480,807. Scope   Budget: On or Under
Start: 5/1/2006                  is to construct grade separation in    Status Reset: 4/22/2014
Schedule Completion: Q4 2015    vicinity of T5 and T18 to minimize   (Commission Construction Auth.)
truck traffic/rail conflicts.
Significant Developments                             Budget/Costs Incurred
Coordination underway within POS and with City for properties and easements   56.5   56.25   56.25
conveyance to City. POS to prepare proposed final documents for review by
City.                                                      56
55.5                    55.30
Schedule                                      Dollars in Millions 55
Anticipate final acceptance by Seattle Department of Transportation (SDOT)
4th Quarter 2015.                                          54.5
Authorized Forecasted   Costs
Incurred
Budget
Project is on track within the April 22, 2014 Commission authorization.        Construction Costs
Change Order                                 25  22.0     22.0
Current Quarter     Project Total         20
Number of COs           0             97           Dollars in Millions 15
Amount of Cos           $0          $1,922,967          10
Justification for COs: None this quarter.
5        2.0
0
Risks
Initial  Change  Spent
Orders
No risks at this time.
Budget Transfers
Amount       From         To
$0



MARITIME 
90  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Viaduct Construction Coordination 
Project: E104324, E104535-38       Participate in the design &       Project Status:
Budget: $2,900,000             construction of the bored tunnel, N.   Schedule: Within or Ahead
Phase: Implementation          & S. portals, Holgate to King St,    Budget: On or Under
Start: 1/1/2009                  Central Waterfront surface streets,   Status Reset: N/A
Schedule Completion: 12/31/2018  & related projects to ensure        (Commission Construction Auth.)
adequate connection to port
facilities.
Significant Developments                             Budget/Costs Incurred
Contractor is implementing repair plans for the SR 99 tunnel boring machine.
4
Seawall and Mercer corridor construction continued.
2.90
3
Schedule
2           1.75
First transfer of port contribution will occur May 1, 2015. Tunnel boring                         1.15
1
machine may be ready to resume operation in the fall of 2015. Mercer West     Dollars in Millions
construction will continue through mid-2015. Seawall Phase I construction to     0
be completed in mid-2016. Central Waterfront completion depends on Viaduct      Authorized Forecasted  Costs
Incurred
demolition in 2017.
Budget                                    Construction Costs
Not Applicable
Port staff costs were within anticipated 2015 spending. 
Photos
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project delays due to repairs to the tunneling machine.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2015 Report  91

FIRST QUARTER REPORT, 2015
FT Net Shed Code Compliance 
Project: E104838               FT Net Sheds 3-11: Improvements  Project Status:
Budget: $2,950,000             required per City of Seattle building  Schedule: Delayed
Phase: Construction             & fire codes.                  Budget: On or Under
Start: 5/1/2012                                            Status Reset: 6/25/2013
Schedule Completion: 6/30/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Port Construction Services completed code compliance improvements to
4
Netsheds 3 and 6 (Netsheds 5, 9, 10 and 11 completed previous quarter).            2.95    2.95
Began retrofit work inside Netshed 3.                                3
2                  1.71
Schedule
1
Netshed retrofit work has taken longer in some netlockers and is impacting      Dollars in Millions
overall construction completion schedule. Currently projecting completing all     0
improvement by fall 2015.                                       Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Project budget is on track.                                        Port Self Perform Construction
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
It is difficult to forecast the amount of stored materials that needs to be moved
out and moved back into the netlockers since tenant storage habits vary
significantly. In addition, the amount of work required in each unit is difficult
to assess until some stored materials are cleared and locker conditions are more
visible. These would impact the overall project schedule and budget.
However, with construction 2/3 complete, budget risks have lessened
significantly since the project budget is trending very well.
Budget Transfers
Amount       From         To
$0

MARITIME 
92  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
T-5 and T-91 Maintenance Dredging 
Project: E104840, U00067          Maintenance Dredge at T-5 all    Project Status:
Budget: $4,800,000             three berths and at T-91 East cruise   Schedule: Delayed
Phase: Design                  berth.                       Budget: On or Under
Start: 8/14/2012                                          Status Reset: N/A
Schedule Completion: 2/28/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
T-5 Maintenance Dredging was completed earlier in 2014.                 6
T-91 East Cruise Berth: The Port continues negotiations with the permitting          4.80    4.80
5
agencies for the preferred under-water regrading alternative to minimize health,    4
safety, and environmental impact, and to reduce costs. Construction is planned    3               2.30
for the 2015-16 in-water construction window.                        Dollars in Millions 2
1
Schedule                                       0
Authorized Forecasted   Costs
T-91 East Cruise Berth is delayed due to permitting complications.
Incurred
Budget
Construction Costs
Project is on budget                                           None at this time
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             2
Amount of Cos           $0          $20,390.33
Justification for COs: None this quarter
Risks
Environmental permitting may cause further delays, scope change, and cost
impact to the T-91 East Cruise Berth Dredging project.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2015 Report  93

FIRST QUARTER REPORT, 2015
T-18 Maintenance Dredging 
Project: U00033                Design, environmental reviews, and Project Status:
Budget: $2,090,000             permitting T-18 Maintenance       Schedule: Within or Ahead
Phase: Design                  Dreddging; Advertise and execute    Budget: On or Under
Start: 2/10/2015                 an on-call major construction       Status Reset: N/A
Schedule Completion: 2/28/2016   dredging contract               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission approved design and permit phase of the project on February 10,
2.5
2015. Design and permitting work is underway.                                 2.09
2
Schedule
Project is on schedule.
1.00
1
Budget                                     Dollars in Millions 1.5 0.5           0.15
0
Project is on budget.                                                Authorized Forecasted  Costs
Incurred
Change Order
Construction Costs
Current Quarter     Project Total
None at this time
Number of COs           0             0
Amount of Cos           $0             $0          Photo
Risks
Project is within an EPA Superfund site requiring additional reviews and
coordination with permitting agencies.
Budget Transfers
Amount       From         To
$0




MARITIME 
94  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
IHI Crane Removal 
Project: U00099                Remove three IHI Cranes from     Project Status:
Budget: $1,500,000             Terminal 18                   Schedule: Delayed
Phase: Construction                                       Budget: On or Under
Start: 9/11/2012                                          Status Reset: 9/11/2012
Schedule Completion: 1/23/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The agreement between PMA and longshore has not been ratified by the rank
2
and file member. As such, the contractor is in a holding pattern. Staff is             1.50    1.50
working out the terms of the change order. Once direction is established, staff     1.5
will begin execution of the change order.                             Dollars in Millions 1
Schedule                                      0.5            0.20
Currently the project is on hold. Once the change order is executed, restarting      0
the project schedule will be re-established.                                Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project is within budget.                                     None at this time
Change Order                               Photo
Current Quarter     Project Total
Number of COs          06             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Anticipate additional project costs for the contract termination for convenience
or contract suspension and subsequent reactivation costs.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2015 Report  95

FIRST QUARTER REPORT, 2015
ID Badge System Replacement 
Project: C800162               Procurement and replacement of    Project Status:
Budget: $2,500,000             the Portwide ID Badge system      Schedule: Delayed
Phase: Implementation          including software, hardware, and    Budget: On or Under
Start: 5/1/2012                  equipment.                   Status Reset: N/A
Schedule Completion: 9/30/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The first phase of the new Badge System deployed on November 5th. A 2nd     2.6   2.50    2.50
deployment to add mobile functionality and authorized signer efficiencies is in    2.5
the implementation stage.
Schedule                                                   2.12
Prior Report: Resource availability and system complexity have delayed project   Dollars in Millions 2.42.32.2 2.1
2
completion.                                               1.9
Authorized Forecasted   Costs
Incurred
Budget
On budget                                            Construction Costs
Not Applicable
Change Order
Current Quarter     Project Total
Number of COs           0             1
Amount of Cos           $0           $108,497
Justification for COs: None this quarter
Risks
Resource availability may continue to delay the second phase mobile
deliverables.
Budget Transfers
Amount       From         To
$0



CORPORATE 
96  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Network Switch Replacement 
Project: C800323               Upgrade the Network switch      Project Status:
Budget: $1,500,000             infrastructure hardware and        Schedule: Within or Ahead
Phase: Closeout                software.                     Budget: On or Under
Start: 12/15/2013                                         Status Reset: N/A
Scheduled Completion: 3/31/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project is complete. This will be the last report.                         1.55
1.50      1.50
Schedule                                      1.5
On schedule                                             1.45 Dollars in Millions               1.40
1.4
Budget
On budget                                             1.35
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: None this quarter
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0





CORPORATE 
Port of Seattle 1Q 2015 Report  97

FIRST QUARTER REPORT, 2015
Terminal 91 Visitor Management 
Project: C800436               Upgrade of the Radio System Core  Project Status:
Budget: $520,000               Hardware and Software and        Schedule: Within or Ahead
Phase: Implementation          Dispatch Consoles.             Budget: On or Under
Start: 7/1/2013                                            Status Reset: 11/4/2014
Scheduled Completion: 5/1/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Development and implementation is in progress.                       0.6   0.52    0.52
0.5
Schedule
On schedule                                             Dollars in Millions 0.40.30.2              0.09
Budget                                     0.1
We are estimating a budget underrun of approximately $1,500,000.             0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Expected grant extensions not approved. The project will need to be
substantially delivered by August 2015. Mitigation plans in progress.
Budget Transfers
Amount       From         To
$0




CORPORATE 
98  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Contractor Data System Upgrade 
Project: C800519               Upgrade of the Contractor Data    Project Status:
Budget: $1,500,000             System used by Engineering and     Schedule: Within or Ahead
Phase: Implementation          other groups to track contracts for    Budget: On or Under
Start: 7/1/2013                  construction projects.            Status Reset: N/A
Schedule Completion: 2/28/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Development is in progress.                                     2
1.50      1.50
Schedule                                      1.5
On schedule                                          Dollars in Millions 1
0.5
Budget                                                 0.16
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0





CORPORATE 
Port of Seattle 1Q 2015 Report  99

FIRST QUARTER REPORT, 2015
Computer Dispatch System Upgrade 
Project: C800520               Upgrade Computer Dispatch      Project Status:
Budget: $790,000               System used by 911 and           Schedule: Within or Ahead
Phase: Implementation          Emergency Responders.          Budget: On or Under
Start: 4/1/2014                                            Status Reset: N/A
Schedule Completion: 8/31/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Upgrade is in progress.                                         1
0.79      0.79
0.8
Schedule
0.6
On schedule
0.4
Budget                                     Dollars in Millions 0.2           0.08
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0




CORPORATE 
100  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Construction Document Management 
Project: C800521               Replacement of the Construction   Project Status:
Budget: $900,000               Document Management System;     Schedule: Delayed
Phase: Implementation          used by Construction Management,   Budget: On or Under
Start: 9/10/2013                 to accept, review, and distribute     Status Reset: N/A
Schedule Completion: 9/30/2015    critical documentation.           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Procurement is complete and implementation is in progress.                 1   0.90    0.90
0.8
Schedule
Procurement took 7 months longer than planned to complete, resulting in a 6-    Dollars in Millions 0.60.4                                                         month delay to the project.
0.2                      0.07
Budget                                      0
Authorized Forecasted   Costs
On budget                                                           Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0




CORPORATE 
Port of Seattle 1Q 2015 Report  101

FIRST QUARTER REPORT, 2015
Radio System Upgrade 
Project: C800586               Upgrade of the Radio System Core  Project Status:
Budget: $6,750,000             Hardware and Software and        Schedule: Within or Ahead
Phase: Closeout                Dispatch Consoles.              Budget: On or Under
Start: 6/9/2013                                            Status Reset: 11/4/2014
Scheduled Completion: 3/31/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project Completed                                         8
6.75
Schedule                                       6       4.80   4.60
On schedule                                             Dollars in Millions 4
2
Budget
We are estimating a budget underrun of approximately $2,000,000.             0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0





CORPORATE 
102  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Noise Monitoring System Replacement 
Project: C800693               Replacement of the Airport Noise   Project Status:
Budget: $1,900,000             Monitoring System              Schedule: Within or Ahead
Phase: Implementation                                   Budget: On or Under
Start: 4/1/2015                                            Status Reset: N/A
Scheduled Completion: 8/31/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Implementation is in progress.                                        1.90    1.90
2
Schedule                                      1.5
On schedule                                              1
Budget                                     Dollars in Millions 0.5
0.08
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: None this quarter
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0





CORPORATE 
Port of Seattle 1Q 2015 Report  103

FIRST QUARTER REPORT, 2015
Expense Project Authorizations 
Project: C800694               Expand planning, tracking, and    Project Status:
Budget: $650,000               commitment control capabilities in   Schedule: Within or Ahead
Phase: Implementation          PeopleSoft Financials System that    Budget: On or Under
Start: 6/3/2014                  will cover an entire authorization    Status Reset: N/A
Scheduled Completion: 7/31/2015  with both capital and expense       (Commission Construction Auth.)
project components.
Significant Developments                             Budget/Costs Incurred
Implementation is in progress.                                    0.8
0.65      0.65
Schedule                                      0.6
On schedule                                             Dollars in Millions 0.40.2              0.14
Budget
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0





CORPORATE 
104  Port of Seattle 1Q 2015 Report

FIRST QUARTER REPORT, 2015
Parking System Replacement 
Project: C800728               Replacement of the Airport Main     Project Status:
Budget: $5,500,000             Garage Parking System            Schedule: Within or Ahead
Phase: Planning                                          Budget: On or Under
Start: 1/6/2015                                            Status Reset: N/A
Scheduled Completion: 6/30/2017                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Port did not receive the number of bids expected from the original          6   5.50    5.50
procurement advertising. Adjusted the process and the procurement is re-        5
advertised to reach additional potential vendors.                         Dollars in Millions 4
3
Schedule
2
On schedule                                              1
0.02
0
Budget                                       Authorized Forecasted  Costs
Incurred
On budget 
Construction Costs
Change Order                               Not Applicable
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
We expect the procurement process changes to engage other vendors but the
risk remains that we may not receive the number of responses desired. In
addition, the re-advertising could delay the project up to three months. At this
time, we expect this delay to be accommodated in the contingency.
Budget Transfers
Amount       From         To
$0



CORPORATE 
Port of Seattle 1Q 2015 Report  105

FIRST QUARTER REPORT, 2015
Human Capital Management System Upgrade 
Project: C800745               Upgrade of the Human Capital     Project Status:
Budget: $1,500,000             Management system.             Schedule: Within or Ahead
Phase: Implementation                                   Budget: On or Under
Start: 2/24/2015                                          Status Reset: N/A
Schedule Completion: 12/31/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Implementation is in progress.                                    2
1.50      1.50
Schedule                                      1.5
On schedule                                              1
Budget                                     Dollars in Millions 0.5
0.02
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0





CORPORATE 
106  Port of Seattle 1Q 2015 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.