4h

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      4h 
ACTION ITEM 
Date of Meeting     April 28, 2015 
DATE:    April 22, 2015 
TO:      Ted Fick, Chief Executive Officer 
FROM:   Michael Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  2015 Apron Pavement Replacement (CIP #C102573) 

Amount of This Request:    $1,561,000       Source of Funds:  Airport Development
Fund and Future
Revenue Bonds 
Est. Total Project Cost:     $1,761,000 
Est. State and Local Taxes:   $ 113,000 

ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to approve and execute a
construction change order for 2015 Apron Panel Replacement (CIP #C102573) to be included in
the Runway 16C/34C Reconstruction (CIP #C800406) or alternatively to advertise and execute a
construction contract, at the discretion of the Chief Executive Officer, based on efficiency and
cost-effectiveness. This authorization is for $1,561,000 and the cost for the complete project is
$1,761,000. 
SYNOPSIS 
The 2015 Apron Panel Replacement project is part of an ongoing Pavement Management and
Maintenance Program (PMMP) as required by the Federal Aviation Administration. The PMMP
includes replacing aged and distressed pavement in non-runway areas. Many sections of airfield
pavement have exceeded their 20-year service life and have become cracked and damaged. The
PMMP is necessary for safe and efficient aircraft operations. This project is included in the
2015-2019 capital budget and plan of finance. 
BACKGROUND 
The 2015 Airfield Pavement Replacement project is a continuation of the programmatic
approach of replacing distressed concrete pavement as part of a multi-year program.
Maintaining critical airfield assets with the PMMP maintains the integrity of airfield pavement

Template revised May 30, 2013.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 22, 2015 
Page 2 of 7 
and efficient airport operations. Deferring panel replacement could potentially increase risk to
airfield operations, airline operations and drive costs higher in the future.
A project labor agreement will be used for this project in order to reduce risk to operations
caused by potential work interruptions. This was approved by Commission November 11, 2014, 
in conjunction with design authorization.
This project is not impacted by and has no conflict with the proposed Sustainable Airport Master
Plan. 
PROJECT JUSTIFICATION AND DETAILS 
2015 Apron Panel Replacement is the proactive program to maintain the reliability and safety of
airfield pavement, reducing risks of operational and airline damage, delays and increased costs. 
Project Objectives 
Replace failed pavement as part of the PMMP 
Provide stable and safe pavement conditions 
Support the Port's Century Agenda 
Scope of Work 
This project will include demolition and replacement of approximately 20 distressed concrete
pavement panels, temporary and permanent striping and temporary modification to airfield
lighting. 
Schedule 
Commission Authorization                             2nd Quarter   2015 
Change Order Execution                               2nd Quarter   2015 
Construction Complete                                4th Quarter   2015 
FINANCIAL IMPLICATIONS 
2015 Apron Pavement Replacement 
Budget/Authorization Summary              Capital     Expense   Total Project 
Original Budget                     $30,800,000          $0   $30,800,000 
Previous Budget Decrease               $6,197,787         $0    $6,197,787 
Revised Budget                     $24,602,213         $0   $24,602,213 
Previous Authorizations                $27,879,495          $0   $27,879,495 
Current request for authorization            $1,561,000          $0    $1,561,000 
Total Authorizations, including this request    $29,440,495          $0    $29,440,495 
Remaining budget to be authorized               $0          $0          $0 
Total Estimated Project Cost             $24,602,213          $0   $24,602,213

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 22, 2015 
Page 3 of 7 

The authorized amount exceeds the revised budget due to budget savings on previously
authorized work under this program. 
Project Cost Breakdown                     This Request       Total Project 
Design Phase                                   $0         $2,374,265 
Construction Phase                          $1,448,000        $22,303,706 
State & Local Taxes (estimated)                   $113,000         $1,685,242 
Total                                      $1,561,000         $26,363,213 
Budget Status and Source of Funds 
2015 Apron Pavement Replacement, CIP C#102573, is included in the 2015-2019 capital budget
and plan of finance. The funding sources will include the Airport Development Fund and future
revenue bonds. The Port plans to issue revenue bonds in 2015 to fund multiple projects. 
Financial Analysis and Summary 
CIP Category             New/Enhancement 
Project Type              Renewal & Replacement 
Risk adjusted discount rate     N/A 
Key risk factors             N/A 
Project cost for analysis        $1,761,000 
Business Unit (BU)          Airfield Apron Area Cost Center 
Effect on business performance  NOI after depreciation will increase 
IRR/NPV             N/A 
CPE Impact             $.01 by 2016, but no change to business plan forecast as
this project was included. 
Lifecycle Cost and Savings 
Annual Operating and Maintenance costs are not anticipated to change appreciably. The
replacement of concrete panels will result in cost avoidance for maintaining them. 
STRATEGIES AND OBJECTIVES 
Maintaining critical airfield assets through proactive distressed pavement replacement supports 
the Port's Century Agenda objective to "Meet the region's air transportation needs at Seattle-
Tacoma international Airport for the next 25 years." These projects also support the Aviation
Division's strategic goals of operating a world-class international airport, providing an
extraordinary customer service. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1)  Status Quo - This alternative will not replace distressed concrete pavement. 
Pros:

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 22, 2015 
Page 4 of 7 
Yearly budget savings, reduced construction traffic on the airfield and
fewer disruptions to airline operations.
Cons: 
Distressed and damaged concrete panels continue to deteriorate, possibly 
to the point of needed emergency repairs at significantly higher cost and
creating even greater risk of producing damaging foreign object debris.
This is not the recommended alternative. 
Alternative 2)  Replace distressed apron pavement during the 2015 construction season by
separate contract. 
Pros:
Maintaining strong and stable runway and apron surfaces through a
consistent and proactive program allows for budget management and
maintains the safety and integrity of the pavement, reducing potential
production of foreign object debris.
Staff inspects the airfield pavement a number of times each year to track
panels and larger pavement sections that are deteriorating and in need of
replacement. Only the areas which have major damage and are in
imminent danger of failing have been included in this alternative. 
Cons: 
Possibility of limited (single bid) or irregular bid which would delay work
outside of dry construction period. 
Limited ability to add/include last minute identified stressed or damaged
panels. 
This is not the recommended alternative. 
Alternative 3)  Replace distressed apron pavement during the 2015 construction season by
Change Order to existing Runway 16C/34C Reconstruction contract. 
Pros:
Greater assurance or work completion in the dry summer construction
season. 
Able to utilize same testing and QC consultant 
More flexibility to accommodate any last minute identified
distressed/damaged panels. 
Reduces soft costs and reduces Construction Management staffing needs 
Maintaining strong and stable runway and apron surfaces through a
consistent and proactive program allows for budget management and
maintains the safety and integrity of the pavement, reducing potential
production of foreign object debris.
Staff inspects the airfield pavement a number of times each year to track
panels and larger pavement sections that are deteriorating and in need of

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 22, 2015 
Page 5 of 7 
replacement. Only the areas which have major damage and are in
imminent danger of failing have been included in this alternative. 
Cons: 
Possible unsuccessful negotiation for the additional work would require
expedited pursuit of Alternative 2. 
This is not the recommended alternative.
Alternative 4)  Replace distressed apron pavement during the 2015 construction season by
Change Order to existing Runway 16C/34C Reconstruction contract or alternatively advertise
and execute a separate construction contract.  Implement whichever alternative the CEO
determines to be the most operationally acceptable and cost effective. 
Pros:
Provides the Port with the ability to choose the most efficient and cost
effective means to complete the work within the 2015 construction season. 
Allows the Port to quickly shift to an alternative procurement method and
still get the project completed in a timely manner. 
Cons: 
Prolonged and unsuccessful change order negotiations may impact the
Port's ability to shift to an alternative procurement method and maintain
the project schedule. 
Project may get delayed to the 2016 construction season and extensive
pavement maintenance would be required in 2015. 
This alternative addresses both operational/safety needs and operational/construction schedule
timing. This is the recommended alternative. 

ATTACHMENTS TO THIS REQUEST 
Attachment A: Panel Replacement Locations 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
On November 11, 2014, the Commission authorized for the Chief Executive Officer to 1)
design, prepare construction document, and implement temporary measures as necessary
to replace distressed pavement and joint sealant for the 2015 Airfield Pavement
Replacement Program at Seattle-Tacoma International Airport (Sea-Tac) in the amount of
$200,000 and 2) for the utilization of a project labor agreement (PLA) for this project.
The total estimated project cost is $1,761,000.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 22, 2015 
Page 6 of 7 
On July 1, 2014, the Commission authorized the rejection of all bids received for the
previously advertised contract for the 2014 Airfield Pavement Replacement Project and
authorized the re-advertisement of a revised project. 
On August 6, 2013, the Commission authorized the use of a project labor agreement for
the 2014 Airfield Pavement Replacement Program. 
On April 2, 2013, the Commission authorized $300,000 and for the Chief Executive
Officer to complete the design and perform any advance preparatory work for the 2014
Airfield Apron Pavement Replacement Program 
On March 26, 2013, the Commission authorized for the Chief Executive Officer to
advertise and execute a single construction contract comprised of Airfield Panel
Replacement and Joint Seal Replacement (CIP #102573) and Runway 16C/34C Panel
Replacement. This authorization request is for $8,967,000, and the estimated total cost of
the complete project is $9,377,000.
On July 24, 2012, the Commission authorized $200,000 and for the Chief Executive
Officer to complete the design and perform any advance preparatory work for the 2013
Airfield Apron Pavement Replacement project. 
On April 10, 2012, the Commission authorized an additional $1,467,000because the 
bids  exceeded the engineer's estimate by greater than 10 percent; and authorized the
Chief Executive Officer to execute a contract in the amount of $6,553,964 with the low 
responsive and responsible bidder for the 2012 Exterior Gates and Airfield Improvement 
Projects. This authorization increased the budget by $1,467,000 due to the higher than 
expected bids, for a total project cost of $10,500,000. 
On January 24, 2012, the Commission authorized $4,707,000 and for the Chief 
Executive Officer to advertise and execute a construction contract that included Apron 
Pavement  Replacement,  Exterior  Gate  Improvements,  Runway  16C/34C Panel 
Replacement, and  South Snow Dump Pavement Expansion. 
On July 26, 2011, the Commissionauthorized $465,000 and for the Chief Executive 
Officer to complete the design and perform any advance work in support of the 2012 
Pavement  and  Joint Replacement  and  Sealant  Project  for  non-runway  concrete
pavement  panels, joint seal replacement, spall repair, and associated or temporary 
facilities, such as  striping, lighting, etc., on the Aircraft Operations Area. 
On March 1, 2011, the Commission authorized $6,235,000 and for the Chief
Executive  Officer to advertise and execute a construction contract that included slot
drain,  pavement, and joint seal replacement at the South Satellite and perform 
installation of temporary facilities in concourses.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 22, 2015 
Page 7 of 7 
On August 10, 2010, the Commission authorized $394,000 and for the Chief Executive 
Officer to direct staff to: 1) proceed with project management, design, environmental
support, and preparation of 100 percent design level construction documents for the 
replacement of slot drains, pavement and joint seal at the South Satellite at Seattle- 
Tacoma  International Airport; 2) execute  and  award outside professional  service 
agreements;  3)  pre-purchase common-use  gate equipment; and  4)  allow  Port
Construction  Services to self-perform, advertise for bids, and execute and award small 
works construction contracts for common use equipment installation.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.