6d

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      6d 
ACTION ITEM 
Date of Meeting     April 28, 2015 
DATE:    April 21, 2015 
TO:      Ted Fick, Chief Executive Officer 
FROM:   Ralph Graves, Director, Capital Development Division 
Joe McWilliams, Managing Director, Real Estate Division 
SUBJECT:  Request Authorization to Execute Lease Agreement with SEATAC VENTURES
2010 LLC for International Arrivals Facility (IAF) Program Management Office
Space near Sea-Tac International Airport. 
Amount of This Request:             $0   Source of Funds:   Airport Development
Fund, Passenger
Est. Total Project Cost:        $608,000,000                  Facility Charges and
future Revenue
Bonds 
Estimated Lease Value:         $1,995,285 

ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to execute a lease agreement
with SEATAC VENTURES 2010 LLC, as Landlord, for IAF Program Management Office
Space near Sea-Tac International Airport for four years for an estimated cost of $1,995,285. 
Funding for this lease is included in the overall IAF program budget and authorization. 
SYNOPSIS 
During interviews with other airport operators in San Diego, San Jose and San Francisco, it was
learned that co-location is a key best practice in the successful management of large Progressive
Design-Build (PDB) programs. It was revealed that providing co-located office space for both
the Owner and the Design-Builder engendered a much more collaborative and productive work
environment than maintaining separated work locations.
Several different locations have been evaluated by staff for the co-location of the IAF program
teams. It has been determined that renting office space at the nearby SeaTac Office Center,
Building III would best satisfy the space requirements for the combined project team offices and
would also allow the teams to be located close to the jobsite. This lease space would require
minimal improvements to accommodate the project teams and could be ready for occupancy in
time for the project kick-off and validation phases of the IAF Program.

Template revised May 30, 2013.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 21, 2015 
Page 2 of 7 

This Action will authorize the Port to enter into a lease with the SEATAC VENTURES 2010
LLC for a four year term. 
BACKGROUND 
Experts in Progressive Design-Build delivery agree that co-located offices for the Owner and
Design-Build project team staff are a key success factor in the PDB delivery method. Sharing
physical office space results in a more efficient, integrated and collaborative project team and
promotes a greater understanding and achievement of common project goals. Challenges are
identified earlier and resolved faster by co-located teams that enjoy the benefits of increased
face-to-face interaction and more productive working meetings. Early integration of the Port
with the multiple professional disciplines required to design and construct a complex facility,
such as the IAF, will act to shift everyone's focus from the "us versus them" mentality prevalent
in more traditional contract delivery methods to "we're in this together", ultimately resulting in a
more collaborative and collegial working relationship between the teams and, in the end, making 
more likely the delivery of a better performing facility that is on-schedule and on-budget.
The IAF Program's project team currently manages the IAF Program from the Aviation Project
Management Group's offices at the Airport Office Building (AOB) at Sea-Tac International
Airport. The AOB is located relatively close to the future construction site of the IAF, but does
not have vacant space available to house the anticipated 80-plus members of the integrated IAF
team. 
The Port compared several nearby alternatives for their relative available space, proximity to the
jobsite, opportunity costs, up-front cost and effort required to prepare the space for occupancy, 
and ongoing maintenance costs. Leasing space for the team at the SeaTac Office Center,
Building III was selected as the best fit.
Although the proposed site for co-location is on the east side of International Boulevard
(Highway 99) it nevertheless provides easy access to the Airport.  The Aviation Project
Management Group was located in this building complex several years ago and successfully
managed the Airport's Capital Improvement Program during construction of the South Terminal
Expansion  and  Central Terminal Expansion  projects. Additional information a bout the
alternatives evaluated for the IAF Program Management Offices is included in the Alternatives
section, below. 
SCOPE OF AGREEMENT 
Landlord:             SEATAC VENTURES 2010 LLC 
Tenant:               Port of Seattle

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 21, 2015 
Page 3 of 7 
Term/Effective Date:      A term of forty-eight (48) months to commence on July 1, 2015, or
upon completion of tenant improvements and receipt of a
Certificate of Occupancy. 

Use:                 General Office and Project Management Administration 

Area:                 21,003 rentable square feet of the fourth floor of Building III at the
SeaTac Office Center (17900 International Blvd. S, Seattle, WA,
98188), including the existing Suite 400 and part of Suite 402. 

Rental:                 Rental rate scheduled is based on a triple net (NNN) lease. 
Months 01 - 12 @ $13.25/sq.ft./yr. = $23,190.81/month 
Months 13 - 24 @ $14.25/sq.ft./yr. = $24,941.06/month 
Months 25 - 36 @ $15.25/sq.ft./yr. = $26,691.31/month 
Months 37 - 48 @ $16.25/sq.ft./yr. = $28,441.56/month 

Tenant Improvements:     Landlord shall provide a tenant improvement allowance up to
$252,036, $12.00 per rentable square foot (RSF), using building
standard improvements and based on a mutually agreeable space
plan. Tenant shall be responsible for tenant voice and data cabling
and any unused portion of the allowance may be used for this
purpose. 

Operating Expenses & 
Real Estate Tax Costs:     Tenant  shall  be  responsible  for  its  pro-rata  share  of
building/complex operating expenses, including, but not limited to,
janitorial services, waste disposal, parking and grounds cleaning
and striping, utilities, insurance, property taxes, property
management fee and premises maintenance and repair, except that
Landlord shall be responsible for the building roof, structural
elements, and parking lot replacement.  No operating expenses
shall be payable during the tenant improvement construction or
free rent periods. Landlord currently estimates operating expenses
at $9.00 per RSF for a total annual cost of $189,027.00. The
estimated lease value includes $756,108 total for four years of
operating expenses.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 21, 2015 
Page 4 of 7 
Security Deposit:         Not required. 

Parking:               Eighty-four stalls are included in the lease rate, four (4) 
stalls to be provided per 1,000 RSF leased. 
FINANCIAL IMPLICATIONS 
Budget Status and Source of Funds 
A previous Commission authorization approved initial capital funding for establishment of the
co-located IAF Program Management Offices. Future authorization requests will include capital
funds for rent and monthly operating expenses for the remaining duration of the IAF Program. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Six different co-location alternatives were evaluated for criteria such as; available space for
project team, proximity to IAF job site, opportunity cost, upfront cost, monthly maintenance cost
and duration required for preparing the space for occupancy. Cost estimates were only prepared
for spaces considered large enough to accommodate the project team. 

Alternative 1)  Airport Parking Garage Former Rental Car Offices. This option would
house the IAF program team in offices located on the 1st floor of the parking garage formerly
used by rental car companies. Estimates were not prepared for this option since the space could
not accommodate the project team. This is not the recommended alternative. 
Pros:
This option is located close to the IAF jobsite.
Cons:
This option proved to be too small to accommodate project staff and the necessary
conference spaces. 
This is also considered leasable space that could generate revenue for the Port. 
Alternative 2)  Airport Parking Garage Former Rental Car Offices, plus existing IAF
AOB offices. The team evaluated keeping existing Port IAF staff in their AOB offices plus
using the rental car offices evaluated in Alternative 1. Estimates were not prepared for this option
since the two spaces combined could not accommodate the project team.   This is not the
recommended alternative. 
Pros:
Existing staff would not need to relocate.
Cons:
Those combined spaces would still not accommodate anticipated Port and Design-
Build project team staff.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 21, 2015 
Page 5 of 7 
Splitting up the team would not permit the Port to capitalize on the proven benefits of
co-location. 
Reduced efficiency because the number and duration of trips made between the two
spaces for meetings would increase.
Alternative 3)  Phased Co-Location from Parking Garage to SeaTac Office Center. This 
option would locate Port and Design-Build project team staff at the Parking Garage offices
through Validation and then move them to the SeaTac Office Center once design and
construction begin. Estimates were not prepared for this option since the Parking Garage office
space could not accommodate the Validation phase project team.  This is not the recommended
alternative. 
Pros:
If the Parking Garage space was large enough, this option would delay payment
of rent for office space.
Cons:
The Parking Garage offices are not large enough to house the project team staff
that will be brought on board during Validation and it would not provide the
number of conference spaces required to work efficiently.
This option would require fit-out of two project office spaces instead of one,
making it a more expensive option. 
Alternative 4)  Trailer Complex on Tyee Golf Course parking lot. This option would house
the co-located IAF Program Team in a complex of construction trailers in the parking lot of the
Tyee Golf Course located at the south end of the Airport's runways. Rough order of magnitude
(ROM) costs for this alternative is $3,700,000 for upfront costs and four years of monthly
maintenance and utility costs. This is not the recommended alternative. 
Pros:
The site is large enough to accommodate the IAF team.
Cons:
The drive time from this location to the IAF jobsite would be approximately 10-15
minutes and would necessitate establishment of an IAF fleet of vehicles.
This option would require the Port to purchase or rent two-story modular buildings
and make site improvements in order to fit the entire team at this location.
Site improvements and procurement of modular structures is estimated to take
significantly longer than other options and could not be accomplished prior to start of
design and construction.
This site would be better used for contractor logistics and/or laydown area during
construction. 
Alternative 5)  Trailer Complex on IAF jobsite. This option would locate IAF staff in
trailers on the IAF jobsite. ROM estimate for initial costs and operating expenses is $4,000,000.
This is not the recommended alternative.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 21, 2015 
Page 6 of 7 

Pros: 
This option provides easiest access to the construction site.
Cons: 
The size of the trailer complex required to accommodate the Port and Design-
Build project team would almost completely negate critical contractor laydown
area needed for onsite construction.
Locating the trailers on site would also drive additional relocation of airline
ground service equipment, Port maintenance functions, and Air Operations Area
(AOA) fence and security gates.
Due to the shape of the IAF jobsite, the trailers would physically impede
construction access to the site and impact air operations at the south end of
Concourse A. 
This option carries a high cost for the trailer complex and would require site
improvements. 
Alternative 6)  IAF Offices in SeaTac Office Center, Building III. This option would
establish the co-located IAF Project Management Offices in rental office space. ROM estimate
for this option is $2,700,000 for upfront costs, rental costs, utilities and operating expenses. This
is the recommended alternative. 
Pros: 
There is adequate contiguous vacant space (21,000 sq. ft.) available in Building III,
requiring only minimal tenant improvements to meet the office and meeting space
needs of the IAF program.
Building III is located across the street from the IAF jobsite, about a 5-minute walk
away. 
This space could be made ready for occupancy quickly, at a minimal cost and in a
short timeframe, so the Port and Design-Build co-located team could begin working 
from this space starting as early as project Kick-Off and Validation.
Cons: 
Although already included in the project budget, this option requires the project, and
therefore the Port, to pay rent for office space. 

ATTACHMENTS TO THIS REQUEST 
None. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
February 24, 2015  Service Agreement for IAF Consultant Program Leader. 
January 27, 2015  IAF Funding Plan. 
January 27, 2015  IAF RFP Advertisement.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 21, 2015 
Page 7 of 7 
January 13, 2015  IAF Update. 
December 2, 2014  IAF Scope and Budget Update. 
October 28, 2014  IAF Q3 Quarterly Briefing. 
August 19, 2014  IAF Q2 Quarterly Briefing. 
August 5, 2014  IAF RFQ Advertisement. 
July 22, 2014  IAF Progress Briefing. 
June 10, 2014  IAF Update and Quarterly Briefing. 
May 6, 2014  IAF Project Delivery Briefing. 
April 22, 2014  Capital Program Briefing. 
March 11, 2014  IAF Master Planning authorization. 
February 25, 2014  IAF Program Briefing. 
November 19, 2013  International Arrivals Facility Construction Management, testing
and inspection; surveying and locating and safety service agreements. 
July 23, 2013  International Arrivals Facility Project & Program Support; and Price
Factor Design-build Methodology authorization. 
July 9, 2013  Sea-Tac Airport International Arrivals Facility Briefing. 
July 9, 2013  Alternative Public Works Contracting Briefing. 
April 9, 2013  Sea-Tac Airport International Arrivals Facility Briefing. 
June 26, 2012  Briefing on Airport Terminal Development Challenges at Seattle-
Tacoma International Airport. 
June 14, 2011  International Air Service Growth and Future Facility briefing. 
February 2, 2010   Briefing on South Satellite Passenger Growth and Facility
Considerations, Delta's Proposed Airline Lounge and Other Possible Future Aviation
Projects.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.