Item Number: 7d_Report
Meeting Date: March 24, 2015


Commission Staff Brieng
Capital Improvement Projects
Fourth Quarter Report 2014

This page intentionally left blank









ii  Port of Seattle 4Q 2014 Report

Port of Seattle
Capital Improvement Project Report
Fourth Quarter 2014
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2014, the Port plans to invest $295,200,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such, the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes "Project Status" illustrating at a
glance if the project is on schedule, and within budget, and the date Construction authorization was received.
x  Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x  Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x  Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
x  Change Orders provides information on current quarter's COs and total project COs including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
x  Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x  Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x  Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 4Q 2014 Report  1

Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C101107 ................160th GT Lot ..........................................................6 ...........
C102032 ...............Sanitary Sewer Pump Station Upgrade ................7 ........... ..............................
C102112 ................Hennelly Service Tunnel Renewal Rep .................8 ...........
C102573 ...............Aireld Pavement Replacement ............................9 ...........
C800019 ...............Gate Utilities Improvement ...................................10 ..........
C800034 ...............North Expressway Relocation ..............................11 ..........
C800061 ...............Main Terminal South Low Voltage ........................12 ..........
C800107 ...............C4 UPS System Improvements ............................13 .......... .............................. 
C800168 ...............C60-C61 BHS Modications ................................14 .......... .............................. 
C800218 ...............Security Exit Lane Breach Control Phase I ..........15 ..........
C800230 ...............Emergency Lighting Parking.................................16 .......... 
C800238 ...............Central Plant Pre-Conditioned Air ......................17-18 ........
C800247 ...............Cargo 2 West Hardstand ......................................19 .......... ..............................
C800251 ...............Vertical Conveyance Modernization.....................20 ..........
C800253 ...............Parking System Replacement ..............................21 .......... ..............................
C800254 ...............Aircraft RON Parking Post Ofce Site..................22 .......... .............................. 
C800274 ...............8th Floor Weather Proong ..................................23 .......... 
C800324 ...............Long-Term Cell Phone Lot ....................................24 .......... ..............................
C800334 ...............Two new CTE Freight Elevators ...........................25 .......... ..............................
C800335 ...............EGSE Electrical Charging Stations ................... 26-27 ....... ..............
C800368 ...............Refurbish Bag Claim Device 8..............................28 ..........
C800376 ...............SSAT HVAC Lights Ceiling Repl...........................29 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ............................ 30-31 .......
C800390 ...............Cargo 6 Enhancements ..................................... 32-33 ....... ..............................
C800406 ...............RW 16C/34C Reconstruction ...............................34 ..........
C800426 ...............FIS Improvement - Short Term .............................35 .......... ..............
C800451 ...............Doug Fox Site Improvement ..............................36-37 ....... .............. ..................
C800464 ...............Fiber Infrastructure to Gate Backstands ..............38 .......... .............................. 
C800479 ...............Fire Station Electrical Upgrades ...........................39 ..........
C800495 ...............Facility Monitoring System Renewal ....................40 .......... ..............................
C800497 ...............Airport Wide Mechanical Controls System ..........41 ..........
C800541 ...............RAC Baggage Claim Renovation .........................42 .......... ..............................
C800543 ...............Replace PLBs at S7, S9, B4 .................................43 ..........
C800544 ...............NorthSTAR Program.............................................44 ..........
C800545 ...............NorthSTAR Main Terminal Improvements............45 ..........



2  Port of Seattle 4Q 2014 Report

Aviation, cont.
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............46 ..........
C800549 ...............SSAT Interior Renovations ...................................47 ..........
C800550 ...............Concourse D Roof Replacement..........................48 .......... .............................. 
C800551 ...............Grease Interceptor Augmentation ........................49 .......... ..............................
C800555 ...............NorthSTAR Refurbish Baggage Systems ............50 ..........
C800556 ...............NorthSTAR North Satellite Lobbies ................... 51-52........
C800557 ...............Snowblower and Deicer Trucks ............................53 ..........
C800560 ...............MT Mezzanine Tenant Relocation ........................54 ..........
C800576 ...............Known Crew Member Employee Bypass .............55 .......... ..............................
C800581 ...............Parking Garage Lights ..........................................56 ..........
C800583 ...............International Arrivals Facility ................................57 ..........
C800585 ...............Wi-Fi Enhancement for Ramp and Terminal ........58 .......... .............................. 
C800609 ...............NSAT - STS Ceiling Leak Repair ..........................59 .......... ..............................
C800612 ...............Checked Baggage Recapitalization/Optimzation.60 ..........
C800615 ...............Second Floor Mezzanine Infra Upgrade ..............61 .......... ..............................
C800629 ...............S1 Ramp ...............................................................62 ..........
C800637 ...............2014-15 Roof Replacement ..................................63 .......... .............................. 
C800638 ...............Dining and Retail Infrastructure Modernization ....64 ..........
C800642 ...............CCTV Camera-Data Improvements .....................65 ..........
C800651 ...............Town-Country Stormwater Pipe ...........................66 ..........
C800657 ...............Domestic Water Piping .........................................67 ..........
C800658 ...............Mech Energy Conservation ..................................68 ..........
C800659 ...............North Utility Tunnel Steam Pipe ...........................69 ..........
C800662 ...............S4 and S6 IC Connection .....................................70 .......... ..............................
C800667 ...............Automated Passport Control ................................71 .......... .............................. 
C800688 ...............Construction Logistics Expansion ........................72 ..........
Other Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................73 .......... ..............................
C200042 ...............Highline Community College Noise Insulation .....74 ..........
C200048 ...............Home Insulation Retrot .......................................75 ..........
C200093 ...............Single Family Home Sound Insulation .................76 ..........
C800146 ...............RMU/Kiosk Concession Program ........................77 .......... ..............................
C800154 ...............Tenant Reimbursement ........................................78 ..........


Port of Seattle 4Q 2014 Report  3

Seaport
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C102554............... Terminal 46 Development....................................79 ..........
C102858 et al ....... Street Vacations T-5/18/105.................................80 .......... ..............................
C800090 ...............Pier 34 Mooring Dolphins .....................................81 ..........
C800132 ...............T-5 Berth Modernization .......................................82 ..........
C800160 ...............T-91 Lighting Upgrade ..........................................83 .......... ..............................
C800430 ...............T-91 Building C175 Roof Replacement ................84 ..........
C800439 ...............T-91 Substation Upgrades ....................................85 ..........
C800546 ...............Argo Yard Truck Roadway ....................................86 .......... ..............................
C800603 ...............T-46 Dock Rehabilitation ......................................87 .......... ..............................
C800689 ...............T-115 Stormwater Separation ...............................88 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................89 ..........
E104324 ................Viaduct Construction Coordination ......................90 ..........
E104840................T-5, T-18 and T-91 E. Maintenance Dredging ......91 .......... ..............................
U00079 .................Clean Truck Program Truck Scrap & Repl ...........92 ..........
U00099 .................IHI Cranes Removal .............................................93 .......... .............................. 

Real Estate
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800137 ...............FT C15 HVAC Improvements ...............................94 .......... ..............................
C800314 ...............P69 Built-up Roof Replacement ...........................95 ..........
C800344 ...............FT C-2 Nordby Roof and HVAC ..........................96 ..........
C800527 ...............FT Net Shed 9 Roof Replacement .......................97 ..........
C800691 ...............P69 Carpet Replacement .....................................98 .......... ..............................
C800698 ...............P69 Beam Rehab .................................................99 ..........
E104838................FT Net Shed Code Compliance ..........................100 .........




4  Port of Seattle 4Q 2014 Report

Corporate
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800162 ...............ID Badge Replacement .......................................101 ......... ..............................
C800321 ...............Enterprise Project Cost Management ..................102 ......... ..............................
C800323 ...............Network Switch Replacement ..............................103 .........
C800436 ...............Terrminal 91 Visitor Management ........................104 .........
C800519 ...............Contractor Data System Upgrade........................105 .........
C800520 ...............Computer Dispatch System Upgrade ..................106 .........
C800521 ...............Construction Document Management ................107 ......... .............................. 
C800586 ...............Radio Systems Upgrade......................................108 .........
C800693 ...............Noise Monitoring System Replacement ..............109 .........
C800694 ...............Expense Project Authorizations ..........................109 .........

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date









Port of Seattle 4Q 2014 Report  5

FOURTH QUARTER REPORT, 2014
So. 160th GT Lot Expansion
Project Status:
Project: C101107    Renovate existing building for better   Schedule:  within or ahead
Budget: $4,532,000   functionality, improve lot drainage,    Budget:   on or under
Phase: Design     underground existing overhead utility   Status Reset: 11/22/2013
Start: 2/1/2013       lines, fencing and landscaping.       (Commission Design Auth.)
Schedule Completion: 9/30/2015
Significant Developments                   Budget/Costs Incurred
Thirty and ninety percent design for building renovation and site        5          4.5
improvements were completed and reviewed. Negotiations with
4
utility companies to underground existing overhead utility lines along
S. 160th are in progress.                                 Millions 3
2
Schedule                            Dollars in     1.06
1
0.29
Complete design January 2015. Advertisement for bids expected in
0
April 2015, followed by construction and beneficial occupancy in
Authorized   Forecasted  Costs Incurred
September 2015.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: Not Applicable
Risks
Unforeseen building or site conditions could increase design and
construction costs. Complications in executing agreements with
utilities for underground lines are a schedule risk.
Budget Transfers
None

AIRPORT
6  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Sanitary Sewer Pump Station Upgrade
Project Status:
Project:   C102032    Upgrade the aging control systems    Schedule: Delayed
Budget: $1,133,000    of 22 sanitary sewer lift stations.     Budget: On or under
Phase: Construction                        Status Reset: Click here to
Start: 3/1/2013                                   enter a date.
Schedule Completion: 3/31/2015                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Over half of the panels have now been installed. Completed         1.2   1.13    1.13
upgrades to these panels, including adding disconnects where
1
necessary.
Millions 0.8                        0.60
0.6
Schedule
0.4
The project is behind schedule due to changes to the control panels    Dollars in 
0.2
and installation challenges. We are carefully proceeding forward in a
0
manner that minimizes risk during and after system switchover.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2014 Report  7

FOURTH QUARTER REPORT, 2014
Service Tunnel Renewal/Replace
Project Status:
Project:   C102112      Seismically upgrade the Service
Schedule: Within or ahead
Budget: $27,586,000     Tunnel that runs beneath the
Budget: On or under
Phase: Design        departures and arrivals drives of
Status Reset: 8/5/2014
the airport.
Start: 11/4/2012                                  (Commission Design Auth.)
Schedule Completion: 6/1/2018
Budget/Costs Incurred
Significant Developments
27.59
Commission authorized procurement of a design team. Design       30
scope was developed. Designer procurement is in process.         25
Millions 20
Schedule                             15
10
Project is underway, and on schedule.                       Dollars in      4.57
5
0.09
0
Budget                               Authorized Forecasted Costs Incurred
Project is currently within budget.
Change Order                         Construction Costs
None at this time
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
8  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Airfield Pavement Replacement
Project Status:
Project:   C102573     This is a multi-year program to      Schedule: Within or ahead
Budget: $25,343,359    replace distressed pavement and   Budget: On or under
Phase: Design       joint seal on the airfield.        Status Reset: 4/1/2014
Start: 5/2/2010                                  (Commission Construction Auth.)
Schedule Completion: 12/31/2016
Significant Developments                    Budget/Costs Incurred
Beneficial Occupancy was granted on October 22, 2014 for the 2014    30   27.93
25.34
contract. Authorization for design on 2015 Apron Panel             25
20.77
Replacement was received November 11, 2014.               Millions 20
15
Schedule
10
Q3 2014 report showed "Delayed" due to the 2014 project which is in   Dollars in 
5
close out. Current status identifies the 2015 effort scheduled to go
0
out for bid May 2015 with construction beginning in August 2015.         Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.              Construction Costs
20
Change Order                             17.14    16.81
Current Quarter   Project Total             15
Number of COs    3          13
10
Millions
Amount of COs    $52,065      $100,024
Dollars in    5
Justification for COs: 1) Additional distressed panel was found                 0.10
0
south of the South Satellite. Operations felt that it was necessary to         Initial  Change  Spent
replace it. It was replaced in the 4th quarter of 2014. 2).                      Orders
Reconciliation of a Force Account bid item that resulted in a credit
back to the project. 3). Channel Drain Bearing Surface.
Risks
None at this time.
Budget Transfers
None at this time.

AIRPORT
Port of Seattle 4Q 2014 Report  9

FOURTH QUARTER REPORT, 2014
Gate Utility Improvements
Project Status:
Upgrade the Concourse B loading    Schedule: On Schedule
Project:   C800019    bridges to the standard 400Hz power.  Budget: On or Under
Budget: $15,648,312   This will reduce aircraft emissions,   Status Reset: Click here to
Phase: Design      improve energy efficiency and save   enter a date..
Start: 6/28/2007       money for the airlines.            (Commission Construction Auth.)
Schedule Completion:
10/16/2017
Budget/Costs Incurred
Significant Developments
20,000,000
South Satellite Port-owned loading bridges complete.
15.6
15,000,000     13.2
Design contract executed for Concourse B
9.2
10,000,000      Millions
Schedule
5,000,000     Dollars in
Design for Concourse B 400Hz is on schedule
0
Budget                                Authorized Forecasted Costs Incurred
Project is within design budget
Change Order                         Construction Costs
Current Quarter   Project Total             6
5.05           6.26
Number of COs    1          45                  5
Amount of COs    $1,893.00     $331,431.92           Millions  4
3
Justification for COs: Changes to existing conditions - Substantial        2
Completion date was extended by 40 calendar days in order to       Dollars in   1      0.16
complete designer and owner requests, additional room for
0
switchboard request by owner and required by state L &I.                Initial  Change  Spent
Orders
Risks
None
Budget Transfers
None this quarter
AIRPORT

10  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
North Expressway Relocation
Project:   C800034                             Project Status:
Reconstruct the Northern Airport
Budget: $102,564,300                        Schedule: Within or ahead
Expressway, support the extension
Phase: Construction                        Budget: On or under
of light rail to the Airport, and
Start: July 2004                                  Status Reset: 2/20/2014
construct improvements to Wall 14.  (Commission Construction Auth.)
Schedule Completion:
January 2015
Budget/Costs Incurred
Significant Developments
Reconstruction of the Northern Airport Expressway and the light rail      $112.00  110.22
$110.00
transit components are complete. The construction of the Wall 14
$108.00
Improvements is complete and beneficial occupancy was issued      Millions $106.00
November 26, 2014. The replacement of a damaged power conduit     $104.00       102.56  101.96
on S 170th St is also complete.                              $102.00
Dollars in   $100.00
Schedule                             $98.00
$96.00
The Wall 14 improvements and the replacement power conduit are          Authorized Forecasted  Costs
both complete.                                                      Incurred
Budget                            Construction Costs
Project forecast is within the approved budget and authorization.
120                    107.67
The total budget for the Wall 14 Improvements is $1,529,000 and          99.45
100
$120,000 for the replacement power conduit.
Millions 80
Change Order                          60
Current Quarter   Project Total           Dollars in  40
Number of COs        2         237             20        8.38
Amount of COs       $11,570     $8,382,359           0
Initial     Change Order     Spent
Justification for COs: Unknown conditions and scope changes
Risks                               Photo
None identified at this time.
Budget Transfers
None during this period.

AIRPORT
Port of Seattle 4Q 2014 Report  11

FOURTH QUARTER REPORT, 2014
Main Terminal Low Voltage
Project:   C800061   Renewal and replacement of low      Project Status:
Budget: $20,780,000   voltage (600 volts and below) electrical  Schedule: Within or ahead
Phase: Design      distribution equipment in the southern   Budget: On or under
Start: 6/28/2007       part of the Main Terminal           Status Reset: N/A
(Commission Construction Auth.)
Schedule Completion: 7/31/2019
Significant Developments                    Budget/Costs Incurred
Due to project deferral and the possibility of changes in site           25
20.78
conditions and building codes, the design phase changed from 100%
20
to 0% complete. The project was approved by Commission on July    Millions
29, 2014.                                          15
10    7.61
Schedule                            Dollars in  5
Finalized the scope of work, schedule and final design budget. The                      0.675
0
100% design documents are scheduled to be complete by the end of      Authorized  Forecasted Costs Incurred
December 2015.
Budget                            Construction Costs
The project budget was increased. The forecast is within the        Not Applicable
approved budget. Commission Authorization for design funding has
been approved.                                 Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area is a 24/7/365 operation. Sequencing of this work
is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
None this quarter
AIRPORT
12  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
C4 UPS System Improvements
Project Status:
Project:   C800107    Replace existing Uninterruptible Power   Schedule: Delayed Schedule
Budget: $4,555,238   Supply (UPS) System, including      Budget: On or under
Phase: Planning     batteries, with a new system located in  Status Reset: Click here to
Start: 6/28/2007       the Airport Combined Communications   enter a date.
Schedule Completion:  and Command Center (C4).        (Commission Construction Auth.)
2/15/2017
Budget/Costs Incurred
Significant Developments
5             4.56
Due to project deferral, changes to site conditions, and building
codes, the design phase changed from 100% to 30% complete.       4
Notebook has been approved.                          Millions 3   2.34
Schedule                             2
Dollars in 
The project was reactivated. Preliminary Schedule shows            1                0.54
Substantial Completion as February 2017.                     0
Authorized   Forecasted  Costs Incurred
Budget
New estimate has been developed based on new design concept.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total          Photo
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The C4 center is a 24/7/365 operation. Sequencing of this work is
critical and electrical power has to be maintained without
interruptions.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2014 Report  13

FOURTH QUARTER REPORT, 2014
C60 - C61 BHS Modifications
Project Status:
Project:   C800168    This work represents a critical       Schedule: Delayed
Budget: $10,864,825   component to providing improved     Budget: On or under
Phase: Construction   operational baggage in-line screening  Status Reset: 11/5/2013
Start: 6/1/2012        at the South end of the Airport and     (Commission Construction Auth.)
Schedule Completion:  more baggage make-up capacity for
airlines.
2/28/2015
Significant Developments                    Budget/Costs Incurred
MD Moore started Automatic Tag Reader (ATR) and upper level
controls installation after Labor day. The project team will be doing      14
11.86
testing on the ATR's and upper level controls once the installation is     12          10.86
completed and in place. High volume baggage testing will begin in
Millions 10
January.                                         8               6.49
Dollars in   6
4
Schedule
2
Project delayed due to work stoppage during summer high baggage     0
volumes that could not be recovered as expected.                   Authorized  Forecasted Costs Incurred
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
6   5.16
Change Order                           5
3.98
Millions   4
Current Quarter   Project Total
3
Number of COs    2          6
Amount of COs    $31,273      52,000                2
Dollars in    1
0.05
Justification for COs: The change order issued was due to varying        0
Initial   Change   Spent
site conditions.
Orders
Risks
None
Budget Transfers
None

AIRPORT
14  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Security Exit Lane Breach Control - Phase 1
Project Status:
Project:   C800218      Procure and install new automated   Schedule: Within or ahead
Budget: $1,562,000      exit lane breach control equipment  Budget: On or under
Phase: Design        at the Concourse B exit.       Status Reset: Click here to
Start: 3/1/2012                                   enter a date
Schedule Completion: 6/30/2015                  (Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
Equipment was received for post-construction work to convert the
twin door lanes to triple door lanes. Additional authorization received     2
1.56      1.47
January 6, 2015.                                    1.5
Millions                           0.93
Schedule                             1
Starting design effort. Anticipate completion Q2 2015.              Dollars in 0.5
0
Budget                               Authorized Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No major risks at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 4Q 2014 Report  15

FOURTH QUARTER REPORT, 2014
Emergency Lighting - Parking
Project Status:
Project:   C800230     Provide electrical infrastructure for a
Schedule: Within or ahead
Budget: $3,602,717    new source of emergency power to
Budget: On or under
Phase: Construction   feed the parking garage emergency
Status Reset: Click here to
Start: 7/24/2012        lighting circuits and ensure that code-
enter a date.
Schedule Completion:   required level of egress illumination is
(Commission Construction Auth.)
provided for safety.
7/16/2014

Significant Developments                    Budget/Costs Incurred
Contractor has completed the job. The Port has final installations to     5   4.60
complete.
4            3.60
Schedule                            Millions 3          2.34
Monitoring on the ESCO project has been completed; however, we      2
are still waiting for the verification report before the project can be      Dollars in  1
closed.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
2   1.69
Current Quarter   Project Total                        1.58
Number of COs    0          0                   1.5
Amount of COs    $0         $0                 Millions  1
Justification for COs: n/a                                   Dollars in   0.5
0.00
0
Risks                                   Initial Change Spent
Orders
None
Budget Transfers
None

AIRPORT

16  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Central Plant Pre-Conditioned Air
Project:   C800238     Provide a centralized pre-conditioned  Project Status:
Schedule: Within or ahead
Budget: $54,310,463    air (PC-Air) plant (PCAP), associated
Budget: On or under
Phase: Construction    heating and cooling piping systems,
and jet bridge terminal air handling    Status Reset: 2/25/2014
Start: 6/15/2009                                  (Commission Construction Auth.)
Schedule Completion:   units to serve airplanes with heating
and cooling while at the gates.
8/31/2013
Significant Developments                    Budget/Costs Incurred
The major-works Contractor's construction is complete. PC-Air is       56
54.31
operating at 68 gates. Work on the four remianing gates is in          54
progress. Completion is scheduled for 1Q 2015. Design to replace     Millions 52
the chilled water insulation, anchor and guides on Concourse A and
50    49.22
the anchors and guides on Concourse B, C and South Satellite will                      47.83
begin in 1Q 2015..                                    Dollars in  48
46
44
Schedule
Authorized   Forecasted  Costs Incurred
The last four gates will be completed in the first quarter of 2015,
contingent on operational needs.
Construction Costs
Budget
40
The major works contract is complete. Work for completing the                     35.20
remaining four gates and anchors and guides is within the budget.
Millions   30   27.01
Change Order                           20
8.41
Current Quarter   Project Total           Dollars in   10
Number of COs        28         230
Amount of COs      $1,649,355    $9,886,034             0
Initial   Change   Spent
Orders
Justification for COs: piping and electrical site conflicts on the
concourse and at the gates.
Risks
None at this time
Budget Transfers
None this quarter

Port of Seattle 4Q 2014 Report  17

Cost of Construction Growth
The major-works conctract cost growth occured due to shortcomings in the bid documents. Current
cost of executed Change Orders is 31% of the base contract price. The trended cost growth
projection is currently 33% over bid price. Approximately 20% are related to error and/or ommissions
(owner or designer), 7% are currently in some form of dispute. The remainder of the cost growth are
due to site conditions, discretionary tenant requests or scope changes and regulatory requirements
respectively.












AIRPORT
18  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Cargo 2 West Cargo Hardstand
Enlarge the western cargo hardstand   Project Status:
Project:   C800247    in the Cargo 2 area. Includes buyout   Schedule: Delayed
Budget: On or under
Budget: $7,890,000    of two cargo buildings and tenant
Phase: Construction   relocations; relocation of FAA      Status Reset: 10/8/2013
antenna, security gate, and guard      (Commission Construction Auth.)
Start: 9/25/2012
Schedule Completion:  shack; and installation of 400Hz in-
11/1/2014           ground power.
Budget/Costs Incurred
Significant Developments
15    13.49
Cargo 2 Hardstand pavement is complete. IWS Control Panel (DDC
connection) has been installed and E190 Security Guard Shelter
Millions 10
construction has been completed.                                   7.89
6.11
5
Schedule
Dollars in 
Partial Beneficial Occupancy was reached on August 11, 2014 with     0
the completion of the hardstand portion of the work. Completion is         Authorized Forecasted Costs Incurred
expected by the end of the 1st quarter 2015. Delay is due to long
lead in procurement for IWS Controls in addition to Building
Department approval of new guard shelter.                   Construction Costs
6    4.98
Budget
3.90
The project forecast is within approved budget and authorization.      Millions 4
2
Change Order
Dollars in                 0.0024
Current Quarter   Project Total            0
Number of COs    2          2                     Initial   Change  Spent
Amount of COs    $2,412       $2,412
Photo
Justification for COs: 1) Channel Drain Bearing Surface; 2) Feeder
ground conductor up-size at Cargo 2
Risks
Continued delay related to new E190 Guard Shelter electronic and
communication installation, existing E185 security gate reconfiguration
and existing E185 guard shelter demolition.
Budget Transfers
None this Quarter.
AIRPORT
Port of Seattle 4Q 2014 Report  19

FOURTH QUARTER REPORT, 2014
Vertical Conveyance Modernization Program -
Aeronautical
Project Status:
Project:   C800251   Perform modernization on 9 existing    Schedule: Within or ahead
Budget: $24,556,408  elevators and 4 escalators: SSAF,     Budget: On or under
Phase: Construction  MT-2, MT-3, MT-4, MT-5, MT-6, MT-   Status Reset: 11/11/2013
Start: 10/25/2011     7, SSB, SSC. Install new elevators     (Commission Construction Auth.)
Schedule Completion: SSM and SSN. Install cooling
10/30/2016         packages on 12 existing hydraulic
elevators throughout Main Terminal.
Budget/Costs Incurred
Significant Developments
Construction continued with the contractor working on first three        30
24.56
elevators.                                            25
Millions 20     16.40
Schedule                             15
Construction is underway with occupancy scheduled for the first
Dollars in  10
phase of construction in Q2 2015.                           5                3.25
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and construction
is underway. Project has returned budget upon defferal of second
phase of work.                                    Construction Costs
8
6.45
Change Order
6
Current Quarter   Project Total           Millions 4
Dollars in 
Number of COs        2          3
Amount of COs       $21,685      $22,685            2             0.94
0.02
0
Justification for COs: Differing site conditions and administrative            Initial  Change Orders Cost Incurred
changes.
Risks
None
Budget Transfers
BT to C800404 $41,009

AIRPORT
20  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Parking System Replacement
Project Status:
Project:   C800253    Replace the previous Parking Revenue  Schedule: Delayed
Budget: $5,577,364   Control System, which manages     Budget: On or under
Phase: Close Out    parking access and revenue collection  Status Reset: 3/8/2011
in the Airport's Main Parking Garage.
Start: 4/6/2010                                   (Commission Construction Auth.)
Schedule Completion: 8/31/2012
Significant Developments                    Budget/Costs Incurred
The Scheidt & Bachmann (S&B) system is operational and exhibits     12
9.78
accuracy and availability rates above 99.99%. However, the Port      10
continues working with S&B to correct a limited number of          Millions 8
outstanding system certification issues. Ports' Legal and ICT                    5.58
6                     5.13
departments are also involved.
Dollars in   4
2
Schedule
0
The system is complete and in use. However, PCI related issues         Authorized  Forecasted Costs Incurred
remain to be resolved prior to closing the project.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  None this quarter
Change Order                         Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: Not applicable this quarter
Risks
The Port is working with the contractor to address outstanding PCI
and unique transaction identifier issues.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2014 Report  21

FOURTH QUARTER REPORT, 2014
Aircraft RON Parking USPS Site
Project Status:
Prepare the site for the construction    Schedule: Delayed Schedule
Project:   C800254
of hardstands for use as Remain      Budget: On or under
Budget: $41,456,350
Overnight (RON) parking of aircraft at   Status Reset: 10/8/2013
Phase: Construction
the Cargo 5 area.                (Commission Construction Auth.)
Start: 8/26/2008
Schedule Completion: 2/28/2015
Significant Developments                    Budget/Costs Incurred
Hardstand construction is complete. New Security Gate E125 and
60
related Guard Shelter construction complete  waiting on                49.99
50
Commissioning and Building Department approval and final electrical              41.46
Millions 40                        33.56
approval from Facilities and Infrastructure.
30
Schedule                             20
Dollars in  10
Hardstand completed and in use. Security Gate and Guard Shelter
0
anticipated to be completed and approved by the end of the 1st
Authorized  Forecasted Costs Incurred
quarter 2015. Delay beyond 2014 due to weather delays and
electrical approvals.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.       27.83
30
23.37
Change Order                          Millions 20
Current Quarter   Project Total            10
Number of COs    3          3                         0.05
Amount of COs    $52,317      $52,317              Dollars in  0
Justification for COs: 1)Furnish and install a power meter; Replace         Initial Change Order Spent
PVC items with Ductile Iron; and add sewer cleanout at E-125
building; 2)Feeder ground conductor upsize; 3)Modifications of
ASDE-X Shelter
Photo
Risks
A significant amount of contaminated soil at Cargo 5  contract bid
quantity was 13,500 total TN's; 21,500 Tn's to date. Overrun is
being managed through construction contingency. E125 Guard
Shelter Buiding Department approval is waiting on Commissioning 
scheduled to be completed by end of the 1st quarter 2015.
Budget Transfers
None this quarter.
AIRPORT
22  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
8th Floor Weatherproofing
Project Status:
Project:   C800274      Removal and replacement of the   Schedule: Within or ahead
Budget: $9,324,000      floor covering system on the eighth  Budget: On or under
Phase: Close Out      floor of the STIA parking garage   Status Reset: 5/27/2014
Start: 3/23/2010          and repair or replacement of      (Commission Construction Auth.)
Schedule Completion:    expansion joints and flashings.
7/31/2014
Significant Developments                    Budget/Costs Incurred
PCL, the Port's contractor, was ordered to install deck coating in
14    13.05
areas where defective coating had been identified and removed.
12
This work was carried out but is the subject of a claim action by the                9.32
10                     8.14
contractor. The project is now being closed out.                  Millions 8
6
Schedule
Dollars in   4
Construction was longer than anticipated, but was completed in Q3      2
2014.                                         0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                          7  6.05        6.07
Current Quarter   Project Total            6
Number of COs    2          30                Millions 5
4
Dollars in 
Amount of COs    -$67,779     $84,555
3
2
Justification for COs: Change orders included: 1) reconciliation
1
addressing post tensioning tendon repair, and 2) reconciliation of                  0.08
0
vapor barrier installation.                                         Initial   Change Order   Spent
Risks
Contractor claim.                                    Photo
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 4Q 2014 Report  23

FOURTH QUARTER REPORT, 2014
Long-Term Cell Phone Lot
Project Status:
Schedule: Delayed Schedule
Project:   C800324      Construct a new cell phone waiting
Budget: On or under
Budget: $3,293,100      lot to replace the existing lot that is
Status Reset: 5/6/2014
Phase: Construction     being displaced, including
(Commission Construction Auth.)
Start: December 2012     permanent access control on South
Schedule Completion:    170th Street.
June 2014
Budget/Costs Incurred
Significant Developments
6            5.06
The wifi system for the Cell Phone Lot is now in service. Staff is        5
continuing to evaluate the cost and performance of the permanent     Millions 4
access control solution, including coordination with the City of              2.65
3                    2.50
SeaTac.                                     2
Dollars in   1
Schedule                             0
Authorized  Forecasted Costs Incurred
A recommendation on the permanent traffic control solution is
expected in Q1 2015, to be followed by a request to Commission for
additional design and construction authorization.
Construction Costs
Budget                             1.2          1.04
The current authorized budget for the Cell Phone Lot is $2,650,100.     1   0.89
Staff will request additional authorization for the permanent traffic      Millions 0.8
control solution previously estimated at $1,222,000 to $2,855,000.      0.6
0.4
Change Order                         Dollars in        0.15
0.2
Current Quarter   Project Total            0
Initial       Change       Spent
Number of COs        0          4                     Orders
Amount of COs        $0       $150,405
Photo
Justification for COs: No change orders issued this quarter.
Risks
Coordination with the City of SeaTac for a recommended permanent
access control solution.
Budget Transfers
None this quarter

AIRPORT
24  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Two New CTE Freight Elevators
Project Status:
Project:   C800334      Provide two new freight elevators   Schedule: Delayed
Budget: $8,315,100      to support concession operations in  Budget: On or under
Phase: Construction     the Central Terminal/Pacific      Status Reset: Click here to
Start: 8/5/2011          Marketplace.                enter a date.
Schedule Completion: 11/19/2014                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Construction is complete, but was later than anticipated by one        8.5   8.32     8.32
month. Both elevators were delivered in the 3rd Quarter. Punchlist
8
was concluded in November 2014.                       Millions
7.5                         7.36
Schedule
Construction complete                                Dollars in  7
6.5
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total             6  5.36
Number of COs        5         44                       4.85
5
Amount of COs       $4,573     $283,663.27
Millions    4
3
Justification for COs: Differing site conditions and code compliance
2
improvements.                                   Dollars in 
1        0.28
Risks                                 0
Initial   Change   Costs
No new risks identified this quarter.                                    Orders Incurred
Budget Transfers
Photo
None at this time


AIRPORT

Port of Seattle 4Q 2014 Report  25

FOURTH QUARTER REPORT, 2014
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations                Project Status:
Schedule: Delayed Schedule
Budget: On or under
Project:   C800335      Airport-wide electrical charging     Status Reset: 10/23/2012
Budget: $30,700,000    system for electrical ground      (Commission Construction
Phase: Construction    support equipment (EGSE) at the   Auth.)
Start: 10/26/2010        Concourses and the North and
Schedule Completion:    South Satellites.
6/30/2016                                  Budget/Costs Incurred
35            30.20
Significant Developments                     30  25.35
EGSE Phase 1 Project: Major contract completion and closeout is    Millions 25
20
underway. Data collection and historical reporting is being tested.                   15.20
15
Record drawings are nearing completion.
Dollars in  10
5
EGSE Phase 2 Project: Preparing final design service directive.       0
Authorized  Forecasted Costs Incurred
FAA, via the VALE grant process, has awarded the Port of Seattle a
total of $5,500,000 for the EGSE Charger Phase 2 Project.
Construction Costs
Washington State Department of Revenue has approved sales tax
5                    4.68
exemption for the construction phase of the EGSE Charger Phase 2
3.88
Project.                                                4
Millions  3
Schedule
2
Dollars in                  0.81
Phase 1 construction is complete except for finalizing the Record        1
Drawings contract closeout.                               0
Phase 2 construction scheduled for completion mid-2016.               Initial  Change Order  Spent
Budget
The project forecast is within the approved budget. Request the
remaining authorization for the construction funding and authority to
advertise for construction when the design and bid documents are
completed for EGSE Charger Phase 2 Project.



26  Port of Seattle 4Q 2014 Report

Change Order
Current Quarter   Project Total
Number of COs   9          104
Amount of COs   $102,364     $805,993
Justification for COs: Errors/Omissions - Designer & Owner, Varying Site Conditions, Scope Change,
and Regulatory Requirements.
Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may affect project implementation and completion of the EGSE Phase 2 Project.
Budget Transfers
None this quarter.
Cost Growth During Construction:
Airline Realignment contributed to cost increase; varying site conditions related to equipment
installation; scope change for providing back-up power to concourse D.







AIRPORT

Port of Seattle 4Q 2014 Report  27

FOURTH QUARTER REPORT, 2014
Refurbish Bag Claim Device
Project Status:
Project:   C800368     Refurbish Claim Device 8 and
Schedule: Within or ahead
Budget: $303,730      replace the current door to a more
Budget: On or under
Phase: Close Out     secure type.
Status Reset: Click here to
Start: 6/24/2014                                  enter a date.
Schedule Completion: 11/24/2014                  (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
The project was completed early and turned back over to           0.35   0.30    0.30
Operations.                                       0.3
0.25   Millions
Schedule                            0.2           0.17
Dollars in 
0.15
Project is on schedule.
0.1
0.05
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                N/A
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None
Budget Transfers
None



AIRPORT
28  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
South Satellite HVAC, Lights, and Ceiling
Replacement
Project Status:
Project:   C800376     Replace the heating ventilation,      Schedule: Within or ahead
Budget: $34,011,000    lighting and ceiling systems in the    Budget: On or under
South Satellite.
Phase: Design                            Status Reset: Click here to
Start: 7/24/2012                                  enter a date.
Completion: 7/31/2016                        (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Project has been delayed. This will be the final report.               40
34.01
Schedule                             30
The project is delayed until the Airport Master Plan effort clarifies the     Millions 20
future operational requirements for the South Satellite.
Dollars in 10     6.35
1.47
Budget
0
The design service directive was terminated in Q4. Approximately         Authorized  Forecasted Costs Incurred
$816,000 was expensed. The balance will be capitilized when the
project is restarted.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Risks
None
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2014 Report  29

FOURTH QUARTER REPORT, 2014
Baggage Handling System (C22-C1, MK1, and
TC3)
Replace the ticket counter (TC3)
conveyors and declines, reroute the     Project Status:
Project:   C800382   conveyors of the C-22 system and      Schedule: Within or ahead
Budget: $5,585,000   connect it to the C-1 screening system,   Budget: On or under
Phase: Close Out    replace the existing makeup (MK1)     Status Reset: 12/11/2012
Start: 3/1/2011        device, and install a new odd size       (Commission Construction Auth.)
Schedule Completion:  baggage system.
5/31/2013
Budget/Costs Incurred
Significant Developments
Project complete. This will be the last Quarterly report.                8
6.76
7
5.59        5.56
Schedule                            Millions 6
5
The project forecast is within the approved budget and authorization.     4
3
Dollars in    2
Budget
1
The project forecast is within the approved budget and authorization.     0
Authorized   Forecasted   Costs Incurr
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          44
2                    1.79
Amount of COs    $0         $202,744.00               1.59
1.5
Justification for COs: None this quarter                        Millions 1
Risks                                0.5      0.20
Dollars in 
None identified at this time.                                  0
Initial    Change Order    Spent
Budget Transfers
None at this time
Cost of Construction Growth
Three changes represent the majority of the cost growth: 1) removed
the C1-CS1 curbside conveyor since replacement was no longer


30  Port of Seattle 4Q 2014 Report

Cost of Construction Growth, Cont.
required, 2) The contract design to replace make-up device MK1 did not include POS ergonomic
standards for this kind of device; and 3) the original contract design for the conveyors in the C1-CS2
conveyor line created unsafe electrical and mechanical conditions for maintenance works. Several
other smaller changes included fire sprinkler and architectural revisions, including a credit to remove
a small scope of work.












AIRPORT
Port of Seattle 4Q 2014 Report  31

Cargo 6 Enhancements               FOURTH QUARTER REPORT, 2014
Project Status:
Project:   C800390    Enlarge the Cargo 6 off-gate        Schedule: Delayed Schedule
Budget: $6,428,000    hardstand to allow simultaneous     Budget: On or under
nose-loading of wide-body freight
Phase: Construction                        Status Reset: 10/8/2013
aircraft as well as provide fuel hydrant
Start: 9/25/2012                                  (Commission Construction Auth.)
and ground power capabilities.
Schedule Completion:
3/31/2015
Budget/Costs Incurred
Significant Developments
Cargo 6 Enhancements was combined with Cargo 2, Cargo 5 and      7   6.48    6.43
Cargo 6 Panel Replacement as a single construction contract and       6
was successfully bid and awarded. Partial occupancy was granted      5
when positions 1, 2 and 3 were turned over for beneficial use the        4
week of December 22, 2014.                           in Millions 3              2.31
Dollars   2
1
Schedule
0
Construction of the Cargo 6 hardstand enhancements began in the        Authorized Forecasted Costs Incurred
3rd quarter 2014. Completion has been delayed to the end of the 1st
quarter, and possibly first part of the 2nd quarter of 2015. Fuel
Hydrant System design issues, long lead procurement items, and    Construction Costs
electric connection design changes are responsible for the
4      3.72
construction completion delay.
3.5
Millions    3
Budget                             2.5
The project forecast is within the approved budget and authorization.     2                1.57
Dollars in    1.5
1
Change Order                                 0.32
0.5
0
Current Quarter   Project Total
Initial      Change Order      Spent
Number of COs    3          3
Amount of COs    $318,950     $318,950
Photo
Justification for COs: 1) Add surge suppressor & vault at Cargo 6
fuel line system; 2) Photometric Testing of Airfield Lighting; 3)
Feeder ground conductor up-size at Cargo 6 & Cargo 6 North Fuel
Rack Pavement Markings

Excavation for final light pole at
Cargo 6
32  Port of Seattle 4Q 2014 Report

Risks
Construction delays are having impact on Cash Flow projections.
Continue delay's maybe expected due to weather's impact on final concrete pouring.
Budget Transfers
None












AIRPORT
Port of Seattle 4Q 2014 Report  33

FOURTH QUARTER REPORT, 2014
RW16C/34C Design and Reconstruction
Project Status:
Project:   C800406    Produce final design and reconstruct
Schedule: Within or ahead
Budget: $113,095,000   the existing RW 16C/34C in its
Budget: On or under
existing location, replace TW C and
Phase: Design                            Status Reset: 12/2/2014
N, reconfigure TWs H and J, install
Start: 5/4/2010                                   (Commission Construction Auth.)
FOD detection equipment, and install
Schedule Completion:   LED lighting system.
11/30/2016
Budget/Costs Incurred
Significant Developments
Commission authorization was received on December 2nd. Project is
113.10
out to bid. Foreign Object Debris (FOD) detection system vendor and   120   110.22
Runway Team are holding coordination meetings.              100
80
Schedule                            60
Bid opening scheduled for January 29th. Construction to begin the     40
first full week of April, 2015 and runway closure to take place around    20                5.48
the first week of May.                                     0
Authorized  Forecasted Costs Incurred
Budget
Construction Costs
There was a Capital increase of approximately $7,000,000 and a
Not Applicable
$3,200,000 Expense increase.
Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
-Bid protest
-Weather issues
Budget Transfers
None this quarter.

AIRPORT
34  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Federal Inspection Services Short Term
Improvements
Project:   C800426    Short Term Improvements to the      Project Status:
Budget: $1,912,000   Federal Inspection Service area at S.   Schedule: Delayed
Satellite to improve through put and     Budget: On or under
Phase: Construction
conditions for passengers waiting in     Status Reset: 12/10/2013
Start: 4/1/2012
the International Corridor prior to        (Commission Construction Auth.)
Schedule Completion:
Primary Inspection.
8/8/2014
Budget/Costs Incurred
Significant Developments
2.5
Major Contract work is complete. Project completed adjacent wall
1.91       1.91
panel replacements for visual continuity.                        2
Millions                           1.59
1.5
Schedule
1
Adjacent wall panel replacements are extending project close out but   Dollars in 0.5
do not impact project beneficial use.
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the increased, approved budget and
authorization.
Construction Costs
Change Order                           0.7 0.61     0.62
Current Quarter   Project Total            0.6
0.5
Number of COs        4          7             Millions 0.4
Amount of COs       $24,699      $56,123
0.3
Justification for COs: Include delays for late flight activity and varying
site conditions.                                          Dollars in  0.2
0.1          0.06
0
Risks                                   Initial Change Spent
Orders
None.
Budget Transfers                        Photo
None at this time.


AIRPORT
Port of Seattle 4Q 2014 Report  35

FOURTH QUARTER REPORT, 2014
Doug Fox Lot Service Upgrades
Project:   C800451    Construct a new drainage system,     Project Status:
Schedule: Delayed Schedule
Budget: $6,930,000   asphalt resurfacing, improved lot
lighting, new building, and road signage  Budget: Forecast Overrun
Phase: Construction
to improve lot appearance, function,     Status Reset: 10/8/2013
Start: February 2012
and revenue generation.            (Commission Construction Auth.)
Schedule Completion:
March 2015
Significant Developments                    Budget/Costs Incurred
Overall project construction is approximately 94% complete. The
8            6.93
modular building was completed and occupied by the tenant, and the        6.50
existing building was demolished. Obtained Commission            6               5.43
Authorization for Resolution 3702 supporting the completion of the     Millions
Developer Extension Agreement with Valley View Sewer District.       4
Dollars in   2
Schedule
The overall project has been delayed with overall project completion     0
Authorized  Forecasted Costs Incurred
forecast for March 2015. Fabrication, delivery, and installation of the
modular building is critical path. Delays have occurred prior to
fabrication due to value engineering, and during fabrication due to    Construction Costs
State Labor &Industries review and approval.                     5
3.99
4                   3.63
Budget
Millions   3
The project is forecast to be overrun with a total estimated budget of
$6,930,000. This is due primarily to the construction schedule         2
delays. Additional budget authorization will be requested in January    Dollars in   1
0.16
in order to complete the project.
0
Initial      Change      Spent
Change Order                                 Orders
Photo
Current Quarter   Project Total
Number of COs        8         23
Amount of COs       $19,746      $159,619
Justification for COs: Changes are related to errors and omissions
(scope gap), varying site conditions (unknown utilities), tenant
requested changes, scope changes (modular building value
engineering), and regulatory requirements (fire alarm).


36  Port of Seattle 4Q 2014 Report

Risks
Additional delays in installation, underground utilities, paving/striping, and activation of the parking
control facility will delay project completion. Wet weather conditons may delay paving and striping.
Budget Transfers
None at this time.











AIRPORT

Port of Seattle 4Q 2014 Report  37

FOURTH QUARTER REPORT, 2014
Fiber Infrastructure to Gate Backstands
Project Status:
Project:   C800464    Extend airport-provided            Schedule: Delayed Schedule
Budget: $2,329,000   communications infrastructure and    Budget: On or under
Phase: Design      Wi-Fi antennas to additional gates on   Status Reset: Click here to
Start: 7/9/2013        Concourses A and B.              enter a date.
Schedule Completion: 3/2/2016                   (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Ninety percent design review completed. Plan-in-hand walkthrough
2.5                   2.33
identified several design issues that are being addressed.
2
Millions
Schedule                             1.5
Schedule impacted by design issues recently uncovered.          Dollars in 
1      0.79

0.5                                0.36
Budget
0
The project forecast is within the approved commission authorization        Authorized    Forecasted   Costs Incurred
for design. Project budget is being reviewed for cost growth due to
recent design issues.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Evaluating budget and schedule risk due to unforeseen field
conditions uncovered at the plan-in-hand review that could increase
construction costs.
Budget Transfers
None this quarter.


AIRPORT
38  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Feeder 101 Taps Replacement/Fire Station
Electric Upgrades
Project:   C800479    Replace the existing 208V transformer  Project Status:
Schedule: Within or ahead
Budget: $4,775,000.    and 12.47 KV feeder, and add a 500
KV generator and a 1000kVA        Budget: On or under
Phase: Construction                        Status Reset: 7/1/2014
Start: 4/1/2013        transformer. Replace the electrical
feeds to 13 locations along Air Cargo   (Commission Construction Auth.)
Schedule Completion:
Road. Also, the electrical transformer
10/31/2016          and associated switchgear for Air
Cargo #4 will be replaced.
Budget/Costs Incurred
Significant Developments
Construction contract awarded. Contractor started pre-construction      6
4.78      4.78
submittals.                                            5
Millions  4
Schedule                             3
Substantial completion scheduled for Q3 2016.                   2
Dollars in                           0.91
1
Budget                              0
Authorized  Forecasted Costs Incurred
The project is currently on budget.
Change Order
Construction Costs
Current Quarter   Project Total
Number of COs    0          0                  2.5  2.26
Amount of COs    $0         $0                   2
Millions  1.5
Justification for COs: n/a
Dollars in 
1
Risks                                 0.5
0.00    0.00
Unplanned electrical shut downs could impact the project schedule.
0
Initial   Change   Spent
Budget Transfers                                Orders
None this quarter

AIRPORT

Port of Seattle 4Q 2014 Report  39

FOURTH QUARTER REPORT, 2014
Facility Monitoring System Renewal
Project:   C800495     Provide a system upgrade that will    Project Status:
Budget: $3,420,180     allow the system to maintain and    Schedule: Delayed
Phase: Construction    expand monitoring of critical systems  Budget: On or under
Start: 1/22/2013        such as elevators, escalators, moving  Status Reset: 12/10/2013
Schedule Completion:   walks, passenger boarding bridges   (Commission Construction Auth.)
and baggage systems.
8/31/2015
Significant Developments                    Budget/Costs Incurred
The FMS network upgrade and Baggage Reporting Software was      4
3.42       3.42
completed and accepted by the Port. The contract was awarded to
3
Kolkay Electric.                                        Millions
2
Schedule                                        1.30
Major construction work has been awarded and notice to proceed     Dollars in  1
was issued on October 31st.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers


AIRPORT

40  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Airportwide Mechanical Controls System
Project Scope and description:
Project:   C800497       Upgrade the HVAC Controls     Project Status:
Budget: $3,500,000       System for the Airport. This    Schedule: Within or ahead
Phase: Design         includes adding a wireless     Budget: On or under
Start: 5/1/2013            connection to the Logistics area to Status Reset: 12/9/2014
Schedule Completion:     the south of the Airport.       (Commission Construction Auth.)
3/11/2016
Significant Developments                    Budget/Costs Incurred
MII approved the project with added scope. Commission approved
4    3.50      3.50
bidding and construction with the added scope and increased
budget. The documents were updated with the new scope. 100%       3
documents were submitted for review.                       Millions
2
Schedule                            Dollars in  1
0.21
The project schedule was updated to reflect the additional scope.
0
Authorized  Forecasted Costs Incurred
Budget
The budget was increased to $3,500,000 with the added scope.
Construction Costs
Change Order                         N/A
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unplanned electrical shut downs could impact the project schedule.
Increased control component costs. An allowance was added to the
estimate.
Budget Transfers
N/A

AIRPORT
Port of Seattle 4Q 2014 Report  41

FOURTH QUARTER REPORT, 2014
RAC Baggage Claim Renovation
Project:   C800541      Renovation of both rental car      Project Status:
Schedule: Delayed Schedule
Budget: $1,218,700      counter locations in baggage claim
into new waiting areas with vending   Budget: On or under
Phase: Closeout                           Status Reset: 4/2/2013
Start: 10/1/2012          machines and other facilities for
Schedule Completion:    special operations           (Commission Construction Auth.)
12/31/2013
Significant Developments                    Budget/Costs Incurred
The completion memo was issued for this project and the last          $1.40   1.35
payment to the contractor was completed. This will be the last
$1.30
quarterly report for this project as this project is in closeout.                        1.22
$1.20                       1.15
Millions
Schedule
Dollars in    $1.10
Beneficial Occupancy occurred on January 24, 2014, one month
$1.00
later than originally intended. The completion memo was issued on
Authorized  Forecasted   Costs
December 1, 2014.                                               Incurred
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
0.35                       0.30
Change Order                          0.3  0.26
0.25
Current Quarter   Project Total           Millions 0.2
Number of COs        0         12
0.15
Amount of COs        $0       $62,052
Dollars in 0.1              0.06
0.05
Justification for COs: No change orders issued this quarter.           0
Initial    Change Order    Spent
Risks
None this quarter
Photo
Budget Transfers
None this quarter.
Construction Cost Growth
Twelve change orders executed for the major works contract
represent 24% of the base contract price. Approximately 69% is due
to regulatory requirements, 19% to errors and omissions, 10% to
unknown site conditions, and 2% to contract scope changes.
AIRPORT
42  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Replace PLBs at S7, S9 & B4
Project Status:
Project:   C800543      Replace the Passenger Loading    Schedule: Within or ahead
Budget: $2,950,000      Bridges at S7 & S9 and install a    Budget: On or under
Phase: Construction     new bridge at B4           Status Reset: 1/21/2014
Start: 1/21/2014                                  (Commission Construction Auth.)
Schedule Completion:
12/31/2014
Significant Developments                    Budget/Costs Incurred
All three gates are operational. PC Air installation on the new B4
3    2.95      2.95
gate is scheduled to be completed during 1Q 2015.
2.9
Millions 2.8                                                                                Schedule
2.7
Project is on schedule.                                                    2.60
2.6
Dollars in 2.5
Budget
2.4
No issues                                          Authorized Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None at this time
Budget Transfers
None



AIRPORT
Port of Seattle 4Q 2014 Report  43

FOURTH QUARTER REPORT, 2014
NorthSTAR Program
Project:   C800544   Includes programmatic project        Project Status:
management and project controls costs   Schedule: Within or ahead
Budget: $20,600,000.
for the NorthSTAR program, consisting    Budget: On or under
Phase: Design     of 5 capital projects that represents a    Status Reset: Click here to
Start: 4/5/2012       unique partnership between the Port     enter a date.
Schedule Completion: and Alaska Airlines.             (Commission Construction Auth.)
8/27/2020
Significant Developments                    Budget/Costs Incurred
Received and incorporated AAG NorthSTAR Governance processes
25
into the programs communication plan and decision matrix.                    20.60
20
Schedule                            Millions 15
Continue programmatic linkage coordination to assure airport-wide     10
gate availability is not compromised during construction.            Dollars in  5   3.60           2.76
Budget                             0
Authorized  Forecasted Costs Incurred
The project forecast is inclusive of Programmatic Management
Reserve and is within the approved budget.
Construction Costs
Change Order
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Communication and coordination across multiple teams and
stakeholders along with identification/monitoring of all "linked"
Capital projects outside of NorthSTAR.
Budget Transfers
None this quarter.

AIRPORT

44  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
NorthSTAR Main Terminal Improvements
Project Status:
Project:   C800545    Renovate the North Main Terminal     Schedule: Within or ahead
Budget: $29,200,000   security checkpoint, curbside and     Budget: On or under
Phase: Design      ticketing lobby areas incorporate self-   Status Reset: Click here to
Start: 12/3/2013       operated technologies and improve     enter a date.
Schedule Completion:  aesthetics.                 (Commission Construction Auth.)
11/29/2018
Budget/Costs Incurred
Significant Developments
40
Completed initial scoping meetings with stakeholders and presented              29.20
preliminary forecast for ticketing lobby circulation/utilization and        30
checkpoint sizing.                                      20
Millions
Schedule                            Dollars in 10
1.50               0.09
Developing passenger forecasts for sizing of checkpoint and          0
alternatives for passenger processing, circulation and checkpoint         Authorized  Forecasted Costs Incurred
configuration.
Budget                            Construction Costs
Not Applicable
Project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for
construction is anticipated Q1 2017, when the bid documents are
completed.
Change Order
Current Quarter   Project Total
Number of COs        n/a         n/a
Amount of COs        n/a         n/a
Justification for COs: n/a
Risks
Project scope definiton could increase scope and budget.
Budget Transfers
None

AIRPORT
Port of Seattle 4Q 2014 Report  45

FOURTH QUARTER REPORT, 2014
NorthSTAR Concourse C Vertical Circulation
Project:   C800547    Construct exterior, weather protected   Project Status:
Schedule: Within or ahead
Budget: $19,375,000   sloped walkways with elevators at
Gates C2/4, C10/12, and C14 to      Budget: On or under
Phase: Construction
provide enhanced access from       Status Reset: 10/22/2013
Start: 11/6/2012
concourse to aircraft ramp for         (Commission Construction Auth.)
Schedule Completion:  Alaska/Horizon regional operations.
4/17/2015
Significant Developments                    Budget/Costs Incurred
New doors in place and utilized for C2 and C10 and permanent       25
19.4
ground level walkway for C2 in place. C16 steel erected with roofing              18
20
and elevator shaft installation. Thirty-four (34) eGSE chargers at C2    Millions 15
in service.
10                    8
Schedule                            Dollars in  5
0
The construction effort is progressing as planned at all 3 locations.
Authorized  Forecasted   Costs
Continuing to work with Forma Construction and AAG's contractor                   Incurred
PCL to coordinate work activities.
Construction Costs
Budget
10    8.72
The project is currently under the commission approved budget.
Re-evaluation of remaining effort will require return of $1.8M out of      8
the $3.2M previously transferred to the Program Reserve           Millions 6              4.67
4
Change Order                         Dollars in  2      0.59
Current Quarter   Project Total
0
Number of COs        12         19                Initial   Change   Spent
Orders
Amount of COs      $409,091     $586,757
Justification for COs: Scope changes-$261k (Dynamic/Static
Passenger Signage; Mods to NEMA Cabinets; Contaminated Soils)
Unforseen Conditions-$125k; Misc E&O-$23k.
Risks
Potential for underground utility conflicts during construction.
Budget Transfers
None this period.

AIRPORT
46  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
SSAT Interior Renovations
Project:   C800549     Modify the mezzanine and         Project Status:
Budget: $5,167,000    concourse levels of the South      Schedule: Within or ahead
Phase: Construction   Satellite to improve the passenger   Budget: On or under
experience.                   Status Reset: 12/9/2014
Start: 11/4/2012
(Commission Construction Auth.)
Schedule Completion: 6/1/2016
Budget/Costs Incurred
Significant Developments
Phase One design is complete.                           6         5.17
Commission Authorization for Phase One Construction received in      5
December. Anticipate a Q1 2015 bid opening.               Millions 4
3
Schedule                                1.92
2
On schedule.                                    Dollars in 
1                     0.19
0
Budget                               Authorized Forecasted Costs Incurred
Within budget.
Change Order                         Construction Costs
Not Applicable at this time
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
No budget transfers this quarter.



AIRPORT
Port of Seattle 4Q 2014 Report  47

FOURTH QUARTER REPORT, 2014
Concourse D Roof Replacement
Project Status:
Project:   C800550     Remove and replace the roofing     Schedule: Delayed
Budget: $3,946,000    systems on Concourse D of the     Budget: On or under
Airport; install ladders, stairs and
Phase: Construction                        Status Reset: Click here to
fall protection on the penthouse
Start: 7/1/2013                                   enter a date.
sections; and make repairs and
Schedule Completion:                        (Commission Construction Auth.)
where required, replacements to
11/24/2014           the KalWall window system.
Budget/Costs Incurred
Significant Developments
4.5
All construction on this project is complete.                           3.95
4
3.5                   3.21
Schedule                            Millions 3
2.32
2.5
Substantial completion reached in January 2015.
Dollars in     2
1.5
1
Budget
0.5
The project forecast is within the approved budget.                 0
Authorized      Forecasted     Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          5
Amount of COs    $0         $47,910               3  2.75
2.5
1.86
Justification for COs: None this quarter.                        Millions  2
1.5
Risks                                 1
None at this time.                                      Dollars in  0.5
0.05
0
Budget Transfers                             Initial Change Spent
Orders
None at this time.



AIRPORT

48  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Grease Interceptor Augmentation
Project Status:
Project:   C800551     Install two underground 9,000 gallon   Schedule: Delayed
Budget: $1,484,200.    grease interceptors to service the    Budget: On or under
Phase: Permitting     Concourse C and South Satellite.    Status Reset: Click here to
Start: 5/1/2013                                   enter a date.
Schedule Completion: 6/15/2015                  (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Project advertised and bids received. Low bid 40% above engineer's
2
estimate. Decision made to reject all bids, redesign utilizing an above
1.48      1.48
ground interceptor in one of the locations to ease schedule           1.5
constraints and rebid. Revised design to be completed in February.
1
Millions
Schedule
Dollars in  0.5                        0.32
Design revision has caused project schedule to slip.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Construction impacts Delta Operations at S. Satellite.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2014 Report  49

FOURTH QUARTER REPORT, 2014
NorthSTAR Refurbish Baggage Systems
Project Status:
Project:   C800555    Refurbish existing baggage systems   Schedule: Within or ahead
Budget: $20,002,500    in support of AAG operation at North   Budget: On or under
Phase: Construction   Satellite and Concourse D. The work  Status Reset: 9/24/2013
will extend the service life of part of
Start: 11/6/2012                                  (Commission Construction Auth.)
the C92 systems, C88 North Satellite
Schedule Completion:
systems, and C88 tunnel systems.
5/15/2015
Budget/Costs Incurred
Significant Developments
25    22.00     22.00
Completed abatement of MCP room at North Satellite. Decision
reached with AAG & Port Operations to shut down C88 to           20
consolidate multi-phase construction efforts and shorten duration.      15
C92 Controls updated and turned over to operations. Concourse D     Millions
10
5.33
mini-sort area in use                                    Dollars in 5
0
Schedule
Authorized  Forecasted Costs Incurred
Construction effort was focused on C88 during shutdown.
Budget                            Construction Costs
The project forecast is within the approved budget.                15
11.83
Change Order                         Millions 10
Current Quarter   Project Total
Number of COs        6         12             5             3.35
0.78
Amount of COs      $289,463     $781,450           Dollars in 
0
Initial      Change      Spent
Justification for COs: Varying Site Conditions - $72k (Pier                      Orders
modifications & photo-eyes); RMM-$120k; E&O-$97k
Risks
Project schedule has no float remaining.
Budget Transfers
None this period

AIRPORT
50  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
NorthSTAR North Satellite Renovation and
NSTS Lobbies
Project:   C800556     Renovation and expansion of the    Project Status:
Budget: $421,612,944   North Satellite (NSAT), including    Schedule: Within or ahead
Phase: Design       NSAT Satellite Transit System     Budget: On or under
Start: 7/24/2012        (STS) stations "refresh", ramp level,   Status Reset: Click here to
Concourse level, and new rooftop    enter a date.
Schedule Completion:
airline lounge.                   (Commission Construction Auth.)
6/10/2020
Budget/Costs Incurred
Significant Developments
Kicked off 60% design effort. Investment Committee approved to
incorporate $1.75M for STS Apron Roof Replacement and $14.4M     500
421.61
for NSAT Baggage System Expansion. Selected Hensel Phelps as
400
the General Contractor/Construction Manager (GC/CM) and are
in Millions
seeking authorization for award of contract, $5M pre-construction      300
services and the transfer of the STS Apron Roof Replacement in      Dollars 200
January, 2015.
100    50.50
8.83
Schedule                             0
Authorized  Forecasted Costs Incurred
Continue to evaluate construction phasing options with AAG. Once
the GC/CM contractor is up to speed, staff and AAG will work       Construction Costs
collaboratively to maximize gate availability/utilization during        Not Applicable
construction. Staff continues to evaluate level of LEED certification
and other sustainable features to incorporate into the project. Start of
30% design delayed by Dual Taxilane decision, technical inputs from
Alaska Airlines and contract negotiations.
Budget
The project forecast is within the approved budget.
Change Order
Current Quarter   Project Total
Number of COs        0          0
Amount of COs       $0         $0
Justification for COs: n/a


Port of Seattle 4Q 2014 Report  51

Risks
Delayed resolution of critical issues such as taxi-lane reconfiguration is impacting design schedule
and may impact construction schedule of early release packages and overall construction costs.
Scope additions absorbed at 30% design may adversely impact project budget.
Budget Transfers
None this quarter











AIRPORT

52  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Snow Blower and Deicer Trucks
Project Status:
Schedule: Within or ahead
Project:   C800557      Purchase1 Deicer Truck and      Budget: On or under
Budget: $2,200,000      2 Snow Blower Trucks        Status Reset: Click here to
enter a date.
Phase: Implementation
(Commission Construction Auth.)
Start: 4/4/2014
Schedule Completion: Deicer - 12/31/2014
Snow Blowers  12/2015
Significant Developments                    Budget/Costs Incurred
(1) Deicer Truck Project #105068 purchased in 2014, and           2.5
2.20          2.20
(2) the two Snow Blower Trucks both to be purchased in 2015.
2
Millions
Schedule                             1.5
1
Not Applicable                                      Dollars in 
0.5
Budget                                        0.00
0
Authorized      Forecasted     Costs Incurred
$400,000 - 2014
$1,800,000 - 2015
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None
Budget Transfers
None


AIRPORT
Port of Seattle 4Q 2014 Report  53

FOURTH QUARTER REPORT, 2014
Main Terminal Mezzanine Tenant Relocations
Construct new tenant leased spaces in  Project Status:
Project:   C800560
order to move existing tenants and     Schedule: Within or ahead
Budget: $2,025,000    provide new leasable office space for   Budget: On or under
Phase: Construction   airlines on the mezzanine of the main   Status Reset: 11/19/2013
Start: 3/26/2013       terminal.                     (Commission Construction Auth.)
Schedule Completion:
3/30/2015
Budget/Costs Incurred
Significant Developments
Airport Jobs will be moved into their new space on Febuary 4th. Sign     2.5
2.03      2.03
Shop and Credit Union are well under construction.
2
Millions 1.5
Schedule
1                    0.84
On schedule
Dollars in 0.5
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within approved budget and authorization.
Change Order
Construction Costs
Current Quarter   Project Total
Number of COs    4          4                   1  0.89
Amount of COs    $10,085      $10,085               0.8
0.6
Justification for COs: Design changes and varying site conditions.
Millions
0.4
Risks                                Dollars in           0.16
0.2
0.01
None identified at this time.                                   0
Initial   Change   Spent
Orders
Budget Transfers
None at this time.


AIRPORT
54  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Known Crewmember Employee Bypass
Project Status:
Project:   C800576      Construct new Known          Schedule: Delayed Schedule
Budget: $780,000      Crewmember Bypass and       Budget: On or under
Phase: Close Out      Employee Bypass locations at the   Status Reset: 9/30/2014
Start: 12/11/2012        Airport.                    (Commission Construction Auth.)
Schedule Completion: 1/15/2015
Budget/Costs Incurred
Significant Developments
Additional authorization received September 30, 2014 due to vendor    0.8   0.78    0.78
problems. Project construction is now complete.
0.75
Millions
Schedule
0.7
0.66
Completion schedule was delayed due to permitting issues and
0.65
testing delays.                                         Dollars in 
0.6
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2014 Report  55

FOURTH QUARTER REPORT, 2014
Parking Garage Lights (CA)
Use current technology to replace all   Project Status:
Project:   C800581     normal lighting in the Airport Parking   Schedule: Within or ahead
Budget: $6,235,700     Garage on all 8 floors and in the    Budget: On or under
helices. This will reduce energy      Status Reset: Click here to
Phase: Design
enter a date.
Start: 1/31/2014        consumption over 60%.
(Commission Construction Auth.)
Schedule Completion: 12/31/2019
Budget/Costs Incurred
Significant Developments
7            6.24
Design is at 90% development.
6
5
Schedule                            Millions 4
The project is on schedule.                                3
Dollars in   2     1.28
Budget                             1          0.54
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                None at this time
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No risks at this time.
Budget Transfers
None




AIRPORT
56  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
International Arrivals Facility (IAF)
Project Status:
Project:   C800583    Planning, Design, Construction of new  Schedule: Within or ahead
Budget: $608,365,000   Federal Inspection Services (FIS)    Budget: On or under
Phase: Planning     facility, including connector between   Status Reset: 10/20/2015
Start: 6/25/2013        South Satellite and FIS and sterile     (Commission Construction Auth.)
Schedule Completion:   corridors and walkways within
Concourse A.
11/8/2019
Budget/Costs Incurred
Significant Developments
Cost estimates for Port's first Progressive Design Build project is                  608.37
600
higher than anticipated, therefore, Port extended the schedule and
500
reconciled scope and assumptions. Identified and evaluated 34       Millions 400
possible scope changes/cost savings options. Engaged airlines in
300
evaluation, evaluated plan of finance. Initiated delivery and          Dollars in 
200
innovation pilot program with CBP. Statements of Qualifications were
100
received on December 24, 2014.                              24.50          5.36
0
Authorized      Forecasted     Costs Incurred
Schedule
Project schedule has been revised to account for reconciliation. Next
schedule revision will occur at end of Design Build Team's validation  Construction Costs
period.                                            Not Applicable
Budget
The Status II Budget approval of the IAF Notebook anticipated in
First Quarter 2015.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Program budget may increase due to additional scope development
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 4Q 2014 Report  57

FOURTH QUARTER REPORT, 2014
Wi-Fi Enhance for Ramp & Terminal
Project Status:
Project:   C800585      Upgrade Wi-Fi system in the public
Schedule: Delayed Schedule
Budget: $9,880,000     and ramp operational areas of the
Budget: On or under
Phase: Design        Airport.
Status Reset: 5/13/2014
Start: 11/4/2012                                  (Commission Construction Auth.)
Schedule Completion: 6/5/2017
Budget/Costs Incurred
Significant Developments
12.000
Procurement of infrastructure designer continues. Wi-Fi signal audits               9.88
10.000
have begun which will identify antenna locations. Airlines have now
8.000
approved project through MII vote.                          Millions
6.000
4.000
Schedule                            Dollars in    1.95
2.000
0.08
Schedule trending late due to resource constraints.               0.000
Authorized   Forecasted  Costs Incurred
Budget
On budget                                   Construction Costs
N/A
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: Not applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT

58  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
North Satellite - STS Ceiling Leak Repair
Project Status:
Project:   C800609      Eliminate ceiling leaks at the North
Schedule: Delayed
Budget: $1,750,000     Satellite (NSAT) that occur
Budget: On or under
Phase: Design        between the satellite transit station
Status Reset: Click here to
(STS) and the elevators.
Start: 5/1/2013                                   enter a date.
Schedule Completion: 10/4/2015                  (Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
The project will be transferred to NSAT project once approved by the     2   1.75    1.75
Port Commission in January, 2015 and be incorporated into the
1.5
NSAT project during design and construction. All future reporting will    Millions
be part of NSAT                                     1
Schedule                            Dollars in 0.5          0.21
The project construction schedule has been delayed by two years       0
with decision to incorproate into the NSAT project.                    Authorized  Forecasted Costs Incurred
Budget
Construction Costs
The project forecast is within the approved budget.
Not Applicable
Change Order
Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Need driest time of the year for construction.
Budget Transfers
Transfered $1,750,000 to C800556


AIRPORT
Port of Seattle 4Q 2014 Report  59

FOURTH QUARTER REPORT, 2014
Checked Baggage Recapitalization/Optimization
Project Status:
Project:   C800612    TSA approached the Airport in 2012
Budget: $317,000,000  with plan to replace all federally owned  Schedule: Within or ahead
Phase: Design      and operated baggage scanning     Budget: On or under
equipment, known as Explosive       Status Reset: Click here to
Start: 2/26/2013
Detection System (EDS) equipment.    enter a date.
Schedule Completion:
The EDS equipment is approaching    (Commission Construction Auth.)
12/31/2024          the end of its life.
Budget/Costs Incurred
Significant Developments
Design work continues to progress towards 70% design. Project       350        317.00
team is defining placement and location of components for testing.     300
The team continues to refine the project phasing. Coordinate with all    250
other programs within the capital program.                     200
Millions
150
Schedule                            Dollars in 100
50    19.85
The project is currently on schedule. Overall schedule will be refined                      6.24
0
to reflect a ten-year program.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Commission
Construction Costs
Authorization for construction funding and authority to advertise for
Not Applicable
construction will be requested when the bid documents are
completed.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
60  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Second Floor Mezzanine Infrastructure Upgrade
Project:   C800615    Upgrade and extend the infrastructure  Project Status:
(HVAC, Communications, Electrical,   Schedule: Delayed Schedule
Budget: $2,666,000
Plumbing, WiFi) to 14,000sq ft of future  Budget: On or under
Phase: Construction
lease space on the 2nd floor, including  Status Reset: 6/12/2013
Start: 8/1/2013         7,000 sq ft for a new USO.         (Commission Construction Auth.)
Schedule Completion:
2/13/2015
Significant Developments                    Budget/Costs Incurred
Contract is on schedule to complete in February 2015.
3
2.67          2.67
2.5
Schedule                            Millions 2
Current project is to complete construction in February 2015.
Dollars in    1.5
1.16
The delay is due to design challenges existing from the second floor
1
to meet egress code requirements and to determine the routing of
0.5
the infrastructure, primarily HVAC.
0
Authorized      Forecasted      Costs Incurred
Budget
The forecast is within the approved budget and authorization..
Construction Costs
Change Order
1.2
Current Quarter   Project Total                0.97
1
Number of COs    3          3
Millions  0.8
Amount of COs    $6000       $6000
0.6
0.4
Justification for COs: Design changes and errors.                Dollars in  0.2
0.01
Risks                                 0
Initial   Change   Spent
None.                                             Orders
Budget Transfers
None.


AIRPORT
Port of Seattle 4Q 2014 Report  61

FOURTH QUARTER REPORT, 2014
S1 Ramp
Project Status:
Project:   C800629      Install a ramp to facilitate travel
Schedule: Within or ahead
Budget: $1,405,000     between the ramp surface and the
Budget: On or under
Phase: Construction    International arrivals facility for
Status Reset: 12/9/2014
passenger use.
Start: 11/4/2012                                  (Commission Construction Auth.)
Schedule Completion: 6/1/2015

Significant Developments                    Budget/Costs Incurred
1.41
On December 9, 2014 received additional budget authorization of      1.5         1.35
$200,000 for high bid. Awarded procurement contract, demolition of
the walkway and electrical has begun to clear the way for the new      1
ramp.
Millions
0.5
Schedule                            Dollars in             0.13
0
On schedule
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within approved budget and authorization.     Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
62  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
2014-2015 Roof Replacement
Project:   C800637     Remove and replace the current     Project Status:
Budget: $4,416,000    roofing system on the Alaska Hangar  Schedule: Delayed Schedule
One and associated maintenance     Budget: On or under
Phase: Design
Start: 4/1/2014         building, the Air Cargo 6 facility, and   Status Reset: Click here to
the former United Cargo Building.     enter a date.
Schedule Completion:                        (Commission Construction Auth.)
10/31/2015
Significant Developments                    Budget/Costs Incurred
No significant developments this quarter.
5            4.42
4
Schedule
Millions  3
Project is behind schedule. 90% Design completed later than
originally planned                                        2
Dollars in   1     0.45
Budget                                        0.03
0
Project forecast is within the approved budget.                      Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                None at this time
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Delay to schedule could impact construction by moving it into less
favorable weather conditions (from summer into fall).
Budget Transfers
None at this time.



AIRPORT
Port of Seattle 4Q 2014 Report  63

FOURTH QUARTER REPORT, 2014
Dining and Retail Infrastructure Modernization
Project:   C800638    Prepare infrastructure modifications    Project Status:
Budget: $17,353,000   to support Airport Dining and Retail    Schedule: Within or ahead
Phase: Design      unit changes.              Budget: On or under
Status Reset: Click here to
Start: 10/28/2014
enter a date.
Schedule Completion: 6/30/2020
(Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Designer selected. In negotiations for Phase 1 design contract.       20         17.353
Schedule                             15
Millions
Currently on schedule.                                  10
Budget                            Dollars in  5  2.616
0.223563
Currently on budget.
0
Authorized   Forecasted  Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    N/A        N/A               Construction Costs
Amount of COs    N/A        N/A               Not Applicable
Justification for COs: N/A
Risks
Design and construction of elements related to the central terminal
will be critical to upcoming project milestone completion.
Budget Transfers
None this quarter.



AIRPORT

64  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
CCTV Camera-Data Improvements
Project Status:
Project:   C800642      Add cameras and improve the
Schedule: Within or ahead
Budget: $11,000,000     video management system at the
Budget: On or under
Phase: Design        Airport. Project funded by a TSA
Status Reset: Click here to
grant.
Start: 11/4/2012                                  enter a date.
Schedule Completion: 11/30/2016                 (Commission Construction Auth.)

Significant Developments
Budget/Costs Incurred
Infrastructure designer procurement continues. Monthly meetings
with TSA are held regularly. Planning to seek authorization for video     12         11.00
management system improvements in Q1 2015.               10
Millions  8
Schedule                             6
4
The project is proceeding on schedule.
Dollars in   2     1.14
0.09
0
Budget
Authorized  Forecasted Costs Incurred
Project continues within approved budget.
Change Order                         Construction Costs
Current Quarter   Project Total          N/A
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2014 Report  65

FOURTH QUARTER REPORT, 2014
Town & Country Stormwater Pipe
Project Status:
Project:   C800651      Stormwater Pipe             Schedule: Within or ahead
Budget: $350,000                          Budget: On or under
Phase: Construction                        Status Reset: 9/3/2014
Start: 1/1/2014                                   (Commission Construction Auth.)
Schedule Completion: 9/30/2014
Budget/Costs Incurred
Significant Developments
Project has been completed. This will be the final report.           0.355
8.32       8.32
0.35
Schedule                            0.345
0.34   Millions
On schedule
0.335
7.36
0.33
Budget                            Dollars in 
0.325
Project is within budget and forecast.                         0.32
Authorized  Forecasted Costs Incurred
Change Order
Construction Costs
Current Quarter   Project Total
Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Budget Transfers
None



AIRPORT
66  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Domestic Water Piping
Project Status:
Project:   C800657      Replace domestic water piping
Schedule: Within or ahead
Budget: $1,950,000     branches and manifolds including
Budget: On or under
Phase: Design        valves.
Status Reset: 5/13/2014
Start: 11/4/2012                                  (Commission Construction Auth.)
Schedule Completion: 1/4/2016
Budget/Costs Incurred
Significant Developments                     3
1.95
Commission authorized the budget for design.                   2
2
Schedule
Millions
1
0.56
Substantial completion scheduled for January 4, 2016 per the project
Dollars in   1
notebook schedule.                                                 0.00
0
Authorized  Forecasted Costs Incurred
Budget
The authorized amount is $558,000 to complete project design.
Construction Costs
Change Order                         N/A
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: None at this time
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2014 Report  67

FOURTH QUARTER REPORT, 2014
Mech Energy Conservation (CA)
Stage 3 Mechanical Energy    Project Status:
Project:   C800658        Conservation to improve the    Schedule: Within or ahead
Budget: $3,500,000        efficiency of portions of the    Budget: On or under
Status Reset: Click here to
Phase: Audit/Notebook     mechanical infrastructure
system at the Airport.         enter a date.
Start: 8/25/2014
(Commission Construction Auth.)
Schedule Completion: 6/30/2016
Significant Developments                    Budget/Costs Incurred
Received Draft Audit report on January 21, 2015. Draft audit report
4            3.50
includes preliminary project contractor construction cost estimates,
projected energy savings if project is completed and operating data      3
gathered during audit. Review comments submitted and draft audit    MillionsDollars in 
scope of work discussed with construction management and         2
asbestos abetment for development of POS costs.
1
0.33
0.03
Schedule                             0
Authorized  Forecasted Costs Incurred
Investment Grade Audit Final Report Submittal target for February
27, 2015. Schedule for completing audit and incorporating POS
costs in funding request is aggressive when considering scope of
work due to diversity of nine separate energy conservation         Construction Costs
measures.                                   Not Applicable
Budget
Future Commission request will be made after completion of Audit
for additional funds with updated construction schedule.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs   $0        $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.

AIRPORT
68  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
North Utility Tunnel Steam Pipe
Project:   C800659      Replace 45 year old steam piping   Project Status:
Budget: $1,250,000      expansion joints in the North Utility  Schedule: Within or ahead
Phase: Close Out      Tunnel.                Budget: On or under
Status Reset: Click here to
Start: 3/18/2014
enter a date.
Schedule Completion: 10/8/2014
(Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Project is in Closeout Phase.
1.5
1.25      1.25
Schedule
Millions  1
0.71
Project is substantially complete.
0.5
Budget                             Dollars in 
Currently the project is on budget.                             0
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    2          5                Construction Costs
Amount of COs    $9,451       $19,915
0.6
0.51
0.5                 0.44
Justification for COs: Unforeseen conditions
Millions  0.4
0.3
Risks
0.2
None                                  Dollars in  0.1     0.02
0
Budget Transfers
Initial   Change   Spent
None                                         Orders




AIRPORT
Port of Seattle 4Q 2014 Report  69

FOURTH QUARTER REPORT, 2014
S4 & S6 International Corridor Connection
Project Status:
Project:   C800662      Installation of a fixed bridge and
Schedule: Delayed Schedule
Budget: $4,850,000     corridor extension to connect gates
Budget: On or under
Phase: Design        S6 and S4 to the International
Status Reset: 5/13/2014
Corridor
Start: 11/4/2012                                  (Commission Construction Auth.)
Schedule Completion: 10/22/2015
Budget/Costs Incurred
Significant Developments
Project advertised for construction bid in January 2015.            6.0000
4.85       4.82
5.0000
Schedule                           4.0000 Millions
3.0000
Project completion is now scheduled for October 2015.
2.0000
1.0000   Dollars in                          0.53
Budget
0.0000
Project is on budget after some scope reductions for HVAC in           Authorized  Forecasted Costs Incurred
corridor.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None this quarter
Budget Transfers
None this quarter.



AIRPORT
70  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Automated Passport Control
Install additional Automated        Project Status:
Project:   C800667
Passport Control (APC) kiosks in    Schedule: Delayed
Budget: $2,197,900      the existing FIS at the South     Budget: On or under
Phase: Construction     Satellite.               Status Reset: Click here to
Start: 10/31/2013                                 enter a date.
Schedule Completion: 6/1/2015                   (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Project will be adding additional kiosks within the existing budget.      2.5   2.20     2.13
2
Schedule
Millions 1.5
Additional kiosks will be installed by May 1, 2015.                                   1.16
1
Budget                            Dollars in 0.5
Project remains within current budget.                         0
Authorized   Forecasted  Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0                Not Applicable
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2014 Report  71

FOURTH QUARTER REPORT, 2014
Construction Logistics Expansion
Project:   C800688      The expansion and reconfiguration  Project Status:
Budget: $7,400,000     of the existing construction logistics  Schedule: Within or ahead
Phase: Design        facilities (including contractor     Budget: On or under
parking) and the renovation of Port  Status Reset: N/A
Start: August 2014
field offices.                     (Commission Construction Auth.)
Schedule Completion: Q4
2016
Budget/Costs Incurred
Significant Developments
8.000             7.40
Port Commission design authorization and airline majority-in-interest
project approved. Began design for the relocation of the contractor     6.000
parking lot and the renovation of the field offices.                  Millions
4.000
2.47
Schedule
Dollars in  2.000
The project is currently on schedule with the following completion                       0.03
0.000
dates:                                                Authorized Forecasted  Costs
x Contractor Parking Relocation  Q3 2015                                Incurred
x Construction Logistics  Q3 2016
x Field Office Renovation - Q4 2016                    Construction Costs
Not Applicable
Budget
The project is currently within budget.                        Location
Change Order
Current Quarter   Project Total
Number of COs        0          0
Amount of COs        $0         $0
Justification for COs: No change orders issued this quarter.
Risks
Completion of this project to accommodate the Aviation Capital
Program.
Budget Transfers
None this quarter

AIRPORT
72  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Highline Schools Noise Insulation
Project Status:
Project:   C200007      Highline School Insulation        Schedule: Delayed
Budget: $101,797,000    Agreement will provide funding for  Budget: On or under
Phase: Construction     sound mitigation for 15 schools that  Status Reset: Click here to
Start: 3/23/1999          are impacted by aircraft noise from   enter a date.
Schedule Completion:    Sea-Tac Airport.            (Commission Construction Auth.)
11/30/2021

Significant Developments                    Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of       120
102.14     101.80
Washington, and the Highline School District (HSD) provide
100
matching funds. HSD anticipates going out for a public vote for a
80                    63.41
school bond in February 2015.
60
in Millions
Schedule                            Dollars  40
20
The schedule for state funds is unknown. The district's schedule is
0
dependent on obtaining general election bonds at various intervals.        Authorized  Forecasted Costs Incurred
Construction may resume in 2015 if a future voter approved bond is
secured.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Project delayed due to funding issues with HSD. There is a risk if no
bonds are passed in the general election, and if FAA Airport
Improvement Program (AIP) Grant funding is not available.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 4Q 2014 Report  73

FOURTH QUARTER REPORT, 2014
Highline Community College Noise Insulation
Project Status:
Project:   C200042      Highline Community College      Schedule: Within or ahead
Budget: $7,970,266      Insulation Agreement will provide   Budget: On or under
Phase: Construction     funding for up to 22 eligible      Status Reset: Click here to
Start: 1/11/2005          buildings that are impacted by      enter a date.
Schedule Completion:    aircraft noise from Sea-Tac Airport.  (Commission Construction Auth.)
12/31/2013
Significant Developments                    Budget/Costs Incurred
Fourteen of the original 22 eligible buildings have been sound         8.3
insulated by the college. The College sound insulation program has         8.19
8.2
been dependent on receiving funds from FAA grants. The FAA       Millions
notified the Port that the Highline Community College Campus is no     8.1
Dollars in 
longer located within the 65 DNL Noise Contour and therefore is not     8         7.97     7.96
eligible for any further grant funding. Without the FAA's approval and
7.9
funding the remainder of the college buildings cannot be sound
7.8
insulated.
Authorized   Forecasted  Costs Incurred
Schedule
The construction is complete on the last building (Building #4) and    Construction Costs
the Noise Office is working with FAA to Close Grant AIP 127. Once   Not Applicable
the FAA sends Final Grant Closure documents, the project will be
closed.
Budget
The project forecast is within the approved budget. No further
authorization is anticipated with this project.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The FAA will not allocate future grant funds to this project.
Budget Transfers
None at this time
AIRPORT
74  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Home Insulation Retrofit
Project Status:
Project:   C200048      This project includes storm window
Schedule: Within or ahead
Budget: $4,060,147      retrofit of previously insulated
Budget: On or under
Phase: Construction     homes.
Status Reset: Click here to
Start: 1/11/2005                                  enter a date.
Schedule Completion: 12/31/2015                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of      6   5.34
their eligibility. The Port is continuing with storm window retrofit.
5
4.06
Millions  4                         3.44
Schedule
3
The project is on hold until new eligible homes are identified.
Dollars in   2
1
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home. Ability to Identify
future potentially eligible homes.
Budget Transfers
None at this time


AIRPORT

Port of Seattle 4Q 2014 Report  75

FOURTH QUARTER REPORT, 2014
Single Family Home Sound Insulation
Project Status:
Project:   C200093      Sound insulate remaining homes    Schedule: Within or ahead
Budget: $13,747,395     that are within the 1998 65 decibel  Budget: On or under
Phase: Construction     day night level (DNL) noise      Status Reset: Click here to
Start: 3/27/2007          contour.                   enter a date.
Schedule Completion: 12/31/2015                 (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Fifty-seven homes are complete; and 24 homes are in the process of
15    13.75     13.75
receiving sound insulation.
Schedule                            Millions 10
Project is on schedule. Anticipate completion by 4th quarter 2015.                       5.40
5
Dollars in 
Budget
0
The project forecast is within approved budget and authorization to        Authorized  Forecasted Costs Incurred
complete all homes currently in progress.
Change Order                         Construction Costs
Current Quarter   Project Total
3.8
4
Number of COs    0          0
Amount of COs    $0         $0                  3
Millions                            1.78
Dollars in 
Justification for COs: n/a                                    2
1
Risks
0
The ability to accomplish the insulation is dependent on the           0
Initial    Change Order    Spent
homeowner's schedules, willingness to sign an aviation easement,
obtain a subordination agreement from their lender, and structural
integrity of the home.
Budget Transfers
None this quarter


AIRPORT
76  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
RMU/Kiosk Concession Program
Design and fabrication of Retail        Project Status:
Project:   C800146
Merchandising Units (RMUs); power,    Schedule: Delayed
Budget: $879,146.
communications, and data to RMU     Budget: On or under
Phase: Construction  locations; and install floor-mounted    Status Reset: Click here to
Start: 11/20/2007      receptacles for the utilities to allow easy  enter a date.
Schedule Completion:  connection points as well as flexibility for  (Commission Construction Auth.)
2/5/2014           future utilization.

Budget/Costs Incurred
Significant Developments
We are working with the vendor to complete punchlist items.         1.4
1.21
1.2
Schedule                             1       0.88
0.75
0.8
Waiting for corrected color of display arms.
in Millions
0.6
Budget                            Dollars 0.4
0.2
The project forecast is currently within the approved budget and
0
authorization.                                             Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None at this time.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 4Q 2014 Report  77

FOURTH QUARTER REPORT, 2014
Tenant Reimbursement
Build-out of spaces for new and       Project Status:
Project:   C800154    existing tenants. If more than a "basic   Schedule: Within or ahead
Budget: $4,709,577    finish" condition space is built for the   Budget: On or under
Phase: Construction   tenant, the tenant is required to      Status Reset: Click here to
Start: 8/14/2007       reimburse the Port for the cost of the    enter a date.
Schedule Completion:  work beyond this "basic finish".      (Commission Construction Auth.)
TBD          Reimbursements allowed under the
guidelines in the "Tenant Reimb
Policy".
Significant Developments                    Budget/Costs Incurred
5    4.69      4.71
In 2015, anticipate a reimbursement to TSA for buildout of the last
unfinished space on the concourse level of the C1 building, likely Q2     4
or Q3.                                           Millions 3
Schedule                             2           1.30
Schedules vary to meet the tenant's needs.                    Dollars in  1
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
78  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
T-46 Lease Improvements - Stormwater
Improvements
Project Status:
Project: U00050 (C102554)  Construct stormwater treatment    Schedule: Within or ahead
Budget: $8,000,000      system to comply with Ecology    Budget: On or under
Phase: Construction     order.                Status Reset: Click here to
enter a date.
Start: 4/12/2013
(Commission Construction Auth.)
Schedule Completion: 2020
Significant Developments                   Budget/Costs Incurred
The installation of the stormwater treatment vaults at Basin 5, 6 and     10
8 are now completed. Contractor is currently working through punch        8      8
8
list items. Change order work started for the outfall pipe
replacement at Basin 6. The broken outfall pipe has caused        Millions 6
3.84
significant loss of material under the transition slab and 100' gauge      4
landside crane rail beam.                               Dollars in  2
Schedule                             0
Authorized   Forecasted  Costs Incurred
The outfall pipe replacement is scheduled to complete by end of
February. The fourth treatment will be installed once Washington
State Department of Transportation (WSDOT) vacates the lease
Construction Costs
area.
2.5
Budget                                1.949
2
$8,000,000 for Stormwater Treatment System. Currently within
budget.                                         Millions 1.5          1.179
1
Change Order                          Dollars in  0.5
0.020
Current Quarter   Project Total             0
Number of COs    2          5                     Initial Change Spent
Orders
Amount of COs    $260,600     $282,991
Justification for COs: CM coded as "Owner discretionary change"
for outfall pipe replacement.
Risks
Construction impact on terminal operation due to unforeseen
condition.
Budget Transfers
Not Applicable
SEAPORT                          Port of Seattle 4Q 2014 Report  79

FOURTH QUARTER REPORT, 2014
Street Vacations T5,18,105
Project Status:
Street vacation related real estate      Schedule: Delayed Schedule
Project: C102858,
negotiations and agreements --T5,     Budget: On or under
C102875, E104366
T18, and T105 (complete).          Status Reset: Click here to
Budget: $1,500,000                         enter a date.
Phase: Permitting                         (Commission Construction Auth.)
Start: 6/1/2010
Schedule Completion: 2014
Budget/Costs Incurred
1.55
Significant Developments                         1.5    1.5
1.5
Draft Easement and Utility transfer documents have been prepared    Millions 1.45
by the City and are under Port Legal Department review for Terminal
1.378
18 (T-18). Discussion and Title work has begun for Terminal 5.        1.4
Dollars in 1.35
Schedule
1.3
Current schedule has T-18 completed by mid 2015 (City Council          Authorized  Forecasted Costs Incurred
action by end of March 2015) and T-5 by the end of 2015 or early
2016.
Construction Costs
Budget                            Not Applicable
The budget has been revised for 2014 and beyond.             Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Not applicable
Budget Transfers
Budget Transfers Proposed. 91,000 to C102875; $4,867 to
C102874; and $95,867 to C102858.

SEAPORT
80  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Pier 34 Mooring Dolphins
Project Status:
Project:   C800090      Replacement of four existing failed   Schedule: Within or ahead
Budget: $1,800,000      timber mooring dolphins with four   Budget: On or under
Phase: Design        new steel dolphin structures     Status Reset: Click here to
Start: 4/1/2014          located at Pier 34 at the head of    enter a date.
Schedule Completion:    the East waterway by March 2015   (Commission Construction Auth.)
for $1.8M
3/30/2015

Budget/Costs Incurred
Significant Developments
Construction contract bid and awarded.                       2   1.8
1.611
Notice to proceed given to contractor on December 10, 2014..
1.5
Millions
Schedule                             1
Construction underway.                               Dollars in  0.5
0.182
Complete construction by March 2015.
0
Authorized   Forecasted  Costs Incurred
Budget
Project is within approved budget.
Construction Costs
Change Order                         None at this time
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None


SEAPORT
Port of Seattle 4Q 2014 Report  81

FOURTH QUARTER REPORT, 2014
T-5 Berth Modernization
Improvements to support larger     Project Status:
Project: C800132      vessels at T5, including crane rail    Schedule:  within or ahead
Budget: $5,000,000    strengthening, berth deepening,    Budget:   on or under
Phase: Design      and electrical upgrades.        Status Reset: 6/3/2014
Start: 6/3/2014                                 (Commission Construction Auth.)
Schedule Completion: 6/30/2018
Significant Developments                   Budget/Costs Incurred
Thirty percent design completed and review comments are being
6
addressed. Completed site surveys, geotechnical investigation and        4.900    5.000
5
environmental analysis.
Millions    4
Schedule                             3
Dollars in 
2
Sixty percent design completion expected in May. Environmental                      1.225
1
review and permit applications to be submitted in March.
0
Authorized      Forecasted     Costs Incurred
Budget
Budget is currently $5,000,000, which will cover 60% level design
and initial environmental review and permit process.
Construction Costs
None at this time
Change Order
Current Quarter   Project Total         Photo
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Scope of work is subject to change depending on securing tenant
and any impacts of leasing requirements. Design and agency
reviews are on critical path.
Budget Transfers
None


SEAPORT
82  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
T91 Lighting Upgrade
Lighting upgrade at Terminal 91      Project Status:
Project: C800160
Schedule: Delayed Schedule
Budget: $1,035,000
Budget: Forecast Overrun
Phase: Construction                       Status Reset: 3/4/2014
Start: 6/23/2014                                 (Commission Construction Auth.)
Schedule Completion: 10/17/2014
Significant Developments                   Budget/Costs Incurred
The fixtures and controls are 95% installed. Equipment costs and
1.4
unanticipated complications have resulted in a budget deficit. While                1.16
1.2     1.04
funds are available to pay for equipment received, sufficient budget                      0.94
1
to finish the project is lacking.
0.8   Millions
0.6
Schedule                            Dollars in 0.4
The project is currently on hold. Completion of the project is          0.2
dependant on availability of additional funding.                    0
Authorized   Forecasted  Costs Incurred
Budget
There is an estimated $125,000 shortfall in the needed budget.
Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total         Photo
Number of COs    0          2
Amount of COs    $0         ($23,000)
Justification for COs: none this quarter
Risks
If the project is not fully funded the benefit of the control system will
not be realized. It is important to complete the work prior to cruise
season to have a fully functional control system available to the
users.
Budget Transfers
Pending

SEAPORT
Port of Seattle 4Q 2014 Report  83

FOURTH QUARTER REPORT, 2014
T-91, Bldg C175 Roof Replacement
Project Status:
Schedule: Delayed Schedule
Project:   C800430      Replace roof on the C175 building   Budget: On or under
Budget: $2,450,000      at Terminal 91.            Status Reset: 1/14/2014
Phase: Construction                        (Commission Construction Auth.)
Start: 7/26/2011
Schedule Completion: 11/14/2014                 Budget/Costs Incurred
3
2.45
Significant Developments                     2.5       2.15
The roof membrane installation milestone was achieved during       Millions 2              1.729
December and beneficial occupancy was issued on January 9, 2015.   1.5
1
Schedule                            Dollars in 
0.5
The project achieved completion 56 days beyond the original         0
Authorized  Forecasted Costs Incurred
completion. Thirty one days were attributable to weather delays and
the balance due to contractor inefficiencies
Budget                            Construction Costs
The project is anticipated to be completed under budget by            2
1.65
approximately $300,000
1.5
Millions                    1.269
Change Order
1
Current Quarter   Project Total
Dollars in   0.5
Number of COs    2          2                        0.007
Amount of COs    $6,871.26     $6,871.26               0
Initial   Change   Spent
Orders
Justification for COs: weather delays and change of conditions
Risks                               Photo
None at this time
Budget Transfers
None


SEAPORT
84  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
T-91 Substation Upgrades
Project Status:
Schedule: Within or ahead
Project:   C800439      Upgrade/replace existing        Budget: On or under
Budget: $424,000       substations/equipment at       Status Reset: 3/11/2014
Phase: Design        Substation Nos. 1, 14 and 15.     (Commission Construction Auth.)
Start: 11/4/2013
Schedule Completion: 12/31/2015
Budget/Costs Incurred
Significant Developments
0.5
Completed 60% design and 90% design development is underway.        0.424    0.424
0.4
Schedule                            Millions 0.3           0.253
On Schedule
0.2
Dollars in 
Budget                             0.1
On Budget                                    0
Authorized   Forecasted  Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    0          0
Photo
Justification for COs: n/a
Risks
Equipment procurement duration could be very volatile due to
demands. Asbuilt condition cannot be verified due to
locations/accessibility issues - differing site condiitons may result.
Budget Transfers
None



SEAPORT
Port of Seattle 4Q 2014 Report  85

FOURTH QUARTER REPORT, 2014
Argo Yard Truck Roadway
Project Status:
Project:   C800546,      New Port of Seattle owned truck    Schedule: Delayed
E104751, E104754       roadway between East Marginal   Budget: On or under
Budget: $7,750,000      Way and Colorado Avenue South   Status Reset: 4/22/2014
right-of-way.                  (Commission Construction Auth.)
Phase: Construction
Start: 3/11/2012
Schedule Completion: 3/31/2015
Significant Developments                    Budget/Costs Incurred
Construction is underway.
10
7.75       7.75
Schedule                             8
Construction is expected to be completed by end of Q1 2015.        Millions 6
4                     3.1
Budget                            Dollars in  2
Project is currently within the budget authorized by Commission on
April 22, 2014. This status may change depending upon the          0
Authorized  Forecasted Costs Incurred
outcome of several contractor claims currently being negotiated.
Change Order
Construction Costs
Current Quarter   Project Total
Number of COs    8          8                   6  5.05
Amount of COs    $157,525     $157,525               5
Millions   4
Justification for COs: Construction requirements not addressed by       3
design documents.                                   2
Dollars in    1          0.16    0.32
Risks                                 0
Initial   Change   Spent
No significant known risks at this time                                  Orders
Budget Transfers
None



SEAPORT
86  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
T-46 Dock Rehabilitation
Project Status:
Project:   C800603      Terminal 46 Dock Rehabilitation    Schedule: Delayed Schedule
Budget: $1,854,000      Project                Budget: On or under
Phase: Design                            Status Reset: Click here to
Start: 11/6/2012                                  enter a date.
Schedule Completion: Q4 2018                   (Commission Construction Auth.)
Significant Developments
The project is at 90% design and is on hold. This project has been   Budget/Costs Incurred
postponed and will resume design upon completion of TIGER grant
2    1.854
contract execution. At this time this is the last report until the project
is resumed.                                       1.5
Millions                  1.023
Schedule                             1
The project has been postponed until completion of TIGER grant      Dollars in                  0.44
0.5
execution. Design work is scheduled to resume in February 2016,
construction is anticipated to start in 2016/2017.                   0
Authorized   Forecasted  Costs Incurred
Budget
The project is on budget                               Construction Costs
None at this time
Change Order
Current Quarter   Project Total          Photo
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Container operation variation which can cause additional
construction phasing.
Budget Transfers
None


SEAPORT
Port of Seattle 4Q 2014 Report  87

FOURTH QUARTER REPORT, 2014
Terminal 115 Stormwater Separation
Project Status:
Project:   C800689      Separate stormwater originating    Schedule: Within or ahead
Budget: $548,000       from the Port leased area and the   Budget: On or under
Phase: Construction     Common Use Area on T-115 from   Status Reset: 5/6/2014
Start: 1/27/2014          the area exclusively used by       (Commission Construction Auth.)
Schedule Completion:    Northland Services.
12/31/2014
Significant Developments                    Budget/Costs Incurred
Design is complete and construction is underway by PCS.          0.6   0.548    0.548
Unanticipated King County Metro 96" sewer line discovered in vault     0.5
alignment. Design revised to accommodate and revised vaults        0.4               0.364
ordered.                                         Millions
0.3
0.2
One hundred percent of stormwater flow diverted to new outfall using   Dollars in  0.1
temporary pumps as of September 30, 2014.
0
Authorized   Forecasted  Costs Incurred
Schedule
Complete construction by February 28, 2015.
Construction Costs
Budget                            Port Self Perform
Construction
Project is within approved budget.
Change Order
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None

SEAPORT
88  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
East Marginal Way Grade Separation
FAST Corridor funded project;      Project Status:
Project:   E102007     FHWA, State, City with Port       Schedule: Within or ahead
Budget: $56,256,171    commitment of $22,480,807. Scope  Budget: On or under
Phase: Close Out      is to construct grade separation in   Status Reset: 4/22/2014
Start: 5/1/2006          vicinity of T5 and T18 to minimize    (Commission Construction Auth.)
Schedule Completion:    truck traffic/rail conflicts.
Q4 2015

Significant Developments                    Budget/Costs Incurred
Coordination underway within POS and with City for properties and    56.4   56.25    56.25
easements conveyance to City. POS to prepare proposed final       56.2
documents for review by City.                              56
Millions55.8
55.6
Schedule
55.4                        55.3
Anticipate final acceptance by Seattle Department of Transportation    Dollars in 55.2
(SDOT) 3rd Quarter 2015.                              55
54.8
Authorized   Forecasted  Costs Incurred
Budget
Project is on track within 4/22/14 Commission authorization.
Construction Costs
Change Order
25   22          22
Current Quarter   Project Total
Number of COs    0          97                  20
Amount of COs    $0         $1,922,967            Millions 15
10
Justification for COs: N/A this quarter
Dollars in    5          1.992
Risks                                 0
Initial   Change   Spent
None at this time.                                                Orders
Budget Transfers
Photo
None


SEAPORT
Port of Seattle 4Q 2014 Report  89

FOURTH QUARTER REPORT, 2014
Viaduct Construction Coordination
Project:   E104324,    Participate in the design & construction  Project Status:
of the bored tunnel, N. & S. portals,
E104535-38                              Schedule: Within or ahead
Holgate to King St, Central Waterfront
Budget: $2,900,000                         Budget: On or under
surface streets, & related projects to
Phase: Implementation                       Status Reset: Click here to
ensure adequate connection to port    enter a date.
Start: 1/1/2009        facilities.                     (Commission Construction Auth.)
Schedule Completion:
12/31/2018
Significant Developments                    Budget/Costs Incurred
Contractor is implementing repair plans for the SR 99 tunnel boring     3.5
2.9
machine. Seawall and Mercer corridor construction continued.        3
Millions 2.5
Schedule                             2       1.75
1.5                         1.145
Tunnel boring machine expected to resume operation in late March
Dollars in   1
2015. Mercer West construction to continue through mid-2015.
0.5
Seawall Phase I construction to be completed in mid-2016. Central
0
Waterfront completion depends on Viaduct demolition in 2017.           Authorized  Forecasted Costs Incurred
Budget
Port staff costs were within anticipated 2014 spending.            Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total          Photo
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Project delays due to repairs to the tunneling machine.
Budget Transfers
None

SEAPORT
90  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
T-5 and T-91 Maintenance Dredging
Project Status:
Project:   E104840 &     Maintenance Dredge at T-5 all     Schedule: Delayed Schedule
U00067            three berths and at T-91 East     Budget: On or under
Budget: $4,800,000      cruise berth.             Status Reset: Click here to
Phase: Design                            enter a date.
Start: 8/14/2012                                  (Commission Construction Auth.)
Schedule Completion: 2/28/2016
Significant Developments                    Budget/Costs Incurred
T-5 Maintenance Dredging was completed earlier in 2014.           6
4.8        4.8
T-91 East Cruise Berth: The Port is in discussions with the permitting     5
agencies regarding alternatives to traditional dredging. The preferred   Millions 4
alternative is under-water regrading to minimize environmental         3                2.21
impact and reduce costs. Under-water regrading is a new            2
construction method in the Puget Sound area; therefore, permitting    Dollars in  1
agencies requested additional studies delaying the project further,       0
to the 2015-16 in-water construction window.                      Authorized  Forecasted Costs Incurred
Schedule
Construction Costs
T-91 East Cruise Berth is delayed due to permitting complications.    None at this time
Budget
Photo
Project is on budget.
Change Order
Current Quarter   Project Total
Number of COs    0          2
Amount of COs    $0         $20,390.33
Justification for COs: None this quarter
Risks
Environmental permitting may cause further delays, scope change,
and cost impact to the T-91 East Cruise Berth Dredging project.
Budget Transfers
None

SEAPORT
Port of Seattle 4Q 2014 Report  91

FOURTH QUARTER REPORT, 2014
Clean Truck Program Truck Scrapping and
Replacement Project
Project Status:
Scrap or retrofit at least 220 trucks   Schedule: Within or ahead
Project: U00079; U00134
with pre-2007 engines currently     Budget: On or under
Budget: $6,327,000
operating at the Port of Seattle.      Status Reset: Click here to
Phase: Implementation                       enter a date.
Start: 12/10/2013                                 (Commission Construction Auth.)
Schedule Completion: 11/30/2015
Budget/Costs Incurred
Significant Developments
The Clean Truck program provides incentive vouchers to truckers
7    6.327     6.327
who operate at the Port and who commit to scrapping trucks with--      6
depending on the grant source--either 2004 or 2006 or older engines    5
in order to purchase trucks with either 2007 or 2010 or newer        Millions 4
Dollars in 
engines. Currently, 179 voucher applications have been pre-          3
approved, and 63 trucks have been scrapped and replaced. The       2              1.187
program will continue through December 2015.                  1
0
Authorized  Forecasted    Costs
Schedule                                       Incurred
On schedule
Construction Costs
Budget                            Not Applicable
On budget
Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Due to multiple funding sources, the project needs to be compliant
with funding agencies' requirements. A consultant has been retained
to provide grant administration services.
Budget Transfers
None

SEAPORT
92  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
IHI Crane Removal
Remove three IHI Cranes from      Project Status:
Project: U00099
Terminal 18                  Schedule: Delayed
Budget: $1,500,000                        Budget: On or under
Phase: Construction                       Status Reset: 9/11/2012
Start: 9/11/2012                                 (Commission Construction Auth.)
Schedule Completion: 1/23/2015
Budget/Costs Incurred
Significant Developments
With the PMA and Longshore Union without a contract and the        1.6   1.5
1.4
potential for labor unrest disrupting terminal operations, the
Millions   1.2
contractor was not given notice to proceed. The Port has entered
1
into change order negotiations with the potential outcome of
0.8
suspension of the contract or a termination for convenience.        Dollars in  0.6
0.4
0.116
Schedule                             0.2
0
By not issuing Notice to Proceed, the contract completion date will         Authorized   Forecasted   Costs Incurred
not be achieved. At this point in the negotiations with the contractor
it is difficult to estimate when the completion date will resume
Construction Costs
Budget                           Not Applicable
The project is within budget
Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Anticipate additional project costs for the contract termination for
convenience or contract suspension and subsequent reactivation
costs.
Budget Transfers
none

SEAPORT

Port of Seattle 4Q 2014 Report  93

FOURTH QUARTER REPORT, 2014
FT C15 HVAC Improvements
Project Status:
Project:   C800137     Provide the preliminary planning,
Schedule: Delayed Schedule
Budget: $4,887,000     design, and construction to replace
Budget: On or under
Phase: Construction    the existing HVAC systems within
Status Reset: 10/8/2013
Start: 5/1/2010         Building C-15 that are at the end of
(Commission Construction Auth.)
their service life.
Schedule Completion:
6/30/2014
Significant Developments                    Budget/Costs Incurred
Major HVAC equipment has been installed and systems are in use.     5   4.887    4.887
Contractor addressing punchlist items. Equipment manufacturer       4.8
discovered heat pumps fabrication errors and will pursue corrective    Millions 4.6
actions.
4.4                         4.281
Dollars in  4.2
Schedule
4
Contractor is behind schedule and substantial completion date is
3.8
further delayed due to equipment manufacturing error. Notice of          Authorized  Forecasted Costs Incurred
forbearance has been issued.
Budget                            Construction Costs
Project is still within the October 8, 2013 Commission funding
authorization.                                            3.5
2.97
3
2.4
Change Order                          Millions 2.5
2
Current Quarter   Project Total             1.5
Number of COs    3          10
Dollars in    1
Amount of COs    $6,554       $110,001              0.5     0.11
0
Initial   Change   Spent
Justification for COs: Mostly varying site conditions and some design
Orders
error and omission.
Risks                               Photo
Some significant cost items have been raised by the contractor but
Port disagrees with their merits. These likely would result in claims
and dispute resolution/mediation may be necessary.
Budget Transfers
None
REAL ESTATE
94  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
P-69 Built-up Roof Replacement
Project Status:
Project:   C800314      Replace 32,000SF of the 65,000SF  Schedule: Within or ahead
Budget: $3,418,000      Built-Up Roof at the P-69       Budget: On or under
Phase: Construction     Headquarters Office Building     Status Reset: 2/25/2014.
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 10/30/2014
Significant Developments                    Budget/Costs Incurred
Construction has reached Substantial Completion. Final punchlist
4
3.418      3.418
items and cleanup is in progress.                            3.5
3
Schedule                            Millions 2.5           2.07
2
Substantially complete and is in close-out.
1.5
Dollars in   1
Budget                             0.5
0
The project is currently below budget.
Authorized   Forecasted  Costs Incurred
Change Order
None                                 Construction Costs
Risks                                3.5  3.13
3
Current Quarter   Project Total
2.5
Number of COs    0          2                 Millions           1.923
2
Amount of COs    $0         -$14,240             1.5
Dollars in  1
Justification for COs: None this quarter                        0.5
0
Budget Transfers                         0.5  Initial  Change0.014  Spent
Orders
None



REAL ESTATE

Port of Seattle 4Q 2014 Report  95

FOURTH QUARTER REPORT, 2014
FT C-2 Nordby HVAC and Roof Replacement
Project Status:
Project:   C800344      Replace 23,000SF of existing      Schedule: Within or ahead
Budget: $2,438,600      Roofing and roof top HVAC units   Budget: On or under
Phase: Construction                        Status Reset: 1/7/2014
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 1/16/2015
Significant Developments                    Budget/Costs Incurred
The project is in the final stages of construction; finalizing the HVAC
3
units Testing and Balancing, Commissioning and Roof replacement        2.438
2.5               2.338
installations. Final punch list items are now being completed.
Millions  2                          1.62
Schedule                             1.5
1
The project is scheduled for completion in Q1 2015               Dollars in 
0.5
Budget                             0
Authorized   Forecasted  Costs Incurred
The project is currently below budget.
Change Order
Construction Costs
Current Quarter   Project Total
Number of COs    0          0                   2.5  2.170
Amount of COs    $0         $0                   2
Millions                     1.480
1.5
Justification for COs: n/a
1
Risks                                Dollars in  0.5
0.000
No risks at this time.                                          0
Initial   Change   Spent
Orders
Budget Transfers
None this quarter



REAL ESTATE
96  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
FT Net Shed #9 Roof Overlay
Project Status:
Project:   C800527      Overlay 12,000SF of existing      Schedule: Within or ahead
Budget: $401,400       corrugated Roof at the FT Net     Budget: On or under
Phase: Construction     Shed Building            Status Reset: 1/7/2014
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 1/16/2015
Budget/Costs Incurred
Significant Developments
0.5
The project is in the final stages of construction. Punchlist and             0.401    0.401
clean-up will occur shortly.                                  0.4
Millions                            0.295
0.3
Schedule
0.2
With the SCL, L&I and Contractor delays, the project is scheduled for   Dollars in  0.1
completion in Q1 2015
0
Budget                               Authorized Forecasted Costs Incurred
The project is currently at budget.
Change Order                         Construction Costs
Current Quarter   Project Total             0.3  0.268
0.237
Number of COs    1          1                  0.25
Amount of COs    $0         $0                 Millions 0.2
0.15
Justification for COs: Nesting Seagulls, Seattle City Light Powerline
0.1
and Time extention due to contract execution date.               Dollars in 
0.05
0
0
Risks
Initial   Change   Spent
None                                         Orders
Budget Transfers
None this quarter


REAL ESTATE
Port of Seattle 4Q 2014 Report  97

FOURTH QUARTER REPORT, 2014
P69 Carpet Replacement
Project: C800691      Replace carpet flooring at        Project Status:
Corporate Headquarters Building    Schedule: Delayed Schedule
Budget: $1,200,000
on the second and third floors.       Budget: On or under
Phase: Construction                       Status Reset: 2/10/2015
Start: 7/7/2014                                 (Commission Construction Auth.)
Schedule Completion: 9/30/2014
Significant Developments                   Budget/Costs Incurred
The Contractor has successfully completed their assigned scope of    1.4
1.2        1.2
work on time and within budget. Punchlist work was completed       1.2
December 14th. Port crafts are performing some detail work as a       1
result of profile differences in the old carpet versus the new. We      Millions 0.8
0.6
anticipate closing the project very soon. This will be the last report      0.6
on this project.                                          Dollars in  0.4
0.2
Schedule                             0
Authorized   Forecasted  Costs Incurred
The contractor began work on October 22 and completed December
14th. Port crafts will be completing with detail work in February
2014.
Construction Costs
Not Applicable
Budget
The project is anticipated to complete within the allotted budget.
Change Order
Current Quarter   Project Total
Number of COs    1          3
Amount of COs    $1,400       $4,700
Justification for COs: CO-03 was issued to add carpet replacement
in a corridor on the second floor.
Risks
None at this time
Budget Transfers
None

REAL ESTATE
98  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
P69 Beam Rehabilitation Project
Project: C800698         Rehabilitate five rows of       Project Status:
Budget: $2,300,00-       concrete beams supporting    Schedule: Within or ahead
$3,300,000             top of clerestory windows at    Budget: On or under
Phase: Design         P69.               Status Reset: Click here to
enter a date.
Start: 7/1/2014
(Commission Construction Auth.)
Schedule Completion: 10/6/2016
Significant Developments                   Budget/Costs Incurred
Commission authorization to proceed with design and preparation of
0.35      0.33          0.33
bid documents received on July 1, 2014.
0.3
Schedule                            Millions 0.25
0.2
Sixty percent Design review complete. Mock-up installation submittal   Dollars in  0.15
review complete.                                    0.1
0.048
0.05
Budget                             0
Authorized      Forecasted     Costs Incurred
Design phase budget authorization is $330,000. Total project costs
are expected to be between $2,300,000 and $3,300,000.
Construction Costs
Change Order                        Not applicable at this time
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Scope of work and costs may escalate as design work and
investigations proceed.
Budget Transfers
Project preliminary design work began under Expense project
#105048  P69 Roof Beam Repair. Cost transferred to this project.
Approx. $51,000 (SP 105146)

REAL ESTATE
Port of Seattle 4Q 2014 Report  99

FOURTH QUARTER REPORT, 2014
FT Net Shed Code Compliance
Project:   E104838      FT Net Sheds 3-11: Improvements   Project Status:
Budget: $2,950,000      required per City of Seattle building  Schedule: Within or ahead
Phase: Construction     & fire codes             Budget: On or under
Status Reset: 6/25/2013
Start: 5/1/2012
(Commission Construction Auth.)
Schedule Completion: 6/30/2015
Budget/Costs Incurred
Significant Developments
Port Construction Services completed code compliance            3.5
2.95       2.95
improvements to Netsheds 5 (Netsheds 9, 10 and 11 completed       3
previous quarter). Began retrofit work inside Netshed 6.            Millions 2.5
2
1.48
1.5
Schedule
Dollars in   1
Netshed retrofit work has taken longer in some netlockers and is
0.5
impacting overall construction completion schedule. Exact schedule     0
impact will be assessed early 2015.                             Authorized  Forecasted Costs Incurred
Budget
Project budget is on track.                               Construction Costs
Port Self Perform
Change Order                         Construction
Current Quarter   Project Total
Number of COs    N/A        N/A               Photo
Amount of COs    N/A        N/A
Justification for COs: N/A
Risks
It is difficult to forecast the amount of stored materials that needs to
be moved out and moved back into the netlockers since tenant
storage habits vary significantly. In addition, the amount of work
required in each unit is difficult to assess until some stored materials
are cleared and locker conditions are more visible. These would
impact the overall project schedule and budget.
Budget Transfers
None

REAL ESTATE
100  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
ID Badge System Replacement
Project Status:
Project: C800162        Procurement and replacement of   Schedule: Delayed Schedule
Budget: $2,500,000      the Portwide ID Badge system     Budget: On or under
Phase:Implementation    including software, hardware, and   Status Reset: Click here to
Start: 5/1/2012           equipment.                 enter a date.
Schedule Completion: 7/30/2015                   (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
The first phase of the new Badge System was deployed on
November 5th. A 2nd deployment to add mobile functionality and      3
2.50      2.50
authorized signer efficiencies is in the planning stage.
2.5
2                    1.68
Schedule
Millions 1.5
Prior Report: Resource availability and system complexity have
Dollars in  1
delayed project completion.
0.5
0
Budget
Authorized  Forecasted    Costs
On Budget                                                Incurred
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          1
Amount of COs    $0         $108,497
Justification for COs: None this quarter.
Risks
Resource availability may continue to delay the second phase mobile
deliverables.
Budget Transfers
None


CORPORATE
Port of Seattle 4Q 2014 Report  101

FOURTH QUARTER REPORT, 2014
Enterprise Project Cost Management
Project Status:
Project: C800321        Replace the current construction    Schedule: Delayed Schedule
Budget: $1,525,000      costing systems with a common    Budget: On or under
Phase:Close Out       enterprise project cost         Status Reset: Click here to
Start: 4/21/2008          management system.           enter a date.
Schedule Completion: 12/30/2014                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
This will be the last report for this project in close-out.
1.54    1.525    1.525
1.52
Schedule
1.5  Millions
Prior Report: Availability of resources is impacting the completion of                   1.48
1.48
the remaining components. These include features such as cash
flows and trend logs as well as additional interfaces that require       1.46 Dollars in 
resources currently focused on the Peoplesoft Financials Upgrade     1.44
Authorized Forecasted   Costs
project. We are in the process of procuring additional configuration
Incurred
assistance and expect to deliver in phases over the next several
months.
Construction Costs
Not Applicable
Budget
None
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No significant risks at this time.
Budget Transfers
None


CORPORATE
102  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Network Switch Replacement
Project Status:
Project: C800323        Upgrade the Network switch      Schedule: Within or ahead
Budget: $1,500,000      infrastructure hardware and      Budget: On or under
Phase: Implementation    software                Status Reset: Click here to
Start: 12/15/2013                                enter a date.
Schedule Completion: 3/31/2015                   (Commission Construction Auth.)

Significant Developments
Budget/Costs Incurred
Network infrastructure at SeaTac and the Port's offsite data center
have been completed. P69 upgrades will be completed in first        1.6
quarter 2015 as planned.                                    1.50    1.50
1.5
Schedule                            Millions 1.4
On schedule.                                     1.3              1.25
Dollars in 1.2
Budget
1.1
On budget.                                        Authorized Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No significant risks.
Budget Transfers
None



CORPORATE
Port of Seattle 4Q 2014 Report  103

FOURTH QUARTER REPORT, 2014
Terminal 91 Visitor Management
Project Status:
Project: C800436        Upgrade of the Radio System Core  Schedule: Within or ahead
Budget: $520,000       Hardware and Software and      Budget: On or under
Phase: Implementation    Dispatch Consoles           Status Reset: Click here to
Start: 7/1/2013                                   enter a date.
Schedule Completion: 5/1/2016                    (Commission Construction Auth.)
Significant Developments
Procurement has been completed and implementation is in process.  Budget/Costs Incurred
Schedule                              0.6  0.52  0.52
0.5
On Schedule
Millions  0.4
Budget                              0.3
0.2
On Budget                                   Dollars in              0.12
0.1
Change Order                           0
Authorized Forecasted   Costs
Current Quarter   Project Total                         Incurred
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
Expected grant extensions have not been approved so the project
will need to substantially deliver by August 2015. Mitigation plans in
progress.
Budget Transfers
None



CORPORATE
104  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Contractor Data System Upgrade
Project Status:
Project: C800519        Upgrade of the Contractor Data    Schedule: Within or ahead
Budget: $1,500,000      System used by Engineering and   Budget: On or under
Phase: Implementation    other groups to track contracts for   Status Reset: Click here to
Start: 7/1/2013           construction projects.           enter a date.
Schedule Completion: 2/28/2016                   (Commission Construction Auth.)
Significant Developments
Development is in progress                            Budget/Costs Incurred
Schedule                              2
1.5      1.5
On Schedule                                    1.5
Millions
Budget                              1
On Budget                                   Dollars in  0.5
0.08
Change Order                           0
Authorized Forecasted   Costs
Current Quarter   Project Total                          Incurred
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
Port of Seattle 4Q 2014 Report  105

FOURTH QUARTER REPORT, 2014
Computer Dispatch System Upgrade
Project Status:
Project: C800520        Upgrade Computer Dispatch
Schedule: Within or ahead
Budget: $790,000       System used by 911 and
Budget: On or under
Phase: Implementation    Emergency Responders
Status Reset: Click here to
Start: 4/1/2013                                   enter a date.
Schedule Completion: 8/31/2015                   (Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Procurement has been completed and design and implementation       1
are in progress.                                             0.79   0.79
0.8
Millions
Schedule                             0.6
0.4
On Schedule
Dollars in   0.2                    0.06
Budget                              0
On Budget                                       Authorized Forecasted Costs
Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None



CORPORATE
106  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Construction Document Management
Project Status:
Project: C800521       Replacement of the Construction    Schedule: Delayed Schedule
Budget: $900,000      Document Management System    Budget: On or under
Phase: Implementation   used by Construction Management   Status Reset: Click here to
Start: 9/10/2013         to accept, review, and distribute     enter a date.
Schedule Completion:   critical documentation.         (Commission Construction Auth.)
9/30/2015
Significant Developments                    Budget/Costs Incurred
Procurement is complete and implementation is in progress
1    0.9     0.9
Schedule                             0.8
Procurement took 7 months longer than planned to complete,        Millions 0.6
resulting in a 6 month delay to the project.
0.4
Dollars in   0.2
Budget                                       0.05
0
On Budget
Authorized Forecasted  Costs
Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No significant risks at this time.
Budget Transfers
None



CORPORATE
Port of Seattle 4Q 2014 Report  107

FOURTH QUARTER REPORT, 2014
Radio System Upgrade
Project Status:
Project: C800586        Upgrade of the Radio System Core  Schedule: Within or ahead
Budget: $6,750,000      Hardware and Software and      Budget: On or under
Phase: Implementation    Dispatch Consoles           Status Reset: 11/4/2014
Start: 6/9/2013                                   (Commission Construction Auth.)
Schedule Completion: 3/31/2015
Significant Developments                    Budget/Costs Incurred
Radio system upgrade was successfully completed in 2nd Quarter.
The following phase will address King County integration and small       8
6.75     6.75
enhancements that will improve availability.
6
4.3
Schedule                              4
Millions
On Schedule
Dollars in     2
Budget                              0
Authorized Forecasted   Costs
We are estimating a budget underrun of approximately $1,500,000.                   Incurred
Change Order
Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None



CORPORATE
108  Port of Seattle 4Q 2014 Report

FOURTH QUARTER REPORT, 2014
Noise Monitoring System Replacement
Project Status:
Project: C800693        Upgrade or Replacement of the    Schedule: Within or ahead
Budget: $1,900,000      Airport Noise Monitoring System    Budget: On or under
Phase: Implementation                        Status Reset: Click here to
Start: 4/1/2014                                   enter a date.
Schedule Completion: 8/31/2015                   (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Procurement has been completed and implementation is in progress.
1.9      1.9
2
Schedule
1.5
On Schedule
1
in Millions
Budget
Dollars    0.5
On Schedule                                                0.03
0
Authorized Forecasted   Costs
Change Order                                    Incurred
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0                Not Applicable
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None



CORPORATE
Port of Seattle 4Q 2014 Report  109

FOURTH QUARTER REPORT, 2014
Expense Project Authorizations
Project Status:
Project: C800694        Expand planning, tracking, and    Schedule: Within or ahead
Budget: $520,000       commitment control capabilities in   Budget: On or under
Phase: Implementation    Peoplesoft Financials System that   Status Reset: Click here to
Start: 6/3/2014           will cover an entire authorization    enter a date.
Schedule Completion:    with both capital and expense     (Commission Construction Auth.)
project components
7/31/2015
Significant Developments                    Budget/Costs Incurred
Implementation is in process.
0.7    0.65     0.65
Schedule                              0.6
Millions   0.5
On Schedule
0.4
0.3
Budget
Dollars in    0.2
On Budget                                     0.1           0.04
0
Authorized Forecasted   Costs
Change Order                                    Incurred
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0                Not Applicable
Justification for COs: n/a
Risks
No significant risks at this time.
Budget Transfers
None



CORPORATE
110  Port of Seattle 4Q 2014 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.