Item Number:  7a_Report
Meeting Date: June 24, 2014


Commission Staff Brieng
Capital Improvement Projects
First Quarter Report 2014

This page intentionally left blank









ii  Port of Seattle 1Q 2014 Report

Port of Seattle
Capital Improvement Project Report
First Quarter 2014
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2014, the Port plans to invest $295,200,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such, the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes "Project Status" illustrating at a
glance if the project is on schedule, and within budget, and the date Construction authorization was received.
x  Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x  Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x  Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
x  Change Orders provides information on current quarter's COs and total project COs including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
x  Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x  Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x  Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 1Q 2014 Report  1

Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ............................................... 7-8.......... ..............................
C101107 ................160th GT Lot ..........................................................9 ...........
C102032 ...............Sanitary Sewer Pump Station Upgrade ...............10 .......... .............................. 
C102573 ...............Aireld Pavement Replacement ...........................11 ..........
C800019 ...............Gate Utilities Improvement ...................................12 .......... ..............................
C800034 ...............North Expressway Relocation ..............................13 ..........
C800061 ...............Main Terminal South Low Voltage ..................... 14-15 ........ ..............................
C800107 ...............C4 UPS System Improvements ............................16 .......... .............................. 
C800168 ...............C60-C61 BHS Modications ................................17 ..........
C800174................FIS - New Primary Inspection Booths ..................18 .......... ..............................
C800218 ...............Security Exit Lane Breach Control Phase I ..........19 .......... ..............................
C800230 ...............Emergency Lighting Parking.................................20 .......... ..............................
C800234 ...............Feeder 101 Tap Replacement ..............................21 .......... .............................. 
C800238 ...............Central Plant Pre-Conditioned Air ..................... 22-23........ .............. ....................................
C800247 ...............Cargo 2 West Hardstand ......................................24 ..........
C800251 ...............Vertical Conveyance Modernization.....................25 ..........
C800253 ...............Parking System Replacement ..............................26 .......... ..............................
C800254 ...............Aircraft RON Parking Post Ofce Site..................27 ..........
C800267 ...............Port Owned Loading Bridges ...............................28 ..........
C800268 ...............Stage 2 Mechanical Energy Implementation .......29 .......... ..............................
C800274 ...............8th Floor Weather Proong ..................................30 .......... ..............................
C800324 ...............Long-Term Cell Phone Lot ....................................31 .......... ..............
C800334 ...............Two new CTE Freight Elevators ........................ 32-33 ....... 
C800335 ...............EGSE Electrical Charging Stations ...................34-35 ....... ..............
C800376 ...............South Satellite HVAC, Lights, and Ceiling Repl. ..36 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ............................ 37-38........
C800390 ...............Cargo 6 Enhancements ........................................39 ..........
C800406 ...............RW 16C/34C Reconstruction ...............................40 ..........
C800412 ...............South Satellite Concessions Project ....................41 .......... .............................. 
C800415 ...............ALCMS Upgrade...................................................42 ..........
C800417 ...............Lagoon 3 Bird Wires .............................................43 ..........
C800426 ...............FIS Improvement - Short Term .............................44 .......... ..............
C800451 ...............Doug Fox Site Improvement .................................45 .......... ..............
C800455 ...............Concourse D Common Use Environment ............46 .......... ..............................
C800459 ...............2011-2013 Roof Replacement Program ...............47 ..........


2  Port of Seattle 1Q 2014 Report

Aviation, cont.

Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800461 ...............IWTP Fiber Installation .........................................48 .......... ..............................
C800464 ...............Fiber Infrastructure to Gate Backstands ..............49 .......... .............................. 
C800466 ...............South Satellite - Additional Gate Lobby ................50 .......... ..............................
C800467 ...............PLB Replacement .................................................51 ..........
C800473 ...............CUSE at Ticket Counters/Gates - AR ..................52 .......... ..............................
C800474 ...............Airport Signage .....................................................53 .......... ..............................
C800475 ...............Miscellaneous Building Improvements - AR.........54 ..........
C800479 ...............Fire Station Electrical Upgrades ...........................55 .......... ..............................
C800484 ...............Laptop Power In Concourses ...............................56 .......... ..............................
C800490 ...............New Window Wall Ticket Zone 1 ..........................57 .......... ..............................
C800491 ...............Convert Ticket Zone 2 Pusback ...........................58 ..........
C800492 ...............Convert Ticket Zone 3 Flow Thru .........................59 ..........
C800495 ...............Facility Monitoring System Renewal ....................60 .......... ..............................
C800497 ...............Airport Wide Mechanical Controls System ..........61 .......... ..............................
C800541 ...............RAC Baggage Claim Renovation .........................62 .......... ..............................
C800543 ...............Replace PLBs at S7, S9, B4 .................................63 ..........
C800544 ...............NorthSTAR Program.............................................64 .......... ..............................
C800545 ...............NorthSTAR Main Terminal Improvements............65 .......... .............................. 
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............66 ..........
C800550 ...............Concourse D Roof Replacement..........................67 ..........
C800551 ...............Grease Interceptor Augmentation ........................68 ..........
C800555 ...............NorthSTAR Refurbish Baggage Systems ............69 ..........
C800556 ...............NorthSTAR North Satellite Lobbies ................... 70-71........ .............................. ....................................
C800557 ...............Snowblower and Deicer Trucks ............................72 ..........
C800560 ...............MT Mezzanine Tenant Relocation ........................73 ..........
C800576 ...............Known Crew Member Employee Bypass .............74 .......... ..............................
C800583 ...............International Arrivals Facility ................................75 ..........
C800605 ...............Security Exit Lane Breach Control Phase 2 .........76 .......... ..............................
C800609 ...............NSAT - STS Ceiling Leak Repair ..........................77 ..........
C800611 ...............Passenger Bridge & Walkway S16 Repl ..............78 ..........
C800612 ...............Checked Baggage Recapitalization/Optimzation.79 ..........
C800615 ...............Second Floor Mezzanine Infra Upgrade ..............80 .......... ..............................
C800651 ...............Town-Country Stormwater Pipe ...........................81 ..........
C800659 ...............North Utility Tunnel Steam Pipe ...........................82 ..........
C800667 ...............Automated Passport Control ................................83 ..........


Port of Seattle 1Q 2014 Report  3

Other Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................84 .......... ..............................
C200042 ...............Highline Community College Noise Insulation .....85 ..........
C200048 ...............Home Insulation Retrot .......................................86 ..........
C200093 ...............Single Family Home Sound Insulation .................87 ..........
C800146 ...............RMU/Kiosk Concession Program ........................88 .......... ..............................
C800150 ...............Burien Commercial Property Acquisition .............89 .......... ..............................
C800154 ...............Tenant Reimbursement ........................................90 ..........
Seaport
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C102554............... Terminal 46 Development....................................91 ..........
C102858 et al ....... Street Vacations T-5/18/105.................................92 .......... ..............................
C800090 ...............Pier 34 Mooring Dolphins .....................................93 ..........
C800183 ...............P91 Fender System Upgrade ...............................94 ..........
C800430 ...............T-91 Building C175 Roof Replacement ................95 .......... ..............................
C800516 ...............SEA P-66 Apron Pile Wrap ..................................96 ..........
C800546 ...............Argo Yard Truck Roadway ....................................97 ..........
C800603 ...............T-46 Dock Rehabilitation ......................................98 .......... ..............................
C800689 ...............T-115 Stormwater Separation ...............................99 ..........
U00079 .................Clean Truck Program Truck Scrap & Repl ..........100 .........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation .................101 .........
E104324 ................Viaduct Construction Coordination .....................102 .........
E104840................T-5, T-18 and T-91 E. Maintenance Dredging .....103 ......... ..............................

Real Estate
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800088 ...............P69 Built-up Roof Replacement ..........................104 .........
C800137 ...............FT C15 HVAC Improvements ..............................105 ......... ..............................
C800314 ...............P69 Built-up Roof Replacement ..........................106 .........

4  Port of Seattle 1Q 2014 Report

Real Estate, Cont.
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800344 ...............FT C-2 Nordby Roof and HVAC .........................107 .........
C800527 ...............FT Net Shed 9 Roof Replacement ......................108 .........
C800571 ...............MIC Built-up Roof Replacement ..........................109 .........
E104765 ................T91 Lighting Upgrade ..........................................110 .........
E104838................FT Net Shed Code Compliance .......................... 111 .........
E105072 ................P69 Carpet Replacement ....................................112 .........
Corporate

Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ...................113 .........
C800003 ...............Maximo Enterprise Implementation .....................114 ......... ..............................
C800162 ...............ID Badge Replacement .......................................115 ......... ..............................
C800321 ...............Enterprise Project Cost Management ..................116 ......... ..............................
C800323 ...............Network Switch Replacement ..............................117 .........
C800387 ...............Time Clock System ..............................................118 ......... ..............................
C800521 ...............Construction Document Management ................119 .........
C800558 ...............Access Control Network Refresh ........................120 .........
C800586 ...............Radio Systems Upgrade......................................121 .........

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date



Port of Seattle 1Q 2014 Report  5

FIRST QUARTER REPORT, 2014
3rd Runway Program
Project Status:
Project: C000683,       The 3rd Runway Program
Schedule: Within or ahead
C001138, C001175,      constructed a new 8,500 foot long
Budget: On or under
C001331, C001751,      runway, connecting taxiways, and
Status Reset: Click here to
C001760, C100172      related infrastructure.
enter a date.
Budget: $914,744,759                        (Commission Construction Auth.)
Phase: Close Out
Start: 5/27/1997
Schedule Completion: 12/31/2011
Budget/Costs Incurred
Significant Developments
1150
1,094.22
All work is complete and utility invoices paid that had a delay in       1100
being received. This is the last report for this program.            1050
1000  Millions
950           914.63    921.79
Schedule
Dollars in 900                                                                            Complete.                                                                850
800
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                        Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Budget Transfer
Total Increase of $198,000 in part to cover SCL payment


AIRPORT
6  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Rental Car Facility
Project Status:
Project:   C100266,     The program will construct a       Schedule: Within or ahead
C102167, C800032     consolidated rental car facility (RCF),  Budget: On or under
off-site roadway improvements (ORI),  Status Reset: 6/30/2009
Budget: $378,014,414
Phase: Construction    a bus maintenance facility (BMF),    (Commission Construction Auth.)
Start: 02/24/1998        improvements at the Main Terminal for
busing (MTI), plus purchase a fleet of
Schedule Completion:
buses.                     Budget/Costs Incurred
Q2 2012
400    396.11
Significant Developments                     395
390
The RCF program is substantially complete with projects either       Millions 385
closed or in closeout. The RCF staff is continuing discussions for                 378.00
380
resolution of final claims. BMF and ORI are in closeout.                               373.24
375
Dollars in 370
Schedule                             365
360
RCF opened May 17, 2012. Resolution of the final claims for the        Authorized Forecasted Costs Incurred
RCF project are expected to continue into 2015.
Budget                            Construction Costs
The RCF program remains under budget with a total program budget
of $419,306,000. The total forecasted cost at completion for the        300          264.66
250.74
RCF program, not including the payment for negotiated final claims,      250
is $398,306,000.                                     Millions 200
150
Change Order                           100
Dollars in 
Current Quarter   Project Total             50      16.35
Number of COs    1          1,756                 0
Initial   Change   Spent
Amount of COs    $64,717      $15,557,250
Orders
Justification for COs: One for additional Commissioning support for
the mechanical systems.                             Photo
Risks
Resolution of the pending claims for the RCF project. No other risks
were identified for the other projects.


Port of Seattle 1Q 2014 Report  7

Budget Transfers
Transferred $17,543 from capital to expense projects in support of the BMF close out.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - This contract is closed
and the final cumulative change order percentage is 21.3%.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - This contract is closed
with a final cumulative change order percentage of 3.97%.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - The final payment was made to the Contractor and the contract is in closeout. The
cumulative change order value through this quarter is $3,017,296 (39.6%) with no activity this quarter.
Bus Maintenance Facility - MC-0316730 - Final payment was made to the Contractor and the contract
is in closeout. The cumulative change order value is $300,190 (2.29%) with no activity this quarter.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - The current cumulative change order
percentage through this quarter is 4.86% with one change order executed this quarter. This contract
is active with final claim negotiations underway.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - This contract is closed with a final cumulative
change order percentage of 19.4%.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  This contract is closed with a final
cumulative change order percentage of 170.5%.





AIRPORT
8  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
160th GT Lot Improvements
Project Status:
Project: C101107     Renovate existing building for      Schedule:  within or ahead
Budget: $4,532,000    better functionality, improve lot     Budget:   on or under
Phase: Design      draingage, underground existing    Status Reset: Click here to enter a
overhead utility lines, fencing and
Start: 2/1/2013                                 date.
landscaping.
Schedule Completion:                       (Commission Construction Auth.)
9/30/2015
Significant Developments                   Budget/Costs Incurred
Completed assessment of existing facilities and refined final scope
5            4.532
of work. Design started with detailed scope of work issued to
4
consultant for building renovation. Preparation of agreements for
underground utility lines in progress.                           3  Millions
2     1.5
Schedule                            Dollars in             1.01795
1
Completion of design and advertisement for bids expected in
0
November 2014, followed by construction and beneficial occupancy
Authorized   Forecasted  Costs Incurred
in September 2015.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
1.6           1.5
Change Order                          1.4
1.2
Millions         1
Current Quarter   Project Total             1          0.843
Number of COs    0          0                  0.8
Amount of COs    $0         $0                  0.6
Dollars in    0.4
0.2
Justification for COs: n/a
0
Initial   Change   Spent
Risks                                      Orders
Unforeseen building or site conditions could increase design and
construction costs. Unforeseen complications in executing
agreements with utilities for undergrounding lines.
Budget Transfers
None

AIRPORT
Port of Seattle 1Q 2014 Report  9

FIRST QUARTER REPORT, 2014
Sanitary Sewer Pump Station Upgrade
Upgrade the aging control systems   Project Status:
Project:   C102032
of 22 sanitary sewer lift stations.     Schedule: Delayed
Budget: $1,133,000                         Budget: On or under
Phase: Design                            Status Reset: Click here to
Start: 3/1/2013                                   enter a date.
Schedule Completion: 9/30/2014                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Control components have been ordered. Pre-construction meeting     1.2   1.13    1.13
for electrical field work was held.                               1
Millions 0.8
Schedule
0.6
The project is behind schedule due to changes to the control panels,
Dollars in 0.4                                                                              causing a delivery delay..
0.2                        0.13
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
10  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Airfield Pavement Replacement
This is a multi-year program to       Project Status:
Project:   C102573     replace distressed pavement and    Schedule: Within or ahead
Budget: $30,162,035    joint seal on the airfield.         Budget: On or under
Status Reset: 4/1/2014
Phase: Construction
(Commission Construction Auth.)
Start: 5/2/2010
Schedule Completion: 12/31/2016
Budget/Costs Incurred
Significant Developments
35
The 2014 AIP is out to bid.                                           29.90
30    25.18
Millions 25
Schedule
20                    17.66
Return to IC for savings determination between estimate and bid the    15
second week of June. NTP scheduled for the last week of July.       Dollars in  10
5
Budget                             0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Final Engineers
estimate is due June 9.
2013 Construction Costs
Change Order
Current Quarter   Project Total              6          5.38
5.09
Number of COs    0          2                   5
Amount of COs    $0         -$4,027.27            Millions  4
3
Justification for COs: N/A this quarter.                            2
Dollars in    1          0.29
Risks                                  0
Initial   Change   Spent
None identified at this time.
Orders
Budget Transfers
2014 Cargo 6 Panel
$129,000 to C800404 (Aeronautical Allowance)
Construction Costs
$137,000 to U00128 (ERL project)
2.5
1.99
2
Millions  1.5
Dollars in 
1
0.5
0
Initial   Change   Spent
Orders
AIRPORT
Port of Seattle 1Q 2014 Report  11

FIRST QUARTER REPORT, 2014
Gate Utility Improvements
Project Status:
Upgrade the South Satellite Port-
Schedule: Delayed
owned loading bridges to the same
Project:   C800019                             Budget: On or under
standards, including 400Hz power and
Budget: $11,744,480                         Status Reset: Click here to
potable water. This will reduce air
Phase: Construction                        enter a date..
emissions, improve energy efficiency
Start: 6/28/2007                                  (Commission Construction Auth.)
and save money for the airlines.
Schedule Completion:
8/29/2014
Budget/Costs Incurred
Significant Developments
14    12.74
11.74
The Contractor is working at both the North and South Satellites and    12
Concourse B. Part of South Satellite 400 Hz turned over for airline     10
use May 5, 2014.                                    8               6.56
in Millions  6
Schedule                            Dollars  4
2
Remaining 400 Hz are to be turned over at South Satellite by June 1,
0
2014. North Satellite and Concourse B gate water to be turned over
Authorized   Forecasted  Costs Incurred
for use by July 1, 2014.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
6
5.05
Change Order                           5
3.61
Current Quarter   Project Total           Millions  4
Number of COs    7          20                  3
Amount of COs    $37,345.52    $73,467.00              2
Dollars in     1
0.03
Justification for COs: Changes to Existing Conditions - Designer and      0
Owner, and varying site conditions.                               Initial  Change  Spent
Orders
Risks
Airport Operations at certain gates could be impacted during the
construction phase of the project, through June 1, 2014.
Budget Transfers
None this quarter

AIRPORT
12  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
North Expressway Relocation
Project:   C800034                             Project Status:
Reconstruct the Northern Airport
Budget: $102,213,605                        Schedule: Within or ahead
Expressway, support the extension
Phase: Construction                        Budget: On or under
of light rail to the Airport, and
Start: 7/27/2004                                  Status Reset: 2/20/2014
construct improvements to Wall 14.  (Commission Construction Auth.)
Schedule Completion:
11/30/2014
Budget/Costs Incurred
Significant Developments
112    110.23
Reconstruction of the Northern Airport Expressway and the light rail    110
transit components are complete. The design for the Wall 14        108
improvements was restarted with the intent to advertise for          Millions 106
104            102.81
construction bids in April 2014.
102                    101.03
Dollars in 100
Schedule                             98
96
The Wall 14 improvements remains on schedule with construction
Authorized   Forecasted  Costs Incurred
anticipated to start in July 2014 and be complete by November 2014.
Budget                            Construction Costs
Project forecast is within the approved budget and authorization.
The total budget for the Wall 14 improvements is $1,891,000.        120               105.38
97.34
100
Change Order                         Millions 80
Current Quarter   Project Total            60
Number of COs    N/A        226                Dollars in  40
Amount of COs    $0         $8,295,574            20        8.03
0
Justification for COs: N/A this quarter                               Initial  Change Order  Spent
Risks
None identified at this time.                                Photo
Budget Transfers
None.


AIRPORT
Port of Seattle 1Q 2014 Report  13

FIRST QUARTER REPORT, 2014
Main Terminal South Low Voltage
Project Status:
Project:   C800061   Renewal and replacement of low      Schedule: Delayed
Budget: $8,530,000   voltage (600 volts and below) electrical  Budget: On or under
Phase: Design      distribution equipment in the southern   Status Reset: Click here to
Start: 6/28/2007       part of the Main Terminal            enter a date.
Schedule Completion: 12/31/2008                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Due to project deferral and the possibility of changes in site           10
8.53
conditions and building codes, the design phase changed from 100%
8
to 0% complete. Finalized Project Notebook to address scope of      Millions 6
work, schedule, and budget, presented to and approved by the
Investment Committee on November 6, 2013. The project will go to      4
Commission in fourth quarter of 2014.                       Dollars in      1.93
2
0.58
0
Schedule
Authorized   Forecasted  Costs Incurred
Staff has finalized the scope of work, schedule and final design
budget. The 100% design documents for this project are scheduled
to be complete by the end of August 2015.                   Construction Costs
Not Applicable
Budget
The project budget was increased. The project forecast is within the   Photo
approved budget. Commission Authorization for design funding will
be requested.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will


14  Port of Seattle 1Q 2014 Report

Risks, cont.
be required to add additional crews to complete work in a timely manner. This area is a 24/7/365
operation. Sequencing of this work is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
From C800404 (Aeronautical Allowance)         $4,274,000











AIRPORT
Port of Seattle 1Q 2014 Report  15

FIRST QUARTER REPORT, 2014
C4 UPS System Improvements
Project Status:
Project:   C800107    Replace existing Uninterruptible Power   Schedule: Delayed Schedule
Budget: $2,336,000   Supply (UPS) System, including      Budget: On or under
Phase: Planning     batteries, with a new system located in  Status Reset: Click here to
Start: 6/28/2007       the Airport Combined Communications   enter a date.
Schedule Completion:  and Command Center (C4).        (Commission Construction Auth.)
TBD
Budget/Costs Incurred
Significant Developments
2.5     2.34       2.34
Due to project deferral and the possibility of changes in site
conditions and building codes, the design phase changed from 100%    2
to 30% complete. Revised scope of work, schedule, and budget is
1.5
being included in the new Project Notebook.
Millions
1
Schedule                            Dollars in             0.50
0.5
The project was reactivated. Staff is in the process of determining      0
the scope of work, schedule and final design budget.                 Authorized  Forecasted Costs Incurred
Budget
The project budget is being evaluated based on delays and scope    Construction Costs
changes.                                    Not Applicable
Change Order                         Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The C4 center is a 24/7/365 operation. Sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter

AIRPORT
16  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
C60 - C61 BHS Modifications
Project Status:
Project:   C800168    This work represents a critical       Schedule: Within or ahead
Budget: $11,864,825   component to providing improved     Budget: On or under
Phase: Construction   operational baggage in-line screening  Status Reset: 11/5/2013
Start: 6/1/2012        at the South end of the Airport and     (Commission Construction Auth.)
Schedule Completion:  more baggage make-up capacity for
airlines.
12/31/2014
Budget/Costs Incurred
Significant Developments
14
11.86      11.86
MD Moore Company was issued Notice to Proceed on February 7,     12
2014. MD Moore has completed 20% of the work thru the end of      10
March. Electrical and conveyor equipment started to ship to the site.   Millions 8
6
Schedule                            Dollars in  4
1.81
2
The project is currently on schedule.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
6
Current Quarter   Project Total                5.16
5
Number of COs    0          0
4
Amount of COs    $0         $0                 Millions
3
Justification for COs: n/a                                      2
Dollars in    1                0.30
0.00
Risks                                  0
Initial   Change   Spent
Completion of baggage make-up device to support Delta Airlines               Orders
added flights.
Budget Transfers
To C800404 (Aeronautical Allowance)        $1,404,176


AIRPORT
Port of Seattle 1Q 2014 Report  17

FIRST QUARTER REPORT, 2014
Federal Inspection Services - New Primary
Inspection Booths
Project Status:
Replace existing primary inspection   Schedule: Delayed
Project:   C800174     booths for Customs and Border     Budget: On or under
Budget: $1,849,000     Protection in the International Arrivals  Status Reset: 7/27/2010
Phase: Construction    Federal Inspection Services (FIS)    (Commission Construction Auth.)
Start: 7/27/2010        facility in the South Satellite.
Schedule Completion: 9/8/2011
Budget/Costs Incurred
Significant Developments                     2.1
2.00
New signs have been installed, we are installing new infrastructure      2
for the signs in May.                                     Millions 1.9          1.85
1.8                        1.73
Schedule
Dollars in  1.7
The project is substantially complete. The current schedule for        1.6
completion of the replacement signs is now the 2nd quarter of 2014.    1.5
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Photo
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT

18  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Security Exit Lane Breach Control - Phase 1
Project Status:
Project:   C800218      Procure and install new automated   Schedule: Delayed
Budget: $1,310,000      exit lane breach control equipment  Budget: On or under
Phase: Close Out      at the Concourse B exit.       Status Reset: 4/2/2013
Start: 3/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 6/30/2013
Budget/Costs Incurred
Significant Developments
Equipment was ordered for post-construction work to convert the      1.5   1.31    1.31
twin door lanes to triple door lanes.
Millions                           0.92
1
Schedule
0.5
Construction was completed July, 2013.                     Dollars in 
0
Budget                               Authorized Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No major risks at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 1Q 2014 Report  19

FIRST QUARTER REPORT, 2014
Emergency Lighting - Parking
Project Status:
Project:   C800230     Provide electrical infrastructure for a   Schedule: Delayed
Budget: $4,683,370    new source of emergency power to   Budget: On or under
Phase: Construction   feed the parking garage emergency   Status Reset: Click here to
Start: 7/24/2012        lighting circuits and ensure that code-  enter a date.
Schedule Completion:   required level of egress illumination is  (Commission Construction Auth.)
provided for safety.
7/16/2014

Budget/Costs Incurred
Significant Developments
The closet construction has been complete and contractor is          5   4.60    4.60
focusing on preparation for final cutovers.
4
3
Schedule
1.84
in Millions  2
The infrastructure construction is on schedule based on the contract
with a substantial completion of July 16, 2014.                   Dollars  1
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total
2
1.69
Number of COs    0          0
1.41
Amount of COs    $0         $0                  1.5
Millions
1
Justification for COs: n/a
Dollars in   0.5
Risks                                      0.00
0
The construction risk is the final cutover.                             Initial  Change  Spent
Orders
Budget Transfers
$81,000 to C800405 (Non-Aeronautical Allowance)


AIRPORT
20  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Feeder 101 Tap Replacements
Project Scope and description:        Project Status:
Project:   C800234    The project includes replacing the     Schedule: Delayed
Budget: $2,646,000    electrical feeds to 13 locations along Air Budget: On or under
Phase: Design      Cargo Road. Also, the electrical     Status Reset: Click here to
Start: 4/1/2013        transformer and associated switchgear  enter a date.
Schedule Completion:  for Air Cargo #4 will be replaced.     (Commission Construction Auth.)
6/30/2015
Budget/Costs Incurred
Significant Developments
3            2.65
Design is 100% complete.                             2.5
Millions  2
Schedule                            1.5
Design is complete. Plan to request authorization from Commission     1
0.50               0.37
to bid the project in June of 2014.                            Dollars in 0.5
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is below the approved budget. Authorization of
construction funding and authority to advertise for construction will    Construction Costs
be requested when the bid documents are completed.           Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None.


AIRPORT
Port of Seattle 1Q 2014 Report  21

FIRST QUARTER REPORT, 2014
Central Plant Pre-Conditioned Air
Project:   C800238     Provide a centralized pre-conditioned  Project Status:
Budget: $51,890,000    air (PC-Air) plant (PCAP), associated  Schedule: Delayed
Phase: Construction    heating and cooling piping systems,   Budget: Forecast Overrun
Start: 6/15/2009        and jet bridge terminal air handling    Status Reset: 2/25/2014
Schedule Completion:   units to serve airplanes with heating   (Commission Construction Auth.)
and cooling while at the gates.
8/31/2013
Budget/Costs Incurred
Significant Developments
54
Contractor's work is complete except for punchlist and warranty                  51.89
52
issues. PC-Air is operating at 66 gates. Four gates are remaining,
Millions 50     49.05
but operational needs have delayed work on these until second and
48
third quarter of 2014. This work was removed from the General                            46.57
Contract and will be completed separately.                    Dollars in  46
44
Schedule                             42
Authorized   Forecasted  Costs Incurred
The original contract completion date for all gates was December 11,
2012. Work was completed in December 2013. The delay was
primarily due to Concourse D redesign, as previously reported. All
Construction Costs
but four gates are complete, and will be completed in 2014
contingent on operational needs.                             40
34.01
Budget                              30 27.01
Millions
Negotiations with the contractor on potential change orders and         20
claims risk are in process. As negotiations proceed, identify potential
Dollars in    10          7.46
budget issues. Current project forecast including open claims
exceeds approved budget and authorization. Staff will return to
0
Commission to request additional funding and authorization to             Initial  Change  Spent
execute change orders.                                        Orders
Change Order
Current Quarter   Project Total
Number of COs    6          196
Amount of COs    $799,709     $8,404,000
Justification for COs: piping and electrical site conflicts on the
concourse and at the gates.


22  Port of Seattle 1Q 2014 Report

Risks
There is budget risk based on the dollar amount of open potential change orders and claims. There is
schedule risk as completing work at each gate is contingent on gates being available.
Budget Transfers
None this quarter.
Cost of Construction Growth
Cost growth occured due to shortcomings in the bid documents. Current cost of executed Change
Orders is 31% of the base contract price. The trended cost growth projection is currently 33% over
bid price. Approximately 20% are related to error and/or ommissions (owner or designer), 7% are
currently in some form of dispute. The remainder of the cost growth are due to site conditions,
discretionary tenant requests or scope changes and regulatory requirements respectively.









AIRPORT
Port of Seattle 1Q 2014 Report  23

FIRST QUARTER REPORT, 2014
Cargo 2 West Cargo Hardstand
Enlarge the western cargo hardstand   Project Status:
Project:   C800247    in the Cargo 2 area. Includes buyout   Schedule: Within or ahead
Budget: $9,247,875    of two cargo buildings and tenant     Budget: On or under
Phase: Construction   relocations; relocation of FAA      Status Reset: 10/8/2013
Start: 9/25/2012       antenna, security gate, and guard      (Commission Construction Auth.)
Schedule Completion:  shack; and installation of 400Hz in-
12/31/2014          ground power.
Budget/Costs Incurred
14    12.77
Significant Developments
12
Cargo 2 Hardstand project is combined with Cargos 5 and 6 into a                9.25
Millions 10
single construction contract which has been successfully bid and        8
awarded.                                      6
Dollars in   4
1.09
Schedule                             2
0
Construction began 1st quarter of 2014 and is scheduled to be           Authorized  Forecasted Costs Incurred
completed in August, beginning of the 3rd quarter. Demolition of
Building #2 will be completed in the 2nd quarter. FAA's antenna will
be relocated during the 2nd quarter.                        Construction Costs
Budget                              6
The project forecast is within approved budget and authorization.           4.20
4
Change Order
MillionsDollars in 
2
Current Quarter   Project Total
Number of COs    0          0
0
Amount of COs    $0         $0                     Initial  Change Order  Spent
Justification for COs: n/a
Photo
Risks
None identified at this time.
Budget Transfers
$82,000 to U00125 (ERL Project)
$2,500,000 to C800404 (Aeronautical Allowance)

AIRPORT
24  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Vertical Conveyance Modernization Program -
Aeronautical - Phase I                   Project Status:
Perform modernization on 9 existing     Schedule: Within or ahead
Project:   C800251   elevators and 4 escalators: SSAF,      Budget: On or under
Budget: $22,823,408  MT-2, MT-3, MT-4, MT-5, MT-6, MT-    Status Reset: 11/11/2013
Phase: Construction  7, SSB, SSC. Install new elevators     (Commission Construction Auth.)
Start: 10/25/2011     SSM and SSN. Install cooling
Schedule Completion: packages on 12 existing hydraulic
10/30/2016         elevators throughout Main Terminal.
Budget/Costs Incurred
Significant Developments                     25       22.82
Changing priorities concerning failure of existing Main Terminal        20
elevators has prompted further review of project scopes, and the      Millions     15.25
15
consolidation of all Main Terminal elevators to Phase I, and two new
South Satellite elevators to Phase II. Also added to the scope was      10
the design of one additional hydraulic oil cooling package for         Dollars in  5                1.84
Elevator Q; this elevator is experiencing overheating time-outs to
0
serve United Airlines' club associated with airline relocation to            Authorized  Forecasted Costs Incurred
Concourse A.
Schedule                           Construction Costs
Construction scheduled to begin in the 3rd Quarter of 2014, with      Not Applicable
construction completion in the 3rd Quarter of 2016.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction has
been requested and bidding is underway.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Budget Transfers
From C800375 (Vertical Convey Modn Aero Ph2)   $8,834,408
From C800404 (Aeronautical Allowance)          $486,789
AIRPORT
Port of Seattle 1Q 2014 Report  25

FIRST QUARTER REPORT, 2014
Parking System Replacement
Project Status:
This project replaces the current   Schedule: Delayed
Project:   C800253       Parking Revenue Control System,  Budget: On or under
Budget: $6,076,999.30     which manages parking access   Status Reset: 3/8/2011
Phase: Construction     and revenue collection in the    (Commission Construction Auth.)
Start: 4/6/2010           Airport's Main Parking Garage.
Schedule Completion: 8/31/2012
Budget/Costs Incurred
Significant Developments
12
Scheidt & Bachmann (S&B), the system vendor completed final           9.78
10
testing. The system is exhibiting accuracy and availability rates
8
above 99.99%. The Port is working with S&B to correct a limited     Millions          6.08
number of outstanding issues.                             6               5.02
Dollars in   4
Schedule                             2
The system is substantially complete and in use. However, PCI        0
Authorized   Forecasted  Costs Incurred
related issues remain to be resolved prior to completion.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
None this quarter
Change Order
Photo
Current Quarter   Project Total
Number of COs    0          9
Amount of COs    $0         $195,780
Justification for COs: Not applicable this quarter
Risks
The Port is working with the contractor to address outstanding PCI
and unique transaction identifier issues.
Budget Transfers
None this quarter.


AIRPORT
26  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Aircraft RON Parking USPS Site
Prepare the site for the construction   Project Status:
Project:   C800254     of hardstands for use as Remain     Schedule: Within or ahead
Budget: $45,602,000    Overnight (RON) parking of aircraft at  Budget: On or under
the Cargo 5 area.               Status Reset: 10/8/2013
Phase: Construction
(Commission Construction Auth.)
Start: 8/26/2008
Schedule Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments
60
A single construction contract with three cargo areas (Cargo Area's         49.99
50           45.60
2, 5 and 6) has been bid and awarded.
Millions 40
30
Schedule
20
Contract execution was in the 1st quarter of 2014. Construction       Dollars in                  8.23
10
began in the 1st quarter of 2014. Cargo 5 is scheduled to be
0
completed by the middle of the 4th quarter of 2014.                   Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                          30
23.46
Current Quarter   Project Total
Millions 20                                                                         Number of COs       0                 0
Amount of COs    $0         $0                 10
Dollars in 
Justification for COs: n/a                                    0
Initial   Change Order   Spent
Risks
None identified at this time.                                Photo
Budget Transfers
$438,000 to U00126 (ERL Project)



AIRPORT
Port of Seattle 1Q 2014 Report  27

FIRST QUARTER REPORT, 2014
Port-Owned Loading Bridge Renewal &
Replacement
Project Status:
Replace or refurbish Port-owned    Schedule: Within or ahead
Project:   C800267      Passenger Loading Bridges (PLBs)  Budget: On or under
Budget: $2,405,000      that have reached the end of their   Status Reset: 2/28/2012
Phase: Construction     service life.              (Commission Construction Auth.)
Start: 2/28/2012
Schedule Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments                      3
2.41       2.41
2.5
The work associated with this CIP has been completed and the                        1.94
project is in closeout. The scope of work at Gate S4 is now being      Millions  2
handled under CIP C800662/12th & 13th FIS Widebody Gate project.    1.5
1
Schedule                            Dollars in 
0.5
The remainder of work programmed for this project is currently on       0
Authorized   Forecasted  Costs Incurred
hold.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
0.7
0.58           0.57
Change Order                           0.6
0.5
Current Quarter   Project Total           Millions  0.4
Number of COs    0          0                  0.3
Amount of COs    $0         $0                  0.2
Dollars in   0.1           0.01
0
Justification for COs: n/a
0.1   Initial   Change   Spent
Orders
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
28  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Stage 2 Mechanical Energy Implementation
Project Status:
Project:   C800268      Improve the energy performance of  Schedule: Delayed
Budget: $2,852,900.00    the mechanical infrastructure     Budget: On or under
Phase: Construction     systems at the Airport.        Status Reset: 10/4/2011
Start: 10/1/2011                                  (Commission Construction Auth.)
Schedule Completion: 10/31/2013
Significant Developments                    Budget/Costs Incurred
The project is complete. Working to close.
2.9     2.85       2.85
2.85
Schedule
Energy savings verification ongoing through April 1, 2014 for WA      2.75  Millions 2.8
state.                                                  2.7                 2.66
2.65   Dollars in 
Budget                             2.6
2.55
The forecast is within the approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    2          7
Amount of COs    $ (12,643.95)   $43,445.23              3
2.48
2.5                 2.12
Justification for COs: none                                 Millions  2
1.5
Risks
1
None identified at this time.                                  Dollars in  0.5
0.00
0
Budget Transfers
Initial   Change   Spent
Orders
None this quarter.



AIRPORT
Port of Seattle 1Q 2014 Report  29

FIRST QUARTER REPORT, 2014
8th Floor Weatherproofing                Project Status:
Schedule: Delayed
Budget: On or under
Project:   C800274      Removal and replacement of the    Status Reset: Click here to
Budget: $9,474,000      floor covering system on the eighth  enter a date.
Phase: Construction     floor of the STIA parking garage   (Commission Construction Auth.)
Start: 03/23/2010         and repair or replacement of
Schedule Completion:    expansion joints and flashings.
07/31/2014                                Budget/Costs Incurred
14    13.05
Significant Developments                      12
9.47
The Port's contractor, PCL Construction, stripped and replaced old     Millions 10
7.97
8
Dollars in 
weatherproofing, and performed crack repair on the eighth floor
6
garage deck. Weatherproofing failed in portions of sections B and C.
The work was rejected and will be repaired during June and July        4
2014 at contractor's expense.                               2
0
Schedule                                Authorized  Forecasted Costs Inc
Defective work has resulted in a delay in receiving beneficial        Construction Costs
occupancy for sections B & C of the 8th floor deck. The new end date
is expected to be July 31, 2014.                              7   6.05           6.00
6
Budget                             Millions 5
4
The project forecast is within the approved budget and authorization.
3
2
Change Order                          Dollars in 
1            0.09
Current Quarter   Project Total             0
Initial    Change Order    Spent
Number of COs    N/A        23
Amount of COs    N/A        $69,558
Photo
Justification for COs: N/A
Risks
This is a weather-dependent project.
Budget Transfers
None this quarter.

AIRPORT
30  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Long-Term Cell Phone Lot
Project:   C800324      Construct a new cell phone waiting  Project Status:
Budget: $1,435,000      lot to replace the existing lot that is  Schedule: Delayed Schedule
being displaced, and construct a    Budget: On or under
Phase: Construction
traffic control roundabout or signal   Status Reset: 5/6/2014
Start: 12/11/2012
(Commission Construction Auth.)
Schedule Completion:    adjacent to the lot on South 170th
Street.
12/31/2014
Budget/Costs Incurred
Significant Developments                     2  1.83   1.83
Sixty parking stalls were opened for use on April 1, when the former    1.5               1.34
cell phone lot closed. Construction was stopped due to expenditures   Millions
1
exceeding authorization and pending Commission authorization of
additional funds. Commission authorized additional funds and
Dollars in 0.5
construction has re-started. Estimated costs for the proposed traffic
0
control roundabout came in high. Staff is evaluating a permanent
Authorized  Forecasted Costs Incurred
signal for performance and cost compared to a roundabout.
Schedule                           Construction Costs (PCS
Cell phone lot beneficial occupancy is expected approximately July   Only)
1, 2014. A recommendation on the traffic control method is expected
by the end of July 2014 with Commission authorization in August.       0.5
0.44
The design and construction schedule will also be prepared at that
0.4
time.
Millions  0.3
Budget
0.2
On May 6, 2014 Commission increased the authorization for the cell    Dollars in 
phone lot portion of the project to $2,207,100. The 60% design level     0.1
estimated budget of the roundabout increased from $1,086,000 to                  0.00     0.00
0
$2,855,000 and the estimated budget for a signal is $1,222,000.             Initial   Change Order   Spent
Change Order                         Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
$393,000 from C800404 (Aeronautical Allowance)

Port of Seattle 1Q 2014 Report  31

Risks
Unforeseen construction conditions and associated costs for completing the cell phone lot portion of
the project. Schedule uncertainties related to roundabout or signal design review and permit
acquisition time requirement.













AIRPORT
32  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Two New CTE Freight Elevators
Project Status:
Project:   C800334      Provide two new freight elevators   Schedule: Within or ahead
Budget: $8,302,648      to support concession operations in  Budget: On or under
Phase: Construction     the Central Terminal/Pacific      Status Reset: Click here to
Start: 8/5/2011          Marketplace.                enter a date.
Schedule Completion: 7/31/2014                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Contractor has completed construction of both elevator shafts and      10
8.29       8.29
attachments to building.
8
Millions                            5.81
Schedule                             6
Dollars in 
As previously reported, the project is anticipating a one-year delay       4
due to scope changes included in the redesign efforts, and delays in     2
reviews.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
5   4.30
Current Quarter   Project Total
4               3.45
Number of COs    12         25
Amount of COs    $126,896.10   $191,979.27           Millions  3
Dollars in 
2
Justification for COs: Differing site conditions and code compliance
1
improvements.                                           0.20
0
Initial   Change   Spent
Risks
Orders
No new risks identified this quarter.
Budget Transfers
$28,000 transferred to Art; $15,000 to expense


AIRPORT
Port of Seattle 1Q 2014 Report  33

FIRST QUARTER REPORT, 2014
Electrical Ground Support Equipment (EGSE)
Project Status:
Electrical Charge Stations
Schedule: Delayed Schedule
Budget: On or under
Airport-wide electrical charging     Status Reset: 10/23/2012
Project:   C800335      system for electrical ground      (Commission Construction
Auth.)
Budget: $30,198,000     support equipment (EGSE) at the
Concourses and the North and
Phase: Design
South Satellites.
Start: 10/26/2010                               Budget/Costs Incurred
Schedule Completion: 6/30/2016
35            30.20
Significant Developments
30    25.35
Project completion "Punch-list" items will be completed May 14 and     25
completion of "Record Drawings" June 14. Automatic GSE data      Millions 20
14.17
collection, storage and report generation is operational but there are     15
Dollars in  10
configuration issues that are being resolved.
5
0
Consultant issued GSE Charger Phase 2 Project 100% bid design        Authorized Forecasted Costs Incurred
documents for review that includes Concourse A, B and South
Satellite. Design review continues and is nearing completion and
lessons learned from the GSE Phase 1 project are being          Construction Costs
incorporated in the design documents. Design bid documents will be
revised to include clear direction to contractors that all materials,                         3.79
4    3.58
labor and commissioning shall be part of project construction phase.
3
Washington Department of Revenue has ruled that the construction    Millions
phase of the GSE Phase 2 project is exempt from Sales Tax.          2
Dollars in   1              0.71
Schedule
Phase 1 construction is basically complete except for some punch       0
list items not in the major contract; Phase 2 construction scheduled          Initial  Change Order  Spent
for completion in mid 2016.
Budget
The project forecast is within the approved budget. The remaining
authorization for the construction funding and authority to advertise
for construction will be requested when the design and bid
documents are completed for GSE Charger Phase 2 Project.



34  Port of Seattle 1Q 2014 Report

Change Order
Current Quarter   Project Total
Number of COs    17         48
Amount of COs    $368,227.00 0  $703,629.00
Justification for COs: Errors/Omissions - Designer & Owner, Varying Site Conditions, Scope Change,
and Regulatory Requirements.
Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may affect project implementation and completion.
Budget Transfers
None this quarter.









AIRPORT
Port of Seattle 1Q 2014 Report  35

FIRST QUARTER REPORT, 2014
South Satellite HVAC, Lights, and Ceiling
Replacement
Project Status:
Replace the heating ventilation,     Schedule: Within or ahead
Project:   C800376      lighting and ceiling systems in the   Budget: On or under
Budget: $34,011,000     South Satellite.            Status Reset: Click here to
Phase: Design                            enter a date.
Start: 7/24/2012                                  (Commission Construction Auth.)
Completion: 7/31/2016
Significant Developments                    Budget/Costs Incurred
Thirty percent design delayed pending finalization of mechanical
40
equipment room locations and review of seismic requirements.                  34.01
Design to resume 2nd quarter of 2014. Completed negotiation of the    30
SD modification to address revised scope of work.
20
in Millions
Schedule
Dollars  10     6.35
Thirty percent design is scheduled to be completed third quarter of                       1.47
2014. The project will then be evaluated prior to proceeding.         0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will    Construction Costs
be requested when the bid documents are completed.           Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
none
Risks
South Satellite siesmic analysis and strategy may impact project
costs and schedule. Seismic upgrade is not currently in the design
scope of work.
Budget Transfers
None this quarter
AIRPORT
36  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Baggage Handling System (C22-C1, MK1, and
TC3)
Replace the ticket counter (TC3)       Project Status:
conveyors and declines, reroute the
Project:   C800382                             Schedule: Within or ahead
conveyors of the C-22 system and      Budget: On or under
Budget: $5,861,000   connect it to the C-1 screening system,  Status Reset: Click here to
Phase: Close Out    replace the existing makeup (MK1)    enter a date.
Start: 3/1/2011        device, and install a new odd size      (Commission Construction Auth.)
Schedule Completion:  baggage system.
5/31/2013
Budget/Costs Incurred
Significant Developments
8
6.76
None                                          5.86
6
4.75
Schedule
Millions  4
The project forecast is within the approved budget and authorization.
Dollars in  2
Budget                              0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          18
Amount of COs    $0         $169,220.39             2
1.59
1.5
Justification for COs: None this quarter                        Millions
1
Risks
None identified at this time.                                 Dollars in   0.5
0.20
Budget Transfers                           0
To C800404 (Aeronautical Allowance)          $900,000
Cost of Construction Growth
Three changes represent the majority of the cost growth: 1) removed
the C1-CS1 curbside conveyor since replacement was no longer


Port of Seattle 1Q 2014 Report  37

Cost of Construction Growth, Cont.
required, 2) The contract design to replace make-up device MK1 did not include POS ergonomic
standards for this kind of device; and 3) the original contact design for the conveyors in the C1-CS2
conveyor line created unsafe electrical and mechanical conditions for maintenance works. Several
other smaller changes included fire sprinkler and architectural revisions, including a credit to remove
a small scope of work.












AIRPORT
38  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Cargo 6 Enhancements
Project Status:
Schedule: Within or ahead
Project:   C800390    Enlarge the Cargo 6 off-gate        Budget: On or under
Budget: $6,345,875    hardstand to allow simultaneous     Status Reset: 10/8/2013
nose-loading of wide-body freight      (Commission Construction Auth.)
Phase: Construction
aircraft as well as provide fuel
Start: 9/25/2012        hydrant and ground power
Schedule Completion:   capabilities.
12/31/2014                                Budget/Costs Incurred
7    6.35      6.35
Significant Developments
6
Cargo 6 Enhancements has been combined with Cargo Areas 2 and     5
5 as a single construction contract and has been successfully bid       4
and awarded.
Millions
3
Dollars in   2
Schedule                             1          0.42
0
Construction of the Cargo 6 hardstand enhancements will begin in         Authorized  Forecasted Costs Incurred
3rd quarter 2014. Completion is scheduled for 4th quarter 2014.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
4
3.16
Change Order                          3
Current Quarter   Project Total           Millions 2
Number of COs    0          0
1
Amount of COs    $0         $0                 Dollars in  0
Initial   Change Order   Spent
Justification for COs: n/a
Risks
Photo
None identified at this time.
Budget Transfers
$82,000 to U00127(ERL Project)


AIRPORT

Port of Seattle 1Q 2014 Report  39

FIRST QUARTER REPORT, 2014
RW16C/34C Reconstruction
Produce final design and reconstruct   Project Status:
Project:   C800406     the existing RW 16C/34C in its      Schedule: Within or ahead
Budget: $99,538,000    existing location, replace TW C and   Budget: On or under
Status Reset: Click here to
Phase: Design       N, reconfigure TWs H and J,install
enter a date.
Start: 5/4/2010         FOD detection equipment, and install
LED lighting system.             (Commission Construction Auth.)
Schedule Completion:
11/30/2016
Budget/Costs Incurred
Significant Developments
120
99.54
The decision has been made to advance the reconstruction of        100
Runway 16C/34C by one year to begin construction in 2015. A
80
revised 60% drawing package has been reviewed. A Foreign Object
60
Millions
Debris (FOD) detection system and LED lighting system have been
added to the original scope.                               Dollars in  40
20    10.68
0.59
Schedule                             0
Design is scheduled for completion in October of 2014.
Construction is scheduled to begin in the second quarter of 2015.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
$9,100,000 from C800404 (Aeronautical Allowance)
$90,000,000 from C800058 (RW 16C/34C Reconstruction)

AIRPORT
40  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
South Satellite Concessions Project
Project Status:
Demolished and relocated the old   Schedule: Delayed
Project:   C800412      duty free shop, electric /         Budget: On or under
Budget: $1,777,400      communications to support a     Status Reset: Click here to
temporary duty free location were
Phase: Construction                        enter a date.
installed and construct a new food
Start: 01/01/2011                                 (Commission Construction Auth.)
and beverage shell space in the
Schedule Completion:    South Satellite at Sea-Tac Airport
12/31/2013            was completed.            Budget/Costs Incurred
1.78      1.78
1.8
Significant Developments
1.7
The project is in closeout. This will be the last Quarterly report.
Millions 1.6                         1.53
Schedule
Dollars in 1.5
This project is in closeout
1.4
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Savings will be returned upon completion of closeout activities.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 1Q 2014 Report  41

FIRST QUARTER REPORT, 2014
Airfield Lighting Control and Monitoring System
(ALCMS) Upgrades
Project Status:
Provide modifications to the Airfield
Project:   C800415                             Schedule: Within or ahead
Lighting Control and Monitoring
Budget: $1,732,144                         Budget: On or under
System to update, enhance and
Phase: Close Out                          Status Reset: Click here to
stabilize the system to meet the
Start: 11/5/2012                                  enter a date.
latest FAA specifications.
Schedule Completion:                        (Commission Construction Auth.)
7/31/2013
Significant Developments                    Budget/Costs Incurred
Liberty Airport Systems was operational on July 12, 2013. The        2.5   2.17
project is in closeout. This will be the last Quarterly report.
2            1.72
Millions 1.5                        1.33
Schedule
1
The project completed on schedule.
Dollars in 0.5
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    2          2
Amount of COs    $68,923      $68,923
Justification for COs: Issued for FAA ALCMS training workstation.
Add security log-in feature.
Risks
None identified at this time.
Budget Transfers
$8,000 to expense


AIRPORT
42  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Lagoon 3 Bird Wires
Reduce access by waterfowl to the   Project Status:
Project:   C800417      industrial wastewater system      Schedule: Within or ahead
Budget: $1,563,000      Lagoon 3, which is located near the  Budget: On or under
Phase: Construction     south end of the airfield.       Status Reset: Click here to
Start: 10/11/2011                                 enter a date.
Schedule Completion: 10/31/2012                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
The major construction work is complete.
2    1.83
1.56      1.53
Schedule                             1.5
Port Construction Services completed work to improve post stability.
Millions
1
Minor work remains but is dependent upon water level.
Dollars in 0.5
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          19                  1         0.91
Amount of COs    $0         $117,370.30               0.79
0.8
Millions  0.6
Justification for COs: n/a
0.4
Risks                                Dollars in  0.2     0.12
No risks have been identified at this time.                         0
Initial   Change   Spent
Orders
Budget Transfers
None this quarter.                                    Photo
Cost of Construction Growth
Minor additional work via Port Construction Services for corrective
items not part of the contract.

AIRPORT

Port of Seattle 1Q 2014 Report  43

FIRST QUARTER REPORT, 2014
Federal Inspection Services Short Term
Improvements
Short Term Improvements to the
Project Status:
Federal Inspection Service area at S.
Project:   C800426                             Schedule: Delayed
Satellite to improve through put and
Budget: $1,141,000                         Budget: On or under
conditions for passengers waiting in
Phase: Construction                        Status Reset: 12/10/2013
the International Corridor prior to
(Commission Construction Auth.)
Start: 4/1/2012         Primary Inspection.
Schedule Completion:
6/23/2014
Budget/Costs Incurred
Significant Developments
2    1.82      1.82
Major Contract work was advertised in January 2014. Bids came in
higher than anticipated and the Commission authorized additional      1.5
funds to award to the lowest responsive bidder. Construction is       Millions
1
currently under way. PCS has started the small works portion of the
project that includes permanent stanchions and installation of a new    Dollars in                   0.42
0.5
PA system.
0
Schedule                               Authorized Forecasted Costs Incurred
Award of the Major Contract work delayed until additional budget
authorized. The new scheduled completion date is in late June
Construction Costs
2014.
0.7    0.61
Budget                              0.6
The project forecast is within the increased, approved budget and      Millions  0.5
authorization.                                           0.4
0.3
Dollars in   0.2
Change Order
0.1
0.00    0.00
Current Quarter   Project Total             0
Number of COs    0          0                     Initial Change Spent
Orders
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The contractor has informed the Port that later than anticipated flight
arrivals to FIS have impacted their ability to start work on time during
their evening shift. On site construction work is performed entirely at
night on this project.
Budget Transfers
$678,000 from C800404 (Aeronautical Allowance)
AIRPORT44  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Doug Fox Lot Service Upgrades
Construct a new drainage system,      Project Status:
Project:   C800451
asphalt resurfacing, improved lot       Schedule: Delayed Schedule
Budget: $6,453,000   lighting, new building, and road signage  Budget: On or under
Phase: Construction   to improve lot appearance, function,    Status Reset: Click here to
Start: 2/1/2012        and revenue generation.            enter a date.
Schedule Completion:                        (Commission Construction Auth.)
9/30/2014
Budget/Costs Incurred
6.45       6.45
Significant Developments                      7
6
Construction is 50% complete and continues on underground utilities
Millions  5
and fabrication of the modular building by an off-site vendor.
4
3
Schedule                                        1.72
Dollars in   2
Project beneficial occupancy scheduled for September 30, 2014.       1
Contractor's construction schedule is being monitored for potential      0
Authorized   Forecasted  Costs Incurred
delay in completion of the building and associated impact on project
benefical occupancy.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.     5
3.99
4
Change Order
Millions  3
Current Quarter   Project Total
Number of COs    5          5                  2
Amount of COs    $103,051     $103,051             Dollars in                0.75
1
0.18
0
Justification for COs: Changes are primarily related to sewer and           Initial  Change Order  Spent
electric utilities and potential unforeseen conditions during site
paving.
Photo
Risks
Wet weather conditions may delay asphalt paving and striping.
Delay in Labor & Industries inspection and permitting of building may
affect overall project beneficial occupancy date.
Budget Transfers
None

AIRPORT
Port of Seattle 1Q 2014 Report  45

FIRST QUARTER REPORT, 2014
Concourse D Common Use Environment
Project Status:
Project:   C800455     Install a common-use environment at  Schedule: Delayed
Budget: $4,100,000    all gates on Concourse D. Scope    Budget: On or under
Phase: Close Out     includes new communications      Status Reset: Click here to
Start: 3/1/2011         infrastructure, casework built to a new  enter a date.
Schedule Completion:   Airport standard, new carpet, wall    (Commission Construction Auth.)
coverings and task lighting .
4/30/2013
Budget/Costs Incurred
Significant Developments                      5  4.25   4.10
Project is in close out. This will be the last Quarterly report.            4                 3.27
Millions  3
Schedule
2
Contractor completed non-essential project work prior to contract
Dollars in   1
end date of August 2013.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total              2
Number of COs    0          14
1.41          1.45
1.5
Amount of COs    $0         $111,155             Millions
1
Justification for COs: n/a
Dollars in   0.5
0.05
None
0
Initial   Change   Spent
Risks                                      Orders
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
46  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
2011-2013 Roof Replacement Program
Project:   C800459      Remove and replace the roofing    Project Status:
Budget: $4,659,000      systems on the fire station and    Schedule: Within or ahead
Phase: Close Out      north end of the main terminal.    Budget: On or under
Start: 7/1/2011                                   Status Reset: 1/8/2013
Schedule Completion: 10/31/2013                 (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Received beneficial occupancy on October 31, 2013. This is the last
5    4.66      4.66
Quarterly report.
4
Schedule                             3          2.52
The project was completed on schedule.
Millions
2
Dollars in   1
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Savings will be returned at closeout.
Change Order                         Construction Costs
Current Quarter   Project Total
Number of COs    0          0                  2
1.54               1.54
Amount of COs    $0         $0                 1.5
1
Justification for COs:                                      Millions
0.5
0.00
None                                  Dollars in  0
Initial    Change Order    Spent
0.5
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 1Q 2014 Report  47

FIRST QUARTER REPORT, 2014
Industrial Waste Treatment Plant (IWTP) Fiber
Installation
Install new Single Mode Fiber cable  Project Status:
Project:   C800461      from Main Terminal to IWTP and    Schedule: Delayed Schedule
Gate E-45.
Budget: $514,000                          Budget: On or under
Phase: Construction                        Status Reset: Click here to
Start: 3/1/2012                                   enter a date.
Schedule Completion: 10/30/2014                  (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Construction is currently stopped until summer construction season.
0.6
Fiber Optic Cable has been installed from the Main Terminal to the          0.51     0.51
new equipment termination cabinet near the Alaska Hangar and       0.5
Gate E-45. Due to a change in FAA Policy/Personel, the original     Millions 0.4
FAA controled conduit to complete the project was deemed full and     0.3
0.21
persmisison to use it was denied. An alternate route was designed
Dollars in  0.2
and accepted by the FAA.                              0.1
0
Schedule                               Authorized Forecasted Costs Incurred
The remaining construction work is scheduled for completion in late
summer 2014.
Construction Costs
Budget                            Not Applicable
Forecast is currently within the approved budget and authorization.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Additional schedule delays. Due to physical constraints, the work is
to be completed during the dry summer months. The new route
requires trenching within the Aircraft Active Movement Area and is
subject to strict operatioal guidelines and requirements.
Budget Transfers
None this quarter.

AIRPORT
48  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Fiber Infrastructure to Gate Backstands
Extend airport provided            Project Status:
Project:   C800464
communications infrastructure and wifi  Schedule: Delayed
Budget: $3,284,000    antennas to additional gates on     Budget: On or under
Phase: Design       Concourses A, B and C.         Status Reset: Click here to
Start: 07/09/2013                                 enter a date.
Schedule Completion: 04/01/2015                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Thirty percent design is complete.                            4
3.28
Schedule                             3
Millions
The project schedule has been delayed due to a delay in Wi-Fi audit.     2
The project sponsors agree that the project should not proceed until         0.79
completion of the Wi-Fi audit has been completed.                Dollars in  1
0.10
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are        Construction Costs
completed.                                     Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Budget Transfers
None.


AIRPORT
Port of Seattle 1Q 2014 Report  49

FIRST QUARTER REPORT, 2014
South Satellite - Additional Gate Lobby
Project Status:
Project:   C800466      Demolition of glass partitions,      Schedule: Delayed
Budget: $1,965,000      restrooms, relocation of gate     Budget: On or under
Phase: Close Out      podiums new flooring, ceilings and  Status Reset: 07/24/2012
Start: 11/1/2010          infrastucture to provide additional    (Commission Construction Auth.)
Schedule Completion:    gate lobby in the South Satellite.
9/15/2013
Budget/Costs Incurred
Significant Developments
This project is complete and in closeout. This will be the last
Quarterly report.                                         2
1.97      1.97
1.95
Schedule                            Millions
As previously reported, project delay was caused by delayed         1.9
1.86
design negotiations and contracting. Additionally, a longer design
1.85
period is required due to dependency on the South Satellite          Dollars in 
Concessions Project (C800412).                          1.8
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Savings will be returned upon completion of closeout activities.      Construction Costs
2.5
Change Order
1.96
2   1.77
Current Quarter   Project Total
Number of COs    0          14                 Millions 1.5
Amount of COs    $0         $141,934               1
Dollars in   0.5          0.19
Justification for COs: n/a
0
Initial   Change   Spent
Risks                                      Orders
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
50  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Passenger Loading Bridge Replacement -
Airline Realignment
Project Status:
Passenger Loading Bridge (PLB)    Schedule: Within or ahead
Project:   C800467      replacements associated with the   Budget: On or under
one-time airline realignment (AR).
Budget: $7,847,539                         Status Reset: 2/22/2011.
The work will take place at
Phase: Close Out                          (Commission Construction Auth.)
Concourse D and Concourse B.
Start: 04/12/2011
Schedule Completion: 09/30/2013
Budget/Costs Incurred
10
Significant Developments                         7.76   7.85
8
Millions                           6.11
Project is complete and in closeout. NSAT bridges that were          6
originally in this scope are now being handled by the NorthStar
4
Project. This will be the last Quarterly report.
Dollars in   2
Schedule                             0
Authorized  Forecasted Costs Incurred
The project was completed on schedule.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
2.5                 2.22
2.09
Change Order
2
Current Quarter   Project Total            Millions 1.5
Number of COs    0          31
1
Amount of COs    $0         $168,886
Dollars in   0.5          0.13
Justification for COs: N/A this quarter                             0
Initial   Change   Spent
Orders
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 1Q 2014 Report  51

FIRST QUARTER REPORT, 2014
CUSE at Gates & Ticket Counters- Airline
Realignment
Provide common use equipment,     Project Status:
Project:   C800473     casework and infrastructure at gates   Schedule: Delayed Schedule
Budget: $1,293,000     and ticket counters for the Airline    Budget: On or under
Phase: Close Out      Realignment program.         Status Reset: 7/12/2012
Start: 4/2/2012                                   (Commission Construction Auth.)
Schedule Completion: 5/1/2013
Budget/Costs Incurred
Significant Developments
Project is complete and in closeout. This will be the last quarterly           2.37
2.5
report.
2            1.85
1.5                        1.25
Schedule
Millions
1
Completed project construction and post-construction work.
Dollars in 0.5
Budget                              0
Authorized  Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Reimbursements to the United Airlines Group still remain.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          20
Amount of COs    $0         $181,087
Justification for COs: Scope, unforseen conditions and design
changes.
Risks
None identified at this time.
Budget Transfers
$560,000 from C800404 (Aernoautical Allowance))


AIRPORT
52  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Airport Signage (Airline Realignment)
Project Status:
Project:   C800474      Provide airport directional signage   Schedule: Delayed
Budget: $646,000       for the airline realignment program.  Budget: On or under
Phase: Close Out                          Status Reset: 06/04/2012
Start: 06/01/2011                                 (Commission Construction Auth.)
Schedule Completion: 06/30/2013
Budget/Costs Incurred
Significant Developments
0.7     0.65       0.65
Project complete. This will be the last Quarterly report.
0.6                         0.51
0.5
Schedule                            Millions 0.4
As previously reported, the change in schedule was based on the      0.3
overall Airline Realignment Program Schedule. Airline relocations     Dollars in  0.2
were delayed.                                     0.1
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 1Q 2014 Report  53

FIRST QUARTER REPORT, 2014
Miscellaneous Building Improvements (Airline
Realignment)
Project Status:
Associated with UA Relocation the   Schedule: Within or ahead
Project:   C800475      buildout of existing empty shelled   Budget: On or under
space within Concourse A Ramp
Budget: $2,172,000                         Status Reset: Click here to
space.
Phase: Close Out                          enter a date.
Start: 11/1/2011                                  (Commission Construction Auth.)
Schedule Completion: 7/31/2013
Budget/Costs Incurred
Significant Developments
5
The project is complete and in closeout.
3.82
4
Schedule                             3  2.66
1.95
Project was completed on schedule.                        in Millions 2
Dollars   1
Budget
0
Project forecast is within the approved budget and authorization.          Authorized  Forecasted Costs Incurred
Reimbursements to the United Airlines Group still remain.
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          55
Amount of COs    $0         $527,587
Justification for COs: For scope, unforeseen conditions and design
Risks
None identified at this time.
Budget Transfers
$1,100,000 from Expense Project 104757
$550,000 to C800404 (Aeronautical Allowance)


AIRPORT
54  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Fire Station Electric Upgrades
Project Status:
Project:   C800479    Rreplace the existing 208V         Schedule: Delayed
Budget: $2,033,000    transformer and 12.47 KV feeder, and  Budget: Forecast Overrun
Phase: Design       add a 500 KV generator and a      Status Reset: Click here to
Start: 4/1/2013         1000kVA transformer.            enter a date.
Schedule Completion: 6/30/2015                  (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Design is 100% complete.
2.5
2.03
Schedule                             2
Design is complete. Plan to request authorization from Commission     Millions 1.5
to bid the project in June 2014.                               1
Dollars in 0.5     0.35
0.21
Budget
0
The project forecast is $398,700 higher than the approved budget         Authorized  Forecasted Costs Incurred
due to increased electrical equipment costs. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.           Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 1Q 2014 Report  55

FIRST QUARTER REPORT, 2014
Laptop Power in Concourses
Project Status:
Provide additional charging        Schedule: Delayed
Project:   C800484      opportunities for personal        Budget: On or under
Budget: $1,937,050      electronic devices at several     Status Reset: 4/23/2013
strategic locations throughout the
Phase: Construction                        (Commission Construction Auth.)
airport terminal.
Start: 6/26/2012
Schedule Completion: 2/14/2014
Budget/Costs Incurred
2.5
Significant Developments                        1.94   1.94
2
1.47
Construction is complete on all charging stations. Some punchlist     Millions 1.5
work still remains. This will be the last Quarterly report..
1
Schedule                            Dollars in 0.5
Construction was complete by the delayed Benficial Occupancy date    0
Authorized  Forecasted Costs Incurred
of February 14, 2014..
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
1.2   1.04           1.03
Change Order                           1
Current Quarter   Project Total            Millions 0.8
Number of COs    0          0                   0.6
Amount of COs    $0         $0                  0.4
Dollars in   0.2          0.02
Justification for COs: n/a                                      0
Initial   Change   Spent
Orders
Risks
No risks identified at this time.
Budget Transfers
None during this quarter


AIRPORT

56  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
New Window Wall Ticket Zone 1
Project Status:
Project:   C800490      Install new common use ticket
Schedule: Delayed Schedule
Budget: $4,810,000     counters and new baggage system
Budget: On or under
Phase: Construction    along the window wall and
Status Reset: 5/13/2014
baggage system renovation.
Start: 7/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 2/17/2014
Budget/Costs Incurred
Significant Developments                     6
4.81      4.81
Project is complete and in use. This will be the last Quarterly report.     5
Millions  4                        3.30
Schedule                             3
2
The project schedule is delayed due to unforeseen structural and
Dollars in   1
design issues.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is above the approved budget and authorization
Additional funding has been approved by the Commision on May 13,  Construction Costs
2014..
4   3.43
Change Order
3
Current Quarter   Project Total            Millions             2.20
2
Number of COs    0          20
Amount of COs    $0         $178,215.61
Dollars in    1
0.20
0
Justification for COs: Due to the accelerated nature of the project, a
Initial   Change   Spent
number of design issues required addressing during construction.              Orders
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 1Q 2014 Report  57

FIRST QUARTER REPORT, 2014
Convert Ticket Zone 2 Pushback
project is to renovate the Ticket
Project:   C800491     counters and Airline Ticket Office    Project Status:
Budget: $3,982,540     (ATO) spaces into a pushback     Schedule: Delayed Schedule
Budget: On or under
Phase: Close Out      configuration.
Status Reset: Click here to
Start: 12/11/2012
enter a date.
Schedule Completion: 11/30/2013                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
No significant developments. This will be the last quarterly report.
4.5      3.98         3.98
Schedule                              4
3.5
The ticket counters are all operational.                           3                   2.63
2.5
in Millions
Budget                              2
Dollars   1.5
The project forecast is within approved budget and authorization.
1
0.5
Change Order                           0
Authorized    Forecasted   Costs Inc
Current Quarter   Project Total
Number of COs    0          62               Construction Costs
Amount of COs    $0         $1,001,966           Not Applicable
Justification for COs: Through the life of the project there were       Photo
various scope, unforeseen conditions and design changes
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
58  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Convert Ticket Zone 3 Flow Through
Project Status:
Project:   C800492      Convert the Zone 3 Ticketing Area   Schedule: Within or ahead
Budget: $10,659,000     to a flow through concept.       Budget: On or under
Phase: Close Out                          Status Reset: Click here to
Start: 8/7/2012                                   enter a date.
Schedule Completion: 10/31/2013                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
The project is complete and the final tenant reimbursement to Delta     12   11.78
has been processed. This will be the last Quarterly report.
11.5
Millions                            11.28
Schedule                             11
10.66
The project was completed on schedule.
Dollars in 10.5
Budget                             10
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
Current Quarter   Project Total
Number of COs    0          0
0.7
0.59
Amount of COs    $0         $0                  0.6  0.50
0.5
Justification for COs: n/a                                   Millions 0.4
0.3
Risks                                Dollars in  0.2     0.10
0.1
None identified at this time.                                    0
Initial   Change   Spent
Budget Transfers                                Orders
None this quarter.



AIRPORT
Port of Seattle 1Q 2014 Report  59

FIRST QUARTER REPORT, 2014
Facility Monitoring System Renewal
Project:   C800495     Provide a system upgrade that will    Project Status:
allow the system to maintain and      Schedule: Delayed
Budget: $3,422,680
expand monitoring of critical systems   Budget: On or under
Phase: Construction                        Status Reset: 12/10/2013
Start: 1/22/2013        such as elevators, escalators, moving
walks, passenger boarding bridges    (Commission Construction Auth.)
Schedule Completion:
and baggage systems.
8/31/2015
Budget/Costs Incurred
Significant Developments
4
3.42       3.42
Completed 100% design on the passenger loading bridges portion of
the work, submitted to Building Department for review and followed      3
Millions
up with some revisions. The network upgrade is progressing well.
2
0.81
Schedule                            Dollars in  1
As previously reported, the project is currently behind schedule.
0
Further design changes were required after initial submittal to the         Authorized  Forecasted Costs Incurred
Building Department per Sponsor's request.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
$2,500 transfer to C800555 NSAT Baggage Refurbishment for
power installation requirements required for this project to be
completed on time.

AIRPORT
60  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Airportwide Mechanical Controls System
Project Scope and description:    Project Status:
Project:   C800497       Upgrade the HVAC Controls     Schedule: Delayed
Budget: $2,157,000       System for the Airport. This     Budget: On or under
Phase: Design         includes adding a wireless     Status Reset: Click here to
Start: 5/1/2013            connection to the Logistics area to  enter a date.
Schedule Completion:     the south of the Airport.       (Commission Construction Auth.)
4/30/2015
Budget/Costs Incurred
Significant Developments
2.5
Completed 90% design.                                       2.16
2
Schedule                            Millions 1.5 Dollars in 
Design is scheduled for completion in May 2014. Plan to request        1
authorization from Commission to bid the project in June 2014.
0.5     0.27
0.13
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.           Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 1Q 2014 Report  61

FIRST QUARTER REPORT, 2014
RAC Baggage Claim Renovation
Project:   C800541      Renovation of both rental car      Project Status:
Budget: $1,318,200      counter locations in baggage claim  Schedule: Delayed Schedule
Phase: Construction     into new waiting areas with vending  Budget: On or under
Start: 10/1/2012          machines and other facilities for     Status Reset: 4/2/2013
Schedule Completion:    special operations           (Commission Construction Auth.)
12/31/2013
Budget/Costs Incurred
Significant Developments
1.5
On January 24, 2014 we reached Beneficial Occupancy, and on          1.32    1.32
March 10, 2014 we reached Substantial Completion. The seating                     1.00
was installed on January 31, 2014. Construction is complete.        Millions 1
Schedule                            0.5
Dollars in 
Construction is now complete with Beneficial Occupancy one month
0
later than originally intended.                                    Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                           0.3
0.26                   0.25
Current Quarter   Project Total            0.25
Number of COs    6          6                 Millions 0.2
Amount of COs    $47,428      $47,428
0.15
Dollars in   0.1
Justification for COs: $11,419 related to errors and omissions,                      0.05
$5,000 to changed site conditions, $1,009 to scope changes, and      0.05
$30,000 for regulatory requirements.                           0
Initial      Change Order      Spen
Risks
Photo
A number of unknown conditions have arisen that will need to be
addressed. We anticipate that they can be addressed within the
approved budget and authorization.
Budget Transfers
None this quarter.

AIRPORT
62  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Replace PLBs at S7, S9 & B4
Project Status:
Project:   C800543      Replace the Passenger Loading    Schedule: Within or ahead
Budget: 2,950,000      Bridges at S-7 & S-9 and install a   Budget: On or under
Phase: Construction     new bridge At B-4          Status Reset: 1/21/2014
Start: 1/21/2014                                  (Commission Construction Auth.)
Schedule Completion:
12/31/2014
Budget/Costs Incurred
Significant Developments
4
B-4 Bridge arrived May 5, 2014 and is being installed. S-7 Bridge is
2.95      2.95
scheduled to arrive May 22, 2014. B-4 and S-7 are scheduled to be     3
operational on June 1, 2014. S-9 will be installed in October 2014.     Millions
2
Schedule                            Dollars in  1
0.06
B-4 and S-7 are scheduled to be operational June 1, 2014. Delivery
0
of some items is very tight.                                     Authorized  Forecasted Costs Incurred
Budget
No issues                                     Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
There are schedule risks as some gate communication equipment
delivery is tight. Contingency Plans are being developed to address
this issue.
Budget Transfers
None

AIRPORT

Port of Seattle 1Q 2014 Report  63

FIRST QUARTER REPORT, 2014
NorthSTAR Program
Includes programmatic project         Project Status:
Project:   C800544   management and project controls costs   Schedule: Delayed
Budget: $15,400,000  for the NorthSTAR program, consisting  Budget: On or under
Phase: Design      of 5 capital projects that represents a   Status Reset: Click here to
Start: 4/5/2012       unique partnership between the Port     enter a date.
Schedule Completion:  and Alaska Airlines.            (Commission Construction Auth.)
8/27/2020
Budget/Costs Incurred
Significant Developments
Executed Service Directive with GluMac for Commissioning design     20
15.40
support associated with potential Leadership in Energy and
15
Environmental Design (LEED) certification. Executed contract with     MillionsDollars in 
Heery for Construction Management Support. Established specific     10
NorthSTAR program performance metrics. Defined programmatic
5    3.60
public relations communication plan. Conducted program update for                    2.04
AAAC meeting. Received airline MII approval of programmatic
0
budget of $15,400,000.                                   Authorized Forecasted Costs Incurred
Schedule
Update Program master schedule to the most current baseline      Construction Costs
assumptions due to changes in design durations and scope.       Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Communication and coordination across multiple teams and
stakeholders along with identification/monitoring of all "linked"
Capital projects outside of NorthSTAR.
Budget Transfers
None
AIRPORT
64  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
NorthSTAR Main Terminal Improvements
Renovate the North Main Terminal     Project Status:
Project:   C800545    security checkpoint, curbside and      Schedule: Delayed
Budget: $29,200,000   ticketing lobby areas incorporate self   Budget: On or under
Phase: Design      operated technologies and improve    Status Reset: 12/3/2013
Start: 12/3/2013       aesthetics.                    (Commission Construction Auth.)
Schedule Completion:
8/27/2018
Budget/Costs Incurred
Significant Developments                     40
29.20
Advertised for RFQ for the Facility Determination Analysis consultant    30
procurement; shortlisted; interviewed and selected firm. Scope to      Millions
20
address space requirements and preliminary configurations for the
north security checkpoint and ticket lobby/curbside uses. Firm
Dollars in  10
1.50
selected on May 9 with contract award process underway.                          0.04
0
Authorized  Forecasted Costs Incurred
Schedule
Schedule has been re-baselined to reflect updated schedule and
approach to conduct facility determination analysis prior to project    Construction Costs
notebook/design phases. Negotiating contract with analysis       Not Applicable
expected to start in third quarter.
Budget
Project forecast is within the approved budget. Request Commission
Authorization for construction funding and authority to advertise for
construction when the bid documents are completed.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Project scope definiton could increase scope and budget.
Budget Transfers
None
AIRPORT
Port of Seattle 1Q 2014 Report  65

FIRST QUARTER REPORT, 2014
NorthSTAR Concourse C Vertical Circulation
Construct exterior, weather protected    Project Status:
Project:   C800547
sloped walkways with elevators at      Schedule: Within or ahead
Budget: $18,525,000   Gates C2/4, C10/12, and C14 to     Budget: On or under
Phase: Construction   provide enhanced access from      Status Reset: 10/22/2013
Start: 11/7/2012       concourse to aircraft ramp for        (Commission Construction Auth.)
Schedule Completion:  Alaska/Horizon regional operations.
4/17/2015
Budget/Costs Incurred
20    18.53     18.53
Significant Developments
15
Bid opening on January 14, 2014. Seven (7) bids received with      Millions
Forma Construction Co. as the successful low bidder at $8,719,940 -    10
14.9% below the Engineer's Estimate. The contract was awarded on
Dollars in   5
February 12, 2014 and NTP for construction was issued on April 10.                    1.78
2014. The C10, C12, C14 and C16 passenger loading bridges were    0
removed in March to accommodate new walkways. eGSE chargers       Authorized Forecasted Costs Incurred
removed from Gate C2 for reinstallation starting later this year.
Schedule                           Construction Costs
The project is currently on schedule for 2nd Quarter 2015 completion.
10   8.72
Construction coordination with AAG to minimize impact on AS/QX
8
operations and for their immediately adjacent ground level walkways
construction is ongoing.                                  Millions  6
4
Budget                             Dollars in  2
The project forecast is within the approved budget and authorization.             0.00  0.00
0
Initial   Change   Spent
Change Order                                Orders
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Construction phasing to minimize impact on airline operations and
potential for underground utility conflicts during construction.
Budget Transfers
None
AIRPORT
66  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Concourse D Roof Replacement
Project Status:
Project:   C800550      Remove and replace the roofing    Schedule: Within or ahead
Budget: $3,727,000      systems on Concourse D of the    Budget: On or under
Phase: Design        Airport; install ladders, stairs and   Status Reset: Click here to
Start: 07/01/2013         fall protection on the penthouse     enter a date.
sections; and make repairs and     (Commission Construction Auth.)
Schedule Completion:
where required, replacments to the
10/31/2014
KalWall window system.
Budget/Costs Incurred
Significant Developments                      4
3.37
3.5      3.25
Returned to Commission in April to request additional funding and       3
authorize awarding contract to the low bidder.                    2.5
MillionsDollars in      2
Schedule                             1.5
1
This project is currently on schedule.                           0.5                 0.08
0
Authorized       Forecasted      Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
$120,000 from C800404 (Aeronautical Allowance)


AIRPORT
Port of Seattle 1Q 2014 Report  67

FIRST QUARTER REPORT, 2014
Grease Interceptor Augmentation
Project Status:
Project:   C800551     Install two underground 9,000 gallon   Schedule: Within or ahead
Budget: $1,559,200     grease interceptors to service the    Budget: On or under
Phase: Permitting     Concourse C and South Satellite.    Status Reset: Click here to
Start: 5/1/2013                                   enter a date.
Schedule Completion: 10/31/2014                 (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Ninety percent design is complete. Project to bid June 2014.
2
1.56      1.56
Schedule
1.5
Project is on schedule for a Mid September NTP.                Millions
1
Budget                             Dollars in 0.5          0.13
The project forecast is within the approved budget. Authorization of
0
construction funding and authority to advertise for construction will         Authorized  Forecasted Costs Incurred
be requested when the bid documents are completed.
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Design may run longer than anticipated due to conflicts with other
projects.
Budget Transfers
None this quarter.


AIRPORT

68  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
NorthSTAR Refurbish Baggage Systems
Refurbish existing baggage systems   Project Status:
Project:   C800555
in support of AAG operation at North   Schedule: Within or ahead
Budget: $21,500,000
Satellite and Concourse D. The work   Budget: On or under
Phase: Construction   will extend the service life of part of   Status Reset: Click here to
Start: 11/6/2012        the C92 systems, C88 North Satellite   enter a date.
Schedule Completion:   systems, and C88 tunnel systems.    (Commission Construction Auth.)
12/31/2015

Significant Developments                    Budget/Costs Incurred
Advertised, awarded and executed contract on April 25, 2014.        25   21.50    21.50
Contractor will begin work in June. Port crews completed tunnel       20
work to the North Satellite.                                 Millions 15
10
Schedule
Dollars in   5
Contractor preparing pre-construction submittals for Port review.                        1.19
0
Beneficial Occupancy set for May 15, 2015.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.              Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Expansion decision may impact baggage. Tracking expansion
decision and coordinating with NSAT Renovation project scope.
Optimization project may impact scope and schedule of the baggage
project.
Budget Transfers
$500,000 transferred to expense

AIRPORT
Port of Seattle 1Q 2014 Report  69

FIRST QUARTER REPORT, 2014
NorthSTAR North Satellite Renovation NSTS
Lobbies
Project Status:
Project:   C800556     Renovation of the North Satellite    Schedule: Delayed
Budget: $383,548,000    (NSAT) terminal, including Satellite   Budget: Forecast Overrun
Phase: Design        Transit System (STS) station      Status Reset: Click here to
Start: 7/24/2012         "refresh", ramp level, Concourse     enter a date.
Schedule Completion:    level, and new rooftop airline lounge.  (Commission Construction Auth.)
8/27/2020
Budget/Costs Incurred
Significant Developments
Port and Alaska Air Group (AAG) recommended expansion of the
500
NSAT to 20 gates based upon airport wide gating analysis. Began
383.55
30% design with completion of two weeks of design charrettes.       Millions 400
Initiated standing meetings to further evaluate aircraft layout, taxilane    300
improvements and Passenger Loading Bridge requirements.        Dollars in 200
AAG continues evaluating internally on dual door aircraft            100   32.93
4.43
enplanement and deplanement. Port established a deadline of
0
May 19, 2014 for AAG response, if viable, on this operational            Authorized  Forecasted Costs Incurred
enhancement representing additional scope and facility modification.
Construction Costs
Schedule                           Not Applicable
Continue development of 30% design and refining floor plans to
balance hold rooms, concessions and circulation Level of Service.
Continue analyzing construction phasing to maximize gate
availability during construction. Thirty percent design delayed due to
expansion MII ballot and Commission Authorization, analyzing
schedule and Dual Door decision. Preparing MII ballot and
Commission Authorization for expansion in June and July,
respectfully.
Budget
Commission has authorized $32,933,556.00 to date for design effort.
The current budget does not include the cost of facility expansion. A
pending request is being prepared for Commission approval for
additional authorization to be preceded by a MII vote.



70  Port of Seattle 1Q 2014 Report

Change Order
Current Quarter   Project Total
Number of COs   0          0
Amount of COs   $0         $0
Justification for COs: n/a
Risks
Airline operational and airport gate demand requirements may change the scope of the NSAT
renovation and the preliminary approach to construction phasing. Dual Door represents a significant
scope addition.
Budget Transfers
None









AIRPORT
Port of Seattle 1Q 2014 Report  71

FIRST QUARTER REPORT, 2014
Snow Blower and Deicer Trucks
Project Status:
Project:   C800557                             Schedule: Within or ahead
Purchase 1 Deicer ion
Budget: 400,000                           Budget: On or under
Status Reset: Click here to
Phase: Implementation
enter a date.
Start: 4/4/2014
(Commission Construction Auth.)
Schedule Completion: 1/30/2015
Significant Developments                    Budget/Costs Incurred
Project split out:
2.5     2.20      2.20
(1) Deicer Truck Project #105068 to be purchased in 2014, and
2
(2) Snow Blower Trucks to be purchased in 2015 and 2016 - one
each year.                                        Millions 1.5
1
Schedule                            Dollars in 0.5
Not Applicable                                                      0.00
0
Authorized  Forecasted   Costs
Budget                                       Incurred
$400,000
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None aware of
Budget Transfers
None



AIRPORT
72  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Main Terminal Mezzanine Tenant Relocations
Project Status:
Project:   C800560    Construct new tenant leased spaces in  Schedule: Within or ahead
Budget: $2,025,000    order to move existing tenants and    Budget: On or under
Phase: Design       provide new leasable office space for  Status Reset: 11/19/2013
Start: 3/26/2013        airlines on the mezzanine of the main   (Commission Construction Auth.)
Schedule Completion:   terminal.
3/30/2015
Budget/Costs Incurred
2.5
Significant Developments                        2.03   2.03
2
Bid documents have been completed, reviewed, and submitted.       Millions 1.5
Anticipate advertising for construction bids ahead of schedule.
1
Schedule                            Dollars in 0.5          0.23
On schedule                                     0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
From C800404 (Aeronautical Allowance)          $275,000



AIRPORT
Port of Seattle 1Q 2014 Report  73

FIRST QUARTER REPORT, 2014
Known Crewmember Employee Bypass
Project Status:
Construct new Known          Schedule: Delayed Schedule
Project:   C800576      Crewmember Bypass and        Budget: On or under
Budget: $650,000       Employee Bypass locations at the   Status Reset: 12/11/2012
Airport.
Phase: Construction                        (Commission Construction Auth.)
Start: 12/11/2012
Schedule Completion: 10/31/2014
Budget/Costs Incurred
0.7     0.65       0.65
Significant Developments
0.6
A new vendor has been selected for the employee bypass portals.
Anticipate delivery in July.                                   Millions 0.5                 0.42
0.4
0.3
Schedule                            Dollars in 0.20.1
Installation of the Employee Bypass at North and South delayed until
0
3rd Quarter 2014.                                        Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None at this time.
Budget Transfers
None this quarter.


AIRPORT
74  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
International Arrivals Facility (IAF)
Project Status:
Project:   C800583    Planning, Design, Construction of new  Schedule: Within or ahead
Budget: $344,000,000   Federal Inspection Services (FIS)    Budget: On or under
Phase: Planning     facility, including connector between   Status Reset: Click here to
Start: 6/25/2013        South Satellite and FIS and sterile     enter a date.
Schedule Completion:   corridors and walkways within      (Commission Construction Auth.)
Concourse A.
6/30/2018
Significant Developments                    Budget/Costs Incurred
Selected and mobilized a Project Management Consultant Team.
400
344.00
The Master Plan consultant authorized to complete IAF planning and    350
project definition. A new Program Leader has been hired. Conducted
Millions  300
21 stakeholder interviews for program definition development. Initial     250
200
Program Schedule progress updating and reporting initiated.        Dollars in  150
100
Schedule
50      8.50                    0.28
The project is currently on schedule.                           0
Authorized      Forecasted     Costs Incurred
Budget
The project forecast is within the current budget.                Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Additional technical analysis of the South Satellite to Concourse A
connector will delay bridge or tunnel decision and advertisement of
RFQ. Program budget may increase due to new scope being added
to the IAF, such as airline relocations.
Budget Transfers
None this quarter. Additional Commission Authorization obtained
March 11, 2014 for $5,000,000 for total authorization to $8,500,000.

AIRPORT
Port of Seattle 1Q 2014 Report  75

FIRST QUARTER REPORT, 2014
Security Exit Lane Breach Control-Phase 2
Project:   C800605    This project will procure and install new  Project Status:
automated breach control equipment at   Schedule: Delayed
Budget: $6,407,000
four security exits in the airport terminal.  Budget: On or under
Phase: Construction                        Status Reset: 9/10/2013
Start: 10/1/2012                                  (Commission Construction Auth.)
Schedule Completion: 11/30/2014

Significant Developments                    Budget/Costs Incurred
Construction Notice-to-Proceed has not been issued due to ongoing
7    6.41      6.41
negotiation with TSA about security control and funding. If             6
negotiations are not successful, the project could be halted.
Millions  5
4
Schedule                             3           2.35
Dollars in   2
As previously reported, Phase 2 project schedule was pushed out
1
later to ensure that there was adequate time for Airport Security and
0
TSA testing of the pilot project (completed in Phase 1).                 Authorized  Forecasted Costs Incurred
Budget
Project forecast is within the approved budget and authorization.     Construction Costs
Change Order                           2  1.76
Current Quarter   Project Total            1.5
Number of COs    0          0                 Millions
1
Amount of COs    $0         $0
Dollars in 0.5
Justification for COs: n/a                                              0.00     0.07
0
Initial    Change Order    Spent
Risks
Project could be halted if negotiations with TSA are not satisfactory
to the Port.
Budget Transfers
None this quarter.


AIRPORT
76  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
North Satellite - STS Ceiling Leak Repair
Eliminate ceiling leaks at the North   Project Status:
Project:   C800609
Satellite (NSAT) that occur        Schedule: Within or ahead
Budget: $1,750,000      between the satellite transit station  Budget: On or under
Phase: Design         (STS) and the elevators.       Status Reset: Click here to
Start: 5/1/2013                                   enter a date.
Schedule Completion: 10/4/2014                  (Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
The project is currently on add.
2
1.75
Schedule
The project construction schedule has been updated to reflect         1.5
change in the advertisement date for the project. This change will not    Millions
affect the overall schedule for construction completion.                1
Dollars in 
0.5
Budget                                 0.22
0.11
The project forecast is within the approved budget. Commission         0
Authorized funding for construction and authority to advertise on            Authorized   Forecasted  Costs Inc
April 1, 2014. Notification of Intent to Award construction planed for
June 11, 2014 after price cost anaylsis of bids are completed.       Construction Costs
Not Applicable
Change Order
Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 1Q 2014 Report  77

FIRST QUARTER REPORT, 2014
Passenger Bridge and Walkway S16
Replacement
Replace existing Passenger       Project Status:
Project:   C800611      Loading Bridge (PLB) and Fixed    Schedule: Within or ahead
Walkway at Gate S16. Upgrade
Budget: $1,000,000                         Budget: On or under
existing foundations and install
Phase: Close Out                          Status Reset: Click here to
infrastructure to support new Wi-Fi
Start: 6/3/2013                                   enter a date.
capabilities
Schedule Completion:                        (Commission Construction Auth.)
12/31/2013
Budget/Costs Incurred
Significant Developments
The project is complete and the bridge is operational. Outstanding      1.2
1.00      1.00
PC Air and Wi-Fi work has been completed. Project is in closeout.      1              0.86
This will be the last Quarterly report..                            0.8
Millions 0.6
Schedule                             0.4
Dollars in
Project was completed on schedule.                        0.2
0
Authorized  Forecasted Costs Incurred
Budget
Project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
78  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT,
Checked Baggage Recapitalization/Optimization
Project Status:
Project:   C800612    TSA approached the Airport in 2012    Schedule: Within or ahead
Budget: 317,000,000   with plan to replace all federally owned  Budget: On or under
Phase: Design      and operated baggage scanning     Status Reset: Click here to
Start: 2/26/2013       equipment, known as Explosive       enter a date.
Schedule Completion:  Detection System (EDS) equipment.   (Commission Construction Auth.)
The EDS equipment is approaching
12/31/2024
the end of its life.
Budget/Costs Incurred
Significant Developments
350           317.00
The Port executed a Service Agreement with BNP Associates Inc.
300
on January 27, 2014 for the completion of 30% design services thru
the end of the program. Design work continues to progress with input    Millions 250200
from all stakeholders. The project team continues to address the       150
TSA's 30% design review comments                      Dollars in 100
50    19.85
2.78
Schedule                             0
Authorized  Forecasted Costs Incurred
The project is currently on schedule. Overall schedule will be refined
to reflect a ten-year program.
Budget                            Construction Costs
The project forecast is within the approved budget. Commission     Not Applicable
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are
completed.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 1Q 2014 Report  79

FIRST QUARTER REPORT, 2014
Second Floor Mezzanine Infrastructure Upgrade
Project:   C800615    Upgrade and extend the infrastructure  Project Status:
(HVAC, Communications, Electrical,
Budget: $2,545,000                         Schedule: Delayed Schedule
Plumbing, WiFi) to 14,000sq ft of future  Budget: On or under
Phase: Design
lease space on the 2nd floor, including  Status Reset: Click here to
Start: 8/1/2013         7,000 sq ft for a new USO.          enter a date.
Schedule Completion:                        (Commission Construction Auth.)
2/13/2015
Significant Developments                    Budget/Costs Incurred
The project is currently in design and is in preparation to advertise to
3
2.55      2.55
bid on June 16, 2014.
2.5
2
Schedule
Millions 1.5
Current project is to complete construction in February 2015.          1
The delay is due to many design challenges existing from the second   Dollars in 0.5               0.30
floor to meet egress code requirements and determining the routing
0
of the infrastructure, primarily HVAC.                             Authorized  Forecasted Costs Incurred
Budget
The forecast is within the approved budget and authorization..       Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The risks are to ensure that the USO infrastructure and utility line up
with the Infrastructure project tie-ins.
Budget Transfers
None.


AIRPORT
80  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Town & Country Stormwater Pipe
Project Status:
Project:   C800651      Stormwater Pipe             Schedule: Within or ahead
Budget: $350,000                          Budget: On or under
Phase: Construction                        Status Reset: Click here to
Start: 1/1/2014                                   enter a date.
Schedule Completion: 9/30/2014                  (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Waiting for period of dry weather to complete construction.
0.4     0.35       0.35
Schedule
0.3
On schedule
0.2                      0.146519
in Millions
Budget
0.1
Project is within budget and forecast.                          Dollars 
0
Change Order                            Authorized Forecasted Costs Incurred
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
Further weather delays
Budget Transfers
None



AIRPORT
Port of Seattle 1Q 2014 Report  81

FIRST QUARTER REPORT, 2014
North Utlity Tunnel Steam Pipe
Project Status:
Project:   C800659      Replace 45 year old steam piping   Schedule: Within or ahead
Budget: $1,250,000      expansion joints in the North Utility  Budget: On or under
Phase: Construction     Tunnel.                Status Reset: Click here to
Start: 8/1/2014                                   enter a date.
Schedule Completion: 10/8/2014                  (Commission Construction Auth.)
Significant Developments
Completed 100% design - Bid date May 22, 2014.              Budget/Costs Incurred
1.5
Schedule                                1.25   1.25
s
Construction scheduled to begin June 25 with completion on October   n
io 1
8, 2014.                                           ill
M
n i
rs0.5
Budget                             lla
o
D                 0.01
Currently on budget. Receive bids on May 22, 2014.               0
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0                Not Applicable
Justification for COs:
Risks
None
Budget Transfers
None




AIRPORT
82  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Automated Passport Control
Install fourteen (14) Automated     Project Status:
Project:   C800667
Passport Control (APC) kiosks in    Schedule: Within or ahead
Budget: $2,207,000      the existing FIS at the South     Budget: On or under
Phase: Construction     Satellite.               Status Reset: Click here to
Start: 10/13/2013                                 enter a date.
Schedule Completion: 12/31/2013                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Project is in close out. PCS is completing a few remaining
2.5     2.21       2.21
adjustments to the queuing stanchions.
2
Schedule                            Millions 1.5          1.10
Currently on schedule for close out.                           1
Dollars in 0.5
Budget
0
This project forecast is currently under budget due to the                Authorized  Forecasted Costs Incurred
acceleration.Commission Authorized construction on 11/8/2013
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 1Q 2014 Report  83

FIRST QUARTER REPORT, 2014
Highline School Noise Insulation
Project Status:
Project:   C200007      Highline School Insulation        Schedule: Delayed
Budget: $101,797,000    Agreement will provide funding for  Budget: On or under
Phase: Construction     sound mitigation for 15 schools that  Status Reset: Click here to
Start: 03/23/1999         are impacted by aircraft noise from   enter a date.
Schedule Completion:    Sea-Tac Airport.            (Commission Construction Auth.)
11/30/2021

Significant Developments                    Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of
120
102.14     101.80
Washington, and the Highline School District provide matching
100
funds.
80
60                   52.04
Schedule                             Millions
40
The schedule for state funds is unknown. The district's schedule is     Dollars in 20
dependent on obtaining general election bonds at various intervals.
0
FAA grant received for Olympic Elementary. Construction may          Authorized Forecasted Costs Incurred
resume in 2015, if a voter approval bond is secured in 2014.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Project delayed due to funding issues with the Highline School
District. There is a risk if no bonds are passed in the general
election. Obtain FAA Airport Improvement Program (AIP) Grant
funding.
Budget Transfers
None this quarter

AIRPORT
84  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Highline Community College Noise Insulation
Project Status:
Project:   C200042      Highline Community College      Schedule: Within or ahead
Budget: $32,050,000     Insulation Agreement will provide   Budget: On or under
Phase: Construction     funding for up to 22 eligible      Status Reset: Click here to
Start: 1/11/2005          buildings that are impacted by      enter a date.
Schedule Completion:    aircraft noise from Sea-Tac Airport.  (Commission Construction Auth.)
12/31/2013
Significant Developments                    Budget/Costs Incurred
Fourteen of the original 22 eligible buildings have been sound         8.3
insulated by the college. The College sound insulation program has         8.19
8.2
been dependent on receiving funding from FAA grants. The FAA
notified the Port that the Highline Community College Campus is no    8.1  Millions
longer located within the 65 DNL Noise Contour and therefore is not     8         7.97     7.96
eligible for any further grant funding. Without the FAA's approval and   Dollars in  7.9
funding the remainder of the college buildings cannot be sound
insulated.                                             7.8
Authorized   Forecasted  Costs Incurred
Schedule
Construction Costs
The construction is complete on the last building (Building #4) and    Not Applicable
the Noise Office is working with FAA to Close Grant AIP 127.
Budget
The project forecast is within the approved budget. No further
authorization is anticipated with this project.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The FAA will not allocate future grant funds to this project.
Budget Transfers
$24,000,000 Budget reduction per Q4 2013 cash flows

AIRPORT
Port of Seattle 1Q 2014 Report  85

FIRST QUARTER REPORT, 2014
Home Insulation Retrofit
Project Status:
Project:   C200048      This project includes storm window
Schedule: Within or ahead
Budget: $5,344,000      retrofit of previously insulated
Budget: On or under
Phase: Construction     homes.
Status Reset: Click here to
Start: 1/11/2005                                  enter a date.
Schedule Completion: 12/31/2015                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of      6   5.34
their eligibility. The Port is continuing with storm window retrofit.
5
4.06
Schedule                            Millions 4           3.44
3
The Port is reviewing other potential homes for eligibility. The project
2
has encountered additional delay due to non-responsive           Dollars in 
1
homeowners willing to participate in the program.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
$1,300,000 reduction based on Q4 2013 cash flows


AIRPORT
86  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Single Family Home Sound Insulation
Project Status:
Project:   C200093      Sound insulate remaining homes    Schedule: Within or ahead
Budget: $13,747,395     that are within the 1998 65 decibel  Budget: On or under
Phase: Construction     day night level (DNL) noise      Status Reset: Click here to
Start: 3/27/2007          contour.                   enter a date.
Schedule Completion: 12/31/2015                 (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Forty homes are complete; 33 homes are in the process of receiving
15    13.75     13.75
sound insulation. Approximately 31 additional homes have been
identified as eligible.
Millions 10
Dollars in 
Schedule
4.46
5
Project is on schedule. Homeowners' are experiencing difficulties in
getting the required paperwork signed by their mortgage companies.
Anticipate completion by 4th quarter 2015.                      0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within approved budget and authorization to   Construction Costs
complete all homes currently in progress.
3.8
4
Change Order
3
Current Quarter   Project Total           Millions                1.78
Number of COs    0          0                  2
Amount of COs    $0         $0
Dollars in   1
0
Justification for COs:                                      0
Initial    Change Order    Spent
Risks
The ability to accomplish the insulation is dependent on the
homeowner's schedules, willingness to sign an aviation easement,
and obtain a subordination agreement from their lender, and
structural integrity of the home. If more eligible homes than
anticipated are identified in the future, then additional funding may be
needed.
Budget Transfers
None this quarter

AIRPORT                            Port of Seattle 1Q 2014 Report  87

FIRST QUARTER REPORT, 2014
RMU/Kiosk Concession Program
Design and fabrication of Retail        Project Status:
Project:   C800146
Merchandising Units (RMUs); power,    Schedule: Delayed
Budget: $879,146
communications, and data to RMU     Budget: On or under
Phase: Construction  locations; and install floor-mounted    Status Reset: Click here to
Start: 11/20/2007      receptacles for the utilities to allow easy  enter a date.
Schedule Completion:  connection points as well as flexibility for  (Commission Construction Auth.)
2/5/2014           future utilization.

Budget/Costs Incurred
Significant Developments
Casework was installed the end of January through the first week of    1.4
1.21
February 2014. We are working with the vendor on punchlist items.     1.2
In addition, communication boxes are pending installation in the        1          0.88
0.74
casework - PCS.                                  0.8
in Millions
0.6
Schedule                            Dollars 0.4
0.2
Punchlist items are pending.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is currently within the approved budget and
authorization.                                        Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    2          2
Amount of COs    $43,363.53    $43,363.53

Justification for COs: One is for the expense of casework, and
possibly a second for installation labor.
Risks
None at this time.
Budget Transfers
None this quarter.

AIRPORT
88  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Burien Commercial Property Acquisition
Project Status:
Project:   C800150     Acquire commercial properties along  Schedule: Delayed
Budget: $3,000,000     Des Moines Memorial Drive, and    Budget: On or under
Phase: Implementation  vacate one street in the City of Burien  Status Reset: Click here to
Start: 05/31/2007        that is surrounded by Port-owned     enter a date.
Schedule Completion:   properties.                (Commission Construction Auth.)
03/31/2014
Budget/Costs Incurred
Significant Developments                     2.9
2.79
2.8
The remaining anticipated acquisitions will be street vacation of 12th               2.70
Place S. in Burien, Washington; possibly the 757 Convenience store;    Millions 2.7
2.6
and a small upholstery shop on the Lora Lake site.                                2.47
2.5
Dollars in 2.4
Schedule
2.3
It is anticipated that the acquisitions will occur in the first quarter of          Authorized  Forecasted Costs Incurred
2014.
Budget                            Construction
The project forecast is within the approved budget.              Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
$300,000 reduction based on Q4 2013 cash flows


AIRPORT
Port of Seattle 1Q 2014 Report  89

FIRST QUARTER REPORT, 2014
Tenant Reimbursement
Build-out of spaces for new and       Project Status:
Project:   C800154    existing tenants. If more than a "basic   Schedule: Within or ahead
Budget: $4,709,577    finish" condition space is built for the   Budget: On or under
Phase: Construction   tenant, the tenant is required to      Status Reset: Click here to
Start: 8/14/2007       reimburse the Port for the cost of the    enter a date.
Schedule Completion:  work beyond this "basic finish".      (Commission Construction Auth.)
TBD          Reimbursements allowed under the
guidelines in the "Tenant Reimb
Policy".                        Budget/Costs Incurred
5    4.69      4.71
Significant Developments                      4
Airport Management Services' office build-out on the ramp level of     Millions 3
Dollars in 
baggage claim in review. Anticipate payment in Q2 or Q3 2014.
2                     1.30
Schedule                             1
Schedules vary to meet the tenant's needs.                     0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
90  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
T-46 Lease Improvements
Project: C102554       Construct stormwater treatment     Project Status:
Budget: $8,000,000     system to comply with Ecology     Schedule: Within or ahead
Phase: Design        order. Terminal pavement overlay   Budget: On or under
Start: 4/12/2013         to fulfill lease obligation.          Status Reset: Click here to
Schedule Completion: 2020                     enter a date.
(Commission Construction Auth.)
Significant Developments
Ecology approved Engineering and Alternatives evaluation reports   Budget/Costs Incurred
on March 27, 2014. Ecology approved extension request to
10
complete two treatment vaults by December 2014, and the third            8
vault by June 2015. Completed construction advertisement.          8
Construction contract awarded to ICON Materials.               Millions 6
4
Schedule                            Dollars in  2           1.404
Installation of the three treatment vaults projected to be complete by
December 2014. The fourth treatment will be installed once        0
Authorized   Forecasted  Costs Incurred
Washington State Department of Transportation (WSDOT) vacates
the lease area.
Budget                           Construction Costs
$8,000,000 for Stormwater Treatment System. Currently within     None at this time
budget.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Construction impact on terminal operation due to unforeseen
condition.
Budget Transfers
Not Applicable

SEAPORT
Port of Seattle 1Q 2014 Report  91

FIRST QUARTER REPORT, 2014
Street Vacations T5,18,105
Project Status:
Street vacation related real estate      Schedule: Delayed Schedule
Project: C102858,
C102875, E104366    negotiations and agreements --T5,    Budget: On or under
T18, and T105 (complete).          Status Reset: Click here to
Budget: $1,500,000                         enter a date.
Phase: Permitting                         (Commission Construction Auth.)
Start: 6/1/2010
Schedule Completion: 2014
Budget/Costs Incurred
2
Significant Developments
1.5        1.5
1.5
Draft Easement and Utility transfer documents have been prepared    Millions                0.992836
by the City and are under Port review for Terminal 18 (T-18).          1
Discussion and Title work has begun for Terminal 5.
Dollars in  0.5
Schedule
0
Current schedule has T-18 completed by the end of 2014 and T-5 by       Authorized  Forecasted Costs Incurred
the end of 2015.
Budget                            Construction Costs
Not Applicable
The budget has been revised for 2014 and beyond.
Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Not applicable
Budget Transfers
Not applicable


SEAPORT
92  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Pier 34 Mooring Dolphins
Project Status:
Project:   C800090      Replacement of four existing failed   Schedule: Within or ahead
Budget: $1,611,000      timber mooring dolphins with four   Budget: On or under
Phase: Design        new steel dolphin structures     Status Reset: Click here to
Start: 4/1/2014          located at Pier 34 at the head of    enter a date.
Schedule Completion:    the East waterway by March 2015   (Commission Construction Auth.)
for $1.611M
3/30/2015
Budget/Costs Incurred
Significant Developments                      2
1.611
Design underway, permit notification submitted.
1.5
Millions
1
Dollars in 
Schedule
Design complete by August 2014. Construction complete by March    0.5   0.275
2015                                                  0.0204
0
Authorized   Forecasted  Costs Incurred
Budget
Project is within approved budget.
Construction Costs
Change Order                         None at this time
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None


SEAPORT
Port of Seattle 1Q 2014 Report  93

FIRST QUARTER REPORT, 2014
P91 Fender System Upgrade
Project Status:
Project:   C800183      Upgrades to the vessel berths to    Schedule: Within or ahead
Budget: $5,700,000      better accommodate cruise ships   Budget: On or under
Phase: Construction     and serve the other industrial     Status Reset: 6/14/2011
Start: 1/31/2010          customers who utilize the berths    (Commission Construction Auth.)
Schedule Completion:    and adjacent dock/apron areas for
less than $6M.
6/1/2014
Budget/Costs Incurred
5.7
6
Significant Developments                      5       4.6
4.304
Fabrication of 7 camel barges complete. Camels completed service   Millions  4
Dollars in 
for the remainder of 2013 cruise season. Option exercised to          3
purchase 3 additional barges under existing purchase and within        2
project budget. These barges will be delivered for the start of the       1
2014 cruise season.                                   0
Authorized      Forecasted     Costs Incurred
Schedule
Full Fender replacement completed April 2012. Camel Barge       Construction Costs
replacement completed by July 2013. Additional barges delivered
May 2014.                                      2.5
2.083              2.083
2
Budget                            Millions
1.5
Project is within approved budget.
Dollars in       1
Change Order                           0.5
None this quarter                                        0
Initial     Change     Spent
Orders
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None

SEAPORT
94  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
T-91, Bldg C175 Roof Replacement
Project Status:
Schedule: Within or ahead
Project:   C800430      Replace roof on the C175 building   Budget: On or under
Budget: $2,450,000      at Terminal 91.            Status Reset: 1/14/2014
Phase: Construction                        (Commission Construction Auth.)
Start: 7/26/2011
Schedule Completion: Q4 2014
Budget/Costs Incurred
Significant Developments                      3
2.45       2.45
The project received Commission authorization to advertise for bids     2.5
on January 14, 2014. Advertised project and received favorable      Millions 2
construction bids during the quarter. Awarded the project and roof      1.5
replacement work has begun. .
Dollars in   1
0.5                         0.194
Schedule
0
Project remains on schedule for installation during 2014.               Authorized  Forecasted Costs Incurred
Budget
On budget                                   Construction Costs
2   1.88
Change Order
Current Quarter   Project Total             1.5
Number of COs    0          0                  Millions
1
Amount of COs    $0         $0
Dollars in   0.5
Justification for COs: n/a                                              0    0
0
Initial   Change   Spent
Risks                                      Orders
None at this time
Photo
Budget Transfers
None



SEAPORT
Port of Seattle 1Q 2014 Report  95

FIRST QUARTER REPORT, 2014
SEA P66 Apron Pile Wrap
Project Status:
Project:   C800516      Design and install a pile wrap      Schedule: Within or ahead
Budget: $3,010,000      system for corrosion protection of   Budget: On or under
Phase: Construction     steel structural pilings associated   Status Reset: 11/6/2012
Start: 3/6/2012          with Seaport structures at Pier 66.   (Commission Construction Auth.)
Schedule Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments
4
Construction continues and progressing well. Work is being
3.01
completed in conjunction with the P69 North Apron Corrosion Control    3
Project (CIP C800313). Beneficial Occupancy milestone date       Millions           1.9
2
reached on April 7th.
1.098
Dollars in   1
Schedule
0
Projected construction substantial completion date remains             Authorized  Forecasted Costs Incurred
unchanged.
Budget                            Construction Costs
Project is on budget.
1.2   1.04           1.03
Change Order                           1
0.8
Current Quarter   Project Total            Millions
0.6
Number of COs    0          4
0.4
Amount of COs    $0         $91,288              Dollars in  0.2     0.088
0
Justification for COs: n/a this quarter
Initial   Change   Spent
Orders
Risks
Risks have reduced significantly since the project has already        Photo
reached the beneficial occupancy milestone.
Budget Transfers
None


SEAPORT
96  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Argo Yard Truck Roadway
Project:   C800546,      New Port of Seattle owned truck    Project Status:
E104751, E104754       roadway between East Marginal    Schedule: Within or ahead
Budget: $7,750,000      Way and Colorado Avenue South   Budget: On or under
Phase: Design        right-of-way.             Status Reset: 4/22/2014
Start: 3/11/2012                                  (Commission Construction Auth.)
Schedule Completion: 12/31/2014
Significant Developments
Budget/Costs Incurred
MOU Supplemental Agreement approved by stakeholders.
Easements conveyed to Port by UPRR and Prologis. 100%         3.5
2.97
engineering design under review by City for approval and issuance      3          2.6
of permits. Commission authorized construction funds.              2.5
2
Schedule                            in Millions 1.5
1                     0.723
Construction to be completed by end of 2014.                  Dollars 
0.5
0
Budget
Authorized   Forecasted  Costs Incurred
Project authorized budget is $7,750,000 (including $600,000 from
FMSIB for roadway construction by Port and $3,750,000 pass-thru
funding from FMSIB for Argo Yard upgrades by UPRR).          Construction Costs
None at this time
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Issuance of City permits in time for construction bids opening in early
July 2014. WSDOT's SR 99 timber trestle replacement scheduled
for construction completion by spring 2014. The EMW Phase II
improvements will also require timely approval by Union Pacific
Railroad and the Ash Grove Cement Co. in order to be completed
within 2014.
Budget Transfers
None
SEAPORT
Port of Seattle 1Q 2014 Report  97

FIRST QUARTER REPORT, 2014
T-46 Dock Rehabilitation
Project Status:
Project:   C800603      Terminal 46 Dock Rehabilitation    Schedule: Delayed Schedule
Budget: $1,854,000      Project                Budget: On or under
Phase: Design                            Status Reset: Click here to
Start: 11/6/2012                                  enter a date.
Schedule Completion: Q1 2016                   (Commission Construction Auth.)
Significant Developments
There are no new developments on the project since the last report.   Budget/Costs Incurred
The remaining design effort from 90% to Final Design remains on
2    1.854
hold. The project will resume once the conflicting construction
project has advanced sufficiently to avoid delay.                  1.5
Millions                  1.023
Schedule                             1
As noted in the previous report, the construction schedule was       Dollars in                   0.412
0.5
delayed a year, from 2014 to 2015, to avoid conflicting construction
projects on the terminal.                                    0
Authorized   Forecasted  Costs Incurred
Budget
The project is on budget                               Construction Costs
None at this time
Change Order
Current Quarter   Project Total          Photo
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None at this time
Budget Transfers
None


SEAPORT
98  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Terminal 115 Stormwater Separation
Project Status:
Project:   C800689      Separate stormwater originating    Schedule: Within or ahead
Budget: $548,000       from the Port leased area and the   Budget: On or under
Phase: Design        Common Use Area on T-115 from   Status Reset: 5/6/2014
Start: 1/27/2014          the area exclusively used by       (Commission Construction Auth.)
Schedule Completion:    Northland Services.
9/30/2014
Budget/Costs Incurred
0.6     0.548      0.548
Significant Developments
0.5
Design underway, acquisition planning indicated self performance by    0.4
PCS crews optimal to meet deadline of September 30, 2014. Force    Millions
0.3
main design selected will require pump system and associated
0.2
power supply from Seattle City Light.                         Dollars in  0.1
0.0077
0
Schedule                               Authorized Forecasted Costs Incurred
Construction complete by September 30, 2014.
Budget                            Construction Costs
None at this time
Project is within approved budget.
Change Order
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None


SEAPORT
Port of Seattle 1Q 2014 Report  99

FIRST QUARTER REPORT, 2014
Clean Truck Program Truck Scrapping and
Replacement Project
Project Status:
Scrap or retrofit at least 180 trucks   Schedule: Within or ahead
Project:   U00079
and replace them with 2007 model-   Budget: On or under
Budget: 4,727,000
year or newer trucks.            Status Reset: Click here to
Phase: Design                            enter a date.
Start: 12/10/2013                                 (Commission Construction Auth.)
Schedule Completion: 6/30/2015
Budget/Costs Incurred
Significant Developments
4.727
5
Clean Truck program is primarily funded by two grants: the Federal
4
Highway Administration and Washington State Department of
Ecology. An Inter-Local Agreement (ILA) with the Puget Sound       Millions 3
Clean Air Agency was executed to implement the project, titled        2
Seaport Truck Scrappage and Replacements for Air in Puget Sound   Dollars in  1
(ScRAPS 2). The ScRAPS 2 truck outreach center at T-5 is                    0    0.063
scheduled to open on May 27th to begin accepting applications for      0
Authorized  Forecasted    Costs
truck replacement. An additional grant from the EPA has recently                    Incurred
been awarded pending Commission approval, scheduled for June.
Construction Costs
Schedule
Not Applicable
On schedule
Photo
Budget
On budget
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Due to multiple funding sources involved, the project needs to be
compliant with funding agencies' requirements. A consultant has
been retained to provide grant administration services.
Budget Transfers
None
SEAPORT
100  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
East Marginal Way Grade Separation
FAST Corridor funded project;      Project Status:
Project:   E102007     FHWA, State, City with Port       Schedule: Delayed Schedule
Budget: $56,256,171    commitment of $22,480,807. Scope  Budget: On or under
Phase: Close Out      is to construct grade separation in   Status Reset: 4/22/2014
Start: 5/1/2006          vicinity of T5 and T18 to minimize    (Commission Construction Auth.)
Schedule Completion:    truck traffic/rail conflicts.
Q4 2015
Budget/Costs Incurred
Significant Developments
57
56.25
An additional $800,000 was authorized by Commission for
56
miscellaneous project loose ends, construction completion and
conveyance of properties and easements to City. Final project       Millions 55
Memo of Agreement (MOA) approved by City Council Transportation    54        53.575    53.5
Committee. As-built drawings are in process of finalization.        Dollars in  53
Schedule                             52
Authorized   Forecasted  Costs Incurred
Anticipate final acceptance by Seattle Department of Transportation
(SDOT) 2nd Quarter 2014.
Construction Costs
Budget
An additional $800,000 authorized by Commission for project          25   22        22
construction completion and conveyance of properties and            20
easements to City.                                   Millions  15
Change Order                           10
Current Quarter   Project Total           Dollars in   5
1.43096
Number of COs    0          97                  0
Amount of COs    $          $1,922,967                Initial Change Spent
Orders
Justification for COs: N/A this quarter
Photo
Risks
None at this time.
Budget Transfers
None

SEAPORT
Port of Seattle 1Q 2014 Report  101

FIRST QUARTER REPORT, 2014
Viaduct Construction Coordination
Participate in the design &          Project Status:
Project:   E104324,     construction of the bored tunnel, N. &  Schedule: Within or ahead
E104535-38         S. portals, Holgate to King St, Central  Budget: On or under
Budget: $2,900,000     Waterfront surface streets, & related  Status Reset: Click here to
Phase: Implementation  projects to ensure adequate      enter a date.
Start: 1/1/2009         connection to port facilities.         (Commission Construction Auth.)
Schedule Completion: 12/31/2018
Budget/Costs Incurred
Significant Developments
3.5
SR 99 tunnel boring delayed and the machine is in need of repair.           2.9
3
Mercer West construction continued. Seawall construction is
2.5
underway. Central Waterfront 30% design completed.           Millions 2        1.75
1.5                         1.08
Schedule
Dollars in   1
Construction of Atlantic St. Overpass opened to traffic. Preparation     0.5
for tunneling machine repairs is underway. Related City projects are     0
making steady progress: Mercer West and Seawall Phase I            Authorized  Forecasted Costs Incurred
construction is underway; Central Waterfront design is at 30% level.
Budget                            Construction Costs
Not Applicable
Port staff costs were within anticipated 2013 spending.
Change Order                         Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Project delays due to repairs to the tunneling machine.
Budget Transfers
None


SEAPORT
102  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
T-5 and T-91 Maintenance Dredging
Project Status:
Project:   E104840 &     Maintenance Dredge at T-5 all     Schedule: Delayed Schedule
U00067            three berths and at T-91 East     Budget: On or under
Budget: $4,800,000      cruise berth.             Status Reset: Click here to
Phase: Design                            enter a date.
Start: 8/14/2012                                  (Commission Construction Auth.)
Schedule Completion: 2/28/2016
Budget/Costs Incurred
Significant Developments
6
T-5 maintenance dredging construction finished in February 2014.          4.8
5
Due to complications and delays in permitting, T-91 maintenance
dredging construction is now delayed for construction in late 2015--    Millions 4
3
Dollars in 
early 2016.                                                          1.744
2
1
Schedule
0
T-5 maintenance dredging completion was on schedule. T-91 East       Authorized  Forecasted Costs Incurred
Cruise Berth maintenance dredging is delayed by two years due to
permitting complications.                                Construction Costs
None at this time
Budget
Project is on budget.                                   Photo
Change Order
Current Quarter   Project Total
Number of COs    2          2
Amount of COs    $20,390.33    $20,390.33
Justification for COs: Permit requirements resulted in additional sand
cover.
Risks
Environmental permitting may cause further delays, scope change,
and cost impact to the T-91 East Cruise Berth dredging project.
Budget Transfers
None

SEAPORT
Port of Seattle 1Q 2014 Report  103

FIRST QUARTER REPORT, 2014
Shilshole Bay Marina Central Seawall
Project Status:
Project:   C800088      Rehabilitation of the timber step    Schedule: Within or ahead
Budget: $915,000       wall section of the central seawall   Budget: On or under
Phase: Construction     at Shilshole Bay Marina        Status Reset: Click here to
Start: 7/9/2013                                   enter a date.
Schedule Completion: 10/31/2014                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Ninety percent design complete. Construction by PCS crews to begin    1   0.915    0.915
upon permit approval in early June. Material and equipment is being    0.8
ordered.                                         Millions 0.6
0.4
Schedule
Dollars in  0.2
In-water work begins June 1, 2014. Complete construction by                        0.0339
October 31, 2014.                                    0
Authorized   Forecasted  Costs Incurred
Budget
Project is within approved budget.                         Construction Costs
None at this time
Change Order
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None


REAL ESTATE
104  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
FT C15 HVAC Improvements
Project Status:
Project:   C800137     Provide the preliminary planning,
Schedule: Within or ahead
Budget: $4,887,000     design, and construction to replace
Budget: On or under
Phase: Construction    the existing HVAC systems within
Status Reset: 10/8/2013
Start: 5/1/2010         Building C-15 that are at the end of
(Commission Construction Auth.)
their service life.
Schedule Completion:
6/30/2014
Budget/Costs Incurred
Significant Developments                      6
4.887      4.887
5
Construction activities began with work concentrating on the west
side of the Fishermen's Center Building, both inside tenant spaces     Millions 4
and in the mechanical wells. Work within the mechanical wells         3
remains extremely challenging due to space limitations.
Dollars in   2
0.771
1
Schedule
0
Based on Port staff observations, contractor needs to take additional       Authorized  Forecasted Costs Incurred
actions to stay on their original construction schedule.
Budget                            Construction Costs
Project is on track to be within the October 8, 2013 Commission
3.5
funding authorization.                                         2.97
3
Change Order                          Millions 2.5
2         1.52
Current Quarter   Project Total             1.5          1.04
Number of COs    1          1                  Dollars in   1
0.5
Amount of COs    $1,520.00     $1,520.00
0
Initial   Change   Spent
Justification for COs: Varying Site Conditions                             Orders
Risks
Construction related access to existing mechanical wells is extremely
difficult and some work will be within areas currently concealed from
view. Challenges may arise and could impact construction costs and
schedule.
Budget Transfers
None

REAL ESTATE
Port of Seattle 1Q 2014 Report  105

FIRST QUARTER REPORT, 2014
P-69 Built-up Roof Replacement
Project Status:
Project:   C800314      Replace 32,000SF of the 65,000SF  Schedule: Within or ahead
Budget: $3,418,000      Built-Up Roof at the P-69       Budget: On or under
Phase: Construction     Headquarters Office Building     Status Reset: 2/25/2014.
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 10/30/2014
Significant Developments                    Budget/Costs Incurred
Commission authorized the project for construction in Q1 2014. The
4
3.418      3.421
project has BID and has been Awarded.                     3.5
3
Schedule                            Millions 2.5
2
Completion date scheduled for Q4 2014.
1.5
Dollars in   1
Budget                             0.5           0.22
0
The project is currently below budget.
Authorized   Forecasted  Costs Incurred
Change Order
None                                 Construction Costs
Risks                                 3.5  3.13
3
Current Quarter   Project Total
Millions  2.5
Number of COs    0          0
2
Amount of COs    $0         $0
1.5
Dollars in     1
Justification for COs: n/a                                    0.5
0    0.013
0
Budget Transfers                             Initial Change Spent
Orders
None



REAL ESTATE

106  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
FT C-2 Nordby HVAC and Roof Replacement
Project Status:
Project:   C800344      Replace 23,000SF of existing      Schedule: Within or ahead
Budget: $2,740,000      Roofing and roof top HVAC units   Budget: On or under
Phase: Construction                        Status Reset: 1/7/2014
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 10/30/2014
Significant Developments                    Budget/Costs Incurred
Commission authorized the project for construction in Q1 2014. The
3    2.74
project has BID and is in the process of Award. Projects FT C-2                  2.4
2.5
Nordby HVAC and FT Net Shed 9 Roof Overlay projects have been
combined together for funding authorization and bid as one (1)       Millions 2
construction package with separate CIP's.                     1.5
Dollars in   1
Schedule                             0.5           0.229
The project is scheduled for completion in Q4 2014                0
Authorized   Forecasted  Costs Incurred
Budget
The project is currently below budget.                       Construction Costs
Change Order
2.5   2.17
Current Quarter   Project Total              2
Number of COs    0          0                  Millions        1.52
1.5
Amount of COs    $0         $0                             1.04
1
Justification for COs: n/a                                   Dollars in   0.5
0.022
0
Risks                                   Initial Change Spent
Orders
None
Budget Transfers
None


REAL ESTATE
Port of Seattle 1Q 2014 Report  107

FIRST QUARTER REPORT, 2014
FT Net Shed #9 Roof Overlay
Project Status:
Project:   C800527      Overlay 12,000SF of existing      Schedule: Within or ahead
Budget: $301,400       corrugated Roof at the FT Net     Budget: On or under
Phase: Construction     Shed Building            Status Reset: 1/7/2014
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 10/30/2014
Budget/Costs Incurred
Significant Developments
0.35
Commission authorized the project for construction in Q1 2014. The         0.301    0.302
0.3
project has BID and is in the process of Award. Projects FT C-2
Nordby HVAC and FT Net Shed 9 Roof Overlay projects have been    Millions0.250.2
combined together for funding authorization and bid as one (1)
0.15                       0.102
construction package with separate CIP's.                     Dollars in  0.1
0.05
Schedule                             0
The project is scheduled for completion in Q4 2014                  Authorized  Forecasted Costs Incurred
Budget
Construction Costs
The project is currently below budget.
0.3   0.268
Change Order
0.25
Current Quarter   Project Total           Millions  0.2
Dollars in 
Number of COs                                 0.15
Amount of COs    $          $
0.1
0.05
Justification for COs: N/A                                            0   0.003
0
Initial   Change   Spent
Risks                                      Orders
None
Budget Transfers
None


REAL ESTATE

108  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Maritime Industrial Center Built-up Roof
Replacement
Project Status:
Replace the 21,000SF Roof at the   Schedule: Within or ahead
Project:   C800571      MIC Office Building            Budget: On or under
Budget: $1,456,000                         Status Reset: 4/23/2013 .
Phase: Construction                        (Commission Construction Auth.)
Start: 9/30/2012
Schedule Completion: 10/30/2013
Budget/Costs Incurred
Significant Developments
1.6     1.456      1.456
The project is completed. Final closeout is scheduled. This will be     1.4
1.2                         1.074
the last report.                                            Millions  1
0.8
Schedule
0.6
The project is scheduled for completion in Q4 2013               Dollars in  0.4
0.2
0
Budget
Authorized   Forecasted  Costs Incurred
The project is currently on budget.
Change Order                         Construction Costs
Current Quarter   Project Total
1.4    1.3
Number of COs    0          4
1.2
Amount of COs    $0         $48,390                         0.959
Millions   1
0.8
Dollars in 
Justification for COs: N/A this quarter                            0.6
0.4
Risks                                 0.2    0.048
0
None
Initial   Change   Spent
Orders
Budget Transfers
None



REAL ESTATE
Port of Seattle 1Q 2014 Report  109

FIRST QUARTER REPORT, 2014
T91 Lighting Upgrade
Lighting upgrade at Terminal 91      Project Status:
Project: E104765
Schedule:  delayed
Budget: $1,035,000
Budget:   on or under
Phase: Construction                       Status Reset: 3/4/2014
Start: 6/23/2014                                 (Commission Construction Auth.)
Schedule Completion: 9/30/2014
Budget/Costs Incurred
Significant Developments
2
Contracts for light fixtures are in place, coordination drawings and
1.5
modeling is complete and deliveries are scheduled. Minor          1.5
coordination with controls are being completed and construction is     Millions                 1.01795
anticipated to begin the last week of June or July 7th.                1
Dollars in  0.5
Schedule
Complications in coordinating lighting configuration and controls        0
Authorized   Forecasted  Costs Incurred
have delayed delivery dates but we anticipate completion of the
work within the third quarter.
Budget                           Construction Costs
The project is anticipated to complete on budget.                  1.6       1.5
1.4
Change Order                          1.2
Millions         1
1               0.843
Current Quarter   Project Total
0.8
Number of COs    2                            0.6
Amount of COs    ($23,000)     ($23,000)            Dollars in  0.4
0.2
0
Justification for COs: Resulting from coordination of fixture positions
Initial   Change   Spent
and selected fixtures; fewer flood lights will be required and                   Orders
mounting requirements have been simplified. The result is a net
reduction in the materials purchase of approximately -$23,000.
Risks
Because of a later start date, the work must be coordinated around
the cruise schedule and with other tenants as to reduce any impact
associated with the work.
Budget Transfers
None
REAL ESTATE
110  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
FT Net Shed Code Compliance
Project Status:
Project:   E104838      FT Net Sheds 3-11: Improvements   Schedule: Within or ahead
Budget: $2,950,000      required per City of Seattle building  Budget: On or under
Phase: Construction     & fire codes             Status Reset: 6/25/2013
Start: 5/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 6/30/2015
Significant Developments                    Budget/Costs Incurred
Net Shed 9 work is complete and crew began working on Net Shed
3.5
10 improvements. Additional permits have been applied and             2.95    2.95
3
received.
Millions 2.5
2
Schedule                             1.5
Despite additional permit process required by the City of Seattle,      Dollars in  1                0.519
overall construction completion is still scheduled by the end of 2nd      0.5
quarter 2015.                                        0
Authorized   Forecasted  Costs Incurred
Budget
Project budget is on track.                               Construction Costs
Port Self Perform
Change Order
Construction
Current Quarter   Project Total
Number of COs    0          0                Photo
Amount of COs    $0         $0
Justification for COs: n/a
Risks
It is difficult to project the amount of stored materials that needs to be
moved out and moved back since tenant storage habit could vary
significantly. In addition, the amount of work required in each unit is
difficult to assess until stored materials are removed. These would
impact the overall project budget.
Budget Transfers
None

REAL ESTATE
Port of Seattle 1Q 2014 Report  111

FIRST QUARTER REPORT, 2014
P69 Carpet Replacement
Project: E105072      Replace carpet flooring at         Project Status:
Corporate Headquarters Building     Schedule: Within or ahead
Budget: $1,200,000
on the second and third floors.       Budget: On or under
Phase: Construction                       Status Reset: 2/4/2014
Start: 7/7/2014                                 (Commission Construction Auth.)
Schedule Completion: 9/30/2014
Budget/Costs Incurred
Significant Developments
1.4
1.2
Bids have been received and CPO is in the process of Executing the   1.2
Contract.
Millions  1
0.8
Schedule                            0.6
The Project is expected to be completed on time.                Dollars in  0.4
0.2
0.002
Budget                             0
Authorized   Forecasted  Costs Incurred
We are predicting the project to complete within the allotted budget.
Change Order                        Construction Costs
Current Quarter   Project Total
1.6           1.5
Number of COs    0          0
1.4
Amount of COs    $0         $0
1.2
Millions         1
1               0.843
Justification for COs: N/A                                   0.8
0.6
Risks                               Dollars in  0.4
0.2
None at this time                                        0
Initial   Change   Spent
Orders
Budget Transfers
None



REAL ESTATE
112  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Flight Information System (FIMS) II
Procure, develop, and implement a     Project Status:
Project: C101117      FIMS system that includes         Schedule: Within or ahead
Budget: $8,220,000     replacement monitors, an airport     Budget: On or under
Phase:Close Out      resource mgmt. system, and a      Status Reset: 5/28/2012
Start: 5/4/2010         flexible digital signage system        (Commission Construction Auth.)
Schedule Completion:  capable of displaying flight
12/30/2014          information, visual paging, and
notifications.
Budget/Costs Incurred
Significant Developments                     10
8.22       8.22
All major components of the planned implementation are in-use. The     8               7.1
close out process will address small items that remain in-process.     Millions 6
This will be the last report on the project.
4
Schedule                            Dollars in  2
On Schedule
0
Authorized  Forecasted Costs Incurred
Budget
On Budget
Construction Costs
Change Order
2.5     2.33
Current Quarter   Project Total                            1.9
2
Number of COs    0          5
Amount of COs    $0         $395,223             Millions 1.5
1
Justification for COs: none this quarter                         Dollars in             0.39
0.5
0
Risks
Initial      Change      Spent
Orders
No significant risks.
Budget Transfers
None



CORPORATE
Port of Seattle 1Q 2014 Report  113

FIRST QUARTER REPORT, 2014
Maximo Enterprise Implementation
Implement latest version of        Project Status:
Project:   C800003      Maximo, merge Aviation and Real   Schedule: Delayed Schedule
Budget: $3,680,000     Estate applications onto one      Budget: On or under
Phase: Close Out      platform, and add service desk    Status Reset: Click here to
Start: 11/25/2007        module and wireless handheld      enter a date.
Schedule Completion:    capabilities.              (Commission Construction Auth.)
6/30/2014

Budget/Costs Incurred
Significant Developments
Major components of the program delivered, including the           3.8
3.68      3.68
deployment of Service Management software for the ICT Service      3.7
Desk in December 2008, the upgrade and consolidation of Marine     3.6
Maintenance and Aviation Maintenance Maximo systems in         3.5
in Millions                           3.4
September 2010, and mobility enhancements 2013. Interfaces       3.4
between Maximo and Peoplesoft originally part of the scope are no    Dollars 3.3
longer required due to changes in business process.              3.2
Authorized  Forecasted   Costs
Incurred
Schedule
Construction Costs
Project is in closeout.                                    Not Applicable
Budget
On Budget
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Budget Transfers
None

CORPORATE
114  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
ID Badge System Replacement
Project Status:
Project: C800162        Procurement and replacement of   Schedule: Delayed Schedule
Budget: $2,500,000      the Portwide ID Badge system     Budget: On or under
Phase:Implementation    including software, hardware, and   Status Reset: Click here to
Start: 5/1/2012           equipment.                 enter a date.
Schedule Completion: 9/30/2014                   (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Testing is in progress for a July 2014 delivery of the new ID Badge
system.                                         3
2.50       2.50
2.5
Schedule
2
Resource availability has delayed project completion.               Millions 1.5                1.20
1
Budget                            Dollars in
0.5
On Budget
0
Authorized   Forecasted  Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    1          1                Construction Costs
Amount of COs    $108,497     $108,497            Not Applicable
Justification for COs: With an additional module for the new ID
Badge system, we had an opportunity to more seamlessly integrate
the Transportation Worker Identification Card (TWIC) registration
creating a more efficient process for Credential Specialists and
Tenants.
Risks
Resource availability may continue to delay the second phase mobile
deliverables.
Budget Transfers
None


CORPORATE
Port of Seattle 1Q 2014 Report  115

FIRST QUARTER REPORT, 2014
Enterprise Project Cost Management
Project Status:
Project: C800321        Replace the current construction    Schedule: Delayed Schedule
Budget: $1,525,000      costing systems with a common    Budget: On or under
Phase:Implementation    enterprise project cost         Status Reset: Click here to
Start: 4/21/2008          management system.           enter a date.
Schedule Completion: 12/30/2014                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
The first phase deployment has been completed and the software is
1.55    1.525      1.525
in-use by the Project Management Groups. Next phase deliverables
1.5
such as trend logs and cash flows are in test and scheduled for
delivery in 2nd Quarter 2014.                              1.45  Millions                 1.4
1.4
Schedule                            1.35 Dollars in 
Prior Report: Availability of resources is impacting the completion of     1.3
Authorized  Forecasted Costs Incurred
the remaining components. These include features such as cash
flows and trend logs as well as additional interfaces that require
resources currently focused on the Peoplesoft Financials Upgrade
project. We are in the process of procuring additional configuration    Construction Costs
assistance and expect to deliver in phases over the next several     Not Applicable
months.
Budget
None
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Availability of Port resources may delay next phase deliverables.
Budget Transfers
None

CORPORATE
116  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Network Switch Replacement
Project Status:
Project: C800323        Upgrade the Network switch      Schedule: Within or ahead
Budget: $1,500,000      infrastructure hardware and      Budget: On or under
Phase: Design         software                Status Reset: Click here to
Start: 12/15/2013                                enter a date.
Schedule Completion: 3/31/2015                   (Commission Construction Auth.)

Significant Developments
Budget/Costs Incurred
Design and procurement are in progress.
2
Schedule
1.50       1.50
1.5
On schedule.                                    Millions
1
Budget
On budget.                                     Dollars in 0.5
0.03
0
Change Order                            Authorized Forecasted Costs Incurred
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
Port resource availability may impact schedule.
Budget Transfers
None



CORPORATE
Port of Seattle 1Q 2014 Report  117

FIRST QUARTER REPORT, 2014
Time Clock System
Procure and implement a Time      Project Status:
Project: C800387       Clock System to accurately capture   Schedule: Delayed Schedule
Budget: $380,000       and track time and attendance for    Budget: On or under
Phase: Close Out      approximately 230 employees in    Status Reset: Click here to
Start: 6/8/2010          Aviation Security and Airport       enter a date.
Schedule Completion:   Operations organizations.        (Commission Construction Auth.)
4/30/2014
Significant Developments                    Budget/Costs Incurred
The new system has been deployed to all planned organizations.
0.38     0.38
0.4
Schedule                             0.35
0.28
0.3
Project is in closeout.                                      Millions 0.25
0.2
Budget                             0.15
Dollars in   0.1
On budget
0.05
0
Change Order                             Authorized Forecasted Costs
Incurred
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None



CORPORATE
118  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Construction Document Management
Replacement of the Construction     Project Status:
Project: C800521       Document Management System    Schedule: Within or ahead
Budget: $900,000       used by Construction Management   Budget: On or under
Phase: Planning       to accept, review, and distribute    Status Reset: Click here to
Start: 9/10/2013         critical documentation.           enter a date.
Schedule Completion: 3/31/2015                   (Commission Construction Auth.)
Significant Developments
Bid proposals are currently being evaluated.                  Budget/Costs Incurred
Schedule                              1  0.9   0.9
On Schedule                                    0.8
Millions   0.6
Budget
0.4
On Budget                                   Dollars in  0.2
0
Change Order                           0
Authorized Forecasted   Costs
Current Quarter   Project Total                          Incurred
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
Port of Seattle 1Q 2014 Report  119

FIRST QUARTER REPORT, 2014
Access Control Network Refresh
Project Status:
Project: C800558        Upgrade the Access Control      Schedule: Within or ahead
Budget: $1,500,000      Network switch infrastructure     Budget: On or under
Phase: Close Out       hardware and software        Status Reset: Click here to
Start: 3/26/2013                                 enter a date.
Schedule Completion: 3/31/2014                   (Commission Construction Auth.)
Significant Developments
All switch infrastructure has been deployed. This will be the last      Budget/Costs Incurred
report for the project.
1.6
1.5      1.5
Schedule                             1.5
On schedule.                                     Millions 1.4
1.3
Budget                             Dollars in  1.3
On budget.                                       1.2
Authorized Forecasted  Costs
Incurred
Change Order
Current Quarter   Project Total
Construction Costs
Number of COs    0          0
Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Budget Transfers
None



CORPORATE
120  Port of Seattle 1Q 2014 Report

FIRST QUARTER REPORT, 2014
Radio System Upgrade
Project Status:
Project: C800586        Upgrade of the Radio System Core  Schedule: Within or ahead
Budget: $6,750,000      Hardware and Software and      Budget: On or under
Phase: Implementation    Dispatch Consoles           Status Reset: Click here to
Start: 6/9/2013                                   enter a date.
Schedule Completion: 5/31/2014                   (Commission Construction Auth.)
Significant Developments
Testing is in progress for 2nd Quarter deployment.               Budget/Costs Incurred
Schedule                              8
6.75     6.75
7
On Schedule
6
Millions    5
Budget                              4         3.1
3
On Budget                                   Dollars in   2
1
Change Order                            0
Authorized Forecasted   Costs
Current Quarter   Project Total
Incurred
Number of COs    0          0
Amount of COs    $0         $0
Construction Costs
Justification for COs: n/a                                 Not Applicable
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
Port of Seattle 1Q 2014 Report  121

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.