7b report

Item Number:  7b _Report
Meeting Date: November 27, 2012


Commission Staff Brieng
Capital Improvement Projects
Third Quarter Report 2012

This page intentionally left blank









ii  Port of Seattle 3Q 2012 Report

Port of Seattle
Capital Improvement Project Report
Third Quarter 2012
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2012 the Port plans to invest over $319,000,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 3Q 2012 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ...............................................7-8 ..........
C102163................Main Terminal Baggage Screening ....................9-10.........
C102334 ...............Water System Isolation Valve Upgrade ................11 .......... ...............
C102573 ...............Airf eld Pavement Replacement ...........................12 ..........
C800019 ...............Loading Bridge Utilities .........................................13 ........................................ 
C800034 ...............North Expressway Relocation ..............................14 ..........
C800061 ...............Main Terminal South Low Voltage ........................15 ..........
C800105 ...............Airport Owned Gate Infrastructure .......................16 .......... ...............
C800107 ...............C4 UPS System Improvements ............................17 ..........
C800112................Runway 16C/34C Panel/Joint Sealant .................18 ..........
C800147 ...............Concessions Unit Readiness Program ................19 .......... ................. ......................
C800148 ...............GML Arrivals Hall Concessions ...........................20 ..........
C800168 ...............C60-C61 BHS Modif cations ................................21 ..........
C800174................FIS - New Primary Inspection Booths ..................22 ..........
C800203 ...............Common Use Lounge Remodel ...........................23 ..........
C800237 ...............Terminal Escalators Modernization ...................24-25 .......
C800238 ...............Central Plant Pre-Conditioned Air .....................26-27 .......
C800242 ...............Security Checkpoint Cameras..............................28 .......... ...............
C800247 ...............Cargo 2 West Hardstand ......................................29 .......... ...............
C800251 ...............Vertical Conveyance Modernization.....................30 ..........
C800253 ...............Parking System Replacement ..............................31 ..........
C800254 ...............Aircraft RON Parking Post Off ce Site..................32 ..........
C800267 ...............Port Owned Loading Bridges ...............................33 ..........
C800268 ...............Stage 2 Mechanical Energy Implementation .......34 ..........
C800274 ...............8th Floor Weather Proof ng ..................................35 .......... 
C800276 ...............Common Use Equipment Expansion (CUSE) ......36 ..........
C800334 ...............Two new CTE Freight Elevators ...........................37 ..........
C800335 ...............EGSE Electrical Charging Stations ...................38-39 .......
C800374 ...............Claim Device 14 and Lower Inland .......................40 ..........
C800376 ...............South Satellite HVAC, Lights, and Ceiling Repl. ..41 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ...............................42 ..........
C800390 ...............Cargo 6 Enhancements ........................................43 ........................................ 
C800406 ...............RW 16C/34C Reconstruction Design ...................44 ..........
C800412 ...............South Satellite Concessions Project ....................45 ..........
C800414 ...............Access Control Door Additions ............................46 .......... ...................................
C800415 ...............ALCMS Upgrade...................................................47 .......... 
C800417 ...............Lagoon 3 Bird Wires .............................................48 ..........


2  Port of Seattle 3Q 2012 Report

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule Budget
C800420 ...............Additional Air f eld Mitigations at Tyee ..................49 ..........
C800426 ...............FIS Improvement - Short Term .............................50 ..........
C800451 ...............Doug Fox Site Improvement .................................51 ..........
C800455 ...............Concourse D Common Use Environment ............52 ..........
C800459 ...............2011-2013 Roof Replacement Program ...............53 ..........
C800461 ...............IWTP Fiber Installation .........................................54 .......... ...................................
C800466 ...............South Satellite - Additional Gate Lobby ................55 ........................................ 
C800467 ...............PLB Replacement .................................................56 .......... 
C800472 ...............Exterior Gate Improvements ................................57 ..........
C800473 ...............CUSE at Ticket Counters/Gates - AR ..................58 ........................................
C800474 ...............Airport Signage .....................................................59 .......... ..............................
C800475 ...............Miscellaneous Building Improvements - AR.........60 ..........
C800484 ...............Laptop Power In Concourses ...............................61 ..........
C800490 ...............New Window Wall Ticket Zone 1 ..........................62 ..........
C800492 ...............Convert Ticket Zone 3 Flow Thru .........................63 ..........
C800544 ...............NorthSTAR Program.............................................64 .......... 
C800556 ...............NorthSTAR North Satellite Renovations ..............65 ..........
Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................66 ..........
C200042 ...............Highline Community College Noise Insulation .....67 ..........
C200048 ...............Home Insulation Retrof t .......................................68 .......... 
C200093 ...............Single Family Home Sound Insulation .................69 ..........
C800146 ...............RMU/Kiosk Concession Program ........................70 ..........
C800150 ...............Burien Commercial Property Acquisition .............71 ..........
C800154 ...............Tenant Reimbursement ........................................72 .......... 
C800482 ...............Rubber and Paint Removal Equipment ................73 ..........
C800498 ...............Snow Removal Equipment ...................................74 ..........
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800165 ..............Seaport Security Grant Round 7 .........................75 ..........

Port of Seattle 3Q 2012 Report  3

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800183 ...............P91 Fender System Upgrade ...............................76 ..........
C800298 ...............T-91 Watermain Replacement ..............................77 ..........
C800349 ...............T-5 Crane Cable Reels .........................................78 ........................................ 
C800430 ...............T-91 Building, C175 Rood Replacement ..............79 ..........
C800516 ...............SEA P-66 Apron Pile Wrap ..................................80 ..........
C800546 ...............Argo Yard Truck Roadway ....................................81 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ...............82-83 .......
E104324 ................Viaduct Construction Coordination ......................84 ..........
E104362 et al ........Street Vacations T-5/18/105 .................................85 ..........
E104559................T-18 Pile Cap Repair Pilot Project ........................86 ..........
E104610 ................Underdock Inspections .........................................87 .......... 
E104840................T-5 and T-18 Maintenance Dredging ....................88 ..........
Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800137 ...............FT C15 HVAC Improvements ...............................89 ..........
C800187 ...............RE Maintenance Shop Solutions..........................90 ..........
C800313 ...............P69 N Apron Corrosion Control ...........................91 ..........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ....................92 ..........
C800003...............Maximo Enterprise Implementation......................93 .......... ................. ......................
C800162 ...............ID Badge Replacement ........................................94 ..........
C800222 ...............Airline Activity Management .................................95 ..........
C800321 ...............Enterprise Project Cost Management ..................96 .......... ...................................
C800322 ...............Records and Document Management .................97 ............................................ ......................


4  Port of Seattle 3Q 2012 Report

Overall Project    Variance since
Statuslast report
CIP Number  Project Title             Page     Schedule  Budget
C800387 ...............Time Clock System ...............................................98 ........................................  ....................
C800392 ...............PeopleSoft Financial Upgrade ..............................99 ............................................ ......................
C800393 ...............Police Records Management System .................100 .......................................  ....................
C800477 ...............CUSS Kiosk Expansion .......................................101 .......................................  ....................
C800501 ...............Maintenance Planning System ............................102 .........

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Variance Since Last Report













Port of Seattle 3Q 2012 Report  5

THIRD QUARTER REPORT, 2012
3rd Runway Program
Status Snapshot
On Schedule
Project: C000683,       The 3rd Runway Program
On Budget
C001138, C001175,      constructed a new 8,500 foot long
13 Change Orders
C001331, C001751,      runway, connecting taxiways, and
Total Change Orders Amount:
C001760, C100172      related infrastructure.
$90,369.25
Budget: $920,415,659
Phase: Construction                       Budget/Costs Incurred
Start: 05/27/1997
1150
Completion: 12/31/2011
1100
1050
1000  Millions
Significant Developments
950
Pond M Modifications project is complete. Maintenance Building
Dollars in 900                                                                              Demolition project is in contract closeout.                                 850
800
Authorized  Forecasted Costs Incurred
Schedule
The remaining construction work includes RST property acquisition.
Purchase of the RST property occurred in September 2012.
Demolition of existing structures and site stabilization of the property  2012 Contract Const. Costs
is scheduled to occur by the end of the year.
2
Budget                             1.5
The project forecast is within the approved budget and authorization.      1   Millions
0.5
Change Order                          Dollars in 
0
None this quarter                                         InitialChange OrdersSpent
Risks
None                                 Photo
Budget Transfer
To Savings                       $384,956


AIRPORT
6  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Rental Car Facility
Status Snapshot Prior Report
Delayed Schedule 2Q 11
Project:   C100266,     The program will construct a       Under Budget
C102167, C800032     consolidated rental car facility (RCF)  1,637 Change Orders
Budget: $400,311,000   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $13,871,730
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.          Budget/Costs Incurred
Significant Developments                     420
The Consolidated Rental Car Facility officially opened May 17, 2012.     410
The rental car industry representatives continue to work with the Port    Millions 400
on closing post-opening issues. Approximately 60% of open          390
purchase orders have been closed.
Dollars in 380
370
BMF construction is complete and substantial completion was issued
360
on July 13, 2012. ORI construction is complete and work is
Authorized  Forecasted Costs Incurred
continuing on remaining punch list items. MTI construction is
complete and the project is nearly closed out.
Asset plans have been submitted for an initial booking of costs      Construction Costs
through June 30, 2012.
300
250
Schedule
Millions  200
RCF opened May 17, 2012. Each project within the program has
150
now begun closing. Nine-month closing deadline for all projects is
100
mid-February 2013                                 Dollars in  50
0
Budget                                Initial Change Spent
Orders
Customer Facility Charge revenues continue to increase slightly
each month, trending over $2,200,000 above projections. Forecasted
cost to complete the program is $396,000,000, $23,300,000 under    Photo
the approved budget. Savings is anticipated on both ORI and BMF.
Change Order
A total of 87 change orders have been executed this quarter for a net
impact of $13,871,730.


Port of Seattle 3Q 2012 Report  7

Risks
x For RCF: claims resolution; quality issues, and post opening work completion.
x For ORI: claims resolution.
x For BMF: claims resolution.
Budget Transfers
$2,158,400 was drawn down from the budget in recognition of savings realized along with $856,000
removed to cover Expense.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - Cumulative change
order percentage remains at 21.3% with no activity this quarter. There are no outstanding Trends
remaining.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - Two (2) change orders
were executed this quarter for a net credit of $1,813. The overall change order percentage remains
at 3.97%.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - Two (2) change orders were executed this quarter for a net value of $12,973. The
cumulative change order value for this quarter is $2,749,029 (39.2%).
Bus Maintenance Facility - MC-0316730 - Twenty four (24) change orders were executed at a net
total $11,069 for various issues and credits. The cumulative change order value for this quarter is
$240,838 (1.84%).
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification. The current cumulative change order
percentage through this quarter is 4.08% with 59 change orders executed for a net reduction of
$49,378.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - cumulative change order percentage is 19.4%
due primarily to removal of contaminated soils and associated impacts. This work and the final
contract reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  the cumulative change order percentage of
170.5% is the result of changes for additional contractor management and support beyond the extent
of the original scope to validate project costs and support the rental car companies and the Port on
final approval of the project. This work and the final contract reconciliation is complete.

AIRPORT
8  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $218,712,358   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget   4Q 09
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
Significant Developments                     235
The C-1 baggage handling/screening system has been placed into     230
revenue service for the Alaska Air Group. The C-1 Lid Replacement    Millions 225
and Repair work is complete. The only work remaining on this project    220
is the installation of new Direct Digital Controls (DDC) to indicate to     Dollars in 215
boiler room when pumps are off-line.                         210
Authorized   Forecasted  Costs Incurred
Schedule
The project was delayed approximately two years from the original
Construction Costs
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope
200
changes. Turner Construction demobilized on May 31, 2009. The
150
GCCM construction contract with Turner Construction has been
closed. The remaining fire sprinkler and fire proofing work was          100   Millions
completed.
50
Dollars in 
Budget                              0
Initial    Change    Spent
Orders
The project forecast is within the approved budget and authorization.
Change Order                         Photo
665 Change Orders have been issued on this project.
Risks
None
Budget Transfers
None this quarter


Port of Seattle 3Q 2012 Report  9

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated as they were unable to meet the
project schedule requirements. The remaining work was rebid in the fall of 2006. Alaska Airlines
asked that we include the BHS work within the 2-step ticket counter project; which increased the
amount of BHS work in the bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.












AIRPORT
10  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Water System Isolation Valve Upgrade-non AF
Status Snapshot
Delayed Schedule
Project:   C102334      This project replaces isolation     On Budget
Budget: $954,000       valves on the aging water       0 Change Orders
Phase: Construction     distribution system, necessary for   Total Change Orders Amount:
Start: 10/01/2010         isolating portions of the system in    $0
Completion: 12/31/2012   the event of breaks, leaks, or tieins
, in non-airfield (AF) locations.    Budget/Costs Incurred
1.2
Significant Developments                      1
Millions    0.8
The project is currently in construction.
Dollars in     0.6
Schedule                             0.4
0.2
The schedule was extended further to minimize operational impacts,
due to unexpected challenges in shutting off water to locations where     0
Authorized       Forecasted      Costs Incurred
the remaining valves will be replaced.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None
Risks
None identified at this time
Budget Transfers
From C800469 (Water System Isolation Valve - Airfield)  $100,000



AIRPORT

Port of Seattle 3Q 2012 Report  11

THIRD QUARTER REPORT, 2012
Airfield Pavement Replacement
Project:   C102573      The project is intended to be a
Budget: $30,262,035     multi-year pavement replacement   Status Snapshot
Phase: Construction     program to replace distressed     On Schedule
Start: 05/02/2010         pavement and joint seal on the     On Budget
Completion: 12/31/2016   airfield.                7 Change Orders
Total Change Orders Amount:
$413,259
Significant Developments
Port of Seattle Commission approved design authorization for 2013   Budget/Costs Incurred
construction work on July 24, 2012. Design for the 2013
40
construction work is 30% complete.
30
Schedule
Millions 20                                                                         Gary Merlino Construction began work in May 2012. The
construction will be complete by the end of November. The          Dollars in 10
construction work to be completed in 2012 will be the second phase
0
of a multi-year pavement replacement program to be performed from
Authorized  Forecasted Costs Incurred
2011 to 2015.
Budget
2012 Construction Costs
The project forecast is within the approved budget.
12
Change Order
10
Seven change orders were executed this quarter.                Millions  8
6
Risks                                  4
None this quarter.                                      Dollars in   2
0
Budget Transfers                             Initial Change Spent
Orders
C102165 (Aeronautical New Projects)          $159,050



AIRPORT
12  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Loading Bridge Utilities
Project:   C800019   This project will upgrade the South
Satellite Port-owned loading bridges to
Budget: $12,883,000                         Status Snapshot
the same standards, including 400Hz
Phase: Design                            Delayed Schedule
power and potable water. This will
Start: 06/28/2007                                 On Budget
reduce air emissions, improve energy
Completion: 8/29/2014                        0 Change Orders
efficiency and save money for the       Total Change Orders Amount:
airlines.                            $0
Budget/Costs Incurred
Significant Developments
Sole source justification for the 400 Hz motor generators at South       15
Satellite has been approved. The 100% design drawings and
specification will be complete by the end of November 2012. As the     10
400Hz equipment will now be provided by the contractor. Sole         Millions
source justification has been approved.                        5
Dollars in
Schedule                             0
Authorized  Forecasted Costs Incurred
After the design completion in November the current schedule has 
the construction starting in April of 2013 and being completed in
August 2014. The project is delayed by six months due to the need
for a sole source justification; designer of record contract           Construction Costs
amendment; and schedule delay in presentation to the Commission.  Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Airport Operations at certain gates could be impacted during the
construction phase of the project. The Port's power centers might
need to be upgraded to support the Pre-Conditioned Air, Electrical
Ground Support Equipment, and Loading Bridge Utilities projects.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 3Q 2012 Report  13

THIRD QUARTER REPORT, 2012
North Expressway Relocation
Project:   C800034
The project is a collaboration       Status Snapshot  Prior Report
Budget: $110,347,700    between the Port and Sound     Delayed Schedule 2Q 11
Phase: Construction     Transit. It reconstructs the North   On Budget
Start: 07/27/2004         Airport Expressway and brought    225 Change Orders
Completion: 07/31/2012   light rail to the Airport.         Total Change Orders Amount:
$8,314,360
Significant Developments
Budget/Costs Incurred
The work in the main contract for reconstruction of the North Airport
Expressway and light rail transit components is complete. The        115
intelligent transportation management system is complete. A final
110
contract to complete paving, landscaping, the north entry art          Millions
features, and other miscellaneous work is complete except for punch    105
list work and the first year plant establishment.
Dollars in 100
Schedule
95
The main contract reached substantial completion in August 2008         Authorized Forecasted Costs Incurred
and plant establishment was completed in December 2010. A
contract for final paving, landscaping, and reclamation is underway 
and is complete except for replacement of some trees as part of the   Construction Costs
first year plant establishment period.
120
Budget                             100
Millions 80
The project forecast is within the approved budget and authorization.
60
Change Order                          40
Dollars in  20
Thirteen change orders were issued this quarter.
0
Initial    Change Order    Spent
Risks
None identified at this time.
Photo
Budget Transfers
None this quarter


AIRPORT
14  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Main Terminal South Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
0 Change Orders
Start: 06/28/2007      equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD    Main Terminal.
$0
Significant Developments
Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
conditions and building codes, the design phase changed from 100%    2.5
to 90% complete. A new Project Notebook is under development to
2
address scope of work, schedule, and budget and will be presented    Millions 1.5
to the Investment Committee. A Service Directive has been executed
with the Design Consultant and they have mobilized to start field        1
investigations and coordinate the design with other underway or       Dollars in 0.5
already completed projects in this area of the Main Terminal.
0
Consultant's work relates to specialized sections of Project              Authorized  Forecasted Costs Incurred
Notebook.
Schedule                           Construction Costs
The project was reactivated and is in the process of determining the   Not Applicable
scope of work, schedule and final design budget.
Photo
Budget
The project budget is being evaluated based on delays and scope
changes.
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area is a 24/7/365 operation. Sequencing of this work
is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
None this quarter.
AIRPORT
Port of Seattle 3Q 2012 Report  15

THIRD QUARTER REPORT, 2012
Airport Owned Gate Infrastructure
This project purchases and        Status Snapshot
Project:   C800105
replaces passenger loading bridges  Delayed Schedule
Budget: $6,000,000
(PLB) at gates throughout the      On Budget
Phase: Construction                        0 Change Orders
Start: 07/24/2007         airport. The project is being
performed in phases.           Total Change Orders Amount:
Completion: 06/30/2012                       $0
Significant Developments                    Budget/Costs Incurred
On April 24, 2012, the Port of Seattle Commission authorized Port      6.2
Construction Services (PCS) to refurbish the PLB removed from        6
Gate S10 and install it in place of the existing Delta Air Lines owned    Millions 5.8
PLB at Gate S8. However, the PLB at S8 suffered a catastrophic      5.6
failure in late June 2012 and was out of service for 9 days. The Port    5.4
approved the diversion of one of the new PLBs manufactured for the    Dollars in 5.2
Concourse D (under project C800467) to replace the existing bridge     5
Authorized  Forecasted Costs Incurred
at S8. The old S10 bridge will still be refurbished but will now be
provided to the Concourse D project in place of the new bridge
diverted to S8.
Construction Costs
Schedule                           Not Applicable
The project was delayed for six months due to the failure of bridge
S8. The new bridge at D3 was diverted to S8, and the bridge at S10
needs to be refurbished and placed at D3.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT

16  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
C4 UPS System Improvements
Project:   C800107    Project will replace existing          Status Snapshot Prior Report
Budget: $2,336,000   Uninterruptible Power Supply (UPS)    Delayed Schedule 1Q 09
Phase: Construction  System, including batteries, with a new  On Budget
Start: 06/28/2007      new system located in the Airport      0 Change Orders
Completion: TBD     Combined Communications and      Total Change Orders Amount:
Command Center (C4).           $0
Significant Developments                    Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
2.5
conditions and building codes, the design phase changed from 100%
to 90% complete. A new Project Notebook is under development to      2
address scope of work, schedule, and budget and will be presented    Millions 1.5
to the Investment Committee. A Service Directive is in the review        1
process and expect Consultant to approve mid third quarter.         Dollars in 0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
The project was reactivated and is in the process of determining the
scope of work, schedule and final design budget.
Construction Costs
Budget
Not Applicable
The project budget is being evaluated based on delays and scope
changes.                                    Photo
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as 
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 3Q 2012 Report  17

THIRD QUARTER REPORT, 2012
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot
The scope of work will remove and   On Schedule
Project:   C800112      replace the pavement and joint seal  On Budget
in areas on Runway 16C-34C.
Budget: $4,161,623                         2 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 02/26/2008                                 $232,732
Completion: 09/01/2012
Budget/Costs Incurred
Significant Developments
6
Bid opening was on March 8, 2012. Gary Merlino Construction is the     5
low bidder. The intent of this contract is to coordinate this work with      4
an apron panel replacement project, an airline realignment project,     Millions
3
and a fuel hydrant installation project all with similar work and timing.
2
Dollars in   1
Schedule
0
The overall construction contract started in May 2012 and the            Authorized  Forecasted Costs Incurred
replacement of runway panels is complete.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
80
Change Order
60
Two change orders were issued this quarter.                   Millions
40
Risks
Dollars in   20
No risks have been identified at this time.
0
Initial   Change   Spent
Budget Transfers                                Orders
None this quarter
Photo


AIRPORT
18  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Concessions Unit Readiness Project
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Close Out      previously vacated or slated to be   Under Budget
Start: 08/26/2008         vacated to Port standards for use    0 Change Orders
Completion: 06/30/2013   as specialty concession space.    Total Change Orders Amount:
$0
Significant Developments
Construction on this project was completed on August 31, 2012. The  Budget/Costs Incurred
project is currently in close out.
1.5
Schedule
The project is complete.                                  Millions 1
Dollars in 
0.5
Budget
The project forecast is within the approved budget and authorization.     0
Savings of approximately $1,500,000 will be returned.                 Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2012 Report  19

THIRD QUARTER REPORT, 2012
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot  Prior Report
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule 1Q 11
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,000
project includes installing three      0 Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      $0
Completion: 07/01/2012   approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
1.2
The design for utilities was previously completed in 2009 but put on      1
hold due to market conditions. Plans for the new food-beverage       Millions 0.8
concession will be reviewed by the Concessions group for viability      0.6
via a cost analysis to be performed later in 2012.                  0.4
Dollars in 0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
As previously reported, the project schedule was delayed due to the
pending decision by the Business Development Group to proceed
with the concessionaire.
Construction Costs
Budget                            Not applicable
The project forecast is within the approved budget and authorization.  Photo
Change Order
None
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter


AIRPORT
20  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
C60 - C61 BHS Modifications
Project:   C800168      The work planned under this      Status Snapshot
Budget: $10,969,000     project represents a critical      On Schedule
Phase: Design        component in providing improved   On Budget
Start: 06/01/2012         operational baggage in-line       0 Change Orders
Completion: 04/30/2014   screening at the south end of the   Total Change Orders Amount:
Airport and provide more baggage   $0
make-up capacity for airlines.
Budget/Costs Incurred
12
Significant Developments
10
The Port of Seattle Commission authorized design funding for the       8
project. The project team is currently working with the design
Millions
6
consultant to start design work.
4
Dollars in   2
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 3Q 2012 Report  21

THIRD QUARTER REPORT, 2012
Federal Inspection Services - New Primary
Inspection Booths
This project will replace existing     Status Snapshot  Prior Report
Project:   C800174      primary inspection booths for      Delayed Schedule 2Q 11
Customs and Border Protection in   On Budget
Budget: $2,000,000
the International Arrivals Federal    0 Change Orders
Phase: Construction     Inspection Services (FIS) facility in  Total Change Orders Amount:
Start: 07/27/2010         the South Satellite.             $0
Completion: 09/08/2011
Budget/Costs Incurred
Significant Developments
Defective signs are being replaced by the signage vendor.           2.5
2
Schedule                            Millions 1.5
The project is substantially complete. The current schedule for
1
completion of the replacement signs is now the end of the fourth       Dollars in 0.5
quarter 2012.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable
None
Risks                               Photo
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

22  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Common Use Lounge Remodel
Status Snapshot
On Schedule
Project:   C800203      This project will relocate the Port's   On Budget
Budget: $1,061,000      common-use lounge from the     9 Change Orders
Phase: Close Out      mezzanine level to the departure   Total Change Orders Amount:
Start: 03/01/2011         level of the South Satellite.        $32,782
Completion: 02/28/2012   Improvements consist of new
finishes, new furnishings and other  Budget/Costs Incurred
minor cosmetic improvements.
1.065
Significant Developments                     1.06
Millions
Project is in closeout awaiting asbuilts.                         1.055
Schedule                            1.05 Dollars in 
Construction was completed in February 2012 and the lounge       1.045
opened on March 1, 2012.                                Authorized Forecasted Costs Incurred
Budget
The current project forecast is within the approved budget and       Construction Costs
authorization.
0.5
Change Order
None this quarter
Risks
Millions
Project is forecast to be completed within the current budget, but
without much remaining. If more soft costs hit the project than        Dollars in  0
Initial    Change Order    Spent
anticipated, the project could run over budget.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 3Q 2012 Report  23

THIRD QUARTER REPORT, 2012
Terminal Escalators Modernization
Status Snapshot
On Schedule
On Budget
Project:   C800237      This project will replace 42        93 Change Orders
Budget: $35,637,293     escalators in the Main Terminal,    Total Change Orders Amount:
Concourse B, and South Satellite.    $5,412,488
Phase: Construction
In addition, two new escalators will
Start: 11/02/2007
be installed at the South Satellite.
Completion: 07/01/2013                       Budget/Costs Incurred
60
Significant Developments
50
Four new escalators at the South Satellite and in the Main Terminal    Millions 40
were placed in service this quarter, for a total of 30. Replacement of     30
eight escalators in the Main Terminal and two in the South Satellite     20
are expected to be in service in the fourth quarter of 2012.           Dollars in  10
Replacement of the remaining South Satellite escalators will
0
continue in multiple phases through second quarter of 2013.            Authorized Forecasted   Costs
Incurred
Schedule
The project is currently on schedule.                        Construction Costs
20
Budget
The project forecast is within the approved budget and authorization.    15
Millions
10
Change Order
The most significant change orders this quarter were required to      Dollars in  5
address rephasing of the Main Terminal Satellite Transit System
0
Station escalators and varying site conditions at the South Satellite.         Initial  Change Order  Spent
Risks
None identified at this time.
Budget Transfers
To C102165 (Aeronautical New Projects)       $2,151,966



24  Port of Seattle 3Q 2012 Report

Cost of Construction Growth
Circumstance contributing to cost growth: Revisions to hoisting plan at Concourse B due to
unforeseen utilities, additional staffing for contractor due to higher than anticipated night work and
scope changes, addition of moisture sensors in escalator pits as required by state inspector,
additional asbestos abatement due to unforeseen conditions, and state inspector requirement to
construct hard barriers to protect the public when on escalators adjacent to units under construction.
Measures taken to respond to these factors: Additional site investigations in advance of construction
to anticipate and mitigate to the extent possible unforeseen conditions. For regulatory changes,
measures are being applied in future construction phases. And, evaluation of means to reduce
additional staff support due to night work and other staffing requirements.










AIRPORT
Port of Seattle 3Q 2012 Report  25

THIRD QUARTER REPORT, 2012
Central Plant Pre-Conditioned Air
Status Snapshot Prior Report
Delayed Schedule 3Q 09
Project:   C800238     This project will provide a centralized  On Budget
Budget: $45,535,000    pre-conditioned air (PC-Air) plant    115 Change Orders
Phase: Construction    (PCAP), associated heating and    Total Change Orders Amount:
Start: 06/15/2009       cooling piping systems, and jet bridge  $4,258,819
Completion: 12/10/2012  terminal air handling units to serve
airplanes with heating and cooling
while at the gates.               Budget/Costs Incurred
Significant Developments                     50
The contractor has finished installation of major equipment and        40
piping in the PCAP. PC-Air equipment is installed at 53 of 73 total      Millions 30
gates. Pipe and electrical conduit installation continue at the
20
Concourse C, Concourse D and North Satellite.
Dollars in  10
Schedule                             0
Authorized  Forecasted Costs Incurred
The original contract completion date was December 11, 2012. One
time extension of 37 days was approved. The contract completion
date is in January 2013.
Construction Costs
Budget
30
Negotiations with the contractor on potential change orders and
25
claims risk are in process. As negotiations proceed, any potential
20
budget issues will be identified. Current project forecast including      Millions
15
open claims exceeds approved budget and authorization by
10
approximately 10%. Commission approved additional funding of      Dollars in   5
$2,000,000 in the third quarter. Staff will return to Commission for
0
additional authorization to execute changes orders and funding.
Initial   Change   Spent
Orders
Change Order
Twenty change orders were issued this quarter, the largest change
orders were issued for piping and electrical site conflicts on the
concourse and at the gates.
Risks
There is budget risk based on the dollar amount of open potential
change orders and claims. There is schedule risk based as no
approved schedule is available.


26  Port of Seattle 3Q 2012 Report

Budget Transfers
None this quarter
Cost of Construction Growth
Cost growth is still occuring due to shortcomings in the bid documents. Current cost of executed
Change Orders is 21.5% of the base contract price. The trended cost growth projection is currently
29% over bid price. Approximately 15% are related to error and/or ommissions (owner or designer),
9% are currently in some form of dispute. The remainder of the cost growth are due to site conditions,
discretionary tenant requested or scope changes and regulatory requirements respectively. The
current projections do not include any cost trending for potential claims due to late project completion
due to owner caused delay.










AIRPORT
Port of Seattle 3Q 2012 Report  27

THIRD QUARTER REPORT, 2012
Security Checkpoint Cameras
Project:   C800242      This project has installed new      Status Snapshot
Budget: $500,000       cameras to view passenger      Delayed Schedule
Phase: Construction     screening processes at passenger  On Budget
Start: 07/17/2011         security checkpoints.           0 Change Orders
Completion: 09/31/2012                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
0.55
Installation is complete at Checkpoints #4, #2 and #3 & #5.
0.5
Millions
Schedule
0.45
The project was completed in September 2012, after a 3 month
delay, due to TSA installation of the new equipment and ordering of     Dollars in 0.4
parts.                                                0.35
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None at this time



AIRPORT

28  Port of Seattle 3Q 2012 Report

THIRDD QUARTER RREPORT, 2012
Cargo 2 WWest Carggo Hardstand
Prooject:  C800247C          This project wwill enlarge the       Statuss Snapshott
Buddget: $11,830,000     weestern cargoo hardstandd in the    Delayeed Schedulee
Phaase: Desiggn        Caargo 2 area, it includess buyout of  On Budget
Start: 09/25/22012         twoo cargo buiildings and tenant     0 Channge Orderss
Commpletion: 12/31/20114   relocations; reelocation off FAA     Total CChange Ordders Amounnt:
antenna, secuurity gate, aand guard    $0
shaack; and installation oof 400Hz in--
groound powerr.              Budgett/Costs Inccurred
15
Significant DDevelopmments
On SSeptember 25, 2012, Port of Seaattle Commission apprroved
10
desiign authorizzation for thhis project.                           Millions
5
Schhedule                            Dollars in 
Leasse terminattion and design underwway. FAA aantenna relocation
0
agreeement is too be compleeted by thee end of 20112. Propossed buildingg       Authorized F o recasted Costs I n curred
acquuisition is scheduled foor the fall of 2013 with the tenantt relocated
by thhe end of thhat year. PProposed coonstruction would be inn the
summmer of 2014. A negattive Majority-In-Interesst (MII) votee resulted
in a two month delay to thhe project coompletion ddate.             Construuction Cossts
Not Appplicable
Buddget
The project foreecast is witthin approveed budget aand authoriization.     Photo
Chaange Ordder
Nonne
Rissks
Nonne identifiedd at this timee.
Buddget Trannsfers
Nonne.


AIRRPORT
Port of Seattle 3Q 2012 Report  29

THIRD QUARTER REPORT, 2012
Vertical Conveyance Modernization Program -
Status Snapshot Prior Report
Aeronautical                        Delayed Schedule 4Q 11
Perform modernization on 8       Forecast Overrun  2Q 12
Project:   C800251      elevators: SSAF, MT-2, MT-6, MT-   0 Change Orders
7, C-4, NSCF & 2 new elevators at   Total Change Orders Amount:
Budget: $9,773,150
S. Satelite, plus install cooling       $0
Phase: Design        packages on 11 existing hydraulic
Start: 10/25/2011         elevators throughout Main
Completion: 12/31/2014   Terminal.
Budget/Costs Incurred
Significant Developments
Phasing of the program has shown a critical link between            12
construction of two new elevators at South Satellite, which must be      10
completed prior to modernization efforts on SSB and SSC elevators.     8
Service Directives were executed for design of Phase I and for pre-
Millions  6
design of two new elevators at South Satellite. Installation of two new
4
elevators moved to Phase I, and elevators SSB, SSC & C4 moved to   Dollars in 2
Phase II.
0
Authorized  Forecasted Costs Incurred
Schedule
The project is scheduled to begin design in the second quarter of
2012; construction is scheduled to begin in the second quarter of     Construction Costs
2013, with construction completion in the fourth quarter of 2014.     Not Applicable
Budget
The project has been revised following Investment Committee (IC)
approval of revision of specific elevators in Phase I & Phase II. IC
approved revised scope and budget. Currently scheduled to request
additional design funds to include two new elevators at November 6,
2012 Commission Meeting. Authorization for construction funding
and authority to advertise for construction will be requested when the
design and bid documents are completed.
Change Order
None
Risks
Delays in siting two new elevators for South Satellite, will require resiting
of TSA passenger checkpoint at SSAT.
Budget Transfers
None this quarter
30  Port of Seattle 3Q 2012 ReportAIRPORT

THIRD QUARTER REPORT, 2012
Parking System Replacement
Status Snapshot Prior Report
Project:   C800253      This project replaces the current    Delayed Schedule 2Q 12
Budget: $6,777,000      Parking Revenue Control System,   On Budget
Phase: Construction     which manages parking access    4 Change Orders
Start: 04/06/2010         and revenue collection in the      Total Change Orders Amount:
Completion: 08/31/2012   Airport's Main Parking Garage.    $128,919
Budget/Costs Incurred
Significant Developments
Scheidt & Bachmann's (S&B) completed installation of the physical      12
components of the system. Kimley Horn performed Lane           10
Acceptance Tests (LAT) on the installed components. Currently       Millions 8
working to resolve reporting issues associated with system            6
development and transition to final testing.                       4
Dollars in   2
Schedule                             0
Authorized  Forecasted Costs Incurred
Several issues during the initial contracting and development phases
of the project caused schedule delays.
Budget                            Construction Costs
None this quarter
The project forecast is within the approved budget and authorization.
Photo
Change Order
Two change orders were issued this quarter for $85,049.
Risks
This project schedule continues to be aggressive.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 3Q 2012 Report  31

THIRD QUARTER REPORT, 2012
Aircraft RON Parking USPS Site
Status Snapshot Prior Report
Delayed Schedule     1Q 11
Project: C800254        This project will prepare the site for
On Budget
Budget: $45,906,000     the construction of hardstands for
4Change Orders
Phase: Closeout       use as Remain Overnight (RON)
Total Change Orders Amount:
Start: 08/26/2008        parking of aircraft at the Cargo 5
-$150,211
area.
Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments
50
Demolition of the USPS building is complete and the project is in
40
contract closeout.
Millions 30
Schedule                             20
The Port of Seattle Commission approved the design authorization     Dollars in  10
of Cargo 5 Hardstand on March 27, 2012. With the design           0
authorization of Cargo 2 and 6 approved by the Port of Seattle           Authorized  Forecasted Costs Incurred
Commission on September 25, 2012, construction of a permanent
hardstand is scheduled to begin the second quarter of 2014.
2012 Contract Const. Costs
Budget
1
The project forecast is within the approved budget.
0.8
Change Order                          Millions 0.6
0.4
None this quarter.                                       0.2
Dollars in    0
Risks                                0.2 Initial Change Spent
Orders
0.4
None identified at this time.
Budget Transfers
None this quarter.                                    Photo



AIRPORT
32  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Port-Owned Loading Bridge Renewal &       Status Snapshot
Replacement                     On Schedule
On Budget
Project:   C800267      This project will allow the Airport to   0 Change Orders
replace or refurbish Port-owned     Total Change Orders Amount:
Budget: $2,405,000
Passenger Loading Bridges (PLBs)  $0
Phase: Design        that have reached the end of their
Start: 02/28/2012         service life.
Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments                      3
This project was approved by the Commission in February 2012 and    2.5
originally included replacement of the PLB at N3 and refurbishment     Millions 2
of the PLBs at S3, S4 & S12. Removal of N3 from this scope and      1.5
replacement of S3 (instead of refurbishment) was approved by the      1
Dollars in 
Commission in June 2012. In addition, the fixed walkway at S3 will     0.5
be replaced and the fixed walkway at S12 will be refurbished. No       0
Authorized  Forecasted Costs Incurred
increase in funding was required as a result of these changes. S3
will be completed in February 2013, followed by S12 in April and S4
in June.
Construction Costs
Schedule                           Not Applicable
The project is currently on schedule.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 3Q 2012 Report  33

THIRD QUARTER REPORT, 2012
Stage 2 Mechanical Energy Implementation
Status Snapshot Prior Report
Delayed Schedule 1Q 12
Project:   C800268      This project will improve the energy  On Budget
Budget: $3,182,000.00    performance of the mechanical    1 Change Orders
Phase: Planning       infrastructure systems at the     Total Change Orders Amount:
Start: 10/01/2011         Airport.                    $8,235.09
Completion: 03/25/2013
Budget/Costs Incurred
3
Significant Developments                     2.5
2
The contract documents have been finalized. University Mechanical    Millions
1.5
Contractors (UMC) will submit 60% design in October 2012.
1
Dollars in 
Schedule                             0.5
0
The design schedule was delayed by three months during the           Authorized Forecasted Costs Incurred
contract document review, as previously reported.
Budget
Construction Costs
The forecast is within the approved budget and authorization.
3
Change Order                           2.5
A Change Order was written to authorize expidited fees for           Millions  2
equipment and systems needed for the Delta Ticket Counter project.     1.5
1
Risks                                Dollars in  0.5
None identified at this time.                                    0
Initial   Change   Spent
Orders
Budget Transfers
None this quarter




AIRPORT
34  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
8th Floor Weatherproofing
Status Snapshot Prior Report
Delayed Schedule 1Q 12
Project:   C800274      This project includes removal and   On Budget
Budget: $10,050,000     replacement of the floor covering   0 Change Orders
Phase: Construction     system on the 8th floor of the STIA  Total Change Orders Amount:
Start: 03/23/2010         parking garage and repair or       $0
Completion: 12/31/2013   replacement of expansion joints
and flashings.
Budget/Costs Incurred
Significant Developments                     15
The Port's contractor, PCL Construction completed construction on
Sections D and E of the garage. The Port has requested a two year    Millions 10
construction schedule, which would extend the completion to the end
of 2013.                                            5
Dollars in 
Schedule                             0
Authorized  Forecasted Costs Incurred
The current schedule is for project completion at the end of 2013.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
8
Change Order
6
No change orders were issued this quarter.                    Millions
4
Risks
2
This is a weather-dependent project.                         Dollars in 
0
Budget Transfers                             Initial  Change Order  Spent
None this quarter
Photo



AIRPORT
Port of Seattle 3Q 2012 Report  35

THIRD QUARTER REPORT, 2012
Common Use Equipment Expansion (CUSE)
Project:   C800276      This project installs flexible       Status Snapshot
Budget: $2,581,000      passenger processing         On Schedule
Phase: Close Out      infrastructure and equipment at the  On Budget
Start: 09/01/2009         airline gates at some South       0 Change Orders
Completion: 09/30/2012   Satellite gates.            Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
3
The contractor completed work on schedule at the end of August.
2.5
Project close out is in progress.                             Millions  2
Dollars in                                                                                                  Schedule                                                                                     1.5
1
The project is in close out.
0.5
Budget                              0
Authorized       Forecasted      Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None
0.7
Risks                                 0.6
Millions    0.5
None identified at this time
0.4
Dollars in 
0.3
Budget Transfers                          0.2
None this quarter.                                       0.1
0
Initial        Change Orders        Spent




AIRPORT
36  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Two New CTE Freight Elevators
Status Snapshot Prior Report
Delayed Schedule 2Q 12
Project:   C800334      Provide two new freight elevators   On Budget
Budget: $8,318,000      to support concession operations in  0 Change Orders
Phase: Design        the Central Terminal/Pacific      Total Change Orders Amount:
Start: 08/05/2011         Marketplace.                $0
Completion: 07/31/2014
Budget/Costs Incurred
10
Significant Developments
8
The project design commenced third quarter 2011. Currently 100%     Millions 6
design is complete. Interferences with ongoing Pre-Conditioned Air
4
Project and Alaska Air Group (AAG) relocation program caused
scoping changes and redesign efforts.                       Dollars in  2
0
Schedule                               Authorized Forecasted Costs Incurred
Construction is anticipated to commence in fourth quarter of 2012.
As previously reported, the project is anticipating a one year delay
due to scope changes included in the redesign efforts, and delays in   Construction Costs
reviews.                                         Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested at the October 23, 2012 Commission Meeting.
Change Order
None
Risks
There is a potential risk due to unknown conditions where the freight
elevator foundations will be constructed, i.e., outside of the Central
Terminal building envelope. Installation and relocation of grease
interceptors will require significant coordination during construction
with Horizon Air and their current use of the site for their ground
service equipment.
Budget Transfers
From C800152 (Non-Aeronautical New Projects)   $1,654,000

AIRPORT
Port of Seattle 3Q 2012 Report  37

THIRD QUARTER REPORT, 2012
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations                Status Snapshot Prior Report
Delayed Schedule 1Q 12
On Budget
Airport-wide electrical charging     0 Change Orders
Project:   C800335      system for electrical ground       Total Change Orders Amount:
Budget: $30,198,000     support equipment (EGSE) at the   $0
Phase: Design        Concourses and the North and
Start: 10/26/2010         South Satellites.
Completion: 09/30/2014
Significant Developments
Budget/Costs Incurred
Design and construction is split into three parts: 1) Installation of 40
demonstration charge stations on Concourse C2 for Horizon Airlines
and this phase is being finalized by PCS with Commissioning          35
scheduled for mid October 2012; 2) Phase 1 includes balance of       30
Concourse C charge stations, Concourse D and North Satellite -      Millions  25
Dollars in 
20
Service Directive now executed and 100% IFC design to be
15
completed on October 22, 2012. Commission approval to advertise
10
on November 1, 2012; secure funds to construct Phase 1 and
5
purchase Phase 2 charger is scheduled for October 23, 2012; and 3)     0
Authorized       Forecasted      Costs Incurred
Phase 2 includes Concourse A, Concourse B and South Satellite -
Service Directive is executed and design is progressing.
Schedule                           Construction Costs
Demonstration charge station construction phase completed end of   Not Applicable
September 2012 with Commissioning by mid October 2012; Phase 1
Construction completion scheduled for September 30, 2013; Phase 2
construction scheduled for completion by end of 2014.
Budget
The project forecast is within the approved budget. Authorization for
the construction funding and authority to advertise for construction
will be requested when the design and bid documents are
completed.
Change Order
None


38  Port of Seattle 3Q 2012 Report

Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may impact project implementation and completion.
Budget Transfers
None this quarter.











AIRPORT
Port of Seattle 3Q 2012 Report  39

THIRD QUARTER REPORT, 2012
Claim Device 14 & Lower Inbound
Project:   C800374      This project will replace the slope-   Status Snapshot
Budget: $3,900,000      plate bag claim device 14 and     On Schedule
Phase: Construction     associated controls, in addition to   On Budget
Start: 04/01/2011         removing the lower feed conveyor   0 Change Orders
Completion: 05/31/2013   and replacing it with a new      Total Change Orders Amount:
overhead feed.               $0
Budget/Costs Incurred
Significant Developments
5
The major construction contract was bid and awarded to MD Moore
4
Company. The contractor is on site and working. Bag claim 14 will     Millions 3
be out of service until Thanksgiving.
2
Schedule                            Dollars in  1
The project is currently on schedule.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
1.2
None
1
Risks                                Millions 0.8
0.6
None identified at this time.                                   0.4
Dollars in   0.2
Budget Transfers                           0
None this quarter                                          Initial  Change  Spent
Orders



AIRPORT

40  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
South Satellite HVAC, Lights, and Ceiling
Status Snapshot
Replacement                     On Schedule
This project will replace the Heating  On Budget
Project:   C800376      Ventilation, lighting and ceiling     0 Change Orders
systems in the South Satellite.      Total Change Orders Amount:
Budget: $6,500,000
$0
Phase: Design
Start: 7/24/2012
Completion: 07/31/2016                       Budget/Costs Incurred
40
Significant Developments
30
Commission approved funding for design. A Service Directive to the   Millions
design firm of CDI Engineers was issued for the design. They         20
started work in September. Design completion is expected in the first
quarter of 2014.                                       Dollars in  10
0
Schedule                               Authorized Forecasted Costs Incurred
The project is currently on schedule.
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 3Q 2012 Report  41

THIRD QUARTER REPORT, 2012
Baggage Handling System (C22-C1, MK1, and
Status Snapshot
TC3)                          On Schedule
This project will replace the ticket    On Budget
Project:   C800382      counter (TC3) conveyors and      4 Change Orders
declines, reroute the conveyors of   Total Change Orders Amount:
Budget: $4,750,000
the C-22 system and connect it to   $45,597.00
Phase: Construction     the C-1 screening system, replace
Start: 03/01/2011         the existing makeup (MK1) device,  Budget/Costs Incurred
Completion: 05/31/2013   and install a new odd size baggage
6
system.
5
Millions  4
Significant Developments                     3
2
MD Moore Company is installing the conveyor and the new makeup    Dollars in  1
unit construction is currently ongoing. All conveyor demolition has
0
been completed.                                     Authorized Forecasted  Costs
Incurred
Schedule
The project is currently on schedule.                        Construction Costs
Budget                              2
The project forecast is within the approved budget and authorization.     1.5
Millions
1
Change Order
There are currently four change orders in process.                Dollars in  0.5
0
Risks                                   Initial Change Spent
Orders
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
42  Port of Seattle 3Q 2012 Report

THIRDD QUARTER RREPORT, 2012
Cargo 6 Ennhancemments
Prooject:  C800390C          This project wwill enlarge the Cargo   Statuss Snapshott
Buddget: $6,4428,000     6 ooff-gate harrdstand to aallow     Delayeed Schedulee
Phaase: Desiggn        simmultaneous nose-loadiing of wide--  On Budget
Start: 09/25/22012         body freight aaircraft as wwell as      0 Channge Orderss
Commpletion: 09/30/20114   proovide fuel hhydrant andd ground   Total CChange Ordders Amounnt:
power capabiilities.              $0
Budgett/Costs Inccurred
8
Significant DDevelopmments
On SSeptember 25, 2012, Port of Seaattle Commission apprroved        6
desiign authorizzation for thhis project.
4
Millions
Schhedule                            Dollars in  2
Design is curreently underwway. The cconstructionn of enhanccements
0
will ttake place in the summmer of 20144. A negatiive Majorityy-In-            Authorized  F o recasted Costs I n curred
Interrest (MII) voote resultedd in a one mmonth projeect delay.
Buddget                           Construuction Cossts
The project foreecast is witthin the appproved budgget and autthorization.  Not Appplicable
Chaange Ordder                         Photo
Nonne this quarter.
Rissks
Nonne identifiedd at this timee.
Buddget Trannsfers
Nonne this quarter.



AIRRPORT
Port of Seattle 3Q 2012 Report  43

THIRD QUARTER REPORT, 2012
RW16C/34C Reconstruction Design
Status Snapshot
On Schedule
Project:   C800406      This project will produce the 60%   On Budget
Budget: $669,000       design for the runway 16C/34C    0 Change Orders
Phase: Design        reconstruction. The design will    Total Change Orders Amount:
Start: 05/04/2010         include utilities, runway status      $0
Completion: TBD       lights, and other scope items
related to the project.            Budget/Costs Incurred
Significant Developments                     0.8
The 60% design was issued in December 2010. Incorporation of       0.6
comments on the 60% design work has been completed.          Millions
0.4
Schedule                            Dollars in 0.2
Staff will return to Commission for authorization of the remaining
0
design funds in late 2014 or early 2015. The forecast will be             Authorized  Forecasted Costs Incurred
reassessed when staff returns to the Commission for authorization of
the final design funds.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
44  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
South Satellite Concessions Project
Status Snapshot Prior Report
Delayed Schedule 3Q 11
Project:   C800412      This project will demolish and      On Budget
Budget: $2,227,400      relocate the existing duty free shop,  0 Change Orders
Phase: Construction     electric/communications to support  Total Change Orders Amount:
Start: 01/01/2011         a temporary duty free location, and   $0
Completion: 03/31/2013   construct a new food and beverage
shell space in the South Satellite at
Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                     2.5
2
The project is currently in phase one of demolishing the space. The
anticipated turn over date for the temporary seating area is           Millions 1.5
November 2012.                                 1
Dollars in 0.5
Schedule
0
As previously reported, the design concept alternatives required          Authorized  Forecasted Costs Incurred
more extensive review than anticipated. The new concept allows the
existing duty free to remain operational during construction, but
requires a longer construction period.                       Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
This project schedule is tied closely to the Duty Free Request for
Proposal.
Budget Transfers
From C800152 (Non-Aeronautical New Projects)   $207,200


AIRPORT
Port of Seattle 3Q 2012 Report  45

THIRD QUARTER REPORT, 2012
Access Control Door Additions
Project:   C800414      This project will provide biometric   Status Snapshot
Budget: $1,800,000      access controls and security     Delayed Schedule
Phase: Design        cameras at airport terminal doors.   Forecast Overrun
Start: 09/27/2011                                 0 Change Orders
Completion: 08/30/2013                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Construction documents were completed and are ready to bid.
2
Schedule
1.5
The project was advertised for bid in May 2012 and a single bid, 48%
1
above the engineer's estimate, was received and rejected. The
Millions
project was then divided into two parts, re-designed and will be re-      Dollars in 0.5
bid in November. The North Satellite work has been moved into the
0
NSAT project to avoid potential additional construction costs to re-         Authorized  Forecasted Costs Incurred
install North Satellite access controls if gates are reconfigured during
the NSAT project. The additional time needed to transfer the North
Satellite scope of work and budget to NorthSTAR program would    Construction Costs
cause the bid award process to occur over the December 2012      Not Applicable
holiday period and additional time will be needed for anticipated
holiday delays by the contractor.
Budget
Approximately $800,000 of scope and budget for the North Satellite
scope of work will be transferred out of this project in the next
quarter, with Commission authorization. Additional budget
(approximately $480,000) will be requested due to: the added direct
construction costs that were missing from the previous cost estimate;
the increased soft costs for the duplicated efforts to re-design and rebid
; and the additional soft costs to break the project into two parts
with two different bid and construction activities.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter
AIRPORT
46  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Airfield Lighting Control and Monitoring System
Status Snapshot
(ALCMS) Upgrades                  On Schedule
Provide modifications to the Airfield   On Budget
Project:   C800415      Lighting Control and Monitoring    0 Change Orders
System to update, enhance and    Total Change Orders Amount:
Budget: $2,129,144
stabilize the system to meet the     $0
Phase: Construction     latest FAA specifications.
Start: 01/01/2011                                Budget/Costs Incurred
Completion: 12/31/2014
2.5
Significant Developments                      2
New single mode fiber optic cable in airfield has been installed and     Millions 1.5
tested. Back-up airfield lighting vault 55-foot tower was installed to       1
raise antenna. The antenna is operational.                     Dollars in 0.5
0
Schedule                               Authorized Forecasted Costs Incurred
The project is currently on schedule.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None this quarter
Risks
Coordination with on-going airfield operations is a consideration.
The Port is also working to eliminate unplanned outages when
transitioning from the older computer platform to the one.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 3Q 2012 Report  47

THIRD QUARTER REPORT, 2012
Lagoon 3 Bird Wires
Status Snapshot
On Schedule
Project:   C800417      This project will reduce access by   On Budget
Budget: $1,833,000      waterfowl to the industrial       6 Change Orders
Phase: Construction     wastewater system Lagoon 3,     Total Change Orders Amount:
Start: 10/11/2011         which is located near the south end  $60,896.19
Completion: 10/31/2012   of the airfield.
Budget/Costs Incurred
2
Significant Developments
1.5
The project was advertised for construction in March 2012 with        Millions
1
contract bid opening in April 2012. Nordic Construction was the low
bidder. The contractor began work in July 2012.                 Dollars in 0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
The construction will be complete in October 2012. Cables will be
re-tensioned in January 2013.
Construction Costs
Budget
The project forecast is within the approved budget.                  1
0.8
Change Order                          Millions 0.6
Dollars in 
Six change orders have been executed this quarter.                0.4
0.2
Risks
0
No risks have been identified at this time.                            Initial  Change  Spent
Orders
Budget Transfers
Photo
None this quarter



AIRPORT
48  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Additional Airfield Mitigation at Tyee
Status Snapshot
Project:   C800420      The project will design and       On Schedule
Budget: $800,000       complete the Tyee Golf Course    On Budget
Phase: Close Out      Area Mitigation which includes    5 Change Orders
Start: 02/08/2011         removing a culvert, new wetland    Total Change Orders Amount:
Completion: 03/30/2012   planting, updating existing wetlands  -$36,704
to environmental permit standards,
and installing a temporary irrigation  Budget/Costs Incurred
system.
1
Significant Developments                     0.8
Substantial completion was issued on April 19, 2012. This will be the    Millions 0.6
last quarterly report for this project.                              0.4
Dollars in 0.2
Schedule
0
The project is complete and is in contract closeout.                    Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                          0.4
None this quarter.                                      0.3
Millions 0.2
Risks
0.1
None identified at this time.                                 Dollars in  0
Initial    Change Order    Spent
0.1
Budget Transfers
None this quarter
Photo



AIRPORT
Port of Seattle 3Q 2012 Report  49

THIRD QUARTER REPORT, 2012
Federal Inspection Service Improvements -
Status Snapshot
Phase 1                         On Schedule
Short Term Improvements to the    On Budget
Project:   C800426      Federal Inspection Service area at   0 Change Orders
the South Satellite to improve      Total Change Orders Amount:
Budget: $1,041,000
through put and improve conditions  $0
Phase: Design        for passengers waiting in the
Start: 04/01/2012         International Corridor prior to
Completion: 05/31/2013   Primary Inspection.
Budget/Costs Incurred
Significant Developments                     1.2
The Site Investigation is complete and 30% design development is in     1
progress.                                          0.8
0.6
in Millions
Schedule                             0.4
Dollars 
The 30% design will be submitted a few weeks later than anticipated    0.2
due to additional time needed for site investigation, but the overall       0
Authorized  Forecasted Costs Incurred
project is still projected to complete on time.
Budget
The project forecast is within the approved budget.              Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
50  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Doug Fox Lot Service Upgrades
Project:   C800451      Construct a new drainage system,   Status Snapshot
Budget: $6,073,000      asphalt resurfacing, improved lot   On Schedule
Phase: Design        lighting, new or renovated building,  On Budget
Start: 02/01/2012         and road signage to improve lot     0 Change Orders
Completion: 12/31/2013   appearance, function, and revenue  Total Change Orders Amount:
generation.                  $0
Budget/Costs Incurred
Significant Developments
8
Design of the drainage system, resurfacing and lighting is
6
approximately 60% complete. A new building will be installed rather    Millions
than renovation of the existing building. Signage options are being      4
evaluated by staff in coordination with the lot operator.
Dollars in   2
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 3Q 2012 Report  51

THIRD QUARTER REPORT, 2012
Concourse D Common Use Environment
Status Snapshot Prior Report
Delayed Schedule 3Q 11
Project:   C800455      This project installs a common-use  On Budget
Budget: $4,250,000      environment at all gates on      0 Change Orders
Phase: Construction     Concourse D. Scope includes new  Total Change Orders Amount:
Start: 03/01/2011         communications infrastructure,     $0
Completion: 12/31/2012   casework built to a new Airport
standard, new carpet, wall        Budget/Costs Incurred
coverings and task lighting.
5
4
Significant Developments
Millions  3
Gates D8 and D9 have been remodeled with new infrastructure,
Dollars in 
casework, finishes and seating. D1 and D2 remodels are in           2
progress.                                          1
0
Schedule                               Authorized Forecasted Costs Incurred
To date the contractor has met their interim project milestones.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
1.5
Change Order
1
None                                  Millions
0.5
Risks                                Dollars in 
Despite inclusion of the schedule milestones referenced above, the
0
contractor is going to be challenged to keep the project on schedule         Initial  Change  Spent
due to the long lead times for casework fabrication.                         Orders
Budget Transfers
None this quarter



AIRPORT
52  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
2011-2013 Roof Replacement Program
Project:   C800459      This project will remove and      Status Snapshot
Budget: $4,777,000      replace the roofing systems on the  On Schedule
Phase: Design        fire station and north end of the    On Budget
Start: 07/01/2011         main terminal.                0 Change Orders
Completion: 10/31/2013                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Design of the main terminal roof is underway.                    6
5
The Fire Station received substantial completion on September 28,
Millions  4
2012.
3
2
Schedule                            Dollars in  1
The project is currently on schedule.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization for
construction funding and authority to award for construction will be    Construction Costs
requested when the design and bid documents are completed.
0.5
Change Order                           0.4
None                                  Millions 0.3
0.2
Risks
Dollars in   0.1
None at this time
0
Initial   Change   Spent
Budget Transfers                                Orders
None this quarter



AIRPORT
Port of Seattle 3Q 2012 Report  53

THIRD QUARTER REPORT, 2012
Industrial Waste Treatment Plant (IWTP) Fiber
Installation
Install new Single Mode Fiber cable  Status Snapshot
Project:   C800461      from Main Terminal to IWTP and    Delayed Schedule
Gate E-45.                 Forecast Overrun
Budget: $514,000
0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 03/01/2012                                 $0
Completion: TBD
Budget/Costs Incurred
Significant Developments
The Fiber Optic Cable has been installed from Main terminal to the      1.2
new equipment termination cabinet near the Alaska Hangar.          1
Connectivity to Gate E-45 is complete. Information and             Millions 0.8
Communications Technology Group is developing the             0.6
communications portion of the project scope. Use of existing         0.4
conduits from the equipment pad to the IWTP was based upon using    Dollars in 0.2
conduits which are shared with FAA fiber optic cable. FAA has         0
declined to allow co-use of existing conduits.                        Authorized  Forecasted Costs Incurred
Schedule
The Port is investigating alternative means to continue fiber         Construction Costs
installation to the IWTP. This will result in a schedule delay.         Not Applicable
Budget
The project will require additional budget and authorization. The Port
is working up cost of alternative means and routes to continue
connectivity from the new equipment cabinet to the IWTP. Once the
design for revised route are completed, revised scope and costs can
be developed.
Change Order
None.
Risks
Possible underground boring for new conduits beneath Taxiway "B"
is being investigated.
Budget Transfers
None this quarter.

AIRPORT
54  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
South Satellite - Additional Gate Lobby
Status Snapshot
Delayed Schedule
Project:   C800466      Demolition of glass partitions,      On Budget
Budget: $1,515,000      restrooms, relocation of gate     0 Change Orders
Phase: Design        podiums new flooring, ceilings and  Total Change Orders Amount:
Start: 11/01/2010         infrastucture to provide additional    $0
Completion: 09/15/2013   gate lobby in the South Satellite.
Significant Developments                    Budget/Costs Incurred
Construction notice to proceed was issued October 3, 2012 and
demolition of the existing restrooms is underway.
2
Schedule
1.5
As previously reported, the project delay was caused by delayed      Millions
1
design negotiations and contracting. Additionally, a longer design
period is required due to dependency on the South Satellite          Dollars in 0.5
Concessions Project (C800412).
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
None                                    2
1.5
Risks                                Millions
This project is tied closely to the Duty Free RFP in that this project is       1
closely aligned with the South Satellite Concessions Project.
Dollars in   0.5
Budget Transfers                           0
Initial   Change   Spent
From C102165 (Aeronautical New Projects)        $171,000             Orders



AIRPORT
Port of Seattle 3Q 2012 Report  55

THIRD QUARTER REPORT, 2012
Passenger Loading Bridge Replacement
Status Snapshot
Project:   C800467      This project entails Passenger     On Schedule
Budget: $14,874,000     Loading Bridge (PLB)         On Budget
Phase: Design        replacements associated with the   0 Change Orders
Start: 04/12/2011         one-time airline realignment (AR).   Total Change Orders Amount:
Completion: 09/30/2013   The work will take place at      $0
Concourse D, Concourse B and
North Satellite.
Budget/Costs Incurred
Significant Developments
The work at Concourse D is underway. Bridge D8 was refurbished
20
and returned to service on schedule. Bridges D1 and D2 are
currently in construction and also on track to be completed on time.      15
Millions 10                                                                         Initial bids for the Concourse B bridges (B1 & B11) were rejected
because they came in at twice the engineer's estimate. The work will   Dollars in 5
be rebid in October with a new completion date of March 2013.
0
Authorized  Forecasted Costs Incurred
Work at North Satellite will now take place under the NorthSTAR
project.
Schedule                           Construction Costs
The project is currently on schedule. Commission approval for each      2
phase is being requested separately.
1.5
Budget
1
Millions
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will      Dollars in  0.5
be requested when the design and bid documents are completed.        0
Initial   Change   Spent
Orders
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
56  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Exterior Gate Improvements (Airline
Realignment)
This project will install new fuel      Status Snapshot
Project:   C800472      hydrant pits and aircraft docking    On Schedule
systems at exterior gates for the     On Budget
Budget: $4,064,000
airline reallocation program.        0 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 06/01/2011                                 $0
Completion: 10/31/2012
Budget/Costs Incurred
Significant Developments                      5
The project is currently in construction.                          4
Millions  3
Schedule
2
The project is currently on schedule.                          Dollars in  1
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                 Not applicable
Risks
If the fuel system lease amendment is not finalized, it could limit the
use of the new fuel hydrants.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2012 Report  57

THIRD QUARTER REPORT, 2012
CUSE at Gates & Ticket Counters- Airline
Realignment
Provide common use equipment,    Status Snapshot
Project:   C800473      casework and infrastructure at     Delayed Schedule
gates and ticket counters for the     On Budget
Budget: $2,371,000
Airline Realignment program.      0 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 04/02/2012                                 $0
Completion: 05/01/13
Budget/Costs Incurred
Significant Developments
The casework procurement process was completed.              2.5
2
Schedule                            Millions 1.5 Dollars in 
The project schedule was delayed five months based on the overall
1
Airline Realignment Program Schedule change.
0.5
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget.
Change Order
Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
58  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Airport Signage (Airline Realignment)
Project:   C800474      The project will provide airport     Status Snapshot
Budget: $646,000       directional signage for the airline   Delayed Schedule
Phase: Design        realignment program.         On Budget
Start: 06/01/2011                                 0 Change Orders
Completion: 05/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
The first Service Directive with the design consultant was executed.     0.8
An inventory of the impacted signs was submitted.
0.6
Millions
Schedule                             0.4
The project schedule was delayed by one month based on the       Dollars in 0.2
overall Airline Realignment Program Schedule change.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
Construction Costs
be requested when the design and bid documents are completed.
Not Applicable
Change Order
None this quarter
Risks
None this quarter
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 3Q 2012 Report  59

THIRD QUARTER REPORT, 2012
Miscellaneous Building Improvements (Airline
Realignment)
Project:   C800475      This project will install a new ramp   Status Snapshot
for passenger access to regional    On Schedule
Budget: $2,722,000
aircraft on Concourse A for the     On Budget
Phase: Design        Airline Realignment program.     0 Change Orders
Start: 11/01/2011                                 Total Change Orders Amount:
Completion: 07/31/2013                       $0
Budget/Costs Incurred
Significant Developments
3
The request for proposal for ramp equipment procurement is         2.5
complete.
2
1.5
Schedule                            in Millions
1
The project is currently on schedule.                          Dollars 0.5
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for equipment RFP
will be requested when the design and bid documents are         Construction Costs
completed.                                     Not Applicable
Change Order
None
Risks
If the aircraft assignments at the gates changes, the ramp would
need to be in a different location.
Budget Transfers
From C800240 (Main Terminal HVAC Upgrades)   $ 125,000
To C102166 (Aeronautical Renewal/Replacement)  $5,165,000
To C800492 (Convert Ticket Zone 3 Flow Thru)    $ 136,000


AIRPORT
60  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Laptop Power in Concourses
Project:   C800484      This project adds additional       Status Snapshot
Budget: $2,020,000      charging opportunities for personal  On Schedule
Phase: Design        electronic devices at several     On Budget
Start: 6/26/12           strategic locations throughout the    0 Change Orders
Completion: 12/2013     airport terminal.            Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
2.5
The 30% design is complete and 90% design is in development.
2
Schedule                            Millions 1.5
The project is currently on schedule.                           1
Dollars in  0.5
Budget
0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
No risks identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2012 Report  61

THIRD QUARTER REPORT, 2012
New Window Wall Ticket Zone 1
Project:   C800490      This project will install new       Status Snapshot
Budget: $4,025,000      common use ticket counters and   On Schedule
Phase: Design        new baggage system along the    On Budget
Start: 07/01/2012         window wall                 0 Change Orders
Completion: 09/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
5
The project is currently in design and close to 90% reviews and
4
issuance of building permits.
Millions  3
Schedule                             2
The project is scheduled to bid a major contract in January 2013.      Dollars in  1
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.    Construction Costs
Not Applicable
Change Order
None
Risks
The project is on an accelerated design and construction schedule.
Budget Transfers
None this quarter




AIRPORT
62  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Convert Ticket Zone 3 Flow Thru
Project:   C800492      This project will convert the Zone 3  Status Snapshot
Budget: $13,000,000     Ticketing Area to a flow through    On Schedule
Phase: Design        concept.               On Budget
Start: 08/07/2012                                 0 Change Orders
Completion: 10/31/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
14
The project was approved by the Commission on August 21, 2012.
12
The project is out to bid and will be awarded in late October. The
10
construction work is on track to begin in November, as scheduled.     Millions 8
6
Schedule                            Dollars in  4
2
The project is currently on schedule.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will    Construction Costs
be requested when the design and bid documents are completed.    Not Applicable
Change Order
None
Risks
Three other projects must take place before the work at Zone 3 can
commence.
Budget Transfers
From C800475 (Misc Building Improvements - AR)  $136,000



AIRPORT

Port of Seattle 3Q 2012 Report  63

THIRD QUARTER REPORT, 2012
NorthSTAR Program
Status Snapshot
On Schedule
Project:   C800544      For all programmatic project      On Budget
Budget: $13,000,000     management and project controls   0 Change Orders
Phase: Design        costs for the NorthSTAR program   Total Change Orders Amount:
Start: 04/05/2012         consisting of five capital projects    $0
Completion: 12/31/2018   that represents a unique
partnership between the Port and   Budget/Costs Incurred
Alaska Airlines.
20
Significant Developments                     15
The Port and Alaska continue to work collaboratively with two Alaska   Millions 10
staff co-located in Port offices adjacent to the Port team. Completed
contract negotiations and signed contract with Jacobs for Program     Dollars in  5
and Project Management and Controls for the NorthSTAR program.    0
Notebooks for both the Concourse C Vertical Circulation and           Authorized Forecasted  Costs
Incurred
Refurbish Baggage System projects were completed and approved
by the Investment Committee.
Construction Costs
Schedule                           Not Applicable
Commission authorized North Satellite project (NSAT) on schedule.
Project is on schedule.
Budget
Commission authorized $4,200,000 to manage the NorthSTAR
program estimated at approximately $300,000,000. Project is on
budget..
Change Order
None
Risks
The Airline Relocation project schedule changes potentially impacts
the program schedule. Alaska concurence at specific milestones is 
critical to the program moving forward. Consultant negotiation is
critical to getting resources on board to begin moving the program
forward.
Budget Transfers
From C800556 (NorthSTAR NSAT NSTS Lobbies)  $3,400,000

AIRPORT
64  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
NorthSTAR NSAT Renovation NSTS Lobbies
Status Snapshot
On Schedule
Project:   C800556      Renovation of the North Satellite      On Budget
Budget: $194,300,000    building, including STS station      0 Change Orders
Phase: Design        "refresh", ramp level, Concourse     Total Change Orders Amount:
Start: 7/24/2012          level, and new rooftop airline         $0
Completion: 12/31/2016   lounge.
Budget/Costs Incurred
Significant Developments
Commission authorized design on July 24, 2012. URS was selected    250
as the prime design consultant. The Port and URS are in contract     Millions 200
negotiations. The Port executed a consultant contract with Jacobs for
150
program controls.
Dollars in  100
Schedule                             50
Acquisition of the architectural firm is behind schedule due to          0
Authorized  Forecasted Costs Incurred
extended negotiations. The impact on the overall project schedule
will be determined after the design contract is executed.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
To C800554 (NorthSTAR Program)         $3,400,000


AIRPORT
Port of Seattle 3Q 2012 Report  65

THIRD QUARTER REPORT, 2012
Highline School Noise Insulation
Status Snapshot Prior Report
Delayed Schedule 4Q 10
Project:   C200007      Highline School Insulation        On Budget
Budget: $101,797,000    Agreement will provide funding for  0 Change Orders
Phase: Construction     sound mitigation for 15 schools that  Total Change Orders Amount:
Start: 03/23/1999         are impacted by aircraft noise from   $0
Completion: 11/30/2021   Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments
120
Port funding is authorized and will be available when the matching
100
funds are provided by the FAA, the State of Washington, and the
Highline School District.                                   Millions 80
60
40
Schedule                            Dollars in 20
The schedule for state funding is not known. The district's schedule
0
is dependent on obtaining general election bonds at various             Authorized Forecasted Costs Incurred
intervals.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Not applicable
Risks
Project delayed due to funding issues with the Highline School
District. Risk is if no bonds are passed in general election. Obtain
FAA Airport Improvement Program (AIP) Grant funding.
Budget Transfers
None this quarter



AIRPORT
66  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $32,050,000     Insulation Agreement will provide   Delayed Schedule 4Q10
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      0 Change Orders
Completion: 12/31/2013   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
$0
Significant Developments
Thirteen of the 22 eligible buildings have been sound insulated by    Budget/Costs Incurred
the college.
40
Schedule                             30
Building #4 received FAA Airport Improvement Program (AIP) Grant    Millions
20
and is scheduled to begin construction in fall 2012. Bids to be
opened November 8, 2012. The schedules for the remaining         Dollars in  10
buildings are dependent on state funding.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
the remaining project budget will be requested for one building at a   Construction Costs
time from the Commission in the future when the schedule is       Not Applicable
determined.
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 3Q 2012 Report  67

THIRD QUARTER REPORT, 2012
Home Insulation Retrofit
Project:   C200048      This project includes storm window  Status Snapshot Prior Report
Budget: $5,344,000      retrofit of previously insulated     Delayed Schedule 4Q 11
Phase: Construction     homes.                On Budget
Start: 01/11/2005                                 2 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$718
Significant Developments
Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners.
Continue with storm window retrofit.                           6
5
Schedule                            Millions 4
Two homes are complete and one is in process. The Port is          3
reviewing other potential homes for eligibility.                      2
Dollars in   1
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
Two change orders were issued, which include miscellaneous small   Not Applicable
items and City permits.
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter



AIRPORT
68  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot Prior Report
Budget: $4,947,395      that are within the 1998 65 decibel  Delayed Schedule    4Q 11
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   10 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$6847
Significant Developments                    Budget/Costs Incurred
Thirty two homes are complete; six homes are in the process of
6
receiving sound insulation; fourteen homes are on the waiting list for
5
the next group.
Millions  4
3
Schedule
2
This project is underway and could be complete by summer 2013.     Dollars in  1
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within approved budget and authorization to
complete all homes currently in progress. Any additional homes
identified as eligible will require additional funding authorization.      Construction Costs
4
Change Order
Change orders are miscellaneous small items and permits for the       3
cities.                                                       MillionsDollars in 
2
Risks                                 1
The ability to accomplish the insulation is dependent on the           0
homeowner's schedules, willingness to sign an aviation easement,         Initial  Change Order  Spent
and obtain a subordination agreement from their lender, and
structural integrity of the home. If more eligible homes than
anticipated are identified in the future, then additional funding may be
needed.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 3Q 2012 Report  69

THIRD QUARTER REPORT, 2012
RMU/Kiosk Concession Program
Status Snapshot Prior Report
Delayed Schedule 3Q 10
Project:   C800146    The project will provide design and     On Budget
Budget: $879,146     fabrication of Retail Merchandising    0 Change Orders
Phase: Construction   Units (RMUs); provide power,       Total Change Orders Amount:
Start: 11/20/2007      communications, and data to RMU     $0
Completion: 04/30/2013 locations; and install floor-mounted
receptacles for the utilities to allow easy
connection points as well as flexibility   Budget/Costs Incurred
for future utilization.
1.5
Significant Developments                     Millions 1
Additional RMU utilities and kiosks are being added to Concourse C.
0.5
An Acquisition Plan has been completed and scope of work is        Dollars in 
currently being prepared for procurement of the casework.
0
Authorized  Forecasted Costs Incurred
Schedule
The procurement for the casework is expected to occur late
2012/early 2013 and the utility infrastructure is tentatively scheduled   Construction Costs
for installation on Concourse C in late 2012.                   Not Applicable
Budget
The project forecast is currently within the approved budget and
authorization.
Change Order
None
Risks
The additional units on Concourse C may exceed the proposed
budget.
Budget Transfers
None this quarter.


AIRPORT
70  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot Prior Report
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule    2Q 10
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   0 Change Orders
Completion: 12/31/2013   owned properties.           Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The remaining anticipated acquisition will be street vacation of
4
12th Place S. in Burien, Washington.
3
Schedule
2
Millions
It is anticipated that the street vacation will occur in the 2012-2013
time frame.                                         Dollars in  1
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Change Order                         Construction
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2012 Report  71

THIRD QUARTER REPORT, 2012
Tenant Reimbursement
Status Snapshot
Project:   C800154    Build out of spaces for new and      On Schedule
Budget: $4,709,577    existing tenants. If more than a "basic  On Budget
Phase: Construction   finish" condition space is built for the   0 Change Orders
tenant, the tenant is required to       Total Change Orders Amount:
Start: 08/14/2007
reimburse the Port for the cost of the   $0
Completion: TBD
work beyond this "basic finish". These
reimbursements are allowed under    Budget/Costs Incurred
the guidelines described in the
"Tenant Reimbursement Policy".        5
4
Millions  3
Significant Developments
2
Future tenant projects will likely be part of the Airline Realignment
over the next few years, so this project may have limited activity.       Dollars in  1
0
Schedule                               Authorized Forecasted Costs Incurred
Schedules vary to meet the tenant's needs.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

72  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Rubber and Paint Removal Equipment
Project:   C800482    Purchase and delivery of a          Status Snapshot
Budget: $600,000    Rubber/Paint Removal Truck       On Schedule
Phase: Implementation                       On Budget
Start: 02/14/2012                                 0 Change Orders
Completion: 08/31/2012                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The contract was awarded to Stripe Hog. Equipment was delivered
0.8
in August 2012.
0.6
Schedule                            Millions
0.4
Dollars in 
The project is currently on schedule.
0.2
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter





AIRPORT
Port of Seattle 3Q 2012 Report  73

THIRD QUARTER REPORT, 2012
Snow Removal Equipment - 2013
Project:   C800498      This project will purchase four     Status Snapshot
Budget: $2,000,000      pieces of runway snow removal    On Schedule
Phase: Implementation   equipment.              On Budget
Start: 02/14/2012                                 0 Change Orders
Completion: 03/31/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
The project went out to bid in April 2012.                        2.5
2
Schedule                            Millions 1.5
Delivery is anticipated for March 2013.
1
Budget                             Dollars in 0.5
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT

74  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Seaport Security Grant Round 7
Project:   C800165      Seaport Security Grant Round 7    Status Snapshot
Budget: $2,283,090                         On Schedule 4Q 11
Revised Budget $2,582,490                      On Budget
Phase: Construction                        1 change Orders
Start: March 2007                                Total Change Orders Amount:
$24,515.00
Completion: Dec 2010
Budget/Costs Incurred
Significant Developments
2.6
The construction is complete except for punch list items and final
programming to get the system up and running. Invoices have been    2.5
submitted for grant reimbursement. Project is in close out.           Millions
2.4
Schedule                            Dollars in 2.3
On schedule as revised.
2.2
Authorized  Forecasted Costs Incurred
Budget
On budget as revised
Construction Costs
Change Order                         Not Applicable
No change orders over 10% in the aggregate.
Risks
None
Budget Transfers
No budget transfers over $200,000.




SEAPORT

Port of Seattle 3Q 2012 Report  75

THIRD QUARTER REPORT, 2012
P91 Fender System Upgrade
Project:   C800183      Upgrades to the vessel berths of    Status Snapshot
Budget: $5,700,000      P91 to better accommodate cruise  On Schedule
Phase: Design        ships and also serve the other    On Budget
Start: 01/31/10          industrial customers who utilize the   0 Change Orders
Completion: 04/30/2012   berths and adjacent dock/apron    Total Change Orders Amount:
areas on P91 for less than $6M by   $0
spring 2011.
Budget/Costs Incurred
Significant Developments
6
Fender pile replacement construction complete in Q2 2012. Design
for Camel standoff barges nearing completion.
Millions  4
Schedule
2
Full Fender replacement has been completed by April 2012. Camel    Dollars in 
Barge replacement will be completed by April 2013.                0
Authorized  Forecasted Costs Incurred
Budget
Project is within approved budget.
Construction Costs
Change Order
2.5
None this quarter
2
Risks                                Millions 1.5
None this quarter                                        1
Dollars in   0.5
Budget Transfers
0
None                                      Initial Change Spent
Orders




SEAPORT
76  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
T-91 Watermain Replacement
Project:   C800298      Replace water main in the vicinity   Status Snapshot Prior Report
Budget: $4,875,000      of Magnolia Bridge and City      On Schedule
Phase: Construction     Ice/Trident areas including various  On Budget
Start: 9/20/2009          buildings at T91              0 Change Orders
Completion: 8/1/2012                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Final construction is complete. This will be the last report on this
4.9
project.
4.85
4.8
Schedule                            4.75 Millions
Project Completed.                                   4.7
4.65   Dollars in 
Budget                             4.6
4.55
Project is on budget.                                        Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Risks                                 4.16
None                                   4.14
Millions 4.12
Budget Transfers
4.1
None
Dollars in  4.08
4.06
Initial   Change   Spent
Orders

Photo


SEAPORT
Port of Seattle 3Q 2012 Report  77

SECOND QUARTER REPORT, 2012
T-5 Crane Cable Reels
Status Snapshot Prior Report
Project:   C800349      Purchase Cable Reels for tenant.
Budget: $3,500,000                         Delayed Schedule
Phase: Design                            On Budget
Start: 05/04/10                                   0 Change Orders
Completion: 03/31/11                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
No changes to the project since last report.
4
Schedule
3
The installation of the cable reels is still anticipated to begin the first     Millions
quarter of 2013. The revised completion date for the project remains     2
the 3rd quarter 2013.
Dollars in   1
Budget
0
None                                     Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
Schedule                                   Photo
Budget Transfers
None




SEAPORT

78  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
T-91, Bldg C175 Roof Replacement
Status Snapshot Prior Report
Project:   C800430      Replace roof on the C175 building
Budget: $240,000       at Terminal 91.            Delayed Schedule
Phase: Design                            On Budget
Start: 7/26/11                                    0 Change Orders
Completion: Q414                          Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Commission authorized design funds in July 2011. The project was
placed on hold as the tenant expressed a desire to modify their lease
0.3
to incorporate the design installation of the roof. After a thorough
0.25
review, a mutual decision was made to have the port design and
install the roof. The project was reactivated during the 3rd quarter and    Millions 0.2
0.15
negotiations were entered into with the designer
0.1
Schedule                            0.05 Dollars in 
0
Service agreement is anticipated to be finalized in the next quarter         Authorized  Forecasted Costs Incurred
and preliminary design and a condition assessment completed in
early 2013. The condition assessment will be used to determine
whether or not the roof will need to be replaced in 2013 or installed   Construction Costs
as planned in 2014.                                 Not Applicable
Budget
On budget
Change Order
None
Risks
None at this time
Budget Transfers
None

SEAPORT

Port of Seattle 3Q 2012 Report  79

THIRD QUARTER REPORT, 2012
SEA P66 Apron Pile Wrap
Status Snapshot
Project:   C800516      Design and install a pile wrap      Delayed Schedule
Budget: $167,000       system for corrosion protection of   On Budget
Phase: Design        steel structural pilings associated   0 Change Orders
Start: 3/6/12            with Seaport structures at Pier 66.   Total Change Orders Amount:
Completion: 12/31/16                         $0
Budget/Costs Incurred
Significant Developments
0.02
Project teams from the P66 Apron Pile Wrap and P69 North Apron
0.015
Corrosion Controls Projects decided that the construction phase of
the two projects could be combined into a single contract to minimize    0.01  Millions
costs and maximize efficiency. The 90% design documents are
0.005
being prepared to reflect this. Permit review continues by the Corps    Dollars in 
and the approval is anticipated in October.                       0
Authorized  Forecasted Costs Incurred
Schedule
With the direction to combine construction into a single contract, the
Construction Costs
P66 Apron Pile Wrap design schedule is being delayed by a couple
Not Applicable
of months so the schedule milestones would coincide with that of the
Pier 69 N. Apron Corrosion Control Project. However, instead of
multi-year construction, the work will be accelerated and be
completed by end of March 2014.
Budget
Project is on budget.
Change Order
None
Risks
Installation of pile wraps is tide and weather dependent. Army Corps
will determine if work is subject to in-water work restrictions - at this
time, in-water work restrictions are not anticipated.
Budget Transfers
None

SEAPORT
80  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Argo Yard Truck Roadway
Status Snapshot
Project:   C800546,      New Port of Seattle owned truck    On Schedule
E104751, E104754       roadway between SR 99 and     On Budget
Budget: $2,200,000      Colorado Way Avenue right-of-way.  0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 03/11/12                                   $0
Completion: 12/31/14                        Budget/Costs Incurred
2.5
Significant Developments
2
Site survey, site geotechnical investigation, and Phase I             Millions 1.5
environmental site assessment have been completed. Coordination
Dollars in 
1
has begun with project stakeholders regarding the roadway
alignment, public street improvements, and required easements.       0.5
0
Schedule                               Authorized Forecasted Costs Incurred
Design & permitting to be completed by fall 2013.
Construction to be completed in 2013/2014                  Construction Costs
Not Applicable
Budget
Final project cost to be determined as a result of design.
Change Order
None
Risks
The actual utilization of the proposed Argo Yard truck roadway is
dependent upon the completion of separate off-site projects -
EMWGS Phase II (East Marginal Way surface street improvements)
and WSDOT's SR-99 timber trestle replacement scheduled for
construction completion by spring 2014. The EMWGS Phase II
improvements, which are currently in initial design discussions with
SDOT, will also require timely approval by Union Pacific Railroad
and the Ash Grove Cement Co. in order to be completed within
2014.
Budget Transfers
None

SEAPORT
Port of Seattle 3Q 2012 Report  81

SECOND QUARTER REPORT, 2012
East Marginal Way Grade Separation
Status Snapshot Prior Report
Delayed Schedule
Project:   E102007      FAST Corridor funded project;     On Budget
Budget: $53,575,171     FHWA, State, City with Port      59 Change Orders
Phase: Construction     commitment of $18,800,000. Scope  Total Change Orders Amount:
Start: 5/2006            is to construct grade separation in   $1,358,306
Completion: Q4 2012     vicinity of T5 and T18 to minimize
truck traffic/rail conflicts.           Budget/Costs Incurred
53.8
53.6
53.4   Millions
53.2
Significant Developments
53
Opening for traffic occurred in mid-March 2012. Recent development
52.8   Dollars in 
in plans to replace adjacent highway structures have resulted in
52.6
opportunity to develop access to UPRR rail yard and improved           Authorized  Forecasted Costs Incurred
freight traffic flow.
Schedule
Construction Costs
Substantial completion was achieved in 2nd Q 2012. Final
acceptance by SDOT is anticipated in 3rd Q 2012 followed by          25
Federal Highway Administration (FHWA) final audit.
20
Millions   15
Budget
10
Current construction costs based on unit line items and cost
reconciliation which are occurring 3rd Q 12 as part of the project        Dollars in   5
closeout. On Budget reflects the active construction budget. Overall       0
Project budget adjusted to incorporate American Recovery and            Initial  Change  Spent
Orders
Reinvestment Act (ARRA) funds.
Change Order                         Photo
Fifty nine change orders have been executed for a total net amount
of $1,358,306. Change order calculations based on unit pricing and
final cost will be based on actual quantities as well as any
outstanding contractor claims calculated at close-out.



82  Port of Seattle 3Q 2012 Report

SECOND QUARTER REPORT, 2012
East Marginal Way Grade Separation
Status Snapshot Prior Report
Delayed Schedule
Project:   E102007      FAST Corridor funded project;     On Budget
Budget: $53,575,171     FHWA, State, City with Port      59 Change Orders
Phase: Construction     commitment of $18,800,000. Scope  Total Change Orders Amount:
Start: 5/2006            is to construct grade separation in   $1,358,306
Completion: Q4 2012     vicinity of T5 and T18 to minimize
truck traffic/rail conflicts.           Budget/Costs Incurred
53.8
53.6
53.4   Millions
53.2
Significant Developments
53
Opening for traffic occurred in mid-March 2012. Recent development
52.8   Dollars in 
in plans to replace adjacent highway structures have resulted in
52.6
opportunity to develop access to UPRR rail yard and improved           Authorized  Forecasted Costs Incurred
freight traffic flow.
Schedule
Construction Costs
Substantial completion was achieved in 2nd Q 2012. Final
acceptance by SDOT is anticipated in 3rd Q 2012 followed by          25
Federal Highway Administration (FHWA) final audit.
20
Millions   15
Budget
10
Current construction costs based on unit line items and cost
reconciliation which are occurring 3rd Q 12 as part of the project        Dollars in   5
closeout. On Budget reflects the active construction budget. Overall       0
Project budget adjusted to incorporate American Recovery and            Initial  Change  Spent
Orders
Reinvestment Act (ARRA) funds.
Change Order                         Photo
Fifty nine change orders have been executed for a total net amount
of $1,358,306. Change order calculations based on unit pricing and
final cost will be based on actual quantities as well as any
outstanding contractor claims calculated at close-out.



Port of Seattle 3Q 2012 Report  83

THIRD QUARTER REPORT, 2012
Viaduct Construction Coordination
Project:   E104324,      Participate in the design &       Status Snapshot
E104535-38          construction of the bored tunnel,   On Schedule 3Q 12
Budget: $980,000       north & south portals, Holgate to   On Budget 3Q 12
Phase: Implementation   King St, Central Waterfront surface  0 Change Orders
Start: 1/1/2009          streets, and related projects to     Total Change Orders Amount:
ensure adequate connection to port  $0
Completion: 12/31/2018
facilities.
Budget/Costs Incurred
Significant Developments
0.78
Excavation of future SR 99 tunnel boring machine launch pit near T-    0.76
46 began in June. Crews rerouted waterfront traffic underneath       0.74
existing Viaduct between Spring and King St. Construction began on   0.72  Millions
mitigation works at T-46 as a condition of leasing 5 acres for tunnel      0.7
construction staging area. Construction of Stage 2 H2K is          0.68  Dollars in 
substantially complete and roadway is open to traffic.              0.66
0.64
Authorized  Forecasted Costs Incurred
Schedule
Stage 3 H2K construction started in August. Tunnel boring machine
delivery is expected in Spring 2013. Related City projects are
Construction Costs
making steady progress (Spokane/Mercer.)
Not Applicable
Budget
Port staff costs are within anticipated 2012 spending.
Change Order
Not applicable
Risks
There are multiple impacts to port tenants and general freight
mobility due to temporary road closures, detours, and other
necessary construction activities.
Budget Transfers
None

SEAPORT
84  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Street Vacations T5,18,105
Status Snapshot
Delayed Schedule 4Q 11
Project: Capital &     Street vacation related real estate     On Budget
E104362, E104364,    negotiations and agreements --T5,    0 Change Orders
E104366         T18, and T105.             Total Change Orders Amount:
Budget: $1,500,000                         $0
Phase: Permitting
Start: June 2010                                 Budget/Costs Incurred
Completion: 2014
2
1.5
Significant Developments                     Millions 1
The T-5 Land Exchange with BNSF was finalized. Escrow closed in
Dollars in 0.5                                                                               mid-September.
0
Authorized  Forecasted Costs Incurred
Schedule
The current effort with the City anticipates a refinement of the Street
Vacation schedule for T-18 with additional confirmation of the T-5    Construction Costs
Street Vacation schedule facilitated by the completion of the BNSF   Not Applicable
property exchange.
Photo
Budget
The revised schedule referenced in the 2nd Quarter report will likely
require a year 2013 amendment to the budget.
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable


SEAPORT
Port of Seattle 3Q 2012 Report  85

THIRD QUARTER REPORT, 2012
T-18 Pile Cap Repair Pilot Project
Project:   E104559      T18 Pilot Pile Cap Repair Project    Status Snapshot
Budget: $1,500,000                         Delayed Schedule 3Q 12
Phase: Construction                        Forecast Overrun 3Q 12
Start: 3/25/11                                    0 Change Orders
Completion: 12/31/12                        Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Construction was completed in August on the first two pile cap bents.
2
Schedule
1.5
Repairs were to be completed by July, but are taking longer than      Millions
originally estimated. Completion is now expected by the end of         1
October and findings will be published in November.
Dollars in 0.5
Budget
0
Costs to date are forecasted higher than expected due to increased        Authorized  Forecasted Costs Incurred
overall duration of construction.
Change Order                         Construction Costs
None
2
Risks
1.5
Risks include preventing deleterious materials from entering water,     Millions
1
minimizing any disruptions to tenant operations, and managing
project costs in order to stay within budget approved.               Dollars in  0.5
Budget Transfers                           0
Initial   Change   Spent
None                                         Orders



SEAPORT
86  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Dock System Condition Assessments
Project:   E104610-12;    Comprehensive Assessments: T5,   Status Snapshot
E104695 & 98         T18, T46, T25/30, and P66      On Schedule 3Q 12
Budget: $2,250,000      Rapid Assessments: T18 and T91   On Budget 3Q 12
Phase: Implementation                       0 Change Orders
Start: 1/1/2011                                   Total Change Orders Amount:
$0
Completion: 12/31/2012
Budget/Costs Incurred
Significant Developments
Results for T-5, T-18, and T-46 were incorporated into the 2013        2.5
budget planning. Field inspections were completed for T-25/30 and
2
P66.                                        Millions 1.5
Schedule                             1
Project is on schedule for completing comprehensive assessments     Dollars in 0.5
of T-25/30 and P66 in 2012.                               0
Authorized  Forecasted Costs Incurred
Budget
Budget is $2,250,000 and is on target to complete within this
amount.                                    Construction Costs
Not Applicable
Change Order
Not applicable
Risks
T-30 structural pile issues requiring further investigation.
Budget Transfers
None for this period



SEAPORT
Port of Seattle 3Q 2012 Report  87

THIRD QUARTER REPORT, 2012
T-5 and T-18 Maintenance Dredging
Status Snapshot
Project:   E104840      Maintenance Dredge T5 Berth 1 to   On Schedule
Budget: $1,950,000      -45', Berth 2 and 3 to -50', and    On Budget
Phase: Design        perform T18 high spot removal if   0 Change Orders
Start: 08/14/12          permit allows                Total Change Orders Amount:
Completion: 02/28/2014                       $
Budget/Costs Incurred
Significant Developments
2.5
Design is underway.
2
1.5
Schedule                            Millions
1
Design is on schedule.
Dollars in 0.5
Budget                              0
Authorized  Forecasted Costs Incurred
Design is on budget.
Change Order                         Construction Costs
None                                 Not Applicable at this time
Risks
None
Budget Transfers
None




SEAPORT

88  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
FT C15 HVAC Improvements
Status Snapshot
Project:   C800137                             Delayed Schedule 4Q 11
Budget: $3,748,000    Provide the preliminary planning,    On Budget
Phase: Design       design, and construction for replacing  0 Change Orders
Start: 05/01/10         the FT C15 HVAC System.         Total Change Orders Amount:
Completion: 5/31/2014                        $0
Budget/Costs Incurred
Significant Developments
5
60% design and design review is complete. New equipment design
concepts are being explored that would allow significantly less          4
amount of construction impacts to our tenants.                  Millions 3
2
Schedule                            Dollars in  1
Design is behind schedule due to the departure of key consultant
0
staff. If new equipment design concept gains traction, additional
Authorized  Forecasted Costs Incurred
design time would be required.
Budget
Construction Costs
On budget                                   Not Applicable
Change Order
None
Risks
New equipment design concept requires time to validate whether it is
indeed a viable option. Cost, schedule, and construction related
impacts would be carefully assessed.
Budget Transfers
None



REAL ESTATE
Port of Seattle 3Q 2012 Report  89

SECOND QUARTER REPORT, 2012
RE Maintenance Shop Solution
Project:   C800187      Marine Maintenance Solution CIP   Status Snapshot
Budget: $2,640,000      facilities continued operations from  Delayed Schedule 4Q11
Phase: Construction     the existing shop location by     On Budget
Start: August 2010       funding the following five projects:   0 Change Orders
Completion: November   MM Office Expansion; MM North-   Total Change Orders Amount:
end Office; MM Elec Upgrade; MM
2012
Roof Replacement; and MM
Kitchen Upgrade.             Budget/Costs Incurred
2.7
Significant Developments                     2.6
All projects, except the Kitchen Upgrade are complete. The Kitchen
Millions 2.5
is currently under construction.
Dollars in 2.4
Schedule                             2.3
Authorized  Forecasted Costs Incurred
Kitchen Upgrade construction is expected to be complete by
November 13, 2012.
Construction Costs
Budget
Not applicable
Total CIP authorization is $2,640,000. Approximately $2,425,000
has been spent to date. CIP is expected to come in under budget.
Change Order
No change orders previous quarter. Kitchen Upgrade work is
Risks
No identified risks for the remainder of the project work.
Budget Transfers
None


REAL ESTATE
90  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
P69 N Apron Corrosion Control
Status Snapshot
Project:   C800313      Install a corrosion control system    On Schedule
Budget: $300,000       for the steel pilings, pile caps, and   On Budget
Phase: Design        beams under the North Apron.    0 Change Orders
Start: 02/28/12                                   Total Change Orders Amount:
Completion: 12/31/2013                       $0
Budget/Costs Incurred
Significant Developments
0.4
Design is underway.
0.3
Schedule                            Millions 0.2
Design is on schedule. We plan on proceeding with Commission
0.1
authorization for construction in November of this year.             Dollars in 
0
Authorized  Forecasted Costs Incurred
Budget
Design is on budget.
Construction Costs
Change Order                         Not Applicable
None
Photo
Risks
None
Budget Transfers
None at this time




REAL ESTATE

Port of Seattle 3Q 2012 Report  91

THIRD QUARTER REPORT, 2012
Flight Information System (FIMS) II
Project: C101117        Procure, develop, and implement a  Status Snapshot
Budget: $8,220,000      FIMS system that includes       On Schedule
Phase:Implementation    replacement monitors, an airport   On Budget
Start: 5/4/2010           resource management system, and  3 Change Orders
Completion: 12/30/2013    a flexible digital signage system    Total Change Orders Amount:
capable of displaying flight         $717,355
information, visual paging, and
notifications.
Budget/Costs Incurred
Significant Developments                     10
Software configuration and testing in progress. Casework            8
construction and display replacement has begun and will continue      6
through 2013.                                       Millions
4
Dollars in  2
Schedule
0
On Schedule
Authorized Forecasted   Costs
Incurred
Budget
On Budget                                  Construction Costs
Change Order                           2.5
Additional signage replacement was approved resulting in a contract      2
change order for construction design.                        Millions 1.5
.
1
Risks                                Dollars in  0.5
No significant risks at this time.                                  0
Initial      Change      Spent
Orders
Budget Transfers
None


CORPORATE

92  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, and add service desk     0 Change Orders
Completion: 12/30/2013   module and wireless handheld    Total Change Orders Amount:
capabilities.                    $0

Significant Developments                    Budget/Costs Incurred
Major components of the program have been delivered including the
4
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of         3
Marine Maintenance and Aviation Maintenance Maximo systems in
2
September 2010. The smaller mobility enhancement is in progress     in Millions
and additional interfaces will be created after the Peoplesoft          Dollars  1
Financials upgrade.
0
Authorized  Forecasted    Costs
Schedule
Incurred
Prior Report - Several of the proposed new interfaces link the
Maximo system to the Peoplesoft Financials Procurement module.
Construction Costs
Because of planned changes in the procurement process with the
Not Applicable
Peoplesoft Financials Upgrade project, the delivery of these
interfaces will be delayed until after the completion of the upgrade
project.
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces and mobility enhancements.
Budget Transfers
None

CORPORATE
Port of Seattle 3Q 2012 Report  93

THIRD QUARTER REPORT, 2012
ID Badge System Replacement
Project: C800162        Procurement and replacement of   Status Snapshot
Budget: $2,500,000      the Portwide ID Badge system     On Schedule
Phase:Planning        including software, hardware, and   On Budget
Start: 5/1/2012           equipment.                 0 Change Orders
Completion: 11/30/2013                         Total Change Orders Amount:
$0

Budget/Costs Incurred
Significant Developments
3
Vendor has been selected via a competitive RFP. Contract
negotiation in progress. Project kickoff is scheduled for early          2.5
November.                                   2
1.5
in Millions
Schedule                             1
Dollars 
On Schedule                                   0.5
0
Authorized  Forecasted    Costs
Budget
Incurred
On Budget
Change Order
Construction Costs
None                                 Not Applicable
Risks
No significant risks
Budget Transfers
None



CORPORATE

94  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Airline Activity Management
Project: C800222        Development of an airline activity   Status Snapshot
Budget: $500,000       management system that       On Schedule
Phase:Implementation    integrates with several Port      On Budget
Start: 6/19/2011          systems to replace aging reporting   0 Change Orders
Completion: 5/1/2013     system and supply data for airline   Total Change Orders Amount:
activity fees.                    $0

Budget/Costs Incurred
Significant Developments
0.6
Development in progress.
0.5
Schedule                             0.4
On Schedule                                   Millions0.3
0.2
Dollars in
Budget                             0.1
0
On Budget
Authorized Forecasted   Costs
Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
Signatory Lease and Operating Agreement (SLOA) negotiation
issues may impact final requirements and delay schedule.
Budget Transfers
None




CORPORATE

Port of Seattle 3Q 2012 Report  95

THIRD QUARTER REPORT, 2012
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot
Budget: $1,525,000      costing systems with a common    Delayed Schedule
Phase:Implementation    enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: 5/30/2013                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The first phase deployment has been completed and the software is
in-use by the Project Management Groups. To ensure resources are     2
available to focus on the current installation, work on the
development of additional interfaces in the final phase has been       1.5
delayed. They will instead be delivered in stages over the next 6
1
months.                                      in Millions
Dollars 0.5
Schedule
0
Prior Report - Vendor did not deliver software per original contract         Authorized Forecasted  Costs
and project was put on-hold to evaluate alternatives. A decision was                   Incurred
made to continue with Skire in July 2010. The estimated completion
date at this time is September 2011 although there may be interim    Construction Costs
deliveries prior to completion.                              Not Applicable
Prior Report - Configuration of the software took longer than
anticipated due to the availability of resources and complexity of the
software delaying the start of the interface development. The system
is scheduled to be deployed in May 2012 with several critical
interfaces in place.
Budget
None
Change Order
None
Risks
After the replanning of the final phase, no significant issues identified
at this time.
Budget Transfers
None
CORPORATE96  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot Prior Report
Budget: $800,000       increase functionality, and lower   Delayed Schedule
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 12/30/2012   records and document         Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
The Sharepoint 2010 upgrade, training, and project-led organization
0.85
roll-out has been completed. Design and implementation of
0.8
Sharepoint 2010 Records Center is in progress.                Millions
0.75
Dollars in                                                                                                  Schedule
0.7
Resource availability has delayed the full implementation of the
0.65
Sharepoint Records Center which is scheduled to be availabile to the
0.6
first Port department in May 2012. Migration of records to Sharepoint
Authorized    Forecasted   Costs Incurred
will not be complete until December 2012.
Construction Costs
Prior Report: Sharepoint 2010 implementation is dependent on the
Not Applicable
completion of several infrastructure projects currently in progress
and requires additional time to complete the upgrade of existing
sites.
Budget
On Budget
Change Order
None
Risks
Scope of Sharepoint 2010 upgrade may require additional funding to
complete migration activities.
Budget Transfers
None
CORPORATE

Port of Seattle 3Q 2012 Report  97

THIRD QUARTER REPORT, 2012
Time Clock System
Project: C800387        Procure and implement a Time    Status Snapshot Prior Report
Budget: $380,000       Clock System to accurately capture  Delayed Schedule
Phase: Planning        and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion: TBD       Aviation Security and Airport     Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
Vendor was unable to deliver software that functioned in our
0.4
environment per the contract. We are working with the legal
department to determine our options for severing the relationship.        0.3
0.2
The project team is evaluating options and a re-planning effort is in      Millions
progress.                                         Dollars in  0.1
Schedule                              0
Authorized Forecasted   Costs
Schedule will be significantly delayed if another vendor solution is                      Incurred
implemented.
Budget                            Construction Costs
Not Applicable
There is a risk that another vendor solution would require additional
funding.
Change Order
None
Risks
Budget and schedule will be impacted by the need to select another
vendor.
Budget Transfers
None


CORPORATE
98  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
PeopleSoft Financials Upgrade
Project: C800392        Upgrade of Peoplesoft Financials   Status Snapshot Prior Report
Budget: $5,000,000      hardware and software         Delayed Schedule
Phase:Planning                            On Budget
Start: 9/28/2010                                 0 Change Orders
Completion: 12/31/2013                         Total Change Orders Amount:
$0
Significant Developments
Technical design is in progress and functional fit/gap workshops     Budget/Costs Incurred
have begun.
6
5
Schedule
4
Prior Report - An implementation vendor was selected via a
Millions 3
competitive procurement but we were unsuccessful in negotiating an
2
acceptable contract. Because of resource constraints during the       Dollars in 1
year-end process, the next optimum window of opportunity for the
0
upgrade begins in mid-2012. This will delay the project one year.
Authorized Forecasted   Costs
Incurred
Budget
On Budget                                  Construction Costs
Not Applicable
Change Order
None
Risks
Significant resources will be required across multiple organizations
which may delay other technology projects.
Budget Transfers
None



CORPORATE
Port of Seattle 3Q 2012 Report  99

THIRD QUARTER REPORT, 2012
Police Records Management System
Project: C800393        Procure and implement a       Status Snapshot
Budget: $1,300,000      replacement Police Records      Delayed Schedule
Phase:Implementation    Management System         On Budget
Start: 10/10/10                                   0 Change Orders
Completion: 3/30/2013                         Total Change Orders Amount:
$0
Significant Developments
Configuration and implementation in progress.                 Budget/Costs Incurred
Schedule                             1.4
1.2
A change request has been approved to implement additional
1
software that will better meet business process for field reporting.
0.8
This will delay the implementation by 6 months.                   Millions
0.6
Dollars in 0.4
Prior Report - Contract negotiations took significantly longer than       0.2
anticipated delaying project completion by 8 months.               0
Authorized  Forecasted   Costs
Incurred
Budget
On Budget
Change Order                         Construction Costs
Not Applicable
None
Risks
No significant risks.
Budget Transfers
None



CORPORATE
100  Port of Seattle 3Q 2012 Report

THIRD QUARTER REPORT, 2012
CUSS Kiosk Expansion
Project: C800477        Procure and install 10 Common-    Status Snapshot
Budget: $425,000       use Self Service (CUSS) kiosks in   On Schedule
Phase: Close Out       the common-use ticket counter    On Budget
Start: 1/10/2012          lobby providing travelers self      0 Change Orders
Completion: 7/30/2012    service check-in options.        Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred
Kiosks have been delivered and installed and the kiosk management
0.44
software has been upgraded.
0.42
0.4
Schedule
Millions 0.38
On Schedule
0.36
Dollars in 0.34
Budget
0.32
On Budget                                      Authorized Forecasted Costs
Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No significant risks identified.
Budget Transfers
None




CORPORATE
Port of Seattle 3Q 2012 Report  101

THIRD QUARTER REPORT, 2012
Maintenance Planning Software
Project: C800501        Procure and implement        Status Snapshot Prior Report
Budget: $402,000       Maintenance Planning and       Delayed Schedule     2Q 11
Phase:Implementation    Scheduling software that integrates  On Budget
Start: 6/26/2011          with our Asset Management       0 Change Orders
Completion: 11/30/2012    system, Maximo.            Total Change Orders Amount:
$0
Significant Developments
Software deployment has been completed as originally scoped.     Budget/Costs Incurred
Schedule                             0.5
A change request for additional licenses and reports has been        0.4
approved. This scope change will delay the schedule by 5 months.     0.3
Millions
0.2
Budget
Dollars in 0.1
On Budget
0
Authorized  Forecasted    Costs
Change Order                                    Incurred
None
Construction Costs
Risks
Not Applicable
No significant risks
Budget Transfers
None





CORPORATE
102  Port of Seattle 3Q 2012 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.