5d

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5d 
ACTION ITEM             Date of Meeting   November 6, 2012 

DATE:    October 30, 2012 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Geri Poor, Manager, Regional Transportation, Public Affairs 
Christine Wolf, Transportation Program Planner, Seaport Leasing and Asset
Management 
SUBJECT:  Indefinite delivery, indefinite quantity (IDIQ) service agreements for transportation
consulting services. 
Maximum Value of IDIQ Contracts:    $500,000 for up to two contracts 
Source of Funds:                 Department annual expense budgets and future
individual project authorizations 
ACTION REQUESTED:
Request Port Commission authorization for the Chief Executive Officer to execute up to two
indefinite delivery, indefinite quantity (IDIQ) consulting contracts for transportation planning,
analysis, review, conceptual design, and strategic advisory services, for a combined value not to
exceed  $500,000 and for a contract ordering period of four years. There is no funding request
associated with this authorization. 
SYNOPSIS:
These contracts will provide transportation planning, engineering, and policy/strategic consulting
services to (1) ensure adequate representation of the Port during meetings with other agencies,
businesses and community stakeholders on issues affecting Port access and freight mobility; (2)
review and evaluate technical analyses and documents prepared by other agencies, the private sector,
or their consultants, or prepare such analysis as needed for Port use; (3) provide strategic advice 
regarding transportation issues and evolving policies related to transportation infrastructure plans,
projects, programs and funding; and (4) provide executive management with advice about staffing
and other resources to strengthen the Port's role in regional transportation projects and policy. 
Ensuring the availability of qualified outside transportation planning, engineering and
policy/strategic professional service support contracts is necessary to support the essential functions
expected of Seaport Transportation Planning and Public Affairs  staff. The specific outside
professional services requested will ensure that Port staff has the ability to provide cost-effective and 
technically sound responses, in order to meet time-sensitive project, plan, strategy and policy
decision information needs. They enable both the Seaport and the Public Affairs teams to determine

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
October 30, 2012 
Page 2 of 2 

ways to meet the goals and objectives of their respective business plans and the Century Agenda. A
joint procurement process will reduce the staff time and effort required to carry out two separate
processes, consolidate contract management requirements, and enable staff to carry out a 
procurement process that will reach a broader audience than two separate smaller contracts. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
The contracts will be written with stipulated not-to-exceed amounts and identified scope of services.
Each contract will have a contract-ordering period of four years during which time service directives
may be issued. The initial contract period will be four years; however, the contract may be extended
to allow time to complete all executed service directives. Each service directive will specify the
scope, duration, and schedule associated with the work. The proposed IDIQ contracts would be
competitively bid and the Office of Social Responsibility will assist in identifying opportunities for
participation by small contractors and suppliers prior to the public advertisement. 
FINANCIAL IMPLICATIONS: 
There is no funding request associated with this authorization. Individual service directives will be
executed to authorize the consultant to perform work on the contract pursuant to approved project or
expense budget authorizations in accordance with Resolution 3605, as amended by Resolution No.
3628. 
Source of Funds 
The source of funds will be based on the approved expense budgets or project authorizations
associated with each service directive. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Undertake a separate procurement process each time services are needed in any discipline.
This option would not be a timely and efficient use of Port resources, as it would result in
multiple contracts for similar services. This is not the recommended alternative. 
Undertake a separate procurement process each for Seaport and Public Affairs. This option
would not be a timely and efficient use of Port resources, as it would result in multiple
contracts for similar services. This is not the recommended alternative. 
Undertake a joint competitive procurement for transportation planning, analysis, conceptual
design, review and strategic advisory services, resulting in up to two contracts that will
provide staff with the tools needed to respond in a timely manner to requests for service.
This is the recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None 
PREVIOUS COMMISSION ACTIONS OR BREIFINGS: 
None

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.