5g

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5g 
ACTION ITEM             Date of Meeting   November 6, 2012 

DATE:    October 29, 2012 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Michael Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Virgin America Airline Ticket Office Construction (CIP #C800492) 
Amount of This Request: $650,000       Source of Funds: Airport Development Fund
and existing bond proceeds 
Est. State and Local Taxes: $762,471     Est. Jobs Created: 16 
Est. Total Project Cost: $13,125,000 
ACTION REQUESTED: 
Request Port Commission authorization for the Chief Executive Officer to advertise, award and
execute a major construction contract in an amount not to exceed $650,000 to construct a new
Virgin America airline ticket office at Seattle-Tacoma International Airport. No additional
funding is required for this authorization as the increased cost can be absorbed within the total
authorized project budget. 
SYNOPSIS: 
This project will remodel and relocate Virgin America's airline ticket office to facilitate
construction of Delta Air Lines new "flow-through" ticket counters. This project was authorized
by the Commission on August 14, 2012, and this portion of the project was originally planned to
be built by Port Construction Services (PCS) as a small works project using existing open order
small works contractors. However, the costs for all the total combined subcontracts needed for
the Virgin America ticket office have increased beyond the $300,000 threshold, and the project
now must be completed using a major construction contract whose estimated value is $650,000.
It is essential to complete the relocation of Virgin's airline ticket office quickly to allow Delta's
new ticket counters to be ready for use by next summer's high traffic season. The additional cost
will be absorbed within the total project budget. 
BACKGROUND: 
On August 14, 2012, the Commission authorized the Conversion of the Zone 3 Ticket Lobby to
Flow-Through Concept project. This portion of the project relocates Virgin America's airline
ticket office to enable construction of Delta Air Lines new flow-through ticket counters.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
October 29, 2012 
Page 2 of 4 
Delta Air Lines experienced severe crowding in the Delta ticket lobby in the summer of 2010,
the first summer of combined operations after their merger with Northwest Airlines. Delta
undertook some minor alterations of the narrow ticket lobby to address the congestion in the near
term but recognized these fixes are insufficient for the long term. 
Since 2010, Delta has increasingly positioned Seattle-Tacoma International Airport as one of its
major international gateways, adding new nonstop service to Beijing, Osaka, Paris, and
Amsterdam. In view of Delta's plans to increase its service to the Seattle market, both Delta and
the Port began investigating ways to reduce overcrowding and make improvements that will last
well into the future. 
After examining different options, Delta and the Port agreed that converting the Delta ticket
counter to a "flow-through" layout similar to Alaska Airline's is the preferred solution.
Computer modeling of the proposed solution by the Airport's Planning Department
demonstrated a significant improvement to customer service. 
Delta has completed design and obtained internal approvals to begin this remodel. Delta has
requested to complete this work as a tenant project before next summer's high traffic season
under a tenant reimbursement agreement similar to the one used earlier for its SkyClub project at
the South Satellite. Since much of the construction will take place in Delta's leased spaces, and
since it must be completed by next summer, Port staff has agreed to their request to build much
of the project per the Port's AV-2 Tenant Reimbursement Guidelines. Staff will work with Delta
to ensure the Port's values, such as setting appropriate small business goals and paying
prevailing wages, are reflected in this construction project. Delta is also expected to spend an
estimated $2,500,000 of Delta's own capital funds in support of this project. 
Delta's desire to complete work on their Flow-Through counters by summer 2013 means that
other projects to enable the Airport to relocate tenants with leased areas within the footprint of
Delta's new counters, such as Virgin America's airline ticket office, have to be handled quickly.
The project team determined that utilizing existing open order design and small works
construction contracts would be the most efficient method to complete the work and meet Delta's
schedule.
Design proceeded rapidly, but significant changes had to be made to the heating, ventilating and
air conditioning design when the design team learned that the mechanical unit originally planned
to supply conditioned air to the new space did not have capacity remaining to do so. The
addition of ducting to a different mechanical unit located farther away increased the scope and
costs of the project's mechanical work such that it can no longer be completed as a small works
project.
The project team analyzed several options for completing Virgin's ticket office relocation and
determined that a major construction contract was needed to complete the tenant improvements
in the new office space. Small works contractors will still be used to provide demolition and
construction of an adjacent public corridor and police storage area necessary to complete the
Virgin America airline ticket office work to keep both projects moving forward as efficiently as
possible.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
October 29, 2012 
Page 3 of 4 
PROJECT JUSTIFICATION: 
The work planned under this authorization will relocate a tenant office space that impedes
construction of Delta's new flow-through ticket counters. Completion of the flow-through
counters support projected increases in passenger traffic, and provide improved overall
circulation, operational flexibility, and efficiency at the Airport.
Project Objectives: 
Relocate Virgin America's airline ticket office in accordance with public procurement
regulations 
Ensure construction of Virgin's new offices is completed in time to meet Delta's
construction schedule. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
Port crews and small works contractors will build out a public corridor and police storage
area adjacent to the vacant tenant space planned for Virgin America's new ticket office 
space just south of Checkpoint #3 in the center of the terminal building. 
A major construction contract will build out the tenant improvements for Virgin
America's new airline ticket office just south of the newly built public corridor and police
storage space. 
Schedule: 
Activity                            Dates 
Commission Authorization of Major Contract                    November 6, 2012 
Construction of Virgin's Airline Ticket Office                January 2013  April 2013 
FINANCIAL IMPLICATIONS: 
Budget Status and Source of Funds: 
This project, CIP #C800492, is included in the 2013-2017 capital budget and plan of finance
with a budget of $11,778,000. Together with an expense budget of $1,347,000, the total project
cost is $13,125,000. The funding sources include the Airport Development Fund and existing
revenue bond proceeds. 
No additional funding is required for this authorization as the increased costs associated with this
enabling project can be absorbed within the total project budget. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
August 14, 2012  Commission authorized Conversion of Zone 3 Ticket Lobby to Flow-Through
Concept (CIP #C800492) including construction of the Virgin America ticket offices as a small
works project.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
October 29, 2012 
Page 4 of 4 
December 6, 2011  Commission authorized Airline Realignment Miscellaneous Building
Improvements project (CIP #C800475) including the Virgin America ticket office design.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.