PORT OF SEATTLE 
MEMORANDUM 
REVISED COPY               Item No.      5c 
COMMISSION AGENDA 
ACTION ITEM           Date of Meeting   September 11, 2012 

DATE:    September 7, 2012 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Michael Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Project Management 
SUBJECT:  Airline Realignment Tenant Improvements (Expense) Regulated Materials
Management for Zone 2 Ticket Counter and Offices and Tenant Relocation 
Amount of This Request: $730,000        Source of Funds: Airport Development Fund 
Est. State and Local Taxes: $37,000        Est. Jobs Created: 12 
Total Project Cost: $23,285,000 
ACTION REQUESTED: 
Request Port Commission authorization for the Chief Executive Officer to: (1) advertise and
execute a construction contract for regulated materials management (RMM) abatement for the
Zone 2 Ticket Counter and Offices; (2) use Port crews for construction to support RMM
abatement; and (3) execute a contract for moving services to relocate airline tenants, all
associated with the Airline Realignment Tenant Improvements Project at Seattle-Tacoma
International Airport. The cost of the RMM and moving services is $730,000 (expense). 
SYNOPSIS: 
This project is for the RMM abatement of portions of the Zone 2 ticket counter and offices in
support of the United Airlines (United) tenant project that is now under design and for which
authorization for construction will be sought at a future date. As part of the airline realignment, 
the Port will contract for moving services in order to move the participating airlines into their
new spaces. 
This authorization is one of many that are necessary for the one-time realignment of air carrier
operations that will take place at the Airport in 2013. The realignment was driven by the merger
of major carriers and the consolidation needs of Alaska Air Group, necessitating the
repositioning of aircraft, gate holdrooms, and ticketing positions throughout the Airport. The
costs associated with this authorization request are included in the total estimated project cost of
$23.3 million (expense), and these costs are included in the 2012 operating budget.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
Revised September 7, 2012 
Page 2 of 6 
BACKGROUND: 
With ongoing airline consolidation and a goal to maximize utilization of our existing facilities,
the Airport is exercising the One-Time Reallocation provision in the current Signatory Lease and 
Operating Agreement. The reallocation will require a number of modifications associated with
the airlines, which will relocate their gate and ticket counter operations to effectively operate in
their new locations. The realignment was driven by the merger of major carriers and the
consolidation needs for Alaska Air Group that necessitated the repositioning of gates, holdrooms,
and ticketing positions throughout the Airport.
Of the airlines involved in the Airline Realignment, Alaska Airlines and United Airlines have 
chosen to complete tenant improvements as tenant projects to be reimbursed by the Port. In order
to allow United to begin its construction of new Zone 2 ticket counters and offices and remain on
the overall project schedule, RMM abatement must begin now. 
PROJECT JUSTIFICATION: 
The work planned under this project represents a critical component in supporting the broader
airline relocation effort while also providing improved operational efficiency throughout the
Airport.
Project Objectives: 
Support the timely relocation of airlines. 
Removal of regulated materials as required. 
Enable the Airport to gain more flexibility to maximize the use of ticket counters. 
Reduce the cost to airlines as they relocate within the existing terminal facilities. 
Provide 'like-for-like' facilities for airlines being relocated to new ticket counters. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
This project is for the RMM abatement of portions of the Zone 2 ticket counter and offices. The
regulated material in this project will include the removal of asbestos-containing material in the
fireproofing above the ceiling and all associated work related to it. 
The moving service contract will provide moving services for the tenants associated with this
realignment program. Also, as part of the airline realignment, the Port will contract for moving
services in order to physically move the participating airlines into their new spaces.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
Revised September 7, 2012 
Page 3 of 6 
Schedule: 
The project schedule is as follows: 
Commission Authorization                    September 2012 
Start RMM work for offices                     November 2012 
Complete RMM work for offices                 December 2012 
Start RMM work for ticket counters                  January 2013 
Complete RMM work for ticket counters             February 2013 
Complete moves of airlines                         May 2013 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary: 
Capital       Expense      Total Project 
Original Budget                             $0   $23,285,000    $23,285,000 
Revised Budget                           $0   $23,285,000    $23,285,000 
Previous Authorizations                       $0    $9,207,255     $9,207,255 
Current request for authorization                   $0     $730,000       $730,000 
Total Authorizations, including this request           $0    $9,937,255     $9,937,255 
Remaining budget to be authorized                $0   $13,347,745    $13,347,745 
Project Cost Breakdown:               This Request  Total Project 
Construction                          $510,000   $4,060,000 
Construction Management                $103,000    $653,500
Design                             $10,000    $515,000
Project Management                    $40,000    $481,700
Permitting                                 $0      $67,400
State & Local Taxes (estimated)               $37,000     $337,400 
Professional Moving Services                $30,000     $30,000 
Future Projects*                             $0   $17,140,000 
Total                                 $730,000    23,285,000 
* The "Future Projects" cost item includes cost breakdown items such as
additional state and local taxes that have not been fully defined at this time. 
Budget Status and Source of Funds: 
This total of $23,285,000 of operating costs will be spread over 2011 through 2013. The Airport
included $8.2 million in the 2012 operating budget and the 2012 expenses for RMM will be
covered by this budget item; remaining expenses that will be incurred in 2013, such as the
majority of the moving services contract, will be included in the 2013 expense budget. All of the
costs will be incorporated into airline rates and charges and recovered through terminal rents. As
such, the funding source will be the Airport Development Fund.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
Revised September 7, 2012 
Page 4 of 6 
Financial Analysis and Summary: 
For 2012, the budgeted operating costs associated with terminal realignment will increase
passenger airline costs per enplaned passenger (CPE) by $0.49. 
STRATEGIC OBJECTIVES: 
This project promotes the Port's business objectives to "Ensure Airport and Seaport Vitality" and
"Be a Catalyst for Regional Transportation Solutions" by realigning Airport users with Airport
resources and improving operational efficiencies throughout the Airport. 
ENVIRONMENTAL SUSTAINABILITY: 
Abatement of regulated materials prior to construction activities will remove a source of
potential air pollution. 
BUSINESS PLAN OBJECTIVES: 
This project supports the Airport's strategic goal of operating a world-class international airport
by anticipating and meeting the needs of our tenants and passengers and by managing our assets
to minimize the long-term total cost of ownership by improving efficiencies. 
TRIPLE BOTTOM LINE SUMMARY: 
This project is being performed at the request of our customer airlines. It will benefit the Airport,
the traveling public, and the environment through consolidating airlines and efficient operations. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1  Require the abatement of regulated materials to be performed by the airline
completing the tenant improvements. The airlines are typically reluctant to complete this work.
This is not the recommended alternative. 
Alternate 2  Do nothing. The airline realignment cannot be executed. This is not the
recommended alternative. 
Alternative 3  Port proceeds with abatement of regulated materials using combination of small
works packages and Port crews to perform the work. This alternative allows for flexibility to
respond to unforeseen conditions and late tenant requests. This is the recommended
alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
On July 10, 2012, the Port Commission authorized Airline Realignment Tenant Improvements in
the amount of $4,243,400 to advertise and execute a construction contract and use of Port Crews
for Airline Tenant Improvements  Airline Realignment. 
On July 10, 2012, the Port Commission authorized CUSE construction at ticket counters and
gates, and seating in the amount of $1,887,000.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
Revised September 7, 2012 
Page 5 of 6 
On June 26, 2012, the Port Commission was provided an update briefing with the NorthSTAR
budget restructuring. 
On June 26, 2012, the Port Commission authorized additional budget of $400,000 to add two
fuel pits (C800472). 
On April 24, 2012, the Port Commission authorized Airline Realignment Tenant Improvements
in the amount of $225,000 for regulated materials management. 
On April 10, 2012, the Port Commission authorized additional budget to enter into a construction
contract for airfield improvements including Exterior Gate Improvements  Airline Realignment
(C800472). 
On March 27, 2012, the Port Commission authorized design and construction of gate B1 and
B11 jet bridges as elements of Passenger Loading Bridge Replacement Project- Airline
Realignment (C800467) in the amount of $1,570,000. 
On January 24, 2012, the Port Commission received a briefing on the Airport Realignment
Program. 
On January 24, 2012, the Port Commission authorized construction of Exterior Gate
Improvements  Airline Realignment (C800472) in the amount of $2,613,000. 
On January 24, 2012, the Port Commission authorized design for CUSE at Ticket Counter/Gates
& Seating (C800473) in the amount of $484,000. 
On December 6, 2011, the Port Commission authorized construction of Baggage Handling
System (BHS) Improvements  C22 BHS Connection to C1/C1-MK1 Replacement (C800382) at
the Airport in the amount of $3,604,000. 
On December 6, 2011, the Port Commission authorized design of the Miscellaneous Building
Improvements  Airline Realignment (C800475) at the Airport in the amount of $1,721,000. 
On December 6, 2011, the Port Commission authorized design of the Airline Tenant
Improvements  Airline Realignment (expense) at the Airport in the amount of $3,776,000. 
On November 22, 2011, the Port Commission was provided with a verbal preliminary briefing of
December 6, 2011, items with a diagram. 
On September 27, 2011, the Port Commission authorized execution of an IDIQ contract for
Airline Realignment Tenant Improvements and Ticket Counter Design services totaling
$10,000,000. 
On September 12, 2011, the Port Commission received a summary briefing on the Airport
Realignment Program at the Airport. 
On June 14, 2011, the Port Commission authorized design of the Exterior Gate Improvements  
Airline Realignment project (C800472) at the Airport in the amount of $499,000. 
On June 14, 2011, the Port Commission authorized design of the Airport Signage  Airline
Realignment project (C800474) at the Airport in the amount of $238,000.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
Revised September 7, 2012 
Page 6 of 6 
On March 1, 2011, the Port Commission authorized design and some construction of the
Baggage Handling System (BHS) Improvements - C22 BHS connection to C1/C1-MK1
Replacement /TC3 Replacement (C800382) in the amount of $1,731,000. 
On February 22, 2011, the Port Commission authorized the first phase of the Passenger Loading
Bridge Replacement  Airline Realignment Project (C800467) including design, purchase, and
execution to replace, refurbish and relocate PLBs at Concourse D.
On February 22, 2011, the Port Commission was shown a summary listing of realignment
projects and authorized Planning for Terminal Realignment in the amount of $713,000. 
On January 25, 2011, the Port Commission was briefed on several projects that are part of the
overall airline realignment program and which required a single Commission authorization in
order to meet the realignment schedule. The first part of the realignment program was authorized
by the Commission on this date under the Concourse D Common Use Expansion Project
(C800455). 
On September 28, 2010, the Port Commission was given a summary briefing of the upcoming
2011 capital improvement plan that included the airline realignment program elements. 
On June 8, 2010, the Port Commission authorized execution of an IDIQ contract for the
Terminal Development Strategy Campus Planning Services IDIQ in the amount of $1,300,000.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.