5e

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5e 
ACTION ITEM            Date of Meeting    July 24, 2012 

DATE:    July 6, 2012 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    David Soike, Director, Aviation Facilities and Capital Program 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Parking Garage Emergency Lights project at Seattle-Tacoma International Airport 
(CIP #C800230) 
Amount of This Request: $1,157,081   Source of Funds: Airport Development Fund 
Est. State and Local Taxes: $0 
Est. Total Project Cost: $5,269,600 
ACTION REQUESTED: 
Request authorization for the Chief Executive Officer to prepare full design and construction bid
documents for the Parking Garage Emergency Lights project at Seattle-Tacoma International
Airport in the amount of $1,157,081, with a total estimated budget for the completed project of 
$5,269,600. 
SYNOPSIS: 
This request authorizes the Airport Parking Garage Emergency Lights project to move forward
with design and preparation of construction documents. This work will be performed under an
existing Emergency System Electrical Infrastructure Design indefinite delivery, indefinite
quantity (IDIQ) contract. This project was included in the 2012  2016 capital budget and plan
of finance. 
The parking garage has light fixtures throughout the parking areas and stairwells that allow for
24-hour operations. A small portion of those fixtures have dual functions and one is to serve as
emergency light fixtures when normal power is lost. The current emergency lighting system was
intended to be a temporary fix after a system failure in 2007. It is not fully code compliant. This
project provides the infrastructure that will ensure the Port continues to meet applicable life
safety code requirements for egress area illumination levels in the parking garage. In addition,
this project will eliminate the need for the battery-powered emergency lights currently in use, 
therefore eliminating the need to purchase batteries and pay associated disposal fees. During
design, staff will review available lighting fixtures and the selection will be based on fixtures that
will decrease electrical loads while providing acceptable light output. In addition, this design

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 6, 2012 
Page 2 of 5 

will provide a foundation for a follow-up project to install new light fixtures throughout the
garage that will further reduce energy consumption. 
BACKGROUND: 
In 2007, the existing uninterruptible power supply (UPS) batteries that provided backup power
for egress lighting in the parking garage failed. In the event of a normal power failure, these
batteries would have provided backup power to the light fixtures on emergency circuits and these
fixtures maintained light levels necessary for safe egress from the garage. Following the battery
failures in 2007, temporary battery backup fixtures were installed to provide emergency egress
lighting until a permanent solution could be implemented. This temporary system is near the end
of its life and is not compliant with code requirements. The permanent solution will comply with 
egress lighting requirements as specified in NFPA 101: Life Safety Code (National Fire
Protection Agency). Failure of the UPS batteries and the corresponding costs to maintain the
temporary fixtures have compelled the Port to look at light fixtures and emergency power
distribution infrastructure alternatives that will utilize energy saving technology with acceptable
light quality while reducing maintenance and operating costs to provide reliable egress lighting. 
Staff has identified grants that may apply to this project, and will make a determination during
design to pursue them if applicable. In addition, staff may partner with the State of Washington
energy contracting office, and will make that determination during design if applicable. These
decisions would be detailed in future requests for authorization. If grants and state energy
partnership are deemed favorable to the project, then staff will return to Commission to request
design, scope, and any associated budget changes. 
PROJECT JUSTIFICATION: 
The purpose of this project is to provide the electrical infrastructure for a new source of
emergency power to feed the parking garage emergency lighting circuits in order to ensure that
code required level of egress illumination is provided for the safety of customers.
This project will provide the infrastructure for a follow-up project to replace the emergency light
fixtures in the parking garage. This new infrastructure capacity will provide the capability to
utilize energy saving lighting technology that will significantly decrease energy usage,
maintenance, and operating costs. 
Project Objectives: 
Satisfy applicable code requirements for emergency lighting; 
Provide proper egress lighting for the safety of customers; 
Allow for the capability to decrease electrical loads on the emergency circuits by
utilizing current lighting technology in fixtures that require less power; and 
Decrease maintenance and operations cost by utilizing current lighting technology in
fixtures with longer lamp life.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 6, 2012 
Page 3 of 5 

PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
Construction of four new electrical closets to house the new electrical equipment for code
compliance that requires normal and emergency power to be segregated. 
Installation of a new distribution panel and automatic transfer switch to support the load
transfer during scheduled system testing by maintenance. 
Installation of meters in each of four new normal and emergency circuit panel-boards
with Ethernet connection to the Port's existing power monitoring system networks. 
Port Construction Services (PCS) to complete a Regulated Material Management (RMM)
good faith survey. 
Installation of conduit and electrical wiring to connect garage lighting to generator
facilities in the terminal that have available capacity in the event of a power outage
emergency. 
Schedule: 
Commission Authorization for Design                   July 2012 
Commission Authorization to Advertise Construction         December 2012 
Advertise                                      February 2013 
Notice to Proceed                                 April 2013 
Construction Complete                            August 2014 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary:        Capital        Expense       Total Project 
Original Budget                      $750,000            $0        $750,000 
Budget Increase                    $4,519,600             $0       $4,519,600 
Revised Budget                    $5,269,600            $0       $5,269,600 
Previous Authorizations                     $0            $0            $0 
Current request for authorization          $1,157,081             $0       $1,157,081 
Total Authorizations, including this
$1,157,081            $0       $1,157,081 
request 
Remaining budget to be authorized        $4,112,519             $0       $4,112,519 
Total Estimated Project Cost             $5,269,600             $0       $5,269,600 
Project Cost Breakdown:                      This Request       Total Project 
Construction                                         $0        $3,293,900 
Construction Management                          $50,661         $554,430 
Design                                      $652,260         $652,260 
Project Management                             $421,550         $431,330

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 6, 2012 
Page 4 of 5 

Permitting                                        $32,610           $32,610 
State & Local Taxes (estimated)                             $0          $305,070 
Total                                           $1,157,081         $5,269,600 
Budget Status and Source of Funds: 
The Parking Garage Emergency Lights project (CIP #C800230) is included in the 2012-2016 
capital budget and plan of finance as a business plan prospective project in the amount of
$750,000. The budget increase of $4,519,600 will be transferred from the Non-Aeronautical 
Renewal/Replacement (C800153), a business plan prospective project allowance, resulting in no
net change to the Aviation capital budget. The source of funds for this project is the Airport
Development Fund. 
The project budget has increased due to scope increase to include replacement of approximately
1,500 emergency light fixtures with more energy-efficient fixtures. This led to design concept
modifications to include four new electrical closets to comply with the National Electrical Code
that requires the segregation of normal and emergency power. Fire heat sensors were added to
comply with Port Fire Department requirements in each closet. The scope also increased to
include electric power revenue meters to provide monitoring of electric loads. The project
budget was also affected by a scope transfer to include emergency lighting replacement and
associated infrastructure on Floors 1 and 2 from the Parking Retrofit Project (CIP #C800225)
for design efficiency. 
Financial Analysis and Summary: 
CIP Category             Electrical Infrastructure 
Project Type              Renewal & Replacement 
Risk adjusted discount rate     N/A 
Key risk factors             N/A 
Project cost for analysis        $5,269,600 
Business Unit (BU)          Landside, Parking 
Effect on business performance  NOI after depreciation will decrease 
IRR/NPV             N/A 
CPE Impact             N/A 
Lifecycle Cost and Savings: 
The estimated life expectancy for this project is 40 years for the electrical panels and electrical
closets. 
STRATEGIC OBJECTIVES: 
This project aligns with the Port's objectives to operate a world-class international airport by
ensuring safe and secure operations and lead the airport industry in environmental innovation
and minimize the Airport's environmental impacts.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 6, 2012 
Page 5 of 5 

ENVIRONMENTAL SUSTAINABILITY: 
This project will provide the opportunity to apply environmental sustainability principles
primarily through the use of energy-efficient light fixtures by reducing the energy use by an
estimated 50% while providing more than four times the lamp operating life compared to what is
currently installed.
TRIPLE BOTTOM LINE SUMMARY: 
The project supports economic development by investing in an upgraded parking garage to serve
the public's safety needs at the Airport. Environmental sustainability principles will be
employed as needed or when practical. Procedures set forth in the Port's new Small Contractor
and Supplier Project from the Office of Social Responsibility will be used when applicable in the
project contracting process. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1  Do nothing. Do not implement any improvements to the existing parking garage.
This alternative is not recommended because the temporary battery backup emergency lighting
fixtures have reached their life expectancy and will begin to fail and the parking garage currently
does not meet egress lighting code. This alternative will negatively affect the safety of the
public. This is not the recommended alternative. 
Alternative 2  Provide new emergency power to allow for the emergency light fixtures to be
replaced with newer and more energy-efficient lighting technology. This alternative will meet
the life/safety code requirements for egress illumination levels and provide safety for the public.
This is the recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
None.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.