7b Report

Item Number: 7b_Report
Meeting Date: April 3, 2012


Commission Staff Brieng
Capital Improvement Projects
Fourth Quarter Report 2011

This page intentionally left blank









ii  Port of Seattle 4Q 2011 Report

Port of Seattle
Capital Improvement Project Report
Fourth Quarter 2011
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2011 the Port plans to invest over $378,000,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 4Q 2011 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................5 ........... 
C100266 et al .......Rental Car Facility ...............................................6-7.......... ...............
C102030 ...............Stormwater Management Program .......................8 ...........
C102163................Main Terminal Baggage Screening ....................9-10......... ...................................
C102334 ...............Water System Isolation Valve Upgrade ................11 .......... ...............
C102573 ...............Airf eld Pavement Replacement ...........................12 ..........
C800019 ...............Loading Bridge Utilities .........................................13 ......... ............................ ......................................
C800034 ...............North Expressway Relocation ..............................14 .......... ...............
C800061 ...............Main Terminal South Low Voltage ........................15 .......... ...............
C800105 ...............Airport Owned Gate Infrastructure .......................16 .......... ................. ............................................
C800107 ...............C4 UPS System Improvements ............................17 .......... ...............
C800109 ...............Garage Escalator & "A" Elevator Upgrade ...........18 .......... ...............
C800112................Runway 16C/34C Panel/Joint Sealant .................19 ..........
C800147 ...............Concessions Unit Readiness Program ................20 .......... ...............
C800148 ...............GML Arrivals Hall Concessions ...........................21 .......... ...............
C800174................FIS - New Primary Inspection Booths ..................22 .........
C800203 ...............Common Use Lounge Remodel ...........................23 ..........
C800237 ...............Terminal Escalators Modernization ......................24 ..........
C800238 ...............Central Plant Pre-Conditioned Air ........................25 .......... ...............
C800242 ...............Security Checkpoint Cameras..............................26 ..........
C800251 ...............Vertical Conveyance Modernization.....................27 ..........
C800253 ...............Parking System Replacement ..............................28 ........................................ 
C800254 ...............Aircraft RON Parking Post Off ce Site..................29 ........................................ 
C800268 ...............Stage 2 Mechanical Energy Implementation .......30 ..........
C800274 ...............8th Floor Weather Proof ng ..................................31 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......32 ..........
C800331 ...............Communication Cable Add To MT, D, CTE ..........33 ..........
C800334 ...............Two new CTE Freight Elevators ...........................34 ..........
C800335 ...............EGSE Electrical Charging Stations ...................35-36 .......
C800336 ...............South Satelite Delta Sky Club Extension .............37 ........................................ 
C800360 ...............Roof Replacement Program .................................38 ..........
C800374 ...............Claim Device 14 and Lower Inland .......................39 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ...............................40 ..........
C800406 ...............RW 16C/34C Reconstruction Design ...................41 ..........
C800412 ...............South Satellite Concessions Project ....................42 ........................................ 
C800414 ...............Access Control Door Additions ............................43 ..........
C800415 ...............ALCMS Upgrade...................................................44 .......... 
C800417 ...............Lagoon 3 Bird Wires .............................................45 ..........


2  Port of Seattle 4Q 2011 Report

C800420 ...............Additional Air f eld Mitigations at Tyee ..................46 ..........
C800426 ...............FIS Improvement - Phase I ...................................47 .......... ...............
C800455 ...............Concourse D Common Use Environment ............48 ........................................ 
C800459 ...............2011-2013 Roof Replacement Program ...............49 ..........
C800466 ...............South Satellite - Additional Gate Lobby ................50 ........................................ 
C800467 ...............PLB Replacement .................................................51 .......... 
C800469 ...............Water System Isolation Valve - Airf eld ................52 ..........
C800471 ...............Security Checkpoint Optimization ........................53 ..........
C800472 ...............Exterior Gate Improvements ................................54 ..........
C800474 ...............Airport Signage .....................................................55 .......... 
C800475 ...............Miscellaneous Building Improvements - AR.........56 ..........
Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................57 .......... ...............
C200042 ...............Highline Community College Noise Insulation .....58 .......... ...............
C200048 ...............Home Insulation Retrof t .......................................59 ..........  ...............
C200093 ...............Single Family Home Sound Insulation .................60 .......... ...............
C800046 ...............Street Vacations  Des Moines Creek 1 ..............61 ........................................ .................................... 
C800146 ...............RMU/Kiosk Concession Program ........................62 ........................................ 
C800150 ...............Burien Commercial Property Acquisition .............63 .......... ...............
C800154 ...............Tenant Reimbursement ........................................64 .......... 
C800354 ...............Paint Stripper Equipment ......................................65 ........................................ ...................................... 
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800133 ..............T-86 Grain Facility Modernization (Phase I) ........66 ..........
C800165 ..............Seaport Security Grant Round 7 .........................67 .......... ...............
C800183 ...............P91 Fender System Upgrade ...............................68 ..........
C800264 ...............T-10 Interim Redevelopment.................................69 ..........
C800298 ...............T-91 Watermain Replacement ..............................70 ..........
C800343 ...............T-91 Roadway Pavement .....................................71 ..........
C800349 ...............T-5 Crane Cable Reels .........................................72 ..........
C800416 ...............T-18 Fender Replacement ....................................73 ..........
WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................74 ..........

Port of Seattle 4Q 2011 Report  3

E104324 ................Viaduct Construction Coordination ......................75 ..........
E104362 et al ........Street Vacations T-5/18/105 .................................76 ........................................ 
E104559................T-18 Pile Cap Repair Pilot Project ........................77 ........................................ 
E104610 ................Underdock Inspections .........................................78 .......... .............................. 
Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800136 ...............FT South Wall Reconstruction Phase VI ..............79 ..........
C800137 ...............FT C15 HVAC Improvements ...............................80 ........................................ 
C800175 ...............MIC Central SeaWall Replacement ......................81 ..........
C800187 ...............RE Maintenance Shop Solutions..........................82 ..........
C800386 ...............FT NW Dock E. Fender System Replacement.....83 ..........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ....................84 ..........
C800003...............Maximo Enterprise Implementation......................85 .......... ...............
C800222 ...............Airline Activity Management .................................86 ..........
C800319...............Port of Seattle Internet Redesign.........................87 ........................................ 
C800321 ...............Enterprise Project Cost Management ..................88 .......... ...............
C800322 ...............Records and Document Management .................89 ........................................ 
C800328 ...............Propworks Upgrade ..............................................90 .......... 
C800387 ...............Time Clock System ...............................................91 ..........
C800392 ...............PeopleSoft Financial Upgrade ..............................92 ........................................ 
C800393 ...............Police Records Management System ..................93 ........................................ 
C800481 ...............CUSE Migration ....................................................94 .......... 
C800501 ...............Maintenance Planning System .............................95 ..........

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
Variance Since Last Report
No Diamond  On Budget or On Schedule

4  Port of Seattle 4Q 2011 Report

FOURTH QUUARTER REPPORT, 2011
3rdd Runwaay Progrram
Status Snapshot
On Schedule
Prooject: C0000683,       Thee 3rd Runwway Programm
On Buddget
C0001138, C0001175,      connstructed a new 8,5000 foot long
0 Changge Orders
C0001331, C0001751,      runnway, conneecting taxiwways, and
Total Change Ordeers Amount:
C0001760, C1000172      relaated infrasttructure.
$0.00
Buddget: $932,325,659
Phaase: Consstruction                       Budgett/Costs Inccurred
Start: 05/27/1997
1150
Commpletion: 12/31/20111
1100
1050
1000  Millions
Significant DDevelopmments
950
The 2011 consstruction contract workk is complette includeinng in-       Dollars in 900850
streaam work. TThe remaining tasks are the Port of Seattle
800
Mainntenance BBuilding demmolition, temmporary inteerchange ddemolition,      A u thorized Foreca s ted Costs Incurre d
and RST propeerty acquisition.
Schhedule
Bidss were openned on Sepptember 22,, 2011 for thhe Alaska         2012 Coontract Connst. Costs
Mainntenance BBuilding demmolition withh Constructtion Group
0.5
Interrnational awwarded the constructioon contract. Construcction is noww
0.4
scheeduled to sttart in the fiirst quarter of 2012.
Millions  0.3
Buddget                             0.2
The project foreecast is witthin the appproved budgget and autthorization.    Dollars in  0.1
0
Initial   Change   Spent
Chaange Ordder
Orders
Nonne this quarter
Rissks                              Photo
Nonne
Buddget Trannsfers
To CC800415 (AALCMS Upggrade)           $83,144


AIRRPORT
Port of Seattle 4Q 2011 Report  5

FOURTH QUARTER REPORT, 2011
Rental Car Facility
Status Snapshot
Delayed Schedule
Project:   C100266,     The program will construct a       Under Budget
C102167, C800032     consolidated rental car facility (RCF)  1,170 Change Orders
Budget: $419,306,000   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $12,814,738
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.          Budget/Costs Incurred
Significant Developments                     440
RCF construction is nearly 98.4 percent complete. Remaining work      420
includes installing on-site roadway signage and structures, 800Mhz     Millions 400
emergency radio system and commissioning. Completing many
punch lists throughout the RCF. Averaging around 50 workers daily.     380
Site work and landscaping is complete. Several major quality issues     Dollars in 
360
being resolved. Analysis of Contractor and sub claims submitted to
340
Contractor. BMF construction is 92 percent complete. Remaining
Authorized  Forecasted Costs Incurred
work includes interior finishes, limited equipment installation,
landscaping, commissioning and training. ORI construction nearing
completion with remaining contract work on International Blvd, SR99
Bridge, S 160th St Bridge, and landscaping. MTI north and south bus  Construction Costs
stops complete, begin installing signs and conduit Januray 9, 2012.
300
Gillig delivered all buses; contract in closeout.
250
200
Schedule                             Millions
150
RCF Opening day set for April 19, 2012 with Temporary Certificate of
100
Occupancy scheduled for February 20, 2012. Tenant work to be       Dollars in   50
completed April 2012. BMF scheduled completion is March 2012.
0
ORI scheduled completion is January 2012 (except for signage            Initial Change Spent
activation). MTI completion is April, 2012 based on award date.                Orders
Budget                            Photo
Customer Facility Charge revenues continue to increase slightly
each month, trending over $1,900,000 above projections. The
program forecast is under the approved budget and authorization.
Change Order
93 change orders were issued this quarter in the amount of
$555,697.

6  Port of Seattle 4Q 2011 Report

Risks
changes as project completes, contractor performance, claims submitted by prime contractor and one
subcontractor; and quality issues.
For ORI: coordination with RCF and TI contractors, weather, and completion of punch list items.
For BMF: multiple subcontractor congestion within building space, and completion of commissioning
and training requirements.
Budget Transfers
$1,810,820 was transferred out of C100266 to expense work projects to fund non-capital expenses
such as training.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - Cumulative change
order percentage through this quarter is 14.5%. Primary reasons for these changes are differing site
conditions, removal of lead based paint and modifications to signage supports.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - Cumulative change
order percentage through this quarter is 0.0%.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - Cumulative change order percentage through this quarter is 29.0%. Primary reasons
for these changes are contaminated materials and unknown conditions.
Bus Maintenance Facility - MC-0316730 - Cumulative change order percentage through this quarter
is 0.82%.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative change order percentage through
this quarter is 19.4%. Primary reason for changes is the removal of contaminated soils and
associated impacts. This work and the final contract reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  Cumulative change order percentage
through this quarter is 170.5%. Primary reasons for changes are for additional contractor
management, estimating, scheduling and bidding effort for cost estimate reconciliation,
constructability reviews and value engineering beyond the extent of the original scope to validate
project costs and support the rental car companies and the Port on final approval of the project. This
work and the final contract reconciliation is complete.
AIRPORT
Port of Seattle 4Q 2011 Report  7

FOURTH QUARTER REPORT, 2011
Stormwater Management Program
Project:   C102030    The program achieves permit       Status Snapshot
Budget: $46,297,347   requirements and makes the Airport a  On Schedule
Phase: Construction   leader in stormwater management by  On Budget
Start: 06/11/2002       construction of flow control, water     11 Change Orders
Completion: 12/31/2011  quality treatment and low stream flow  Total Change Orders Amount:
mitigation facilities.                  $8,103
Budget/Costs Incurred
Significant Developments
100
All project work is complete and the Stormwater Management
Program is in the close-out phase. This will be the last quarterly        80
report for this project.                                        Millions 60
40
Schedule                            Dollars in 20
The Stormwater Management program is projected to be closed out
0
during the first half of 2012.                                      Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                          1.2
None                                   1
Millions 0.8
Risks
0.6
None identified at this time.
Dollars in 0.4
0.2
Budget Transfers
0
None this quarter                                          Initial   Change   Spent
Orders



AIRPORT
8  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $223,533,540   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget   4Q 09
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
Significant Developments                     235
The C-1 baggage handling/screening system has been placed into     230
revenue service for the Alaska Air Group. The C-1 Lid Replacement    Millions 225
and Repair work is complete. The only work remaining on this        220
project is the installation of new Direct Digital Controls (DDC) for the    Dollars in 215
boiler room to indicate when pumps are off-line.                  210
Authorized   Forecasted  Costs Incurred
Schedule
The project was delayed approximately two years from the original
Construction Costs
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope
200
changes. Turner Construction demobilized on May 31, 2009. The
150
GCCM construction contract with Turner Construction has been
closed. The remaining fire sprinkler and fire proofing work was          100   Millions
completed.
50
Dollars in 
Budget                              0
Initial    Change    Spent
Orders
The project forecast is within the approved budget and authorization.
Change Order                         Photo
665 Change Orders have been issued on this project.
Risks
None
Budget Transfers
None this quarter


Port of Seattle 4Q 2011 Report  9

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated as they were unable to meet the
project schedule requirements. The remaining work was rebid in the fall of 2006. Alaska Airlines
asked that we include the BHS work within the 2-step ticket counter project; which increased the
amount of BHS work in the bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.












AIRPORT
10  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Water System Isolation Valve Upgrade-non AF
Status Snapshot
Delayed Schedule
Project:   C102334      This project replaces isolation     On Budget
Budget: $854,000       valves on the aging water       0 Change Orders
Phase: Design        distribution system, necessary for   Total Change Orders Amount:
Start: 10/01/2010         isolating portions of the system in    $0
Completion: 06/31/2012   the event of breaks, leaks, or tieins
, in non-airfield (AF) locations.    Budget/Costs Incurred
1
Significant Developments                     0.8
The project is currently in construction.                         Millions 0.6
0.4
Schedule                            Dollars in 0.2
The schedule was extended to avoid operational impacts during the
0
busy holiday season, as previously reported. Additional delays are        Authorized  Forecasted Costs Incurred
anticipated, due to demolition of an obstructing fence. TSA
requested replacement for the entire section (increase from 60 feet
to 700 feet) and to replace the existing with 12 foot high.
Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time
Budget Transfers
From C800469 (Water System Isolation Valve - Airfield)  $150,000



AIRPORT
Port of Seattle 4Q 2011 Report  11

FOURTH QUARTER REPORT, 2011
Airfield Pavement Replacement
Project:   C102573      The project is intended to be a
Budget: $30,800,000     multi-year pavement replacement   Status Snapshot
Phase: Construction     program to replace some of the    On Schedule
Start: 05/02/2010         worst pavement and joint seal on    On Budget
Completion: 12/31/2016   the airfield.              3 Change Orders
Total Change Orders Amount:
$106,682.16
Significant Developments
Gary Merlino Construction was awarded the 2011 contract. The     Budget/Costs Incurred
2011 contract portion of the program was completed in December
40
2011.
30
Schedule
Millions 20                                                                         The construction work scheduled in 2012 will be the second phase of
a multi-year pavement replacement program performed from 2011 to   Dollars in 10
2015. Port of Seattle Commission authorized design funds on July
0
26, 2011 for the 2012 portion of the program. Authorization of
Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested in the first quarter of 2012 with construction scheduled
to begin in May 2012.
2011 Construction Costs
Budget
5
The project forecast is within the approved budget.
4
Change Order                          Millions 3
Dollars in 
Three change orders were executed this quarter.                   2
1
Risks
0
Any delay will put project out of typical construction window.               Initial  Change  Spent
Orders
Budget Transfers
None this quarter
Photo


AIRPORT
12  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Loading Bridge Utilities
Status Snapshot
Delayed Schedule
Project:   C800019   This project will upgrade all Port-       On Budget
owned loading bridges to the same
Budget: $12,883,000                         0 Change Orders
standards, including 400Hz power and
Phase: Design                            Total Change Orders Amount:
potable water. It will reduce air
Start: 06/28/2007                                 $0
emissions, improve energy efficiency
Completion: 2/28/2014 and save money for the airlines.      Budget/Costs Incurred
15
Significant Developments
Bid opening for the pre-purchased equipment has been delayed due    Millions 10
to the issuance of two addendums (design drawing & equipment
schedules updates) and pre-bid protests for the 400Hz equipment       5
specified in the request for quotation bid package.                 Dollars in 
0
Schedule                               Authorized Forecasted  Costs
Incurred
The equipment procurement schedule has been delayed due to prebid
protests from several motor generator suppliers. The 100%
design review schedule was delayed due to work load of several key  Construction Costs
reviewers.                                        Not Applicable
Budget
The project will be requesting budget for the Regulated Materials
Management (RMM) costs which were not included in the original
request.
Change Order
None
Risks
Airport Operations at certain gates could be impacted during the
construction phase of the project. The Port's power centers might
need to be upgraded to support the Pre-Conditioned Air, Electrical
Ground Support Equipment, and Loading Bridge Utilities projects.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2011 Report  13

FOURTH QUARTER REPORT, 2011
North Expressway Relocation
Project:   C800034
The project is a collaboration       Status Snapshot  Prior Report
Budget: $110,347,700    between the Port and Sound     Delayed Schedule 2Q 11
Phase: Construction     Transit. It reconstructs the North   On Budget
Start: 07/27/2004         Airport Expressway and brought    212 Change Orders
Completion: 07/31/2012   light rail to the Airport.         Total Change Orders Amount:
$8,134,800
Significant Developments
Budget/Costs Incurred
The work in the main contract for reconstruction of the North Airport
Expressway and light rail transit components is complete. The        115
intelligent transportation management system is complete. A final
110
contract to complete paving, landscaping, the north entry art          Millions
features, and other miscellaneous work is complete except for punch    105
Dollars in 
list work and the first year plant establishment.
100
Schedule
95
The main contract reached substantial completion in August 2008         Authorized Forecasted Costs Incurred
and plant establishment was completed in December 2010. A
contract for final paving, landscaping, and reclamation is underway 
and is complete except for punch list work and the first year plant     Construction Costs
establishment period to be complete in mid-2012.
120
Budget                             100
80
The project forecast is within the approved budget and authorization.    Millions
60
Change Order                          40
Dollars in  20
Two change orders were issued this quarter in the amount of
0
$23,535.                                            Initial  Change Order  Spent
Risks
None identified at this time.                                Photo
Budget Transfers
None this quarter


AIRPORT
14  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Main Terminal South Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
0 Change Orders
Start: 06/28/2007      equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD    Main Terminal.
$0
Significant Developments
Budget/Costs Incurred
Due to project deferral and possibility of changes in site conditions
and building codes, the design phase changed from 100% to 90%      2.5
complete. Continue to define additional scope of work due to
2
increased electrical loads and site conditions changes. The 90%       Millions 1.5
design review documents were submitted for review and comments
are currently being addressed. A new Project Notebook is under        1
development to address scope of work, schedule, budget and new     Dollars in 0.5
CPO bid document and contracting processes.
0
Authorized  Forecasted Costs Incurred
Schedule
The project was reactivated and is in the process of determining the
scope of work, schedule and final design budget. The project will     Construction Costs
return to the Commission for authorization of additional design funds  Not Applicable
in the first quarter of 2012.
Photo
Budget
The project budget has been evaluated based on delays and scope
changes and will be submitted to Commission during the first quarter
in 2012.
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area is a 24/7/365 operation. Sequencing of this work
is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
None this quarter
AIRPORT                             Port of Seattle 4Q 2011 Report  15

FOURTH QUARTER REPORT, 2011
Airport Owned Gate Infrastructure
This project purchases and        Status Snapshot
Project:   C800105
On Schedule
Budget: $6,000,000      replaces passenger loading bridges
(PLB) at gates throughout the      Under Budget
Phase: Construction                        0 Change Orders
Start: 07/24/2007         airport. The project is being
performed in phases.           Total Change Orders Amount:
Completion: 12/31/2011                       $0
Significant Developments                    Budget/Costs Incurred
The PLB replacements at Gates B5 and S10 were completed in        8
December 2011 with some follow on field modifications to the
bridges to be completed, continuing through the end of February        6
2012. It was determined that the existing PLB at Gate S3 is not a      Millions
4
good candidate for refurbishment due to its age. As a result, the S3
PLB and associated 60' fixed bridge section are being recommended   Dollars in  2
for replacement instead of refurbishment. It appears that sufficient
0
funds remain in the CIP to accomplish this.
Authorized  Forecasted Costs Incurred
Schedule
The project completed on schedule and under budget. The project   Construction Costs
anticipates requesting approval from the Commission to replace     Not Applicable
additional gates, including the addition of the PLB and fixed bridge
replacement work at S3. Upon approval, the anticipated completion
date for the new scope of work would be 12/31/2012.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
16  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
C4 UPS System Improvements
Project:   C800107    Project will replace existing          Status Snapshot Prior Report
Budget: $2,336,000   Uninterruptible Power Supply (UPS)    Delayed Schedule 1Q 09
Phase: Construction  System, including batteries, with a new  On Budget
Start: 06/28/2007      new system located in the Airport      0 Change Orders
Completion: TBD     Combined Communications and      Total Change Orders Amount:
Command Center (C4).           $0
Significant Developments                    Budget/Costs Incurred
Due to project deferral and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. Continue to define additional scope of work due to          2
increased electrical loads and site conditions changes. The 90%      Millions 1.5
design review documents were submitted for review and comments     1
are currently being addressed. A new Project Notebook is under      Dollars in 0.5
development to address scope of work, schedule, budget and new
0
CPO bid document and contracting processes.
Authorized  Forecasted Costs Incurred
Schedule
The project was reactivated and is in the process of determining the   Construction Costs
scope of work, schedule and final design budget. The project will     Not Applicable
return to the Commission for authorization of additional design funds
in the first quarter of 2012.
Budget
The project budget has been evaluated based on delays and scope
changes and will be submitted to Commission during the first quarter
in 2012.
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as 
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter
AIRPORT                             Port of Seattle 4Q 2011 Report  17

FOURTH QUARTER REPORT, 2011
Garage Escalator & A-Bank Elevator Upgrade
Project:   C800109    This project renews aging elevators    Status Snapshot Prior Report
Budget: $5,815,000    and escalators in the Airport Parking   Delayed Schedule    3Q 10
Phase: Close Out     Garage to provide reliable vertical    On Budget
Start: 09/11/2007       transportation to customers for years   26 Change Orders
Completion: 10/31/2011  to come.                 Total Change Orders Amount:
$234,937
Significant Developments                    Budget/Costs Incurred
The project is complete and is in the close-out phase. This will be
8
the last quarterly report for this project.
6
Schedule                            Millions
4
Final project close-out is anticipated to be completed during the first
quarter of 2012.                                       Dollars in  2
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None
4
Risks                                 3
Millions
None.                                       2
Dollars in 
1
Budget Transfers
0
None                                     Initial Change Order Spent




AIRPORT

18  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot
The scope of work will remove and   On Schedule
Project:   C800112      replace the pavement and joint seal  On Budget
in areas on Runway 16C-34C.
Budget: $4,161,623                         0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 02/26/2008                                 $0.00
Completion: 09/01/2012
Significant Developments                    Budget/Costs Incurred
On July 26, 2011, the Port Commission authorized the remaining       6
funding for this project. The intent of this contract is to coordinate        5
this work with an apron panel replacement project, an airline           4
realignment project, and a fuel hydrant installation project all with
3
Millions
similar work and timing.
2
Dollars in   1
Schedule
0
The design efforts for the 2012 contract is at 90%. Authority to            Authorized  Forecasted Costs Incurred
advertise for construction will be requested in the first quarter of
2012 with construction scheduled to start in May 2012.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Photo
Change Order
None this quarter
Risks
No risks have been identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2011 Report  19

FOURTH QUARTER REPORT, 2011
Concessions Unit Readiness Project
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Construction     previously vacated or slated to be   On Budget
Start: 08/26/2008         vacated to Port standards for use    0 Change Orders
Completion: 06/30/2013   as specialty concession space.    Total Change Orders Amount:
$0
Significant Developments
This project received Commission authorization in September 2010   Budget/Costs Incurred
to design and build concession spaces in two locations. Design of
these two locations is complete. Commission authorized            2.5
design/construction of two additional locations on August 9, 2011.       2
Construction is underway.
1.5
in Millions
Schedule                             1
Dollars 0.5
The construction phase has been restructured and re-sequenced,
with the intent to maximize the timing for new Concessions            0
opportunities. The project was put on hold until the prioritization           Authorized  Forecasted Costs Incurred
decisions were made by Aviation Business Development.
Construction Costs
Budget
Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
20  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot  Prior Report
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule 1Q 11
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,000
project includes installing three      0 Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      $0
Completion: 07/01/2012   approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
1.2
The design for utilities was previously completed in 2009 but put on      1
hold due to market conditions. Plans for the new food-beverage       0.8
concession will be reviewed by the Concessions group for viability      0.6
via a cost analysis to be performed in early 2012.                 in Millions
0.4
Dollars 0.2
Schedule
0
The project schedule was delayed due to the pending decision by         Authorized  Forecasted Costs Incurred
the Business Development Group to proceed with the
concessionaire, as previously reported.
Construction Costs
Budget                            Not applicable
The project forecast is within the approved budget and authorization.
Photo
Change Order
None
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2011 Report  21

FOURTH QUARTER REPORT, 2011
Federal Inspection Services - New Primary
Inspection Booths
This project will replace existing     Status Snapshot  Prior Report
Project:   C800174      primary inspection booths for      Delayed Schedule 2Q 11
Customs and Border Protection in   On Budget
Budget: $2,000,000
the International Arrivals Federal    0 Change Orders
Phase: Construction     Inspection Services (FIS) facility in  Total Change Orders Amount:
Start: 07/27/2010         the South Satellite.             $0
Completion: 09/08/2011
Budget/Costs Incurred
Significant Developments
All of the new booths are complete and operational. A few items       2.5
remain prior to completion including final signage and camera          2
installation.                                                Millions 1.5  Dollars in 
1
Schedule
0.5
Due to construction resourse constraints, final items are now
planned to be complete by the end of the 2nd Quarter 2012.           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
22  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Common Use Lounge Remodel
Project:   C800203      This project will relocate the Port's   Status Snapshot
Budget: $1,061,000      common-use lounge from the     On Schedule
Phase: Design        mezzanine level to the departure   On Budget
Start: 03/01/2011         level of the South Satellite.        0 Change Orders
Completion: 02/28/2012   Improvements consist of new     Total Change Orders Amount:
finishes, new furnishings and other   $0
minor cosmetic improvements.
Budget/Costs Incurred
Significant Developments
1.2
Construction has been awarded to the low bidder and work is          1
underway.                                     Millions 0.8
0.6
Schedule
0.4
Construction is still on track to complete by the end of February 2012    Dollars in 0.2
for the lounge opening on March 1.                           0
Authorized  Forecasted Costs Incurred
Budget
Authorization for construction funding has been approved. The
current project forecast is within the approved budget.            Construction Costs
Change Order                          0.5
None
Risks                                Millions
Construction work is currently due to complete on time to meet the
accelerated schedule, but there are several items scheduled to         0
complete "just in time" to meet the deadline.                     Dollars in     Initial  Change Order  Spent
Budget Transfers
From C800152 (Non-Aeronautical New Projects)     $90,000




Port of Seattle 4Q 2011 Report  23
AIRPORT

FOURTHH QUARTER RREPORT, 2011
Terrminal EEscalators Modeernizatioon
Prooject:  C800237C          This project wwill replace 42       Statuss Snapshott
Buddget: $38,212,733     esccalators in the Main Terminal,    On Schedule
Phaase: Desiggn        Cooncourse B,, and Southh Satellite.   On Budget
Start: 11/02/22007         In addition, twwo new esccalators will   47 Chaange Orderrs
Commpletion: 07/01/20113   be installed at the Southh Satellite.   Total CChange Ordders Amounnt:
$2,4188,342
Significant DDevelopmments                   Budgett/Costs Inccurred
Eighht new escaalators at twwo sky bridgges were placed in service and     60
the SSouth Sateellite (SSATT) Communication Rooom Relocatiion was
50
commpleted. Reeplacementt of six escaalators in Concourse BB, two
40
escaalators in thhe SSAT, and eight esscalators at two other ssky bridgess   Millions
30
begaan in fourthh quarter of 2011. Conncourse B is scheduleed to be
20
commplete in firsst quarter off 2012. Reeplacement of the escaalators will    Dollars in  10
conttinue in multiple phasees through ssecond quaarter of 2013.
0
A uthorized Fo r ecasted   C o sts
Schhedule                                       Inc u rred
The project is ccurrently onn schedule.
Construuction Cossts
Buddget
20
The project foreecast is witthin the appproved budgget and autthorization.
15
Chaange Ordder                         Millions
10
The most signifficant change orders hhave involved significaant
elecctrical panell replacemeents/upgraddes to accoommodate tthe need     Dollars in  5
for aadditional circuits for thhe new esccalators as wwell as upggrades
0
wirinng. These upgrades wwere anticippated duringg project sccoping.
Initial   Chan ge Order   Sp e nt
Alsoo, added ennclosures under sky brridges, re-pphasing of SSTS stationn
escaalators to mminimize connflicts, and additional costs for assbestos
abattement andd unforeseeen conditionns.
Rissks
Nonne identifiedd at this timee.
Buddget Trannsfers
To CC102166 (AAeronauticaal Renewal//Replacemeent)   $1,951,517

AIRRPORT
24  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Central Plant Pre-Conditioned Air
Project:   C800238     This project will provide a centralized  Status Snapshot Prior Report
Budget: $43,535,000    pre-conditioned air (PC-Air) plant,    Delayed Schedule 3Q 09
Phase: Construction    associated heating and cooling piping  On Budget
Start: 06/15/2009       systems, and jet bridge terminal air    69 Change Orders
Completion: 12/10/2012  handling units to serve airplanes with  Total Change Orders Amount:
heating and cooling while at the      $1,580,563
gates.
Significant Developments                    Budget/Costs Incurred
The contractor is installing piping and major equipment in the Central
Terminal Basement. Pipe and electrical conduit installation continue     50
at the South Satellite, Concourse B and Concourse C. Contractor is     40
installing PC-Air units at the gates in Concourse A.                Millions 30
20
Schedule
Dollars in  10
The original contract completion date was 12/11/2012. One time
extension of 37 days was approved. New completion date is          0
Authorized  Forecasted Costs Incurred
1/17/2013.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
30
Change Order
25
Twelve change orders were issued this quarter. There are 69 total      Millions  20
change orders on this contract. The large change orders were issued     15
for piping and electrical site conflicts on the concourse and at the         10
gates.                                            Dollars in   5
0
Risks                                   Initial Change Spent
Orders
Due to a contract dispute with the PC-Air unit supplier, the
Contractor has not received products to facilitate installation of any of
the 73 PC-Air unts. Installation of gate equipment started in late
December. Currently the contractor is only working on one gate per
week. There is a risk that the PC-Air Units will not be installed at the
gates within the existing contract time.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2011 Report  25

FOURTHH QUARTER RREPORT, 2011
Seccurity Checkpoint Cameras
Prooject:  C800242C          This project wwill install neew       Statuss Snapshott
Buddget: $500,000      cameras to viiew passennger      On Schedule
Phaase: Consstruction     scrreening proocesses at ppassenger  On Budget
Start: 07/17/22011         seccurity checkpoints.           0 Channge Orderss
Commpletion: 05/31/20112                      Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Budgett/Costs Inccurred
The electrical aand low volttage work is completee at Checkppoint #4.
The security caameras havve been recceived.                    0.6
0.5
Schhedule
Millions 0.4
The project is ccurrently onn schedule.                          0.3
0.2
Buddget                             Dollars in 0.1
The project foreecast is witthin the appproved budgget and autthorization.     0
Authorized  F o recasted Costs I ncurred
Chaange Ordder
Nonne
Constrruction Coosts
Rissks
Nonne identifiedd at this timee.
Buddget Trannsfers
Nonne at this timme





AIRRPORT
26  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Vertical Conveyance Modernization Program -
Aeronautical
Perform modernization on 8
Project:   C800251      elevators: SSAF, SSB, SSC, MT-2,
MT-6, MT-7, C-4 and NSCF, plus   Status Snapshot
Budget: $9,773,150
install cooling packages on 11      Delayed Schedule
Phase: Planning       existing hydraulic elevators      On Budget
Start: 10/25/2011         throughout Main Terminal.        0 Change Orders
Completion: 12/31/2014                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Phasing of the program has shown a critical link between            12
construction of two new elevators at South Satellite, which must be      10
completed prior to modernization efforts on SSB and SSC elevators.    Millions 8
6
Schedule
4
The project is scheduled to begin design in the second quarter of      Dollars in  2
2012; construction is scheduled to begin in first quarter of 2013, with     0
construction completion in fourth quarter of 2014.                     Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization for  Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the design and bid documents are completed.
Change Order
None
Risks
Delays in siting two new elevators for South Satellite, currently
scheduled to be included in the second phase of the project.
Budget Transfers
None


AIRPORT
Port of Seattle 4Q 2011 Report  27

FOURTH QUARTER REPORT, 2011
Parking System Replacement
Project:   C800253      This project replaces the current    Status Snapshot Prior Report
Budget: $9,777,000      Parking Revenue Control System,   Delayed Schedule 3Q 11
Phase: Construction     which manages parking access    On Budget
Start: 04/06/2010         and revenue collection in the      0 Change Orders
Completion: 05/31/2012   Airport's Main Parking Garage.    Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The contract scope of work was finalized, leading to contract award.
The test script for the factory acceptance test has been developed.      12
10
Schedule                            Millions 8
6
Dollars in 
Project advertisement was delayed with decision to select "best bid"
4
procurement approach and completing the bid documents.
2
Negotiations and development of the final contract specifications and
0
performance took longer than anticipated. Completion of the system
Authorized  Forecasted Costs Incurred
was delayed to May 2012.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  None this quarter
Change Order
Photo
No change orders were issued this quarter.
Risks
This project schedule is aggressive.
Budget Transfers
None this quarter




AIRPORT
28  Port of Seattle 4Q 2011 Report

FOURTH QUUARTER REPPORT, 2011
Airrcraft ROON Parkking USPPS Site
Statuss Snapshott Prior Reportt
Delayeed Schedulee     1QQ 11
Prooject: C8000254       Thiis project wwill prepare the site forr
On Buddget
Buddget: $51,706,000     thee constructioon of Hardsstands for
0 Channge Orders
Phaase: Consstruction    usee as Remaiin Overnighht (RON)
Total CChange Ordders Amounnt:
Start: 08/26/22008        parrking of airccraft at the AAir Mail
$0
Center site.
Commpletion: 12/31/20114
Significant DDevelopmments                   Budget//Costs Incuurred
The temporary lease with the United States Posstal Servicee (USPS)     60
for the Air Mail Center sitee ended in JJanuary 20011. Designn efforts
50
startted in Summmar 2010 foor the demoolition of the Air Mail CCenter
40
incluuding the deesign for mminimal site improvemeents allowinng for       Millions
30
tempporary usess and amennities, and 115% hardsttand designn.
20
Hazardous material removval will be included ass a part of thhe         Dollars in  10
demmolition conttract.
0
A uthorized  For e casted Costs In curred
Schhedule
Rhinne Demolition, Inc. waas awardedd the contraact. Abatemment and
demmolition of thhe USPS Building is sccheduled too start in thee first     Construuction Costs
quarrter of 20122. Proposed constructtion of a peermanent haardstand is
1
scheeduled to begin the seecond quartter of 2013.
0.8
Buddget                            Millions 0.6
0.4
The project foreecast is witthin the appproved budgget. Authorization for
consstruction funding and aauthority too advertise ffor construcction will     Dollars in   0.2
be requested wwhen the deesign and bbid documents are commpleted.       0
Initial   Chan g e   Spent
Orde rs
Chaange Ordder
Nonne                                 Photo
Rissks
The extent of aasbestos in the USPS Building maay affect thhe project
costt.
Buddget Trannsfers
Fromm C1021655 (Aeronauttical New Projects)       $77,806,000

AIRRPORT
Port of Seattle 4Q 2011 Report  29

FOURTH QUARTER REPORT, 2011
Stage 2 Mech Energy Implementation
Status Snapshot
On Schedule
Project:   C800268      This project will improve the energy  On Budget
Budget: $3,182,000.00    performance of the mechanical    0 Change Orders
Phase: Planning       infrastructure systems at the     Total Change Orders Amount:
Start: 10/01/2011         Airport.                    $0
Completion: 12/31/2012
Budget/Costs Incurred
3
Significant Developments                     2.5
2
This project is in the final planning and scope of work development     Millions
1.5
phase.
1
Dollars in 
Schedule                             0.5
0
The project is awaiting Majority In Interest (MII) approval and the          Authorized  Forecasted Costs Incurred
schedule may be revised based on the outcome.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None.
Risks
Delay in MII approval could result in Energy Services Company
(ESCO) contract with State expiring.
Budget Transfers
None this quarter.



AIRPORT
30  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
8th Floor Weatherproofing
Status Snapshot
On Schedule
Project:   C800274      This project includes removal and   On Budget
Budget: $13,050,000     replacement of the floor covering   0 Change Orders
Phase: Construction     system on the 8th floor of the STIA  Total Change Orders Amount:
Start: 03/23/2010         parking garage and repair or       $0
Completion: 03/31/2013   replacement of expansion joints
and flashings.
Budget/Costs Incurred
Significant Developments                     15
The design is complete, and the project has a signed Project Labor
Agreement (PLA). The Port bid the project with the low bidder being    Millions 10
PCL Construction. The Port is requesting a two year construction
schedule, which would extend the completion to the end of 2013.       5
Dollars in 
Schedule                             0
Authorized  Forecasted Costs Incurred
Bid advertisement and award occurred during the fourth quarter of
2011. The Port is requesting a two year construction schedule,
which would extend project completion to the end of 2013.
Construction Costs
Budget
8
The project forecast is within the approved budget and authorization.
6
Change Order                          Millions
4
No change orders were issued this quarter.
Dollars in   2
Risks
0
This is a weather-dependent project.                             Initial  Change Order  Spent
Budget Transfers
Photo
None this quarter



AIRPORT
Port of Seattle 4Q 2011 Report  31

FOURTHH QUARTER RREPORT, 2011
Common UUse Equuipment Expanssion (CUUSE)
Prooject:  C800276C          This project innstalls flexibble       Statuss Snapshott
Buddget: $3,0090,000     passenger processing        On Schedule
Phaase: Desiggn        infrastructure and equipmment at thee  On Budget
Start: 09/01/22009         airrline gates aat some Soouth       0 Channge Orderss
Commpletion: 09/30/20112   Saatellite and CConcourse A gates,   Total CChange Ordders Amounnt:
as well as at tthe former Delta       $0
loccation.
Budgett/Costs Inccurred
Significant DDevelopmments
3.5
Design documeents are beeing finalizeed and the pproject is exxpected to      3
bid iin Februaryy 2012.                                  Millions  2.5
2
Schhedule                            Dollars in 
1.5
The project schhedule anticcipates connstruction coompletion bby the end     1
of thhird quarter 2012.                                      0.5
0
Authorized       F o recasted      Costs I n curred
Buddget
The project foreecast is witthin the appproved budgget. Authorrization of
Construuction Cossts
consstruction funding has bbeen approoved.
Not Appplicable
Chaange Ordder
Nonne
Rissks
Nonne identifiedd at this timee
Buddget Trannsfers
Nonne this quarter




AIRRPORT
32  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Communications Cable Additions to MT, D, CTE
Project:   C800331      Addition of copper and fiber cabling  Status Snapshot
Budget: $377,000       to create a redundant pathway    On Schedule
Phase: Close Out      throughout the Central Terminal    On Budget
Start: 08/11/2011         and Main Terminal             0 Change Orders
Completion: 12/31/2011   Communications Rooms.       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
Construction of this project was completed in November 2011. The     0.4
project is currently in close-out
0.3
Millions
Schedule                             0.2
The project completed on schedule.                        Dollars in 0.1
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 4Q 2011 Report  33

FOURTH QUARTER REPORT, 2011
Two New CTE Freight Elevators
Project:   C800334      Provide two new freight elevators
Budget: $6,664,000      to support concession operations in
Phase: Design        the Central Terminal/Pacific      Status Snapshot
Start: 08/05/2011         Marketplace.                On Schedule
Completion: 07/31/2013                       On Budget
0 Change Orders
Total Change Orders Amount:
$0
Significant Developments
The project design commenced in third quarter 2011. The 60%      Budget/Costs Incurred
design documents will be submitted for review in early first quarter of
2012.                                          8
6
Schedule                            Millions
4
The project is scheduled to complete design in first quarter of 2012.
Construction is anticipated to commence in fourth quarter of 2012.
Dollars in   2
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
There is a potential risk due to unknown conditions where the freight
elevator foundations will be constructed, i.e., outside of the Central
Terminal building envelope.Installation of Passenger Loading Bridge
at Gate B-1 will require significant coordination during construction.
Budget Transfers
None this quarter


AIRPORT
34  Port of Seattle 4Q 2011 Report

FOURTHH QUARTER RREPORT, 2011
Eleectrical GGround Supporrt Equipmment (EGSE)
Eleectrical CCharge Stationss
Statuss Snapshott
Prooject:  C800335C          Airrport-wide eelectrical chharging     On Schedule
sysstem for eleectrical grouund        On Budget
Buddget: $14,410,000
support equippment (EGSSE) at the   0 Channge Orderss
Phaase: Desiggn        Cooncourses aand the Norrth and    Total CChange Ordders Amounnt:
Start: 10/26/22010         Soouth Satellittes.              $0
Commpletion: 4/30/20133
Significant DDevelopmments
Budgett/Costs Inccurred
The Port will bee finalizing the bid process and selection forr the EGSEE
batteery chargerrs in early FFebruary 20012. The deesign consuultant is       16
finallizing the scchematic deesign documents for thhe Project NNotebook.     14
12
Currrent design plan is to ssplit projectt implementtation into tthree parts   Millions
10
in foollowing seqquence: 1) Concourse C - 20 demmonstrationn charge     Dollars in   8
statiions; 2) Phaase I - Concourse C - Balance off charge staations,        6
Conncourse D aand North SSatellite; andd 3) Concoourse A, Cooncourse B     4
2
and South Sateellite.
0
Authorized       F o recasted      Costs I n curred
Schhedule
The project teaam is in the process off developingg the implementation
scheedule and ccoordinatingg with Airlinne Carries. Current plaan is to     Construuction Cossts
commplete desiggn in 2012 aand begin implementaation of demmonstration  Not Appplicable
charrge station and the balance of Phhase I work. Phase II wwork to be
impllemented inn 2013.
Buddget
The project foreecast is witthin the appproved budgget. Authorization for
the cconstruction funding aand authoritty to advertise for consstruction
will bbe requesteed when the design annd bid docuuments are
commpleted.
Chaange Ordder
Nonne




Port of Seattle 4Q 2011 Report  35

Rissks
Poteential risks include latee execution of agreements betweeen Port and Airline Caarriers, Cooordination
with other airfieeld projects and Airlinee Realignment programm. Budget iincrease may impact pproject
impllementationn.
Buddget Trannsfers
Nonne this quarter












AIRRPORT
36  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
South Satellite Delta Sky Club Expansion
Status Snapshot Prior Report
Delayed Schedule 1Q 11
Project:   C800336     Construction of a new 6,800 square   On Budget
Budget: $8,930,000    foot Sky Club lounge on the roof of   0 Change Orders
Phase: Close Out     the South Satellite for Delta Air Lines.  Total Change Orders Amount:
Start: 06/01/2010                                 $0
Completion: 08/30/2011
Budget/Costs Incurred
Significant Developments                     10
Port reimbursement to Delta Air Lines for their work on Port scope       8
has been approved and payment sent to Delta Air Lines. This will be    Millions 6
the last quarterly report for this project.
4
Schedule                            Dollars in  2
0
Project close out is in process.
Authorized  Forecasted Costs Incurred
Budget
The project is forecast to complete within the approved budget and   Construction Costs
authorization.                                        Not Applicable
Change Order
None
Risks
None
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2011 Report  37

FOURTH QUARTER REPORT, 2011
Roof Replacement Program
Status Snapshot Prior Report
On Schedule
Project:   C800360      Remove and replace the roofing    Under Budget    3Q 11
Budget: $2,640,000      systems on the south and central   0 Change Orders
Phase: Close Out      sections of the Main Terminal. The  Total Change Orders Amount:
Start: 4/25/2010          new roofing systems will achieve    $0
Completion: 10/31/2011   LEED credits and are Energy Star
rated. This project is part of a      Budget/Costs Incurred
multi-phased program.
3
2.5
Significant Developments
Millions  2
The project reached beneficial occupancy in October 2011. The       1.5
project is complete and in closeout.                            1
Dollars in 0.5
Schedule
0
The project finished on schedule.                               Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
The project anticipates a savings of approximately $1,000,000.
1.2
1
Change Order
Millions  0.8
None                                   0.6
0.4
Risks
Dollars in   0.2
0
None at this time
0.2   Initial   Change   Spent
Orders
Budget Transfers
None this quarter




AIRPORT
38  Port of Seattle 4Q 2011 Report

FOURTHH QUARTER RREPORT, 2011
Claaim Device 14 && Lower Inboundd
Prooject:  C800374C          This project wwill replace the slope-   Statuss Snapshott
Buddget: $3,9900,000     plaate bag claim device 14 and     On Schedule
Phaase: Desiggn        asssociated coontrols, in aaddition to   On Budget
Start: 04/01/22011         remmoving the lower feed conveyor   0 Channge Orderss
Commpletion: 05/31/20112   and replacingg it with a neew      Total CChange Ordders Amounnt:
oveerhead feedd.               $0
Budgett/Costs Inccurred
5
Significant DDevelopmments                    4
The project is ccurrently at 90% desiggn.                        Millions 32
Schhedule                            1
Dollars in 0
The project is ccurrently onn schedule.                           Aut horized Foreca s ted  Costs
Incurred
Buddget
The project foreecast is witthin the appproved budgget. Authorrization of   Construuction Cossts
consstruction funding and aauthority too award for constructioon will be    Not Appplicable
requuested when the desiggn and bid ddocuments are compleeted.
Chaange Ordder
Nonne
Rissks
Nonne identifiedd at this timee.
Buddget Trannsfers
Nonne this quarter



AIRRPORT

Port of Seattle 4Q 2011 Report  39

FOURTHH QUARTER RREPORT, 2011
Bagggage HHandlingg Systemm (C22-CC1, MK1, and
Statuss Snapshott
TC3)                          On Schedule
This project wwill replace the ticket    On Budget
Prooject:  C800382C          counter (TC3) conveyorss and      0 Channge Orderss
declines, rerooute the connveyors of   Total CChange Ordders Amounnt:
Buddget: $5,3335,000
thee C-22 systtem and connnect it to    $0
Phaase: Desiggn        thee C-1 screeening systemm, replace
Start: 03/01/22011         thee existing mmakeup (MKK1) device,  Budgett/Costs Inccurred
Commpletion: 05/31/20113   and install a nnew odd sizze baggagee
6
sysstem.
5
Millions  4
Significant DDevelopmments                    3
2
The design connsultant finaalized desiggn of TC3 cconveyor syystem.      Dollars in  1
Design of the remainder oof the projecct is almostt complete. Port
0
Connstruction Services started demolishing the eexisting tickket counter       A u thorized Fore c asted  Costs
convveyor. We rreceived the new convveyor equippment on site                       Incurr e d
September 26, 2011. The team expeects the first phase of wwork to be
commpleted by the end of the year.                         Construuction Cossts
Not Appplicable
Schhedule
The project is ccurrently onn schedule.
Buddget
The project foreecast is witthin the appproved budgget. Authorrization of
consstruction funding and aauthority too award for constructioon will be
requuested when the desiggn and bid ddocuments are compleeted.
Chaange Ordder
Nonne
Rissks
Nonne identifiedd at this timee
Buddget Trannsfers
Nonne this quarter


AIRRPORT
40  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
RW16C/34C Reconstruction Design
Project:   C800406      This project will produce the 60%   Status Snapshot
Budget: $669,000       design for the runway 16C/34C    On Schedule
Phase: Design        reconstruction. The design will    On Budget
Start: 05/04/2010         include utilities, runway status      0 Change Orders
Completion: TBD       lights, and other scope items     Total Change Orders Amount:
related to the project.             $0
Significant Developments                    Budget/Costs Incurred
The 60% design was issued in December 2010. Incorporation of
0.8
comments on the 60% design work is completed.
0.6
Schedule                            Millions
0.4
Dollars in 
Staff will return to Commission for authorization of the remaining
design funds in late 2014 or early 2015. The forecast will be          0.2
reassessed when staff returns to the Commission for authorization of
0
the final design funds.                                        Authorized  Forecasted Costs Incurred
Budget
The Port Commission authorized $669,000 on May 4, 2010. The     Construction Costs
current forecast for 60% design is within the approved budget and    Not Applicable
authorization. Any potential savings will be returned.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 4Q 2011 Report  41

FOURTH QUARTER REPORT, 2011
South Satellite Concessions Project
Status Snapshot Prior Report
Delayed Schedule 3Q 11
Project:   C800412      This project will demolish and      On Budget
Budget: $1,872,739      relocate the existing duty free shop,  0 Change Orders
Phase: Design        electric/communications to support  Total Change Orders Amount:
Start: 01/01/2011         a temporary duty free location, and   $0
Completion: 03/31/2013   construct a new food and beverage
shell space in the South Satellite at
Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                      2
The project is currently in the design phase.                     1.5
Millions
1
Schedule
Design concept alternatives required more extensive review than      Dollars in 0.5
anticipated. The new concept allows the existing duty free to remain
0
operational during construction, but requires a longer construction         Authorized  Forecasted Costs Incurred
period, which was reported last quarter.
Budget
Construction Costs
The project forecast is within the approved budget. Authorization of   Not Applicable
construction funding and authority to award for construction will be
requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
42  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT,
Access Control Door Additions
Project:   C800414      This project will provide biometric   Status Snapshot
Budget: $1,800,000      access controls and security     On Schedule
Phase: Design        cameras at airport terminal doors.   On Budget
Start: 09/27/2011                                 0 Change Orders
Completion: 11/15/2012                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The 60% design documents were completed in third quarter of 2011.
2
Schedule
1.5
The project is currently on schedule.                          Millions
1
Budget
Dollars in 0.5
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will       0
Authorized  Forecasted Costs Incurred
be requested when the design and bid documents are completed.
Change Order
Construction Costs
None
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2011 Report  43

FOURTHH QUARTER RREPORT, 2011
Airrfield Ligghting CControl aand Monnitoring Systemm
Statuss Snapshott
(ALLCMS) UUpgradees                 On Schedule
Proovide modiffications to the Airfieldd   On Budget
Prooject:  C800415C          Ligghting Conttrol and Monitoring    0 Channge Orderss
Syystem to upddate, enhannce and    Total CChange Ordders Amounnt:
Buddget: $2,1129,144
staabilize the ssystem to mmeet the     $0
Phaase: Consstruction     lateest FAA sppecificationss.
Start: 01/01/22011                                Budgett/Costs Inccurred
Commpletion: 12/31/20114
2.5
Significant DDevelopmments
2
Connstruction off the duct bbank on the south end of Runwayy 16C-34C    Millions 1.5
is coomplete. The fiber arrrived and teested positivve. Once ccomplete,
1
this will providee a full communicationns loop arouund the airffield. The
neww tower anteenna base ddesign is coomplete.                  Dollars in 0.5
0
Schhedule                               Authorized F o recasted Costs Incurred
The project is ccurrently onn schedule.
Construuction Cossts
Buddget                           Not Appplicable
The project foreecast is witthin the appproved budgget and autthorization.
Chaange Ordder
Nonne this quarter
Rissks
Cooordination wwith on-going airfield opperations iss a consideeration.
The Port is alsoo working too eliminate unplannedd outages wwhen
transsitioning froom the oldeer computerr platform too the one.
Buddget Trannsfers
Fromm C1001722 (Third Runnway Construction)   $83,144



AIRRPORT
44  Port of Seattle 4Q 2011 Report

FOURTHH QUARTER RREPORT, 2011
Laggoon 3 BBird Wirres
Statuss Snapshott
On Schedule
Prooject:  C800417C          This project wwill reduce aaccess by   On Budget
Buddget: $1,6631,000     waaterfowl to tthe industriaal       0 Channge Orderss
Phaase: Desiggn        waastewater syystem Lagooon 3,     Total CChange Ordders Amounnt:
Start: 10/11/22011         whhich is locatted near thee south endd  $0
Commpletion: 10/31/20112   of the airfield..
Budgett/Costs Inccurred
2
Significant DDevelopmments
1.5
Portt of Seattle Commissioon authorizeed design ffunds on Occtober 11,    Millions
1
2011.
Dollars in 0.5
Schhedule
0
Design efforts have starteed and are aat a 90% leevel.                   Authorized  F o recasted Costs I n curred
Buddget
The project foreecast is witthin the appproved budgget. Authorrization of   Construuction Cossts
consstruction funding and aauthority too advertise ffor construcction will    Not Appplicable
be requested inn the first quarter of 20012 with coonstruction sstarting thee
summmer of 2012.
Photo
Chaange Ordder
Nonne this quarter
Rissks
No rrisks have bbeen identiffied at this time.
Buddget Trannsfers
Nonne this quarter



AIRRPORT
Port of Seattle 4Q 2011 Report  45

FOURTH QUARTER REPORT, 2011
Additional Airfield Mitigation at Tyee
Status Snapshot
Project:   C800420      The project will design and       On Schedule
Budget: $800,000       complete the Tyee Golf Course    On Budget
Phase: Construction     Area Mitigation which includes    0 Change Orders
Start: 02/08/2011         removing a culvert, new wetland    Total Change Orders Amount:
Completion: 03/30/2012   planting, updating existing wetlands  $0
to environmental permit standards,
and installing a temporary irrigation  Budget/Costs Incurred
system.
1
Significant Developments                     0.8
The project was advertised on September 8, 2011 with bid opening     Millions 0.6
scheduled for October 2011.                             0.4
Dollars in 0.2
Schedule
0
Construction is scheduled to begin in February 2012.                 Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                          0.4
None                                   0.3
Millions
Risks                                0.2
None identified at this time.                                 Dollars in 0.1
0
Budget Transfers
Initial    Change Order    Spent
None this quarter
Photo



AIRPORT

46  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Federal Inspection Service Improvements -
Phase 1
Improvements to the Federal
Project:   C800426      Inspection Service area at the     Status Snapshot Prior Report
South Satellite to remedy queuing   Delayed Schedule 4Q 10
Budget: $31,700,000
pinch points and add additional     On Budget
Phase: Design        passenger processing capacity.    0 Change Orders
Start: 04/01/2011                                 Total Change Orders Amount:
Completion: 05/31/2013                       $0
Budget/Costs Incurred
Significant Developments
Airline review prior to issuance of a Majority In Interest (MII) ballot       40
was not favorable. The project scope will be reviewed prior to moving
30
this project forward.                                       Millions
20
Schedule
Dollars in  10
This project is delayed from its original schedule, as reported
previously.                                            0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will    Construction Costs
be requested when the design and bid documents are completed.    Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2011 Report  47

FOURTH QUARTER REPORT, 2011
Concourse D Common Use Environment
Status Snapshot Prior Report
Delayed Schedule 3Q 11
Project:   C800455      This project installs a common-use  On Budget
Budget: $4,250,000      environment at all gates on      0 Change Orders
Phase: Design        Concourse D. Scope includes new  Total Change Orders Amount:
Start: 03/01/2011         communications infrastructure,     $0
Completion: 12/31/2012   casework built to a new Airport
standard, new carpet, wall        Budget/Costs Incurred
coverings and task lighting.
5
4
Significant Developments
Millions  3
New casework standards have been finalized for incorporation into
this project. Final design documents are in progress.                2
Dollars in   1
Schedule
0
Construction of the mock-up casework negatively impacted the           Authorized Forecasted Costs Incurred
project schedule and the project team is evaluating ways to make up
the time to match the loading bridge work currently scheduled for
Concourse D.                                  Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Phasing of the construction work could push the completion date out
further.
Budget Transfers
None this quarter

AIRPORT

48  Port of Seattle 4Q 2011 Report

FOURTHH QUARTER RREPORT, 2011
20111-2013 Roof Reeplacemment Proogram
Prooject:  C800459C          This project wwill remove and      Statuss Snapshott
Buddget: $4,7777,000     repplace the rooofing systeems on the  On Schedule
Phaase: Desiggn        firee station annd north endd of the    On Budget
Start: 07/01/22011         maain terminall.                0 Channge Orderss
Commpletion: 10/31/20113                      Total CChange Ordders Amounnt:
$0
Significant DDevelopmments                   Budgett/Costs Inccurred
Design and bidd documentt preparatioon is underwway.
6
Schhedule                             5
4
The project is ccurrently onn schedule.
3
in Millions
Buddget                             2
Dollars   1
The project foreecast is witthin the appproved budgget. Authorization for
0
consstruction funding and aauthority too award for constructioon will be
Authorized  F o recasted Costs Incurred
requuested when the desiggn and bid ddocuments are compleeted.
Chaange Ordder                         Construuction Cossts
Nonne                                 Not Appplicable
Rissks
Nonne at this timme
Buddget Trannsfers
Nonne this quarter




AIRRPORT
Port of Seattle 4Q 2011 Report  49

FOURTH QUARTER REPORT, 2011
South Satellite - Additional Gate Lobby
Status Snapshot Prior Report
Project:   C800466      Demolition of glass partitions,      Delayed Schedule 3Q 11
Budget: $1,257,000      restrooms, relocation of gate     On Budget
Phase: Design        podiums new flooring, ceilings and  0 Change Orders
Start: 11/01/2010         infrastucture to provide additional    Total Change Orders Amount:
Completion: 03/31/2013   gate lobby in the South Satellite.   $0
Significant Developments
Commission Authorization for design and removal of glass panels    Budget/Costs Incurred
was received in November 2010.
Schedule                             1.5
Project delay was caused by delayed design negotiations and
1
contracting. Additionally, a longer design period is required due to
dependency on the South Satellite Concessions Project (C800412),    in Millions
0.5
which was reported last quarter.                            Dollars 
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested when the design and bid documents are completed.      Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
50  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Passenger Loading Bridge Replacement
Project:   C800467      This project entails Passenger     Status Snapshot
Budget: $14,850,000     Loading Bridge (PLB)         On Schedule
Phase: Design        replacements associated with the   On Budget
Start: 04/12/2011         one-time airline realignment (AR).   0 Change Orders
Completion: 09/30/2013   The work will take place at      Total Change Orders Amount:
Concourse D, Concourse B and    $0
North Satellite.
Significant Developments
Budget/Costs Incurred
The phasing and scope of the Concourse D gates refurbishment and
replacement is being modified. A new bid package will be advertised
20
in early Q2 2012. PLB work at Concourse B will go for Commission
authorization on March 27, 2012 with the work scheduled to take       15
place during Q2 and Q3 of 2012.                          Millions
10
The PLB work at the North Satellite is currently under review and if it    Dollars in  5
continues it is tentatively scheduled to begin in Q2 of 2013 and
0
continue through the end of Q2 2014.
Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule. Commission approval for each  Construction Costs
phase is being requested separately.                       Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2011 Report  51

FOURTH QUARTER REPORT, 2011
Water System Isolation Valve Upgrade - Airfield
Status Snapshot
On Schedule
Project:   C800469      The water distribution system at the  On Budget
Budget: $1,293,000      Airport is almost 40 years old. This  0 Change Orders
Phase: Construction     project will replace and add      Total Change Orders Amount:
Start: 11/15/2010         additional water valves in several    $0
Completion: 12/31/2011   strategic locations to prevent
possible outages.             Budget/Costs Incurred
1.5
Significant Developments
Millions  1
All water valves near the South Satellite were completed in August
with the North end water valves completed in October 2011.          0.5
Dollars in 
Schedule                             0
Authorized  Forecasted Costs Incurred
The project is currently being closed out.
Budget
The project forecast is within the approved budget. Any possible     Construction Costs
project savings will be returned once the project is closed out.       Not applicable
Change Order                         Photo
None
Risks
The replacement valve sizes were taken from 25-40 year old
documents.
Budget Transfers
To C102334 (Water System Isolation Valve - Non-Airfield) $150,000



AIRPORT

52  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Security Checkpoint Optimization
Project:   C800471      This project supports TSA initiative  Status Snapshot
Budget: $430,000       to accomodate emerging       On Schedule
Phase: Construction     technologies. Major elements were  On Budget
Start: 08/15/2010         new electrical infrastructure to      0 Change Orders
Completion: 10/31/2011   checkpoints and minor relocation of  Total Change Orders Amount:
lanes for installation of Advanced    $0
Imaging Technology (AIT) units.
Budget/Costs Incurred
Significant Developments                    0.435
0.43
The project is complete and is in the closeout phase. This will be the
0.425
last quarterly report for this project.
0.42   Millions
0.415
Schedule                            0.41
0.405   Dollars in 
The project is complete.
0.4
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 4Q 2011 Report  53

FOURTH QUARTER REPORT, 2011
Exterior Gate Improvements (Airline
Realignment)
This project will install new fuel      Status Snapshot
Project:   C800472      hydrant pits and aircraft docking    On Schedule
systems at exterior gates for the     On Budget
Budget: $2,650,000
airline reallocation program.        0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 06/01/2011                                 $0
Completion: 10/31/2012
Budget/Costs Incurred
Significant Developments                      3
2.5
The 90% design documents were completed in the fourth quarter of
Millions  2
2011.
1.5
Schedule                             1
Dollars in 0.5
The project is currently on schedule.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will    Construction Costs
be requested when the design and bid documents are completed.    Not Applicable
Change Order
None
Risks
If the fuel system lease amendment is not finalized, it could limit the
use of the new fuel hydrants.
Budget Transfers
None this quarter



AIRPORT
54  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Airport Signage (Airline Realignment)
Project:   C800474      The project will provide airport     Status Snapshot
Budget: $646,000       directional signage for the airline   On Schedule
Phase: Design        reallocation program.         On Budget
Start: 06/01/2011                                 0 Change Orders
Completion: 04/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
A firm was selected through the Request for Proposal process for a     0.8
signage design services contract.
0.6
Millions
Schedule                             0.4
The project is currently on schedule.                          Dollars in 0.2
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2011 Report  55

FOURTH QUARTER REPORT, 2011
Miscellaneous Building Improvements (Airline
Realignment)                       Status Snapshot
This project will install a new        On Schedule
Project:   C800475      elevator/stair for passenger access  On Budget
to regional aircraft on Concourse A   0 Change Orders
Budget: $7,922,000
for the airline realignment program.   Total Change Orders Amount:
Phase: Design                            $0
Start: 11/01/2011
Completion: 02/28/2013                       Budget/Costs Incurred
10
Significant Developments                      8
Millions  6
The Port Commission authorized funding for design of the project in
the fourth quarter of 2011.                                  4
Dollars in   2
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the design and bid documents are completed.
Change Order
None
Risks
If the aircraft assignments at the gates changes, the elevator/stairs
would need to be in a different location.
Budget Transfers
None this quarter



AIRPORT
56  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Highline School Noise Insulation
Status Snapshot Prior Report
Delayed Schedule 4Q 10
Project:   C200007      Highline School Insulation        On Budget
Budget: $101,797,000    Agreement will provide funding for  0 Change Orders
Phase: Construction     sound mitigation for 15 schools that  Total Change Orders Amount:
Start: 03/23/1999         are impacted by aircraft noise from   $0
Completion: 11/30/2021   Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments
120
The insulation of seven schools has been completed and no more
100
are scheduled until Olympic is closed in 2013. Olympic will be
closed, however it is eligible for funds if the square footage of other     Millions 80
built schools increases to accommodate displaced students from       60
Olympic.                                        40
Dollars in  20
Schedule                             0
Authorized  Forecasted Costs Incurred
Port funding is authorized and will be available when the matching
funds are provided by the FAA, the State of Washington, and the
Highline School District. The schedule for state funding is not known.  Construction Costs
The district's schedule is dependent on obtaining general election    Not Applicable
bonds at various intervals.
Budget
The project forecast is within the approved budget and authorization.
Change Order
Not applicable
Risks
Project delayed due to funding issues with the Highline School
District. Risk is if no bonds are passed.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2011 Report  57

FOURTH QUARTER REPORT, 2011
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $10,822,000     Insulation Agreement will provide   Delayed Schedule 4Q10
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      0 Change Orders
Completion: 12/31/2013   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
$0
Significant Developments
Thirteen of the 22 eligible buildings have been sound insulated by    Budget/Costs Incurred
the college.
12
10
Schedule
Millions  8
Building #4 anticipated to begin construction in summer 2012. The
6
schedules for the remaining buildings are dependent on state
4
funding.                                            Dollars in  2
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
the remaining project budget will be requested for one building at a
time from the Commission in the future when schedule is          Construction Costs
determined.                                     Not Applicable
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed. The Port is working with the College to determine
estimates for the remaining college buildings that have not been
completed.
Budget Transfers
None this quarter


AIRPORT
58  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Home Insulation Retrofit
Project:   C200048      This project includes storm window  Status Snapshot
Budget: $5,344,000      retrofit of previously insulated     Delayed Schedule
Phase: Construction     homes.                On Budget
Start: 01/11/2005                                 0 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The Port is researching remaining eligible homes to continue with
insulation retrofit and storm window retrofit.                        6
5
Schedule                             4
Two homes are in process and reviewing potential homes for          3
in Millions
eligibility.                                                          2
Dollars   1
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
Not Applicable                                     Not Applicable
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2011 Report  59

FOURTH QUARTER REPORT, 2011
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot
Budget: $4,947,395      that are within the 1998 65 decibel  Delayed Schedule
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   7 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$31,911.00
Significant Developments                    Budget/Costs Incurred
Seventeen homes are in process of receiving sound insulation;
6
eleven homes are on the waiting list for the next group.
5
Schedule                            Millions 4
3
Dollars in 
This project schedule was delayed due to changes in contracting
2
methods.
1
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within approved budget and authorization.
Change Order                         Construction Costs
Manufacturing issues with VPI windows and header/sill work to
4
accommodate heavier windows and doors.
3
Risks                                Millions
2
The ability to accomplish the insulation is dependent on the
homeowner's schedules, willingness to sign an aviation easement      Dollars in  1
and obtain a subordination agreement from their lender, and
0
structural integrity of the home. If more eligible homes than
Initial    Change Order    Spent
anticipated are identified in the future, then additional funding may be
needed.
Budget Transfers
None this quarter


AIRPORT
60  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Street Vacations - Des Moines Creek 1
Project:   C800046    Purchase the City of Des Moines-      Status Snapshot
Budget: $3,850,000   owned streets in the Des Moines Creek  Delayed Schedule
Phase: Implementation Business Park site that are surrounded  Under Budget
Start: 10/01/2008      by Port-owned property. This        0 Change Orders
Completion: 01/31/2012 acquisition will enable the Port to     Total Change Orders Amount:
develop the business park site.        $0
Significant Developments                    Budget/Costs Incurred
Closing on the large majority of the streets with the City of Des
5
Moines occurred in March, 2011. Closing on the last, small parcel
from the Washington State Department of Transportation is           4
anticipated in January, 2012.                               Millions 3
Dollars in 
Schedule                             2
Final acquisition was delayed by one month and should be complete     1
in January, 2012.
0
Authorized  Forecasted Costs Incurred
Budget
The project was under the approved budget and authorization. It is
anticipated that approximately $1,400,000 in unspent funds will be    Construction Costs
returned back to the Airport CIP.                           Not Applicable
Change Order
Not applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2011 Report  61

FOURTH QUARTER REPORT, 2011
RMU/Kiosk Concession Program
Project:   C800146    The project will provide design and     Status Snapshot Prior Report
Budget: $1,209,000   fabrication of eight Retail         Delayed Schedule 3Q 10
Phase: Construction   Merchandising Units (RMUs); provide   On Budget
Start: 11/20/2007      power, communications, and data to    0 Change Orders
Completion: 06/30/2011 sixteen RMU locations; and install floor-  Total Change Orders Amount:
mounted receptacles for the utilities to    $0
allow easy connection points as well as
flexibility for future utilization.
Budget/Costs Incurred
1.5
Significant Developments
All RMU utility installations are complete, and considered
substantially complete. The remaining tasks include purchasing and    Millions 1
installing the RMU kiosk units.
0.5
Dollars in 
Schedule
0
The project has been on hold pending the staffing of a vacant            Authorized  Forecasted Costs Incurred
position in Concessions. This position was filled in third quarter of
2011 and work has begun to develop this portion of the small
business program and procure these RMU units.              Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

62  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot Prior Report
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule    2Q 10
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   0 Change Orders
Completion: 12/31/2013   owned properties.           Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The Sunnydale sub-station was purchased from Seattle City Light on
4
July 25, 2011. The last anticipated acquisition will be the street
vacation of 12th Place S. in Burien, Washington.                   3
Millions
Schedule                             2
It is anticipated that the street vacation will occur in the 2012-2013      Dollars in  1
time frame.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2011 Report  63

FOURTH QUARTER REPORT, 2011
Tenant Reimbursement
Status Snapshot
Project:   C800154    Build out of spaces for new and      On Schedule
Budget: $4,709,577    existing tenants. If more than a "basic  On Budget
finish" condition space is built for the    0 Change Orders
Phase: Construction
tenant, the tenant is required to       Total Change Orders Amount:
Start: 08/14/2007
reimburse the Port for the cost of the   $0
Completion: 03/31/2012
work beyond this "basic finish". These
reimbursements are allowed under    Budget/Costs Incurred
the guidelines described in the
"Tenant Reimbursement Policy".        5
4
Significant Developments                     Millions 3
There were no tenant reimbursements during the fourth quarter of       2
2011. Future tenant projects will likely be part of the Airline           Dollars in  1
Realignment over the next few years, so this project may have
limited activity.                                               0
Authorized  Forecasted Costs Incurred
Schedule
Schedules vary to meet the tenant's needs.                  Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
64  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Paint Striper Equipment
Project:   C800354      Via a competitive process,       Status Snapshot Prior Report
Budget: $420,000       purchase one Truck Chassis     Delayed Schedule 1Q 11
Phase: Implementation   Mounted Airless Application Paint   Under Budget
Start: 09/01/2010         Striping Unit for the Airport. This    0 Change Orders
Completion: 10/31/2011   requested paint striper equipment   Total Change Orders Amount:
is necessary to meet operational,    $0
safety and regulatory requirements.
Budget/Costs Incurred
Significant Developments
The paint striper unit was received in the fourth quarter and came in    0.44
under budget at $366,727. This will be the last quarterly report for      0.42
this project.                                               Millions 0.4
0.38
Schedule                            0.36
0.34   Dollars in 
The project is complete.
0.32
Budget                               Authorized Forecasted Costs Incurred
The project came in under the approved budget and authorization. 
Change Order                         Construction Costs
Not Applicable
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 4Q 2011 Report  65

FOURTH QUARTER REPORT, 2011
T-86 Grain Facility Modernization           Status Snapshot Prior Report
Ahead of Schedule 3Q 11
Modernize and replace aging grain   Under Budget    3Q 11
Project:   C800133      facility equipment/controls for $5M   2 Change Orders
by 12/31/2011 to maximize       Total Change Orders Amount:
Budget: $2,900,000
operational efficiencies and allow    $58,123.00
Phase: Construction     continuation of uninterrupted grain
Start: 2/21/2010          terminal operations.           Budget/Costs Incurred
Completion: 12/30/2011
3
2.9
Millions 2.8                                                                                 Significant Developments
2.7
Phase-1 - project is complete.                              2.6
Dollars in 2.5
Phase-2 - project is complete.                              2.4
This is the final Report.                                     2.3
Authorized  Forecasted Costs Incurred
Schedule
Phase-2 - portion was completed ahead of schedule.
Construction Costs
Budget
2.5
On Budget.
2
Millions  1.5
Change Order
1
Phase-1 $33,123
Phase-2 $25,000                                 Dollars in  0.5
0
Risks                                   Initial Change Spent
Orders
None
Budget Transfers                        Photo
None



SEAPORT
66  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Seaport Security Grant Round 7
Project:   C800165      Seaport Security Grant Round 7    Status Snapshot
Budget: $2,283,090                         Delayed Schedule 3Q 11
Revised Budget $2,582,490                      On Budget
Phase: Construction                        0 change Orders
Start: March 2007                                Total Change Orders Amount:
Completion: Dec 2010
Budget/Costs Incurred
Significant Developments
2.5
Three bids were received with the lowest at 17.6% over the
2
Engineer's estimate. We reviewed the estimate and the entire
project budget. As a result, the revised project budget was over the     Millions 1.5
estimate and we went back to the Commission and requested and      1
received additional funding.                                Dollars in 0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
Slightly delayed. Project was delayed due to bids coming in over the
Engineer's estimate. Construction is expected to start late, either in.
December or early January and completed in 6 to 8 weeks (weather
Construction Costs
dependent).
Not Applicable
Budget
On budget as revised
Change Order
None
Risks
Although construction may not be complete until after Cruise starts in
April, there should be little or no impact to the Cruise operations.
Budget Transfers
None


SEAPORT

Port of Seattle 4Q 2011 Report  67

FOURTH QUARTER REPORT, 2011
P91 Fender System Upgrade
Project:   C800183      Upgrades to the vessel berths of    Status Snapshot
Budget: $5,700,000      P91 to better accommodate cruise  On Schedule
Phase: Design        ships and also serve the other    On Budget
Start: 01/31/10          industrial customers who utilize the   0 Change Orders
Completion: 04/30/2012   berths and adjacent dock/apron    Total Change Orders Amount:
areas on P91 for less than $6M by   $0
spring 2011.
Budget/Costs Incurred
Significant Developments
2.5
Construction underway. Contract completion expected in Q2 2012
2
Schedule                             1.5 Millions
Full replacement is to be completed by April 2012.                 1
Dollars in 0.5
Budget                              0
Authorized  Forecasted Costs Incurred
Project is within approved budget.
Change Order
Construction Costs
None this quarter
2.5
Risks                                 2
None this quarter                                     Millions 1.5
1
Budget Transfers
Dollars in   0.5
None
0
Initial   Change   Spent
Orders




SEAPORT
68  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
T-10 Interim Redevelopment
Status Snapshot
Project:   C800264      Redevelop site, complete with new  On Schedule 3Q 11
Budget: $7,205,000      stormwater treatment facilities,    On Budget
Phase: Construction     outfall, yard lighting, security fence,  13 Change Orders
Start: 03/22/08          and paving to support terminal     Total Change Orders Amount:
Completion: 12/31/2011   related activities.           $190,130
Budget/Costs Incurred
Significant Developments
7.4
Construction is complete. Substantial Completion Certification        7.2
issued on December 6, 2011.                           Millions 7
6.8
Schedule                             6.6
Construction phase is complete. Close out and reporting phase       Dollars in 6.4
6.2
underway.                                        Authorized Forecasted Costs Incurred
Budget
Forecast that all work will be completed within authorized funding.    Construction Costs
Change Order                           6
5
Thirteen change orders have been executed with a total amount of
Millions   4
$190,130.
3
Risks                                  2
Dollars in    1
None
0
Initial   Change   Spent
Budget Transfers                                Orders
None
Photo



SEAPORT
Port of Seattle 4Q 2011 Report  69

FOURTH QUARTER REPORT, 2011
T-91 Watermain Replacement
Project:   C800298      Replace water main in the vicinity   Status Snapshot
Budget: $4,255,000      of Magnolia Bridge and City      On Schedule
Phase: Construction     Ice/Trident including various     On Budget
Start: 9/20/2009          buildings at T91              0 Change Orders
Completion: 4/30/2012                        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Construction is in progress.
4.4
Schedule                             4.2
Millions  4
Schedule extended to Q2 2012 to accommodate construction and
site operations.                                         3.8
Dollars in 3.6
Budget
3.4
Currently the project is on budget. Additional funds of approximately       Authorized  Forecasted Costs Incurred
$320,000 will be requested in Q1 2012 to accommodate unforeseen
conditions.
Construction Costs
Change Order
None                                    4
3
Risks                                Millions
2
Contaminated material may be encountered throughout the
excavation process.
Dollars in    1
Budget Transfers                           0
Initial   Change   Spent
None                                        Orders
Photo


SEAPORT

70  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
T-91 Roadway Pavement Project
Status Snapshot Prior Report
Project:   C800343                             Delayed Schedule 2Q 11
Budget: $982,000     Repave two main roadway        On Budget
Phase: Construction   intersections and the adjacent areas   0 Change Orders
Start: 12/18/09         west of the east guard shack.        Total Change Orders Amount:
Completion: 5/1/2011                         $0
Budget/Costs Incurred
Significant Developments
0.99
Project closed out. This will be the last report on this project.
0.98
Schedule                            0.97 Millions
Construction is complete.                                0.96
0.95   Dollars in 
Budget
0.94
Project is on budget.                                        Authorized  Forecasted Costs Incurred
Change Order
Construction was performed by Port Construction Services.        Construction Costs
Risks                                  1
None                                   0.8
Millions  0.6
Budget Transfers
0.4
None                                  Dollars in  0.2
0
Initial   Change   Spent
Orders

Photo



SEAPORT

Port of Seattle 4Q 2011 Report  71

FOURTH QUARTER REPORT, 2011
T-5 Crane Cable Reels
Status Snapshot
Project:   C800349      Purchase Cable Reels for tenant.
Budget: $3,500,000                         On Schedule 4Q 11
Phase: Design                            On Budget
Start: 05/04/10                                   0 Change Orders
Completion: 03/31/11                         Total Change Orders Amount:
0
Significant Developments
Budget/Costs Incurred
Installation of the cable reels is scheduled to begin during the first
quarter on 2012.
4
Schedule                             3
Project is on schedule. Installation is anticipated to be complete by       2
in Millions
June 2012.
Dollars   1
Budget
0
None                                     Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
Photo
Schedule
Budget Transfers
None




SEAPORT

72  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
T18 Fender Replacement
Project:   C800416      Replacement of 202 timber fender   Status Snapshot
Budget: $5,465,000      piles and their supporting members  On Schedule
Phase: Construction     along the face of the SSA crane    On Budget
Start: 02/07/2010         terminal.                   2 Change Orders
Completion: 03/15/2012                       Total Change Orders Amount:
$16,500
Significant Developments                    Budget/Costs Incurred
Second phase of construction is underway; remaining 110 timber       8
fender piles being replaced, and beneficial occupancy expected for
6
all work in Q2 2012.                                    Millions 4
Schedule
2
Construction scheduled in two phases to accommodate permit       Dollars in 
0
windows and tenant operations. Resumption of construction of           Authorized Forecasted Costs Incurred
second phase work in December 2011, all work to be completed by
April 2012.
Construction Costs
Budget
Project is within the approved budget.                          1.5
Change Order                          Millions 1
None this quarter
0.5
Risks                                Dollars in 
0
None this quarter
Initial   Change   Spent
Orders
Budget Transfers
None                                 Photo



SEAPORT
Port of Seattle 4Q 2011 Report  73

FOURTH QUARTER REPORT, 2011
East Marginal Way Grade Separation
Project:   E102007      FAST Corridor funded project;     Status Snapshot Prior Report
Budget: $50,700,000     FHWA, State, City with Port      Delayed Schedule 2Q 11
Phase: Construction     commitment of $18,800,000. Scope  On Budget 2Q 11
Start: 5/2006            is to construct grade separation in   50 Change Orders
Completion: Q2 2012     vicinity of T5 and T18 to minimize   Total Change Orders Amount:
truck traffic/rail conflicts.            $640,482
Budget/Costs Incurred
Significant Developments
51
Bridge opened for southbound traffic on October 21, 2011. Opening
50
for northbound traffic is expected in mid-March 2012.              Millions 49
Schedule                             48
Construction is 97% complete and scheduled completion is extended   Dollars in  47
to 2nd Qtr. 2012 to allow overlay paving in good weather. The overall    46
program schedule remains as was reported in 4Q 09.                Authorized Forecasted Costs Incurred
Budget
The overall program budget remains the same as reported in 4Q 09.  Construction Costs
On future reports the budget that will be tracked will be the current
25
construction costs. The Budget status snapshot is On Budget
reflecting the active construction budget.                         20
Millions   15
Change Order
10
Fifty change orders have been executed for a total net amount of      Dollars in   5
$640,482. Change order to replace waterline expected to cost
0
$317,000.
Initial   Change   Spent
Orders
Risks
Construction change orders could occur, which could increase cost   Photo
of construction.
Budget Transfers
New source of funds indicates that no budget transfers will be
required.

SEAPORT

74  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Viaduct Construction Coordination
Project:   E104324,      Participate in the design &       Status Snapshot Prior Report
E104535-38          construction of the bored tunnel,   On Schedule 3Q 11
Budget: $366,400       north & south portals, Central     On Budget 3Q 11
Phase: Implementation   Waterfront surface streets, and    0 Change Orders
Start: 1/1/2009          related projects to ensure adequate  Total Change Orders Amount:
connection to port facilities.         $0
Completion: 12/31/2018
Budget/Costs Incurred
Significant Developments
Initial Viaduct demolition work began in October removing a          0.38
significant portion of the south end main line SR99 and creating a
0.375
detour around future tunnel boring machine launch pit near Terminal    Millions
46.                                             0.37
Schedule                            0.365 Dollars in 
Stage 3 H2K construction is expected to advertise for bids by spring    0.36
2012. Bored Tunnel Contractor completed installation of first traffic        Authorized Forecasted   Costs
Incurred
detour under existing Viaduct in order to relocate utilities, and begin
construction of secant pile walls. Terminal 46 mitigation measures
are expected to begin construction by March.                 Construction Costs
None
Budget
Port staff costs are within budget, which was increased from
$241,000 to $366,400.
Change Order
Not applicable
Risks
There are multiple impacts to port tenants and general freight
mobility due to temporary road closures, detours, and other
necessary construction activities.
Budget Transfers
None

SEAPORT

Port of Seattle 4Q 2011 Report  75

FOURTH QUARTER REPORT, 2011
Street Vacations T5,18,105
Status Snapshot
Delayed Schedule 4Q 11
Project: Capital &     Street vacation related real estate     On Budget
Expense         negotiations and agreements --T5,    0 Change Orders
104362, 104364, 104366 T18, and T105.               Total Change Orders Amount:
Budget: $1,500,000                         $0
Phase: Permitting
Start: June 2010                                 Budget/Costs Incurred
Completion: 2012
2
1.5
Millions
Significant Developments                      1
T-105 related street vacation is on schedule for City Council's final      0.5
approval early in 2012. T-18 street vacation is behind schedule due    Dollars in 
0
to on-going negotiations. T-5 negotiations are pending completion of       Authorized Forecasted Costs Incurred
T-18 negotiations and therefore delayed.
Schedule                           Construction Costs
T-18 and T-5 Street vacations are delayed by approximately a year,   Not Applicable
with T-18 expected to be completed by the end of 2012 and T-5
expected to be completed by the end of 2014.                 Photo
Budget
On Budget
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable


SEAPORT
76  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
T-18 Pile Cap Repair Pilot Project
Project:   E104559      T18 Pile Cap Repair Pilot Project    Status Snapshot
Budget: $1,000,000                         Delayed Schedule 4Q 11
Phase: Design                            On Budget 3Q 11
Start: 3/25/11                                    0 Change Orders
Completion: 12/31/12                        Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Design and permitting are complete and team is preparing for
construction phase.                                    0.4
Schedule                             0.3
Millions
Project is delayed by 2 months due to tenant operations.            0.2
Construction initially scheduled to start in January is now expected to
0.1
begin March 2012.                                  Dollars in 
0
Budget                               Authorized Forecasted Costs Incurred
Costs to date are lower than expected due to efficiencies in design
development and delays in start of construction.
Construction Costs
Change Order                         None
None
Risks
Risks include preventing deleterious materials from entering water,
minimizing any disruptions to tenant operations, and managing
project costs in order to stay within budget approved.
Budget Transfers
None



SEAPORT

Port of Seattle 4Q 2011 Report  77

FOURTH QUARTER REPORT, 2011
Dock System Condition Assessments
Project:   E104610-12    Inspections for T5, T18 & T46     Status Snapshot
Budget: $1,250,000                         Delayed Schedule 4Q 11
Phase: Implementation                       Forecast Overrun 4Q 11
Start: 1/1/2011                                   0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Final reports are complete, but require amendments for consultant
provided pile diving inspections.                              1.5
Schedule
Millions  1
Project is delayed past year end by about 6 weeks in order to
incorporate final reports related to pile diving inspections. 2012        0.5
assessment will include Pier 66 and Terminals 25 & 30.            Dollars in 
0
Budget                               Authorized Forecasted  Costs
Incurred
Budget is increased from $1,000,000 to $1,250,000 and is on target
to complete within this amount.
Construction Costs
Change Order                         Not Applicable
Not applicable.
Risks
Cost estimates provided require additional work in order to include all
soft costs before ready to include in budgeting process.
Budget Transfers
None for this period



SEAPORT

78  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
FT South Wall Reconstruction Phase IV
Project:   C800136      Completion of Fishermen's       Status Snapshot
Budget: $5,535,000      Terminal South Wall         Delayed Schedule
Phase: Construction     Reconstruction. Phase IV is located  On Budget
Start: 6/2009            along parcel currently leased by    8 Change Orders
Completion: 9/2011      FVO.                 Total Change Orders Amount:
$
Significant Developments                    Budget/Costs Incurred
All major works construction was completed in September 2011 and
6
the project is in close-out.
5
4
Schedule                            Millions
3
Project will be fully closed by May 2012.
2
Dollars in   1
Budget
0
None this quarter                                         Authorized Forecasted Costs Incurred
Change Order
None this quarter                                    Construction Costs
Risks                                  5
Successful installation of the sheet pile tie backs.                    4
Millions   3
Budget Transfers                           2
None                                  Dollars in   1
0
Initial   Change   Spent
Orders

Photo


REAL ESTATE
Port of Seattle 4Q 2011 Report  79

FOURTH QUARTER REPORT, 2011
FT C15 HVAC Improvements
Status Snapshot
Project:   C800137                             Delayed Schedule 4Q 11
Budget: $4,000,000    Provide the preliminary planning,    On Budget
Phase: Design       design, and construction for replacing  0 Change Orders
Start: 05/01/10         the FT C15 HVAC System.         Total Change Orders Amount:
Completion: 12/31/2012                       $0
Budget/Costs Incurred
Significant Developments
1.2
Schematic design options received on October 17th. After project
1
team reviewed the options, decision was made to look at a hybrid
0.8
option that replaced the roof top units for the restaurant and retail       Millions
0.6
spaces on the first floor "in kind" and changed out the second floor 
0.4
office spaces to a variable refrigerant flow (VRF) system. The        Dollars in 0.2
lifecycle costs for the hybrid solution were received on November
0
21st and will be reviewed by the team the following week. This
Authorized  Forecasted Costs Incurred
option, although slightly higher in initial costs, is the most cost
effective in the long run.
Schedule                           Construction Costs
Not Applicable
The schedule is delayed slightly (2-4 weeks) due to additional
reviews of the schematic options. .
Budget
On budget
Change Order
None
Risks
Further delays could cause construction to occur in winter (colder)
months but consultant has come up with a solution that will keep the
tenants comfortable even if the project occurs in cold weather
months. The risk now, albeit slight, is that the cost of the solution
could impact the budget.
Budget Transfers
None

SEAPORT
80  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
MIC Central Seawall Replacement
Status Snapshot
Project:   C800175      Replacement of steel sheet pile    Delayed Schedule
seawall between West Pier and     On Budget
Budget: $2,650,000
Phase: Construction     Central Pier at Maritime Industrial   4 Change Orders
Start: 9/2008            Center.                    Total Change Orders Amount:
$
Completion: 8/2011
Budget/Costs Incurred
Significant Developments                      3
All major works construction was completed by August 2011 and the
project is in close-out. This is the final report.                     Millions 2
1
Schedule
Dollars in 
Project will be fully closed out by April 2012.                       0
Authorized  Forecasted Costs Incurred
Budget
None this quarter
Construction Costs
Change Order                           1.8
None this quarter                                       1.7
1.6
Risks                                 1.5
Millions
None this quarter
Dollars in   1.4
1.3
Budget Transfers                             InitialChange OrdersSpent
None this quarter
Photo




REAL ESTATE

Port of Seattle 4Q 2011 Report  81

FOURTH QUARTER REPORT, 2011
RE Maintenance Shop Solution
Project:   C800187      Marine Maintenance Solution CIP   Status Snapshot
Budget: $2,640,000      facilities continued operations from  On Schedule
Phase: Construction     the existing shop location by     On Budget
Start: August 2010       funding the following five projects:   1 Change Orders
Completion: August 2012  MM Office Expansion; MM North-   Total Change Orders Amount:
end Office; MM Elec Upgrade; MM   1890
Roof Replacement; and MM
Kitchen Upgrade.             Budget/Costs Incurred
3
Significant Developments
Roof construction is essentially complete. Some work remains to      Millions 2
complete after electrical upgrade. Electrical equipment and materials
on-site and upgrade work began in December.                  1
Dollars in 
Schedule                             0
Authorized  Forecasted Costs Incurred
The Office Expansion project is complete. The Northend Office is
substantially complete. Roof Replacement is substantially complete.
The Electrical Upgrade will be completed in Q1 2012. The Kitchen    Construction Costs
Upgrade is expected to begin design in Q1 2012 with construction    None
completed during Q3 2012. All projects in CIP are expected to be
complete by the end of Q3 2012.
Budget
Commission authorized a $340,000 increase in the CIP budget for a
total authorization of $2,640,000 on June 14, 2011.
Change Order
There was one change order for less than $2000 to install additional
flashing.
Risks
Risk to the project is the coordination of electrical upgrade with SCL.
SCL must upgrade their service to the shop and schedule shutdown.
Budget Transfers
None

REAL ESTATE
82  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
FT NW Dock East Fender System Replacement
Project:   C800386      Replace existing timber fender     Status Snapshot
Budget: $3,750,000      system for the east section of the   On Schedule
Phase: Construction     NW Dock at Fishermen's Terminal  On Budget
Start: January 2010       including all new steel piling and    2 Change Orders
Completion: May 27, 2011  associated fender system.       Total Change Orders Amount:
$48,757
Significant Developments                    Budget/Costs Incurred
Project is in close-out phase.
4
Schedule                             3
Actual substantial completion was May 27, 2011; planned substantial   Millions
2
completion was June 14, 2011. Project close-out is in progress and
estimated to be completed during the first half of 2012.              Dollars in  1
0
Budget                               Authorized Forecasted Costs Incurred
Total project budget is $3,750,000.
Change Order                         Construction Costs
None
2.6
Risks
2.4
None                                  Millions
2.2
Budget Transfers
Dollars in    2
None
1.8
Initial   Change   Spent
Orders



REAL ESTATE
Port of Seattle 4Q 2011 Report  83

FOURTH QUARTER REPORT, 2011
Flight Information System (FIMS) II
Project: C101117        Procure, develop, and implement a  Status Snapshot
Budget: $5,400,000      FIMS system that includes       On Schedule
Phase:Implementation    replacement monitors, an airport   On Budget
Start: 5/4/2010           resource management system, and  0 Change Orders
Completion: 12/30/2012    a flexible digital signage system    Total Change Orders Amount:
capable of displaying flight         $0
information, visual paging, and
notifications.
Budget/Costs Incurred
Significant Developments                      6
5
Software configuration workshops in progress. Completed 90%
4
design on casework upgrades.
3
in Millions
Schedule                             2
Dollars   1
On Schedule
0
Authorized  Forecasted Costs Incurred
Budget
On Budget
Construction Costs
Change Order                         Not Applicable in this phase
None
Risks
Several scope changes have been requested that will impact budget
and schedule. These will be presented to Commission in February
2012.
Budget Transfers
None



CORPORATE
84  Port of Seattle 4Q 2011 Report

FOURTH QUARTER REPORT, 2011
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, and add service desk     0 Change Orders
Completion: 12/30/2012   module and wireless handheld    Total Change Orders Amount:
capabilities.                    $0

Significant Developments                    Budget/Costs Incurred
Major components of the program have been delivered including the
4
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of        3
Marine Maintenance and Aviation Maintenance Maximo systems in
2
September 2010. The smaller components of mobility enhancements   in Millions
and additional interfaces are in progress.                       Dollars  1
Schedule                             0
Authorized Forecasted   Costs
Prior Report - Several of the proposed new interfaces link the                       Incurred
Maximo system to the Peoplesoft Financials Procurement module.
Because of planned changes in the procurement process with the
Construction Costs
Peoplesoft Financials Upgrade project, the delivery of these
Not Applicable
interfaces will be delayed until after the completion of the upgrade
project.
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces and mobility enhancements.
Budget Transfers
None

CORPORATE
Port of Seattle 4Q 2011 Report  85

FOURTHH QUARTER RREPORT, 2011
Airrline Acttivity Maanagemeent
Prooject: C8000222       Deevelopmentt of an airlinne activity   Statuss Snapshott
Buddget: $5000,000       maanagement system thaat       On Schedule
Phaase:Planning        inteegrates witth several PPort      On Budget
Start: 6/19/20011          sysstems to reeplace agingg reporting   0 Channge Orderss
Commpletion: 5/1/2013     sysstem and supply data for airline   Total CChange Ordders Amounnt:
acttivity fees.                    $0

Budgett/Costs Inccurred
Significant DDevelopmments
0.6
Reqquirements and designn in progresss.
0.5
Schhedule                             0.4
0.3
On SSchedule                                  in Millions
0.2
Dollars 
Buddget                             0.1
0
On BBudget
Authorized  F o recasted Costs I ncurred
Chaange Ordder
Nonne
Construuction Cossts
Rissks                               Not Appplicable
No ssignificant rrisks
Buddget Trannsfers
Nonne




CORRPORATEE

86  Port of Seattle 4Q 2011 Report

SECOND QUARTER REPORT, 2011
Port of Seattle Internet Redesign
Project: C800319        Create a new Internet web site, and  Status Snapshot
Budget: $500,000       underlying infrastructure, with     Delayed Schedule
Phase:Planning        dynamic content and interactive    On Budget
Start: 1/6/2009           communication tools such as blogs,  0 Change Orders
Completion: 12/30/2011    video, podcasts, discussion forums  Total Change Orders Amount:
and interactive maps.           $0
Significant Developments                    Budget/Costs Incurred
New website builds complete. Content migration is in progress.
0.6
Schedule                            0.5
0.4
Resource availability to migrate content as well as additional time
0.3
required to fully test the new site has delayed the implementation to     in Millions
0.2
4th Quarter 2011.
0.1  Dollars 
Prior Report - The delay caused by the need to re-advertise the RFP    0
Authorized Forecasted   Costs
for an implementation vendor will delay the estimated completion to
Incurred
2Q 2011.
Budget                            Construction Costs
Not Applicable
On Budget
Change Order
None
Risks
Significant amount work will be required to clean up the website
content from the previous site. Individuals across the Port are
working on this effort but it may require additional time to complete.
Budget Transfers
None

CORPORATE

Port of Seattle 4Q 2011 Report  87

SECOND QUARTER REPORT, 2011
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot Prior Report
Budget: $1,525,000      costing systems with a common    Delayed Schedule
Phase:Implementation    enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: 9/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Installation of the software in the Port environment has been
completed. Final configuration and interface development in           2
progress.
1.5
Schedule
Millions  1
Prior Report - Vendor did not deliver software per original contract
and project was put on-hold to evaluate alternatives. A decision was    Dollars in 0.5
made to continue with Skire in July 2010. The estimated completion      0
date at this time is September 2011 although there may be interim         Authorized  Forecasted Costs Incurred
deliveries prior to completion.
Budget                            Construction Costs
None                                 Not Applicable
Change Order
None
Risks
See Schedule
Budget Transfers
None



CORPORATE
88  Port of Seattle 4Q 2011 Report

SECOND QUARTER REPORT, 2011
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot Prior Report
Budget: $800,000       increase functionality, and lower   Delayed Schedule    4Q 10
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 4/30/2012    records and document        Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
Sharepoint 2010 Upgrade has been completed. Design and
implementation of Sharepoint 2010 Records Center in progress.
1
Schedule                            0.8
Prior Report: Sharepoint 2010 implementation is dependent on the     0.6 Millions
completion of several infrastructure projects currently in progress      0.4
and requires additional time to complete the upgrade of existing
0.2  Dollars in 
sites. While Sharepoint 2010 will be available to departments
0
beginning in April 2011, the implementation of Sharepoint Records
Authorized Forecasted   Costs
Center will not be complete until December 2011. The full project is                  Incurred
estimated to be completed in April 2012.
Budget                            Construction Costs
Not Applicable
On Budget
Change Order
None
Risks
Scope of Sharepoint 2010 upgrade may require additional funding to
complete migration activities.
Budget Transfers
None

CORPORATE

Port of Seattle 4Q 2011 Report  89

SECONDD QUARTER RREPORT, 2011
Proopworkss Upgradde
Prooject: C8000328       Uppgrade the pproperty maanagementt  Statuss Snapshott
Buddget: $4500,000       sysstem, Propwworks, used by      On Schedule
Phaase: Impleementationn    Avviation Propperties and Real Estatee  On Budget
Start: 3/1/2011           orgganizationss.               0 Channge Orderss
Commpletion: 7/30/20122                         Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Aviaation implemmentation inn progress. Real Estatte/Seaport upgrade    Budgett/Costs Inccurred
will ffollow.
0.5
Schhedule                            0.4
On SSchedule                                  0.3
0.2  in Millions
Buddget
0.1  Dollars 
On BBudget
0
A u thorized Foreca s ted  Costs
Chaange Ordder                                   Incurred
Nonne
Construuction Cossts
Rissks
Not Appplicable
No ssignificant rrisks
Buddget Trannsfers
Nonne




CORPORATTE

90  Port of Seattle 4Q 2011 Report

SECOND QUARTER REPORT, 2011
Time Clock System
Project:C800387        Procure and implement a Time    Status Snapshot
Budget:$840,000       Clock System to accurately capture  On Schedule
Phase:Planning        and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion:7/30/2012     Aviation Security and Airport      Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
System configuration and interface development in progress
0.4
Schedule                            0.3
On Schedule
0.2   Millions
Budget                             0.1 Dollars in
On Budget
0
Authorized Forecasted   Costs
Change Order                                   Incurred
None
Construction Costs
Risks                               Not Applicable
No significant risks at this time.
Budget Transfers
None




CORPORATE

Port of Seattle 4Q 2011 Report  91

SECOND QUARTER REPORT, 2011
Peoplesoft Financials Upgrade
Project:C800392        Upgrade of Peoplesoft Financials   Status Snapshot
Budget:$5,000,000       hardware and software        Delayed Schedule
Phase:Planning                            On Budget
Start: 9/28/2010                                 0 Change Orders
Completion:12/31/2013                        Total Change Orders Amount:
$0
Significant Developments
An implementation vendor was selected via a competitive         Budget/Costs Incurred
procurement but we were unsuccessful in negotiating an acceptable
6
contract.
5
4
Schedule
Millions 3
Because of resource constraints during the year-end process, the
2
next optimum window of opportunity for the upgrade begins in mid-     Dollars in 1
2012. This will delay the project one year. In the interim, steps are
0
being taken to minimize risk to the overall project and resolve
Authorized  Forecasted Costs Incurred
procurement issues.
Budget
Construction Costs
On Budget                                  Not Applicable
Change Order
None
Risks
Significant resources will be required across multiple organizations
which may delay other technology projects.
Budget Transfers
None


CORPORATE

92  Port of Seattle 4Q 2011 Report

SECOND QUARTER REPORT, 2011
Police Records Management System
Project: C800393        Procure and implement a       Status Snapshot
Budget: $1,300,000      replacement Police Records      On Schedule
Phase:Planning        Management System         On Budget
Start: 10/10/2010                                0 Change Orders
Completion: 1/31/2012                         Total Change Orders Amount:
$0

Budget/Costs Incurred
Significant Developments
1.4
Negotiating contract with selected vendor.
1.2
1
Schedule                             0.8
On Schedule                                  in Millions 0.6
Dollars 0.4
0.2
Budget
0
On Budget                                      Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable in the phase
Risks
No significant risks identified at this time
Budget Transfers
None




CORPORATE

Port of Seattle 4Q 2011 Report  93

FOURTHH QUARTER RREPORT, 2011
CUUSE Migrration
Prooject: C8000481       Miggrate the AAirport Common-Use   Statuss Snapshott
Buddget: $4855,000       Paassenger Prrocessing SSystem,    On Schedule
Phaase:Planning        CUUSE, from aa virtual to aa physical   On Budget
Start: 6/19/20011          based infrastrructure           0 Channge Orderss
Commpletion: 2/29/20122                         Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Harddware purcchased and software innstalled in test environnment.     Budgett/Costs Inccurred
Testting in proggress.
0.6
Schhedule                             0.5
On SSchedule                                  0.4
Millions 0.3
Buddget                             0.2
Dollars in 0.1
On BBudget
0
Authorized  F o recasted Costs I ncurred
Chaange Ordder
Nonne
Rissks
Construuction Cossts
ICT has propossed a changge in the neetwork that will providee additional  Not Appplicable
capaacity for neww CUSE poositions andd better prootect network
avaiilability. This new depeendency will require airlines to make a
channge to theirr own netwoork before wwe move too the new CCUSE
enviironment. Iff airlines doo not responnd by the reequested daate, it will
delaay the comppletion of thhe project.
Buddget Trannsfers
Nonne



CORPORATTE

94  Port of Seattle 4Q 2011 Report

FOURTHH QUARTER RREPORT, 2011
Maaintenance Planning Sooftware
Prooject: C8000501       Proocure and iimplement        Statuss Snapshott
Buddget: $4022,000       Maaintenance Planning aand      On Schedule
Phaase:Implemmentationn    Sccheduling sooftware thaat integratess  On Budget
Start: 6/26/20011          witth our Asseet Managemment       0 Channge Orderss
Commpletion: 5/30/20122    sysstem, Maximo.            Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Softtware has bbeen installeed in test environmentt in preparaation for     Budgett/Costs Inccurred
conffiguration wworkshops sscheduled in January.
0.5
Schhedule                            0.4
On SSchedule                                  0.3
in Millions 0.2
Buddget
Dollars 0.1
On BBudget
0
A uthorized Fore c asted  Costs
Chaange Ordder                                    Incurre d
Nonne
Rissks
Construuction Cossts
No ssignificant rrisks                                      Not Appplicable
Buddget Trannsfers
Nonne




CORRPORATE

Port of Seattle 4Q 2011 Report  95

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.