7c Report

Item Number: _Report
Meeting Date: Dec 13, 2011


Commission Staff Brieng
Capital Improvement Projects
Third Quarter Report 2011

This page intentionally left blank









ii  Port of Seattle 3Q 2011 Report

Port of Seattle
Capital Improvement Project Report
Third Quarter 2011
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the statue of the Port's capital projects.
Background
During 2010 the Port plans to invest over $378,000,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 3Q 2011 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ............................................... 7-8.......... ...............
C102030 ...............Stormwater Management Program .......................9 ...........
C102163................Main Terminal Baggage Screening ................... 10-11 ........ ...................................
C102334 ...............Water System Isolation Valve Upgrade ................12 .......... ...............
C102573 ...............Aireld Pavement Replacement ...........................13 ..........
C800019 ...............Loading Bridge Utilities .........................................14 .......... ...............
C800034 ...............North Expressway Relocation ..............................15 .......... ...............
C800061 ...............Main Terminal South Low Voltage ........................16 .......... ...............
C800071 ...............Consolidated Warehouse .....................................17 .......... ...............
C800105 ...............Airport Owned Gate Infrastructure .......................18 ..........
C800107 ...............C4 UPS System Improvements ............................19 .......... ...............
C800109 ...............Garage Escalator & "A" Elevator Upgrade ...........20 .......... ...............
C800112................Runway 16C/34C Panel/Joint Sealant .................21 ..........
C800144 ...............Security CCTV System Improvements.................22 .......... ...............
C800147 ...............Concessions Unit Readiness Program ................23 .......... ...............
C800148 ...............GML Arrivals Hall Concessions ...........................24 .......... ...............
C800174................FIS - New Primary Inspection Booths ..................25 .......... .............................. 
C800203 ...............Common Use Lounge Remodel ...........................26 ..........
C800237 ...............Terminal Escalators Modernization ......................27 .......... ...............
C800238 ...............Central Plant Pre-Conditioned Air ........................28 .......... ...............
C800242 ...............Security Checkpoint Cameras..............................29 ..........
C800253 ...............Parking System Replacement ..............................30 .......... ..............................
C800254 ...............Aircraft RON Parking Post Ofce Site..................31 .......... .............................. 
C800274 ...............8th Floor Weather Proong ..................................32 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......33 .......... ..............................
C800331 ...............Communication Cable Add To MT, D, CTE ..........34 ..........
C800334 ...............Two new CTE Freight Elevators ...........................35 ..........
C800335 ...............EGSE Electrical Charging Stations ......................36 ..........
C800336 ...............South Satelite Delta Sky Club Extension .............37 .......... .............................. 
C800360 ...............Roof Replacement Program .................................38 .......... .............................................................................. 
C800374 ...............Claim Device 14 and Lower Inland .......................39 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ...............................40 ..........
C800406 ...............RW 16C/34C Reconstruction Design ...................41 ..........
C800412 ...............South Satellite Concessions Project ....................42 .......... ..............................
C800414 ...............Access Control Door Additions ............................43 ..........



2  Port of Seattle 3Q 2011 Report

C800415 ...............ALCMS Upgrade...................................................44 ..........
C800420 ...............Additional Aireld Mitigations at Tyee ..................45 ..........
C800426 ...............FIS Improvement - Phase I ...................................46 ..........
C800455 ...............Concourse D Common Use Environment ............47 .......... ..............................
C800457 ...............EGSE Rolling Stock ..............................................48 ..........
C800459 ...............2011-2013 Roof Replacement Program ...............49 ..........
C800466 ...............South Satellite - Additional Gate Lobby ................50 .......... ..............................
C800467 ...............PLB Replacement .................................................51 ..........
C800469 ...............Water System Isolation Valve - Aireld ................52 ..........
C800471 ...............Security Checkpoint Optimization ........................53 ..........
C800472 ...............Exterior Gate Improvements ................................54 ..........
C800474 ...............Airport Signage .....................................................55 ..........
Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................56 .......... ...............
C200042 ...............Highline Community College Noise Insulation .....57 .......... ...............
C200048 ...............Home Insulation Retrot .......................................58 .......... ...............
C200093 ...............Single Family Home Sound Insulation .................59 ..........
C800046 ...............Street Vacations  Des Moines Creek 1 ..............60 .......... .............................. 
C800146 ...............RMU/Kiosk Concession Program ........................61 .......... .............................. 
C800150 ...............Burien Commercial Property Acquisition .............62 .......... ...............
C800154 ...............Tenant Reimbursement ........................................63 ..........
C800354 ...............Paint Stripper Equipment ......................................64 .......... .............................. 
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800133 .............. T-86 Grain Facility Modernization (Phase I) ........65 .......... ................................................................................
C800165 .............. Seaport Security Grant Round 7 .........................66 .......... ..............................  ........................................
C800183 ...............P91 Fender System Upgrade ...............................67 ..........
C800264 ...............T-10 Interim Redevelopment.................................68 ..........
C800298 ...............T-91 Watermain Replacement ..............................69 ..........
C800343 ...............T-91 Roadway Pavement .....................................70 ..........
C800349 ...............T-5 Crane Cable Reels .........................................71 ..........
C800416 ...............T-18 Fender Replacement ....................................72 ..........



Port of Seattle 3Q 2011 Report  3

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget

E102007 ................East Marginal Way Grade Separation ..................73 ..........
E104324 ................Viaduct Construction Coordination ......................74 ..........
E104362 et al ........Street Vacations T-5/18/105 .................................75 ..........
E104559................T-18 Pile Cap Repair Pilot Project ........................76 ..........
E104610 ................Underdock Inspections .........................................77 ..........
Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800136 ...............FT South Wall Reconstruction Phase VI ..............78 ..........
C800137 ...............FT C15 HVAC Improvements ...............................79 .......... ...............
C800175 ...............MIC Central SeaWall Replacement ......................80 ..........
C800187 ...............RE Maintenance Shop Solutions..........................81 ..........
C800386 ...............FT NW Dock E. Fender System Replacement.....82 ..........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ....................83 ..........
C800003...............Maximo Enterprise Implementation......................84 .......... ...............
C800222 ...............Airline Activity Management .................................85 .......... .................................. ............................................
C800227 ...............Ground Transportation Management System ......86 .......... .............................. 
C800319............... Port of Seattle Internet Redesign.........................87 .......... .............................. 
C800321 ...............Enterprise Project Cost Management ..................88 .......... ...............
C800322 ...............Records and Document Management .................89 .......... .............................. 
C800326 ...............Business Continuity ..............................................90 .......... .............................. 
C800328 ...............Propworks Upgrade ..............................................91 ..........
C800387 ...............Time Clock System ...............................................92 ..........
C800392 ...............PeopleSoft Financial Upgrade ..............................93 .......... .............................. 
C800393 ...............Police Records Management System ..................94 ..........
C800395 ...............Upgrade to Windows 7 & Ofce 2010...................95 ..........
C800481 ...............CUSE Migration ....................................................96 ..........
C800501 ...............Maintenance Planning System .............................97 ..........


4  Port of Seattle 3Q 2011 Report

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
Previously Reported
No Diamond  On Budget or On Schedule















Port of Seattle 3Q 2011 Report  5

THIRD QUUARTER REPPORT, 2011
3rdd Runwaay Progrram
Status Snapshot
On Schedule
Prooject: C0000683,       Thee 3rd Runwway Programm
On Buddget
C0001138, C0001175,      connstructed a new 8,5000 foot long
5 Changge Orders
C0001331, C0001751,      runnway, conneecting taxiwways, and
Total Change Ordeers Amount:
C0001760, C1000172      relaated infrasttructure.
$43,2866.08
Buddget: $932,408,802
Phaase: Consstruction                       Budgett/Costs Inccurred
Start: 05/27/1997
1200
Commpletion: 12/31/20111
1000
Millions 800
Significant DDevelopmments                    600
400
The 2010 consstruction contract workk is complette except foor the in-     Dollars in 
200
streaam work that will be coompleted inn 2011. The remainingg tasks on
0
this project incllude: contrract in-streaam work, Allaska Mainttenance         Au t horized Forecast e d Costs Incurred
Buildding demolition, minorr in-stream work to adddress tempporal
impaacts, and PPond M moddifications.
Schhedule                           2011 Coontract Connst. Costs
Bidss were openned on Sepptember 22,, 2011 for thhe Alaska
2
Mainntenance BBuilding demmolition withh Constructtion Group
Interrnational ass the apparrent low bidder. Consttruction is nnow          1.5
scheeduled to sttart in the foourth quarteer of 2011.                  Millions
1
Buddget                            Dollars in  0.5
The project foreecast is witthin the appproved budgget and autthorization.
0
Initial   Change   Spent
Chaange Ordder                               Orders
5 Chhange ordeers were exeecuted this quarter.
Rissks                              Photo
Nonne
Buddget Trannsfers
Nonne this quarter

AIRRPORT

6  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Rental Car Facility
Status Snapshot Prior Report
Delayed Schedule 4Q 08
Project:   C100266,     The program will construct a       On Budget
C102167, C800032     consolidated rental car facility (RCF)  1,077 Change Orders
Budget: $419,306,000   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $12,259,041
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.          Budget/Costs Incurred
Significant Developments                     500
RCF construction is nearly 97 percent complete. Permanent power is    400
on and commissioning underway. Completing punch list of the        300 Millions
Customer Service Building, each floor plate and quick turnaround
200
areas. Averaging around 60 workers daily. Site work and
100  Dollars in 
landscaping is nearly complete. Analysis of Contractor and sub
claims continues. BMF and wash building shells complete with         0
Authorized Forecasted   Costs
building systems and finishes being installed througout the building.
Incurred
Site paving well underway and CNG equipment being installed.ORI
construction continues on the bridge demolition for widening and
seismic upgrade column wraps. Final paving complete on S160th St,  Construction Costs
the new ramp to SR518 and Host Road. MTI north and south bus
stops under construction, evaluating conduit routing and signs to be
300
replaced. Gillig has deleivered six buses and continues to
250
manufacture the remaining.
Millions 200
150
Schedule
100
The revised program schedule remains on-track for spring 2012       Dollars in  50
completion. RCF scheduled completion is February 13, 2012. Tenant
0
work to be completed March 2012. BMF scheduled completion is          Initial Change Spent
March 2012. ORI scheduled completion is December 2011 (except            Orders
for signage activation). MTI completion is February 2012. Bus
delivery planned through 4Q 2011.                        Photo
Budget
Customer Facility Charge revenues continue to increase slightly
each month, trending over $1,700,000 above projections. The
program forecast is within the approved budget and authorization.
Change Order
149 change orders were issued this quarter in the amount of
$2,220,263.
Port of Seattle 3Q 2011 Report  7

Risks
For RCF: schedule extended 90 days at no cost for concurrent delays to power on, changes as
project completes, contractor performance, claims submitted by prime contractor and one
subcontractor; and quality issues.
For ORI: unforeseen conditions; coordination with RCF contractor. weather and site congestion.
For BMF: multiple subcontractor congestion within building space; and completion of aggressive
construction schedule.
Budget Transfers
None this quarter.
Cost Growth of Construction
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - Cumulative change order percentage through this quarter is 26.8%. Primary reasons
for these changes are unknown conditions and contaminated materials.
Bus Maintenance Facility - MC-0316730 - Cumulative change order percentage through this quarter
is 0.6%.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative change order percentage through
this quarter is 19.4%. Primary reason for changes is the removal of contaminated soils and
associated impacts. This work and the final contract reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  Cumulative change order percentage
through this quarter is 170.5%. Primary reasons for changes are for additional contractor
management, estimating, scheduling and bidding effort for cost estimate reconciliation,
constructability reviews and value engineering beyond the extent of the original scope to validate
project costs and support the rental car companies and the Port on final approval of the project. This
work and the final contract reconciliation is complete.


AIRPORT

8  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Stormwater Management Program
Project:   C102030,    The program achieves permit       Status Snapshot
C800026, C800030     requirements and makes the Airport a  On Schedule
Budget: $50,329,788   leader in stormwater management by  On Budget
Phase: Construction   construction of flow control, water    11 Change Orders
Start: 06/11/2002       quality treatment and low stream flow   Total Change Orders Amount:
mitigation facilities.                  $8,103
Completion: 12/31/2011
Budget/Costs Incurred
Significant Developments
The stormwater program (C102030) is in its adaptive management     100
phase under which additional or upgraded water quality treatment
80
facilities are being implemented based on the stricter effluent         Millions 60
standards of the new (April 2009) stormwater National Pollutant
Discharge Elimination System (NPDES) permit. Construction work     40
was completed on stormwwater quality treatment upgrades at four     Dollars in 20
project sites and the contract is in the close-out phase.
0
Authorized Forecasted   Costs
Schedule                                      Incurred
The current adaptive management construction contract will be
closed out during the first half of 2012. The stormwater (C800026)    Construction Costs
and sanitary sewer (C800030) pipeliner projects, which are not part
of adaptive management, have been deferred until the second half of
1.2
2012, or later.
1
Budget                             Millions 0.8
0.6
The project forecast is within the approved budget and authorization.
Dollars in 0.4
Change Order                          0.2
Change orders were issued to execute minor design changes to        0
Initial      Change      Spent
improve the final construction and to reflect unforseen conditions.
Orders
Risks
Additional adaptive management facilities or upgrades may be
required beyond those recently completed, depending upon future
water quality monitoring results.
Budget Transfers
To Expense                         $17,446
AIRPORT
Port of Seattle 3Q 2011 Report  9

THIRD QUARTER REPORT, 2011
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $223,533,540   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget   4Q 09
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
Significant Developments                     235
The C-1 baggage handling/screening system has been placed into     230
revenue service for the Alaska Air Group. The C-1 Lid Replacement    225 Millions
is the only work remaining on this project.                       220
215  Dollars in 
Schedule
210
The project was delayed approximately two years from the original        Authorized Forecasted  Costs
Incurred
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope
changes. Turner Construction demobilized on May 31, 2009. The    Construction Costs
GCCM construction contract with Turner Construction has been
closed. The remaining fire sprinkler and fire proofing work was         200
completed.                                       150
Millions
Budget                             100
The project forecast is within the approved budget and authorization.
Dollars in   50
0
Change Order                             Initial Change Spent
Orders
665 Change Orders have been issued on this project.
Risks                               Photo
None
Budget Transfers
None this quarter



10  Port of Seattle 3Q 2011 Report

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated as they were unable to meet the
project schedule requirements. The remaining work was rebid in the fall of 2006. Alaska Airlines
asked that we include the BHS work within the 2-step ticket counter project; which increased the
amount of BHS work in the bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.












AIRPORT

Port of Seattle 3Q 2011 Report  11

THIRDD QUARTER RREPORT, 2011
Waater Systtem Isollation Vaalve Upggrade-noon AF
Statuss Snapshott
Delayeed Schedulee
Prooject:  C102334C          This project reeplaces isoolation     On Budget
Buddget: $704,000      valves on the aging wateer       0 Channge Orderss
Phaase: Desiggn        disstribution syystem, neceessary for   Total CChange Ordders Amounnt:
Start: 10/01/22010         isoolating portions of the ssystem in    $0
Commpletion: 3/31/20122    thee event of bbreaks, leakks, or tieinss.
Budgett/Costs Inccurred
0.8
0.7
Significant DDevelopmments
0.6
The project is ccurrently in constructioon.                        Millions 0.5
0.4
0.3
Schhedule                            Dollars in 0.2
The schedule is extendedd for three mmonths to aavoid operattional       0.1
impaacts during the busy hholiday seasson.                      0
A u thorized Fore c asted   Cost s
Incurr e d
Buddget
Construuction Cossts
The project foreecast is witthin the appproved budgget and autthorization.
Not Appplicable
Chaange Ordder
Nonne
Rissks
Nonne identifiedd at this timee
Buddget Trannsfers
Nonne this quarter



AIRRPORT

12  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Airfield Pavement Replacement
Status Snapshot
Project:   C102573      The project is intended to be a     On Schedule
Budget: $30,800,000     multi-year pavement replacement   On Budget
Phase: Construction     program to replace some of the    2 Change Orders
Start: 05/02/2010         worst pavement and joint seal on    Total Change Orders Amount:
Completion: 12/31/2016   the airfield.              $17,276.33
Budget/Costs Incurred
Significant Developments
35
Bids were opened on April 14, 2011. Gary Merlino Construction was
30
the selected bidder.
Millions 25
20
Schedule
15
The contractor is scheduled to be done with construction the week of    Dollars in  10
November 14, 2011. The construction work in 2011 was the initial      5
phase of a multi-year pavement replacement program scheduled       0
Authorized  Forecasted Costs Incurred
from 2011 to 2015.
Budget
Construction Costs
The project forecast is within the approved budget.
5
Change Order
4
Two change orders were executed this quarter. During replacement,
additional cracked panels and environmental monitoring wells were     Millions  3
discovered that needed commissioning.                        2
Dollars in    1
Risks
0
Any delay will put project out of typical construction window.               Initial  Change  Spent
Orders
Budget Transfers
None this quarter
Photo


AIRPORT

Port of Seattle 3Q 2011 Report  13

THIRD QUARTER REPORT, 2011
Loading Bridge Utilities
Project:   C800019   This project will upgrade all Port-       Status Snapshot Prior Report
Budget: $12,883,000  owned loading bridges to the same     Delayed Schedule    2Q 09
Phase: Design     standards, including 400Hz power and   On Budget
potable water. It will reduce air
Start: 06/28/2007                                 0 Change Orders
emissions, improve energy efficiency
Completion:                              Total Change Orders Amount:
and save money for the airlines.        $0
12/31/2013
Budget/Costs Incurred
Significant Developments                     14
The scope of this project has been increased to include two          12
additional gates (B-1 and B-5), and to increase the number of 400 Hz   Millions 108 Dollars in 
generators from two to three at the South Satellite to service 787s in
6
the future. The project will be redesigned to include the new scope.
4
2
Schedule
0
The schedule has been delayed due to the new scope additions.         Authorized Forecasted  Costs
Incurred
The advertisment for purchasing the equipment has been delayed
due to additional equipment requirements.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Airport Operations at certain gates could be impacted during the
construction phase of the project. The Ports power centers might
need to be upgraded to support the Pre-Conditioned Air, Electrical
Ground Support Equipment, and Loading Bridge Utilities projects.
Budget Transfers
None this quarter

AIRPORT

14  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
North Expressway Relocation
Project:   C800034
The project is a collaboration      Status Snapshot  Prior Report
Budget: $110,347,700    between the Port and Sound     Delayed Schedule 2Q 11
Phase: Construction     Transit. It reconstructs the North   On Budget
Start: 07/27/2004         Airport Expressway and brought    212 Change Orders
Completion: 07/31/2012   light rail to the Airport.         Total Change Orders Amount:
$8,134,800
Significant Developments
Budget/Costs Incurred
The work in the main contract for reconstruction of the North Airport
Expressway and light rail transit components is complete. The        115
intelligent transportation management system is complete. A final
110
contract to complete paving, landscaping, the north entry art          Millions
features, and other miscellaneous work is complete except for punch
105
list work and the first year plant establishment.
100  Dollars in 
Schedule
95
The main contract reached substantial completion in August 2008        Authorized Forecasted  Costs
and plant establishment was completed in December 2010. A                     Incurred
contract for final paving, landscaping, and reclamation is underway
and is complete except for punch list work and the first year plant     Construction Costs
establishment period to be complete in mid-2012.
120
Budget
100
The project forecast is within the approved budget and authorization.    Millions 80
60
Change Order
40
Two change orders were issued this quarter in the amount of         Dollars in 20
$23,535.                                         0
Initial      Change      Spent
Order
Risks
None identified at this time.
Photo
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 3Q 2011 Report  15

THIRD QUARTER REPORT, 2011
Main Terminal South Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
On Budget
Phase: Design      and below) electrical distribution
equipment in the southern part of the    0 Change Orders
Start: 06/28/2007
Total Change Orders Amount:
Completion: TBD    Main Terminal.
$0
Significant Developments                    Budget/Costs Incurred
Due to project deferral and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. Additional scope of work is being added due to increased     2
electrical loads and site condition changes. The 90% design review    Millions1.5
documents were submitted for review and comments are currently
1
being addressed. A new Project Notebook is under development to    Dollars in 0.5
address scope of work and budget.
0
Schedule                              Authorized Forecasted Costs
Incurred
The project was reactivated on June 24, 2009 and is in the process
of determining the scope of work, schedule and final design budget.
The project will return to the Commission for authorization of        Construction Costs
additional design funds in the first quarter of 2012.               Not Applicable
Budget                            Photo
The project budget has been evaluated based on delays and scope
changes and will be submitted to Commission during the first quarter
in 2012.
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area of the Main Terminal is a 24/7/365 operation.
Sequencing of this work is critical and electrical power has to be
maintained without interruptions.
Budget Transfers
None this quarter
AIRPORT
16  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Consolidated Warehouse
Project:   C800071     This project will construct a 50,000    Status Snapshot Prior Report
Budget: $9,237,000     square foot warehouse for storage   Ahead of Schedule    3Q 09
Phase: Close Out     and inventory management of spare  On Budget
Start: 06/27/2006       parts for the Aviation Maintenance    34 Change Orders
Department.
Completion: 02/15/2010                       Total Change Orders Amount:
$770,658
Significant Developments                    Budget/Costs Incurred
The project is complete and in close out, with the building open for
use and in operation. This will be the last quarterly report for this      9.35
project.                                                9.3
9.25
Schedule
9.2
Millions
The project was completed ahead of schedule.                 9.15 Dollars in 9.1
Budget
9.05
The project forecast is within the approved budget and authorization.       Authorized Forecasted  Costs
Incurred
Change Order
None this quarter                                    Construction Costs
6
Risks
5
None this quarter                                     Millions  4
3
Budget Transfers                           2
None this quarter                                     Dollars in   1
0
Initial    Change    Spent
Cost of Construction Growth                         Orders
CO's exceeding 10% were due to the following:
1. Soil and foundation changes due to the site being an old,
Photo
unconsolidated fill of unknown material;
2. Perceived market conditions during bidding, structural mezzanine
was deleted. The bid climate changes allowed the mezzanine to
be installed; and
3. Pallet racks were anticipated to be a Port purchase and install.
The purchasing officer recommended the contractor purchase and
install as a CO.

AIRPORT
Port of Seattle 3Q 2011 Report  17

THIRD QUARTER REPORT, 2011
Airport Owned Gate Infrastructure
Project:   C800105      This project purchases and
Status Snapshot
Budget: $6,000,000      replaces passenger loading bridges
(PLB) at gates throughout the      On Schedule
Phase: Construction
airport. The project is being        On Budget
Start: 07/24/2007
performed in phases.           0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The work at Gate B5 will begin in November 2011 and will be
completed by the end of November. Recladding of the exterior of the
7
B5 stair tower has been added to this scope. The work at Gate S10
6
will begin in November and completed by the end of the year. This
Millions 5
PLB is being retained for refurbishment and reinstallation at another     4
gate.                                               3
Schedule                            Dollars in  2
1
The project is currently on schedule to complete the original scope      0
Authorized Forecasted   Costs
by December 31, 2012. There may be sufficient funds remaining in
Incurred
this project to also cover the refurbishment of the PLB at Gate S3.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

18  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
C4 UPS System Improvements
Project:   C800107    Project will replace existing          Status Snapshot Prior Report
Budget: $2,336,000   Uninterruptible Power Supply (UPS)    Delayed Schedule 1Q 09
Phase: Construction  System, including batteries, with a new  On Budget
Start: 06/28/2007      new system located in the Airport      0 Change Orders
Completion: TBD     Combined Communications and      Total Change Orders Amount:
Command Center (C4).           $0
Significant Developments                    Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. Additional scope of work is being added due to increased     2
electrical loads and site conditions changes. The 90% design review    Millions1.5
documents were submitted for review and comments are currently
1
being addressed. A new Project Notebook is under development to    Dollars in 0.5
address scope of work and budget.
0
Schedule                              Authorized Forecasted Costs
Incurred
The project was reactivated on June 24, 2009 and is in the process
of determining the scope of work, schedule and final design budget.
The project will return to the Commission for authorization of        Construction Costs
additional design funds in the first quarter of 2012.               Not Applicable
Budget
The project budget has been evaluated based on delays and scope
changes and will be submitted to Commission during the first quarter
in 2012.
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 3Q 2011 Report  19

THIRD QUARTER REPORT, 2011
Garage Escalator & A-Bank Elevator Upgrade
Project:   C800109    This project renews aging elevators    Status Snapshot Prior Report
Budget: $5,815,000    and escalators in the Airport Parking   Delayed Schedule    3Q 10
Phase: Close Out     Garage to provide reliable vertical    On Budget
Start: 09/11/2007       transportation to customers for years   26 Change Orders
Completion: 10/31/2011  to come.                 Total Change Orders Amount:
$234,937
Significant Developments                    Budget/Costs Incurred
Contractor work on all six Garage Escalators is complete and all
8
escalators are operational. The A-Bank elevator work was
completed in 2010. Construction contract is in close-out phase.        6
Millions
Schedule                             4
Project close-out will be completed during the first quarter of 2012.      Dollars in  2
Budget                             0
Authorized Forecasted   Costs
The project forecast is within the approved budget and authorization.                   Incurred
Change Order                         Construction Costs
Three change orders were issued this quarter to bring the existing
electrical system up to code, to install additional electrical junction       4
boxes, and to activate the escalator communication system.
3
Millions
Risks                                2
None identified at this time.                                 Dollars in  1
0
Budget Transfers                            Initial  Change  Spent
Order
To C800152 (Non-Aeronautical New Projects)       $756,735



AIRPORT

20  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot
The scope of work will remove and   On Schedule
Project:   C800112      replace the pavement and joint seal  On Budget
in areas on Runway 16C-34C.
Budget: $4,161,623                         0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 02/26/2008                                 $0.00
Completion: 09/01/2012
Significant Developments                    Budget/Costs Incurred
On July 26, 2011, the Port Commission authorized the remaining       6
funding for this project.
5
Millions  4
Schedule
3
Design efforts for 2012 contract has started and is at a 60% level.       2
The intent of this contract is to coordinate this work with an apron      Dollars in  1
panel replacement project, an airline realignment project, and a fuel
0
hydrant installation project all with similar work and timing.               Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
None this quarter.                                    Photo
Risks
No risks have been identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 3Q 2011 Report  21

THIRD QUARTER REPORT, 2011
Security CCTV System Improvements
Project:   C800144      This project will install          Status Snapshot Prior Report
Budget: $2,037,591      approximately 70 new cameras for  Delayed Schedule 3Q 09
Phase: Implementation   TSA and integrate existing Airport   On Budget
Start: 9/11/2007          camera networks which contain     0 Change Orders
Completion: 05/31/2010   over 800 cameras.          Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Project is complete and in close out. This will be the last quarterly
2.038
report for this project.
2.036
Schedule                            Millions
2.034
Project substantial completion occurred in March 2010.
2.032  Dollars in 
Budget
2.03
The project forecast is within the approved budget and authorization.       Authorized Forecasted  Costs
Incurred
Change Order
Not Applicable                                     Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

22  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Concessions Unit Readiness Project
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Construction     previously vacated or slated to be   On Budget
Start: 08/26/2008         vacated to Port standards for use    0 Change Orders
Completion: 06/30/2013   as specialty concession space.    Total Change Orders Amount:
$0
Significant Developments
This project received Commission authorization in September 2010   Budget/Costs Incurred
to design and build concession spaces in two locations. Design of
these two locations is complete. Commission authorized            2.5
design/construction of two additional locations on August 9, 2011.
2
Millions
Schedule                             1.5
The construction phase has been restructured and re-sequenced,      1
with the intent to maximize the timing for new Concessions          Dollars in 0.5
opportunities. The project was put on hold until the prioritization
0
decisions were made by Aviation Business Development.             Authorized Forecasted  Costs
Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 3Q 2011 Report  23

THIRD QUARTER REPORT, 2011
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot  Prior Report
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule 1Q 11
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,000
project includes installing three      0 Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new     $0
Completion: 07/01/2012   approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
1.2
The design for utilities was previously completed in 2009 but put on
1
hold due to market conditions. Plans for the new food-beverage
0.8
concession will be reviewed by the Concessions group for viability
0.6
via a cost analysis to be performed in early 2012.                 in Millions
0.4
Dollars 
Schedule                             0.2
The project schedule was delayed due to the pending decision by       0
Authorized Forecasted   Costs
the Business Development Group to proceed with the                           Incurred
concessionaire.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not applicable
Change Order                         Photo
None
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter


AIRPORT

24  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Federal Inspection Services - New Primary
Inspection Booths
This project will replace existing     Status Snapshot  Prior Report
Project:   C800174      primary inspection booths for      Delayed Schedule 2Q 11
Customs and Border Protection in   On Budget
Budget: $2,000,000
the International Arrivals Federal    0 Change Orders
Phase: Construction     Inspection Services (FIS) facility in  Total Change Orders Amount:
Start: 07/27/2010         the South Satellite.             $0
Completion: 09/08/2011
Budget/Costs Incurred
Significant Developments
All of the new booths are complete and operational. A few items       2.5
remain prior to completion including final signage and camera          2
installation.                                                Millions 1.5
1
Schedule
Dollars in 0.5
Final items are planned to be complete by the end of the year.
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 3Q 2011 Report  25

THIRD QUARTER REPORT, 2011
Common Use Lounge Remodel
Project:   C800203      This project will relocate the Port's   Status Snapshot
Budget: $1,061,000      common-use lounge from the     On Schedule
Phase: Design        mezzanine level to the departure   On Budget
Start: 03/01/2011         level of the South Satellite.        0 Change Orders
Completion: 02/28/2012   Improvements consist of new     Total Change Orders Amount:
finishes, new furnishings and other   $0
minor cosmetic improvements.
Budget/Costs Incurred
Significant Developments
1.2
The construction contract is pending award to the low bidder.          1
0.8
Schedule
0.6
Millions
The schedule has been accelerated to recover the potential delay.      0.4
Construction is currently scheduled to begin in late fall 2011 and will     Dollars in 0.2
complete by the end of February 2012.
0
Authorized Forecasted   Costs
Budget                                      Incurred
The project budget was increased to support double construction
shifts necessary to meet accelerated completion schedule. The     Construction Costs
current project forecast is within the approved budget. Authorization   Not Applicable
of construction funding and authority to award for construction will be
requested when the design and bid documents are completed..
Change Order
None
Risks
Meeting targeted completion date will be a challenge even with the
accelerated schedule.
Budget Transfers
None this quarter


AIRPORT

26  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Terminal Escalators Modernization
Project:   C800237      This project will replace 42       Status Snapshot Prior Report
Budget: $38,212,733     escalators in the Main Terminal,    Ahead of Schedule 1Q 11
Phase: Design        Concourse B, and South Satellite.   On Budget
Start: 11/02/2007         In addition, two new escalators will   23 Change Orders
Completion: 07/01/2013   be installed at the South Satellite.   Total Change Orders Amount:
$1,147,453
Significant Developments                    Budget/Costs Incurred
Replacement of six escalators in Concourse B and eight escalators
60
at two of the Main Terminal Sky Bridges began in third quarter.
Additionally, started relocation of the South Satellite (SSAT)           50
Communications Room. Concourse B is scheduled to be complete    Millions 40
in first quarter of 2012. Replacement of the Main Terminal            30
escalators will continue in multiple phases into 2013. Replacement     20
of the SSAT escalators will begin in fourth quarter of 2011.           Dollars in 10
0
Schedule                               Authorized Forecasted  Costs
Incurred
The project is currently on schedule.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
20
Change Order
15
The most significant change orders have involved significant         Millions
electrical panel replacements/upgrades to accommodate the need      10
for additional circuits for the new escalators as well as upgrades        5
wiring. These upgrades were anticipated during project scoping.       Dollars in 
Also, added enclosures under sky bridges and additional costs for       0
Initial      Change      Spent
asbestos abatement.
Order
Risks
None identified at this time.
Budget Transfers
To C102166 (Aeronautical Renewal/Replace)    $7,500,000
To Expense                       $517,559

AIRPORT
Port of Seattle 3Q 2011 Report  27

THIRD QUARTER REPORT, 2011
Central Plant Pre-Conditioned Air
Project:   C800238     This project will provide a centralized  Status Snapshot Prior Report
Budget: $43,535,000    pre-conditioned air (PC-Air) plant,    Delayed Schedule 3Q 09
Phase: Design       associated heating and cooling piping  Forecast Overrun
Start: 06/15/2009       systems, and jet bridge terminal air    57 Change Orders
Completion: 12/10/2012  handling units to serve airplanes with  Total Change Orders Amount:
heating and cooling while at the      $1,177,600
gates.
Significant Developments                    Budget/Costs Incurred
The contractor is installing equipment foundations in the Central
Terminal Basement, and piping and electrical conduit at the South      50
Satellite, Concourse B and Concourse C.                     40
Millions 30
Schedule
20
The design process took longer than anticipated and the project is
Dollars in 
approximately two months behind the original schedule.            10
0
Budget                               Authorized Forecasted Costs
Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Twenty seven change orders were issued this quarter. There are 57
30
total change orders on this contract. The large change orders were
25
issued for piping and electrical site conflicts, sump pump
Millions  20
specification revision, and PCAP area door schedule revision.
15
Risks                                 10
Dollars in    5
The design schedule had to be accelerated in order to meet VALE
grant submission dates, which could impact the number of change       0
Initial  Change  Spent
orders and design modifications. The design consultant has                 Orders
improved response time on Requests for Information and Submittal
review. Due to a contract dispute with the PC-Air unit supplier, the
Contractor has not received products to facilitate installation of any of
the 73 PC-Air unts. Each installation will take at least a couple of
days and requires a gate to be shutdown. As of October 1, there are
62 weeks to the end of contract. There is a risk that the PC-Air Units
will not be installed at the gates within the existing contract time.
Budget Transfers
None this quarter
AIRPORT
28  Port of Seattle 3Q 2011 Report

THIRDD QUARTER RREPORT, 2011
Seccurity Checkpoint Cameras
Prooject:  C800242C          Insstall new caameras to vview      Statuss Snapshott
Buddget: $500,000      passenger sccreening proocesses at  On Schedule
Phaase: Consstruction     passenger seecurity checckpoints.   On Budget
Start: 07/17/22011                                 0 Channge Orderss
Commpletion: 03/31/20112                      Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Budgett/Costs Inccurred
The design is ccomplete. EEquipment pprocuremennt is underwway and
consstruction wiill start in November 2011.                       0.6
0.5
Schhedule
The project is ccurrently onn schedule.                          Millions0.4
0.3
0.2
Buddget                             Dollars in 0.1
The project foreecast is witthin the appproved budgget and autthorization.
0
A uthorized For e casted  Cos t s
Chaange Ordder                                    Incur r ed
Nonne
Construuction Cossts
Rissks
Not Appplicable
Nonne identifiedd at this timee.
Buddget Trannsfers
Nonne at this timme




AIRRPORT

Port of Seattle 3Q 2011 Report  29

THIRD QUARTER REPORT, 2011
Parking System Replacement
Project:   C800253      This project replaces the current    Status Snapshot
Budget: $9,777,000      Parking Revenue Control System,   Delayed Schedule
Phase: Construction     which manages parking access    On Budget
Start: 04/06/2010         and revenue collection in the      0 Change Orders
Completion: 05/31/2012   Airport's Main Parking Garage.    Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Three competitive proposals were received for the parking revenue
control system. The evaluation process included interviews and        12
system demonstrations. Developing final contract scope of work.       10
Expect to award in October 2011.                          Millions 8
6
Schedule                             4
Dollars in 
Project advertisement was delayed with decision to select "best bid"     2
procurement approach and completing the bid documents.           0
Negotiations and development of the final contract specifications and      Authorized Forecasted  Costs
Incurred
performance are taking longer than anticipated. Completion of the
system likely delayed as late as May 2012 including avoiding work
during the holidays.                                    Construction Costs
None this quarter
Budget
The project forecast is within the approved budget and authorization.   Photo
Change Order
No change orders were issued this quarter.
Risks
This project schedule is aggressive.
Budget Transfers
None this quarter


AIRPORT

30  Port of Seattle 3Q 2011 Report

THIRD QUUARTER REPPORT, 2011
Airrcraft ROON Parkking USPPS Site
Statuss Snapshott Prior Reportt
Delayeed Schedulee     1QQ 11
Prooject: C8000254       Thiis project wwill prepare the site forr
On Buddget
Buddget: $43,900,000     thee constructioon of Hardsstands for
0 Channge Orders
Phaase: Consstruction    usee as Remaiin Overnighht (RON)
Total CChange Ordders Amounnt:
Start: 08/26/22008        parrking of airccraft at the AAir Mail
$0
Center site.
Commpletion: 12/31/20114
Significant DDevelopmments                   Budget//Costs Incuurred
The temporary lease with the United States Posstal Servicee (USPS)     50
for the Air Mail Center sitee ended in JJanuary 20011. Designn efforts
40
for the demolition of the AAir Mail Cennter includinng the desiggn for
miniimal site immprovementts allowing ffor temporaary uses annd         Millions 30
ameenities, and 15% hardsstand desiggn started inn Summer 22010.       20
Hazardous material removval will be included ass a part of thhe         Dollars in  10
demmolition conttract.
0
A uthorized  Forecasted Costs I n curred
Schhedule
Bid wwere openeed on Septeember 13, 22011 with RRhine Demoolition, Inc.
as thhe apparennt low biddeer. Abatement and demolition of the USPS  Construuction Costs
Buildding is scheeduled to start in the foourth quarter of 2011.         Not Applicable
Propposed consstruction of a permaneent hardstannd is scheduled to
begiin the second quarter of 2013.                         Photo
Buddget
The project foreecast is witthin the appproved budgget.
Chaange Ordder
Nonne
Rissks
Exteent of asbesstos in the USPS Buildding may afffect the prooject cost.
Buddget Trannsfers
Nonne this quarter

AIRRPORT
Port of Seattle 3Q 2011 Report  31

THIRD QUARTER REPORT, 2011
8th Floor Weatherproofing
Project:   C800274      This project includes removal and   Status Snapshot
Budget: $13,050,000     replacement of the floor covering   On Schedule
Phase: Construction     system on the 8th floor of the STIA  On Budget
Start: 03/23/2010         parking garage and repair or       0 Change Orders
Completion: 03/31/2013   replacement of expansion joints    Total Change Orders Amount:
and flashings.                 $0
Significant Developments                    Budget/Costs Incurred
The design is almost complete and the project is awaiting final
signatures to Project Labor Agreement (PLA). The Port is currently     14
working on bid documents and preparing for advertisement. The Port    12
10
is evaluating the construction schedule to determine if work can be
8
completed in one or two seasons, which could extend the completion     Millions
6
to the end of 2013 due to the application of weather-sensitive
4
material.                                             Dollars in
2
0
Schedule                              Authorized Forecasted Costs
Incurred
The delivery of the design by the consultant was delayed; in addition
a late decision to require a PLA for this project delayed the schedule.
It has taken more time than anticipated to get Unions to sign the     Construction Costs
agreement. Bid advertisement and award is now scheduled for fourth  Not Applicable
quarter of 2011.
Photo
Budget
The project forecast is within the approved budget and authorization.
Change Order
No change orders were issued this quarter.
Risks
This is a weather-dependent project.
Budget Transfers
None this quarter

AIRPORT
32  Port of Seattle 3Q 2011 Report

THIRDD QUARTER RREPORT, 2011
Common UUse Equuipment Expanssion (CUUSE)
Prooject:  C800276C          This project innstalls flexibble       Statuss Snapshott
Buddget: $3,0090,000     passenger processing        Delayeed Schedulee
Phaase: Desiggn        infrastructure and equipmment at thee  On Budget
Start: 09/01/22009         airrline gates aat some Soouth       0 Channge Orderss
Commpletion: 6/31/20122    Saatellite and CConcourse A gates,   Total CChange Ordders Amounnt:
as well as at tthe former Delta       $0
loccation.
Budgett/Costs Inccurred
Significant DDevelopmments
4
The 100% desiign documeents are being finalizedd after scoppe to install
commmon use innfrastructure at the forrmer Delta AAir Lines ticcket         3
counnters was ddeleted fromm the projecct.                       Millions
2
Dollars in                                                                             Schhedule                                                                 1
The project is bbehind scheedule because investiggation of exxisting        0
infraastructure aand cable trray pathwayys took longger than annticipated        A uthorized Forec asted  Costs
Incurred
and removal off ticket counnter scope at a late staage of desiggn
requuired changges to the design docuuments.
Buddget                           Construuction Cossts
Not Appplicable
The project foreecast is witthin the appproved budgget. Authorrization of
consstruction funding and aauthority too advertise ffor construcction will
be requested wwhen the deesign and bbid documents are commpleted.
Chaange Ordder
Nonne
Rissks
Nonne identifiedd at this timee
Buddget Trannsfers
Nonne this quarter


AIRRPORT
Port of Seattle 3Q 2011 Report  33

THIRD QUARTER REPORT, 2011
Communications Cable Additions to MT, D, CTE
Project:   C800331      Addition of copper and fiber cabling  Status Snapshot
Budget: $377,000       to create a redundant pathway    On Schedule
Phase: Construction     throughout the Central Terminal    On Budget
Start: 08/11/2011         and Main Terminal             0 Change Orders
Completion: 12/31/2011   Communications Rooms.       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
The construction notice to proceed will be issued in October 2011.      0.4
0.3
Schedule                            Millions
The project is currently on schedule.                          0.2
Dollars in 0.1                                                                               Budget
The project forecast is within the approved budget and authorization.     0
Authorized Forecasted   Costs
Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

34  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Two New CTE Freight Elevators
Project:   C800334      Provide two new freight elevators   Status Snapshot
Budget: $6,664,000      to support concession operations in  On Schedule
Phase: Design        the Central Terminal/Pacific      On Budget
Start: 08/05/2011         Marketplace.                0 Change Orders
Completion: 07/31/2011                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
The project design commenced in third quarter 2011. The 30%        7
design documents will be submitted for review in late October.         6
Millions 5
Schedule                             4
3
The project is scheduled to complete design in first quarter 2012.       2
Construction is anticipated to commence in fourth quarter 2012.       Dollars in 
1
0
Budget                               Authorized Forecasted Costs
Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.    Construction Costs
Not Applicable
Change Order
None
Risks
There is a potential risk due to unknown conditions where the freight
elevator foundations will be constructed, i.e., outside of the Central
Terminal building envelope.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 3Q 2011 Report  35

THIRDD QUARTER RREPORT, 2011
Eleectrical GGround Supporrt Equipmment (EGSE)
Statuss Snapshott
Eleectrical CCharge Stationss                On Schedule
On Budget
Prooject:  C800335C          Airrport-wide eelectrical chharging     0 Channge Orderss
Total CChange Ordders Amounnt:
Buddget: $14,410,000     sysstem for eleectrical grouund
$0
Phaase: Desiggn        support equippment (EGSSE) at the
Start: 10/26/22010         Cooncourses aand the Norrth and
Commpletion: 4/30/20133    Soouth Satellittes.
Budgett/Costs Inccurred
Significant DDevelopmments                     20
The Port is finaalizing the EEGSE batteery chargerss Request ffor
15
Propposal. The design consultant commpleted the schematicc design      Millions
docuuments that will be useed for the PProject Noteebook oncee the        10
revieew processses are commpleted.
Dollars in   5
Schhedule                             0
A uthorized  For ecasted Costs In c c urred
The project teaam is in the process off developingg the implementation
scheedule.
Buddget                           Construuction Cossts
Not Appplicable
The project foreecast may need to be increased based on the
Scheematic Dessign documents. Authorization foor the consttruction
fundding and auuthority to advertise forr constructioon will be rerequested
wheen the desiggn and bid ddocuments are compleeted.
Chaange Ordder
Nonne
Rissks
Poteential risks include latee execution of agreements betweeen Port
and Airline Carrrier Consorrtium, and CCoordinatioon with otheer airfield
projeects and Aiirline Realiggnment proogram.
Buddget Trannsfers
Nonne this quarter

AIRRPORT

36  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
South Satellite Delta Sky Club Expansion
Status Snapshot Prior Report
Delayed Schedule 1Q 11
Project:   C800336     Construction of a new 6,800 square   On Budget
Budget: $8,930,000    foot Sky Club lounge on the roof of   0 Change Orders
Phase: Close Out     the South Satellite for Delta Air Lines.  Total Change Orders Amount:
Start: 06/01/2010                                 $0
Completion: 08/30/2011
Budget/Costs Incurred
Significant Developments                     10
The Delta Air Lines Sky Club is complete and open to Delta           8
customers. The Port is currently reviewing change orders to Port      Millions 6
scope.
4
Schedule                            Dollars in  2
The construction work is complete. Project close out is in process.      0
Authorized  Forecasted Costs Incurred
Budget
The project forecast for the current scope has increased and is within
Construction Costs
the approved budget and authorization.
Not Applicable
Change Order
None
Risks
The Port's scope and costs could still increase beyond current
authorization as change orders are negotiated and costs split
between Delta and the Port. However, now that construction is
complete the risk is reduced.
Budget Transfers
From C102165 (Aeronautical New Projects)     $3,490,000


AIRPORT

Port of Seattle 3Q 2011 Report  37

THIRD QUARTER REPORT, 2011
Roof Replacement Program
Status Snapshot
On Schedule
Project:   C800360      Remove and replace the roofing    Under Budget
Budget: $2,640,000      systems on the south and central   0 Change Orders
Phase: Construction     sections of the Main Terminal. The  Total Change Orders Amount:
Start: 4/25/2010          new roofing systems will achieve    $0
Completion: 10/31/2011   LEED credits and are Energy Star
rated. This project is part of a      Budget/Costs Incurred
multi-phased program.
3
2.5
Significant Developments
Millions  2
Project is scheduled to reach beneficial occupancy in October 2011.
1.5
1
Schedule                            Dollars in 0.5
The project is currently on schedule.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
The project anticipates a savings of approximately $1,000,000.      Construction Costs
Change Order                           1.2
None                                    1
Millions 0.8
Risks                                 0.6
None at this time                                        0.4
Dollars in  0.2
Budget Transfers                           0
None this quarter                                          Initial Change Spent
Orders



AIRPORT

38  Port of Seattle 3Q 2011 Report

THIRDD QUARTER RREPORT, 2011
Claaim Device 14 && Lower Inboundd
Prooject:  C800374C          This project wwill replace the slope-   Statuss Snapshott
Buddget: $3,9900,000     plaate bag claim device 14 and     On Schedule
Phaase: Desiggn        asssociated coontrols, in aaddition to   On Budget
Start: 04/01/22011         remmoving the lower feed conveyor   0 Channge Orderss
Commpletion: 05/31/20112   and replacingg it with a neew      Total CChange Ordders Amounnt:
oveerhead feedd.               $0
Budgett/Costs Inccurred
Significant DDevelopmments                     4.5
4
The project is ccurrently at 90% desiggn.                       Millions  3.5
3
Dollars in     2.5
Schhedule                             2
1.5
The project is ccurrently onn schedule.
1
0.5
Buddget                             0
Authorized       For e casted      Costs Incurr e d
The project foreecast is witthin the appproved budgget. Authorrization of
consstruction funding and aauthority too award for constructioon will be
Construuction Cossts
requuested when the desiggn and bid ddocuments are compleeted.
Not Appplicable
Chaange Ordder
Nonne
Rissks
Nonne
Buddget Trannsfers
Nonne



AIRRPORT

Port of Seattle 3Q 2011 Report  39

THIRDD QUARTER RREPORT, 2011
Bagggage HHandlingg Systemm (C22-CC1, MK1, and
TC3)
This project wwill replace the ticket    Statuss Snapshott
Prooject:  C800382C          counter (TC3) conveyorss and      On Schedule
declines, rerooute the connveyors of   On Budget
Buddget: $5,3335,000
thee C-22 systtem and connnect it to    0 Channge Orderss
Phaase: Desiggn        thee C-1 screeening systemm, replace  Total CChange Ordders Amounnt:
Start: 03/01/22011         thee existing mmakeup (MKK1) device,   $0
Commpletion: 05/31/20113   and install a nnew odd sizze baggagee
sysstem.                  Budgett/Costs Inccurred
6
Significant DDevelopmments                     5
Millions
The design connsultant finaalized desiggn of TC3 cconveyor syystem.        4
Design on the rremainder oof the projeect is almosst complete. Port      Dollars in 
3
Connstruction Services started demolishing the eexisting tickket counter     2
convveyor. We rreceived the new convveyor equippment on site
1
September 26, 2011. The team expeects the first phase of wwork to be
0
commpleted by the end of the year.                              Authorized   For e casted   Costs Incurr e d
Schhedule                           Construuction Cossts
The project is ccurrently onn schedule.                        Not Appplicable
Buddget
The project foreecast is witthin the appproved budgget. Authorrization of
consstruction funding and aauthority too award for constructioon will be
requuested when the desiggn and bid ddocuments are compleeted.
Chaange Ordder
Nonne
Rissks
Nonne identifiedd at this timee
Buddget Trannsfers
Nonne this quarter

AIRRPORT

40  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
RW16C/34C Reconstruction Design
Project:   C800406      This project will produce the 60%   Status Snapshot
Budget: $669,000       design for the runway 16C/34C    On Schedule
Phase: Design        reconstruction. The design will    On Budget
Start: 05/04/2010         include utilities, runway status      0 Change Orders
Completion: TBD       lights, and other scope items     Total Change Orders Amount:
related to the project.             $0
Significant Developments                    Budget/Costs Incurred
The 60% design was issued in December 2010. Incorporation of
0.8
comments on the 60% design work is completed.
0.6
Schedule                            Millions
0.4
Staff will return to Commission for authorization of the remaining
design funds in late 2014 or early 2015. The forecast will be         Dollars in 0.2
reassessed when staff returns to the Commission for authorization of
0
the final design funds.
Authorized  Forecasted Costs Incurred
Budget
The Port Commission authorized $669,000 on May 4, 2010. The     Construction Costs
current forecast for 60% design is within the approved budget and    Not Applicable
authorization. Any potential savings will be returned.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 3Q 2011 Report  41

THIRD QUARTER REPORT, 2011
South Satellite Concessions Project
Status Snapshot
Delayed Schedule
Project:   C800412      This project will demolish and      On Budget
Budget: $1,872,739      relocate the existing duty free shop,  0 Change Orders
Phase: Design        electric/communications to support  Total Change Orders Amount:
Start: 01/01/2011         a temporary duty free location, and   $0
Completion: 03/31/2013   construct a new food and beverage
shell space in the South Satellite at
Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                      2
The project received Commission Authorization for design on         1.5
March 8, 2011. Design procurement is underway.               Millions
1
Schedule                            Dollars in 0.5
Design concept alternatives required more extensive review than
0
anticipated. The new concept allows the existing duty free to remain
Authorized  Forecasted Costs Incurred
operational during construction, but requires a longer construction
period.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

42  Port of Seattle 3Q 2011 Report

THIRDD QUARTER RREPORT, 2011
Access Coontrol Dooor Addditions
Prooject:  C800414C          This project wwill provide biometric   Statuss Snapshott
Buddget: $1,8800,000     acccess controols and seccurity     On Schedule
Phaase: Desiggn        cameras at aiirport terminnal doors.   On Budget
Start: 09/27/22011                                 0 Channge Orderss
Commpletion: 09/30/20112                      Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Budgett/Costs Inccurred
Design fundingg was authoorized by the Commisssion in thirdd quarter off
2011.                                         2
Schhedule                            1.5
The project is ccurrently onn schedule.
1
Millions
Buddget                             Dollars in 0.5
The project foreecast is witthin the appproved budgget. Authorrization of
0
consstruction funding and aauthority too advertise ffor construcction will
A uthorized For e casted  Cos t s
be requested wwhen the deesign and bbid documents are commpleted.                   Incur r ed
Chaange Ordder
Construuction Cossts
Nonne.
Not Appplicable
Rissks
Nonne identifiedd at this timee.
Buddget Trannsfers
Nonne this quarter




AIRRPORT
Port of Seattle 3Q 2011 Report  43

THIRDD QUARTER RREPORT, 2011
ALCMS Uppgrades
Statuss Snapshott
On Schedule
Prooject:  C800415C          Proovide modiffications to the Airfieldd  On Budget
Buddget: $2,1109,000     Ligghting Conttrol and Monitoring    0 Channge Orderss
Phaase: Consstruction     Syystem to upddate, enhannce and    Total CChange Ordders Amounnt:
Start: 01/01/22011         staabilize the ssystem to mmeet the     $0
Commpletion: 12/31/20114   lateest FAA sppecificationss.
Budgett/Costs Inccurred
Significant DDevelopmments
2.5
Connstruction off the duct bbank on the south end of RW16CC-34C is
2
commplete; this aaccommodates a full ccommunicaations loop aaround the
airfieeld. The fiber optic cabble contractor will be pperforming            Millions1.5
acceeptance tessting prior too installatioon next monnth. The neew tower
1
anteenna base ddesign is coomplete. PCCS is prepaaring constrruction bid    Dollars in 
for aaward and iinstallation of the anteenna in Deccember.              0.5
0
Schhedule                              A uthorized For e casted  Cos t s
Incur r ed
The project is ccurrently onn schedule.
Buddget                           Construuction Cossts
The project foreecast is witthin the appproved budgget and autthorization.  Not Appplicable
Chaange Ordder
Nonne this quarter
Rissks
Cooordination wwith on-going airfield opperations iss a consideeration.
The Port is alsoo working too eliminate unplannedd outages wwhen
transsitioning froom the oldeer computerr platform too the one.
Buddget Trannsfers
Nonne this quarter



AIRRPORT
44  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Additional Airfield Mitigation at Tyee
Project:   C800420      The project will design and       Status Snapshot
Budget: $800,000       complete the Tyee Golf Course    On Schedule
Phase: Construction     Area Mitigation which includes    On Budget
Start: 02/08/2011         removing a culvert, new wetland    0 Change Orders
Completion: 03/30/2012   planting, updating existing wetlands  Total Change Orders Amount:
to environmental permit standards,   $0
and installing a temporary irrigation
system.                  Budget/Costs Incurred
1
Significant Developments
0.8
The Port Commission authorized design funds on February 8, 2011.
On August 2, 2011, the Commission authorized the remaining funds    Millions 0.6
to complete the project.                                   0.4
Dollars in 0.2
Schedule
0
Project was advertised on September 8, 2011 with bid opening           Authorized Forecasted Costs Incurred
scheduled for October 11, 2011. Construction is scheduled to begin
in December 2011.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget.
Photo
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 3Q 2011 Report  45

THIRD QUARTER REPORT, 2011
Federal Inspection Service Improvements -
Phase 1
Improvements to the Federal      Status Snapshot
Project:   C800426      Inspection Service area at the     On Schedule
South Satellite to remedy queuing   On Budget
Budget: $31,700,000
pinch points and add additional     0 Change Orders
Phase: Design        passenger processing capacity.    Total Change Orders Amount:
Start: 04/01/2011                                 $0
Completion: 05/31/2013
Budget/Costs Incurred
Significant Developments                     35
Rate negotiation with selected design consultant is in progress.        30
Millions 25
Schedule                             20
15
This project is currently projected to complete on schedule.
Dollars in  10
5
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

46  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Concourse D Common Use Environment
Project:   C800455      This project installs a common-use  Status Snapshot
Budget: $4,250,000      environment at all gates on      Delayed Schedule
Phase: Design        Concourse D. Scope includes new  On Budget
Start: 03/01/2011         communications infrastructure,     0 Change Orders
Completion: 12/31/2012   casework built to a new Airport    Total Change Orders Amount:
standard, new carpet, wall        $0
coverings and task lighting.
Budget/Costs Incurred
Significant Developments
5
The casework mock-up is being completed for project stakeholders
4
to review on site. Feedback on the mock-up will be incorporated into
the final design documents which will be complete by the end of
Millions  3
2011.                                          2
Dollars in   1
Schedule
0
Construction of the mock-up casework took longer than anticipated,        Authorized  Forecasted Costs Incurred
plus gate shutdowns associated with this project are currently being
coordinated with other Concourse D shutdown work. Construction is
now anticipated to be complete in December 2012.             Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Phasing of the construction work could push the completion date out
further.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 3Q 2011 Report  47

THIRDD QUARTER RREPORT, 2011
Eleectrical GGround Supporrt Equipmment (EGSE)
Rolling Stoock
The Port of Seattle was to procure   Statuss Snapshott
Prooject:  C800457C          and deploy thhe initial fleeet of EGSEE  On Schedule
rolling stock.                    On Budget
Buddget: $30,000,000
0 Channge Orderss
Phaase: Desiggn                           Total CChange Ordders Amounnt:
Start: 0/26/20010                                  $0
Commpletion: Not applicable
Budgett/Costs Inccurred
Significant DDevelopmments
On OOctober 27, 2011, Alaska Airliness notified thhe Port of SSeattle that    2.5
theyy will not bee particpatinng in the Poort purchaseed EGSE RRolling        2
Stocck program. Based on this inforammtion the PPort is now iin the       Millions1.5
proccess to closse out this pprogram. This will be tT       the last quaarterly
repoort for this pproject.                                        1
Dollars in 0.5
Schhedule
0
Nonne                                     A uthorized For e casted  Cos t s
Incur r ed
Buddget
Nonne.                                    Construuction Cossts
Not Appplicable
Chaange Ordder
Nonne
Rissks
Nonne.
Buddget Trannsfers
Nonne



AIRRPORT
48  Port of Seattle 3Q 2011 Report

THIRDD QUARTER RREPORT, 2011
20111-2013 Roof Reeplacemment Proogram
Prooject:  C800459C          This project wwill remove and      Statuss Snapshott
Buddget: $4,7777,000     repplace the rooofing systeems on the  On Schedule
Phaase: Desiggn        firee station annd north endd of the    On Budget
Start: 07/01/22011         maain terminall.                0 Channge Orderss
Commpletion: 10/31/20111                      Total CChange Ordders Amounnt:
$0
Significant DDevelopmments                   Budgett/Costs Inccurred
Design and bidd documentt preparatioon is underwway.
6
Schhedule                             5
The project is ccurrently onn schedule.                          Millions 4
3
Buddget
2
The project foreecast is witthin the appproved budgget. Authorization for    Dollars in 
1
consstruction funding and aauthority too award for constructioon will be
0
requuested when the desiggn and bid ddocuments are compleeted.
A uthorized F o recasted  C o o sts
Inc u rred
Chaange Ordder
Nonne                                 Construuction Cossts
Not Appplicable
Rissks
Nonne at this timme
Buddget Trannsfers
Nonne this quarter




AIRRPORT
Port of Seattle 3Q 2011 Report  49

THIRD QUARTER REPORT, 2011
South Satellite - Additional Gate Lobby
Status Snapshot
Delayed Schedule
Project:   C800466      Demolition of glass partitions,      On Budget
Budget: $1,257,000      restrooms, relocation of gate     0 Change Orders
Phase: Design        podiums new flooring, ceilings and  Total Change Orders Amount:
Start: 11/01/2010         infrastucture to provide additional    $0
Completion: 03/31/2013   gate lobby in the South Satellite.
Significant Developments                    Budget/Costs Incurred
Commission Authorization for design and removal of glass panels
was received in November 2010. Design procurement is underway.
1.4
1.2
Schedule
1
Project delay was caused by delayed design negotiations and        0.8
contracting. Additionally, a longer design period is required due to       Millions
0.6
dependency on the South Satellite Concessions Project (C800412).    Dollars in 0.4
0.2
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

50  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Passenger Loading Bridge Replacement
Status Snapshot
Project:   C800467      This project entails Passenger     On Schedule
Budget: $14,850,000     Loading Bridge (PLB)         On Budget
Phase: Design        replacements associated with the   0 Change Orders
Start: 04/12/2011         one-time airline realignment (AR).   Total Change Orders Amount:
Completion: 04/30/2012   The work will take place at      $0
Concourse D, Concourse B and
North Satellite.
Budget/Costs Incurred
Significant Developments
The phasing of Concourse D gates refurbishment and replacement
20
was modified. A new bid package will go out to bid at the end of the
first quarter of 2012. PLB work at Concourse B is scheduled to take     15
place during the second half of 2012. The PLB work at the North      Millions
10
Satellite is currently scheduled to begin in second quarter of 2013
and continue through the end of the year.                      Dollars in  5
Schedule                             0
Authorized  Forecasted Costs Incurred
The project is currently on schedule.
Budget
Construction Costs
The project forecast is within the approved budget. Authorization of   Not Applicable
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 3Q 2011 Report  51

THIRD QUARTER REPORT, 2011
Water System Isolation Valve Upgrade - Airfield
Project:   C800469      The water distribution system at the
Budget: $1,443,000      Airport is almost 40 years old. This  Status Snapshot
Phase: Construction     project will replace and add      On Schedule
Start: 11/15/2010         additional water valves in several    On Budget
Completion: 12/31/2011   strategic locations to prevent     0 Change Orders
possible outages.              Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
On November 15, 2010, Commission authorized dividing the Water      2
System Isolation Valve Upgrade project into two projects, Airfield and
1.5
Non-Airfield. Construction work started in June. All water valves
near the South Satellite were completed in August with the North end    Millions 1
water valves scheduled to be completed by October 2011.
Dollars in 0.5
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not applicable
be requested when the design and bid documents are completed.
Photo
Change Order
None
Risks
The replacement valve sizes were taken from 25-40 year old
documents.
Budget Transfers
None this quarter


AIRPORT

52  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Security Checkpoint Optimization
Project:   C800471      This project supports TSA initiative  Status Snapshot
Budget: $430,000       to accomodate emerging       On Schedule
Phase: Construction     technologies. Major elements were  On Budget
Start: 08/15/2010         new electrical infrastructure to      0 Change Orders
Completion: 10/31/2011   checkpoints and minor relocation of  Total Change Orders Amount:
lanes for installation of Advanced    $0
Imaging Technology (AIT) units.
Budget/Costs Incurred
Significant Developments                     0.44
0.43
Construction is almost complete. Only final punchlist items remain
0.42
and will be completed in the fourth quarter.
0.41  Millions
0.4
Schedule
0.39  Dollars in 
The project is currently on schedule.                         0.38
0.37
Budget                               Authorized Forecasted Costs
Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 3Q 2011 Report  53

THIRD QUARTER REPORT, 2011
Exterior Gate Improvements (Airline
Realignment)
This project will install new fuel pits   Status Snapshot
Project:   C800472      and aircraft docking systems at     On Schedule
exterior gates for the airline         On Budget
Budget: $2,650,000
reallocation program.            0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 06/01/2011                                 $0
Completion: 10/31/2012
Budget/Costs Incurred
Significant Developments                      3
2.5
The 60% design documents are complete.
2
Schedule                             1.5
in Millions
1
The project is currently on schedule.                          Dollars 0.5
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.    Construction Costs
Not Applicable
Change Order
None
Risks
If the proposed future gate locations for the airlines change, it could
impact the project schedule and budget.
Budget Transfers
None this quarter



AIRPORT
54  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Airport Signage (Airline Realignment)
Project:   C800474      The project will provide airport     Status Snapshot
Budget: $646,000       directional signage for the airline   On Schedule
Phase: Design        reallocation program.         On Budget
Start: 06/01/2011                                 0 Change Orders
Completion: 04/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
A Request for Qualifications was issued for a signage design         0.7
services contract.                                       0.6
Millions 0.50.4
Schedule
0.3
The project is currently on schedule.
Dollars in 0.2
0.1
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 3Q 2011 Report  55

THIRD QUARTER REPORT, 2011
Highline School Noise Insulation
Project:   C200007      Highline School Insulation        Status Snapshot Prior Report
Budget: $101,797,000    Agreement will provide funding for  Delayed Schedule 4Q 10
Phase: Construction     sound mitigation for 15 schools that  On Budget
Start: 03/23/1999         are impacted by aircraft noise from   0 Change Orders
Completion: 11/30/2021   Sea-Tac Airport.            Total Change Orders Amount:
$0
Significant Developments
The insulation of seven schools has been completed and no more    Budget/Costs Incurred
are scheduled until 2013.
120
Schedule                            100
80
Port funding is authorized and will be available when the matching
funds are provided by the FAA, the State of Washington, and the       60
in Millions
Highline School District. The schedule for state funding is not known.    40
Dollars 
The district's schedule is dependent on obtaining general election      20
bonds at various intervals.                                  0
Authorized Forecasted   Costs
Budget                                       Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Not applicable
Risks
Project delayed due to funding issues with the Highline School
District.
Budget Transfers
None this quarter



AIRPORT
56  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $10,822,000     Insulation Agreement will provide   Delayed Schedule 4Q 10
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      0 Change Orders
Completion: 10/01/2011   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
$0
Significant Developments
Thirteen of the 22 eligible buildings have been sound insulated by    Budget/Costs Incurred
the college.
12
Schedule                             10
Building #9 construction was completed in the first quarter of 2011,     Millions 8
6
with some remaining punchlist items. Building #4 anticipated to
4
begin construction in the summer 2012. The schedules for the        Dollars in 
remaining buildings are dependent on state funding.               2
0
Authorized Forecasted   Costs
Budget
Incurred
The project forecast is within the approved budget. Authorization of
the remaining project budget will be requested for one building at a
time from the Commission in the future when schedule is          Construction Costs
determined.                                     Not Applicable
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed. The Port is working with the College to determine
estimates for the remaining college buildings that have not been
completed.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 3Q 2011 Report  57

THIRD QUARTER REPORT, 2011
Home Insulation Retrofit
Project:   C200048      This project includes storm window  Status Snapshot Prior Report
Budget: $5,344,000      retrofit of previously insulated     Delayed Schedule 4Q 10
Phase: Construction     homes.                On Budget
Start: 01/11/2005                                 0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The Port is researching remaining eligible homes to continue with
insulation retrofit and storm window retrofit.                       6
5
Schedule                             4
Two homes are in the process and reviewing potential 34 homes for     3
in Millions
eligibility.                                                          2
Dollars   1
Budget
0
The project forecast is within the approved budget and authorization.       Authorized Forecasted  Costs
Incurred
Change Order
Not Applicable                                     Construction Costs
Not Applicable
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter



AIRPORT

58  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot
Budget: $4,947,395      that are within the 1998 65 decibel  On Schedule
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   1 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Sixteen homes are in process of receiving sound insulation; nineteen
6
homes are on the waiting list for the next group.
5
Schedule                             Millions 4
This project is currently on schedule.                           3
2
Budget                             Dollars in  1
The project forecast is within approved budget and authorization.       0
Authorized Forecasted   Costs
Incurred
Change Order
None
Construction Costs
Risks
4
The ability to accomplish the insulation is dependent on the
homeowner's schedules, willingness to sign an aviation easement      3
and obtain a subordination agreement from their lender, and         Millions
structural integrity of the home. If more eligible homes than            2
anticipated are identified in the future, then additional funding may be
1
needed.                                      Dollars in 
0
Budget Transfers                             Initial  Change  Spent
Order
None this quarter



AIRPORT
Port of Seattle 3Q 2011 Report  59

THIRD QUARTER REPORT, 2011
Street Vacations - Des Moines Creek 1
Project:   C800046    Purchase the City of Des Moines-      Status Snapshot Prior Report
Budget: $3,850,000   owned streets in the Des Moines Creek  Delayed Schedule 2Q 11
Phase: Implementation Business Park site that are surrounded  On Budget
Start: 10/01/2008      by Port-owned property. This        0 Change Orders
Completion: 12/31/2011 acquisition will enable the Port to     Total Change Orders Amount:
develop the business park site.        $0
Significant Developments                    Budget/Costs Incurred
Closing on the large majority of the streets with the City of Des
4.6
Moines occurred in March 2011. One small parcel must still be
4.4
acquired from the Washington State Department of Transportation
(WSDOT).                                Millions4.2 Dollars in 
4
Schedule                             3.8
Final acquisition of the WSDOT parcel is expected to be completed     3.6
by December 31, 2011, which is a delay due to a delay in acquisition    3.4
approval by WSDOT.                                Authorized Forecasted  Costs
Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Not applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
60  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
RMU/Kiosk Concession Program
Project:   C800146    The project will provide design and     Status Snapshot Prior Report
Budget: $1,209,000   fabrication of eight Retail         Delayed Schedule 3Q 10
Phase: Construction   Merchandising Units (RMUs); provide   On Budget
Start: 11/20/2007      power, communications, and data to    0 Change Orders
Completion: 06/30/2011 sixteen RMU locations; and install floor-  Total Change Orders Amount:
mounted receptacles for the utilities to    $0
allow easy connection points as well as
flexibility for future utilization.
Budget/Costs Incurred
1.4
Significant Developments
1.2
All RMU utility installations are complete, and considered
Millions 1
substantially complete. The remaining tasks include purchasing and    0.8
installing the RMU kiosk units.                              0.6
Dollars in 0.4
Schedule                             0.2
0
The project has been on hold pending the staffing of a vacant
Authorized Forecasted   Costs
position in Concessions. This position was filled in third quarter of                    Incurred
2011 and work has begun to develop this portion of the small
business program and procure these RMU units.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 3Q 2011 Report  61

THIRD QUARTER REPORT, 2011
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot Prior Report
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule    2Q 10
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   0 Change Orders
Completion: 12/31/2013   owned properties.           Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The Sunnydale sub-station was purchased from Seattle City Light on
3.5
July 25, 2011. The last anticipated acquisition will be the street
3
vacation of 12th Place S. in Burien, Washington.
Millions2.52
Schedule
1.5
It is anticipated that the street vacation will occur in the 2012-2013
Dollars in  1
time frame.                                         0.5
0
Budget                               Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget.
Change Order                         Construction
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
62  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Tenant Reimbursement
Status Snapshot
Project:   C800154    Build out of spaces for new and      On Schedule
Budget: $4,709,577    existing tenants. If more than a "basic  On Budget
0 Change Orders
Phase: Construction   finish" condition space is built for the
tenant, the tenant is required to       Total Change Orders Amount:
Start: 08/14/2007
reimburse the Port for the cost of the   $0
Completion: 03/31/2012
work beyond this "basic finish". These
reimbursements are allowed under    Budget/Costs Incurred
the guidelines described in the
"Tenant Reimbursement Policy".       5
4
Significant Developments                     Millions 3
There were no tenant reimbursements during the third quarter of
2
2011. Future tenant projects will likely be part of the Airline
Dollars in 
Realignment over the next few years, so this project may have         1
limited activity.                                               0
Authorized Forecasted   Costs
Incurred
Schedule
Schedules vary to meet the tenant's needs.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 3Q 2011 Report  63

THIRD QUARTER REPORT, 2011
Paint Striper Equipment
Project:   C800354      Via a competitive process,       Status Snapshot Prior Report
Budget: $420,000       purchase one Truck Chassis     Delayed Schedule 1Q 11
Phase: Implementation   Mounted Airless Application Paint   On Budget
Start: 09/01/2010         Striping Unit for the Airport. This    0 Change Orders
Completion: 10/31/2011   requested paint striper equipment   Total Change Orders Amount:
is necessary to meet operational,    $0
safety and regulatory requirements.
Budget/Costs Incurred
Significant Developments
The contract has been advertised and bid opening date was in        0.5
March.                                       0.4
Millions0.3
Schedule
0.2
The project is currently on schedule for completion in fourth quarter
Dollars in 
2011.                                         0.1
0
Budget                               Authorized Forecasted Costs
Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

64  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
T-86 Grain Facility Modernization           Status Snapshot Prior Report
Ahead of Schedule 3Q 11
Modernize and replace aging grain   Under Budget    3Q 11
Project:   C800133      facility equipment/controls for $5M   2 Change Orders
by 12/31/2011 to maximize       Total Change Orders Amount:
Budget: $2,900,000
operational efficiencies and allow    $58,123.00
Phase: Construction     continuation of uninterrupted grain
Start: 2/21/2010          terminal operations.           Budget/Costs Incurred
Completion: 12/30/2011
4
3
Significant Developments                     Millions 2
Phase-1 - project is complete.                               1
Dollars in   0
Phase-2 - project is complete.                                 Authorized  Forecasted Costs Incurred
Schedule
Phase-2 - portion was completed ahead of schedule.            Construction Costs
3
Budget
Declaration of "Critical Work", requested an additional $180,000       Millions  2
to support the project by allowing the increase of Port labor to
1
accommodate the tenant's critical shutdown schedule.
Dollars in    0
Change Order                             InitialChange OrdersSpent
Phase-1 $33,123
Phase-2 $25,000                                Photo
Risks
None
Budget Transfers
None


SEAPORT

Port of Seattle 3Q 2011 Report  65

FOURTH QUARTER REPORT, 2011
Seaport Security Grant Round 7
Project:   C800165      Seaport Security Grant Round 7    Status Snapshot
Budget: $2,283,090                         On Schedule 4Q 11
Revised Budget $2,582,490                      On Budget
Phase: Construction                        0 change Orders
Start: March 2007                                Total Change Orders Amount:
Completion: Dec 2010
Budget/Costs Incurred
Significant Developments
2.5
Three bids were received with the lowest at 17.6% over the
2
Engineer's estimate. We reviewed the estimate and the entire
project budget. As a result, the revised project budget was over the    Millions 1.5
estimate and we went back to the Commission and requested and      1
received additional funding.                                Dollars in 0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
Slightly delayed. Project was delayed due to bids coming in over the
Engineer's estimate sot construction is expected to start late
December or early January and completed in 6 to 8 weeks (weather
Construction Costs
dependent).
Not Applicable
Budget
On budget as revised
Change Order
None
Risks
Construction won't be complete until after Cruise starts in April.
Budget Transfers
None


SEAPORT

66  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
P91 Fender System Upgrade
Project:   C800183      Upgrades to the vessel berths of    Status Snapshot
Budget: $5,700,000      P91 to better accommodate cruise  On Schedule
Phase: Design        ships and also serve the other    On Budget
Start: 01/31/10          industrial customers who utilize the   0 Change Orders
Completion: 04/30/2012   berths and adjacent dock/apron    Total Change Orders Amount:
areas on P91 for less than $6M by   $0
spring 2011.
Budget/Costs Incurred
Significant Developments
Final design is complete, contract advertised, award and            2.5
construction start expected Q4 2011.                          2
Millions 1.5   Dollars in 
Schedule
1
Construction contract advertised for remaining fender replacement .
0.5
Full replacement is to be completed by April 2012.
0
Budget                               Authorized Forecasted Costs Incurred
Project is within approved budget.
Change Order                         Construction Costs
None
None this quarter
Risks
None this quarter
Budget Transfers
None




SEAPORT

Port of Seattle 3Q 2011 Report  67

THIRD QUARTER REPORT, 2011
T-10 Interim Redevelopment
Status Snapshot Prior Report
Project:   C800264      Redevelop site, complete with new  Delayed Schedule 2Q 11
Budget: $7,205,000      stormwater treatment facilities,    On Budget
Phase: Construction     outfall, yard lighting, security fence,  5 Change Orders
Start: 03/22/08          and paving to support terminal     Total Change Orders Amount:
Completion: 12/31/2011   related activities.           $110,693
Budget/Costs Incurred
Significant Developments
8
Construction is underway with demolition, contaminated soils
6
removal, and majority of storm drain installation complete. EPA staff
has been on site monitoring construction and is pleased with the
Millions  4
work at this superfund site.
Dollars in   2
Schedule                             0
Authorized  Forecasted Costs Incurred
Construction completion is scheduled for end of November 2011 and
construction is on target to meet this milestone.
Construction Costs
Budget
Forecasting all work will be completed within authorized funding.         6
5
Change Order
Millions   4
Five change orders have been executed with a total amount of          3
$110,693.                                         2
Dollars in    1
Risks
0
Significantly more runoff still may occur compared with the amount          Initial  Change  Spent
Orders
specified in the contract documents -- higher stormwater disposal
costs will then be handled through change order.
Photo
Budget Transfers
None


SEAPORT

68  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
T-91 Watermain Replacement
Project:   C800298      Replace water main in the vicinity   Status Snapshot Prior Report
Budget: $4,255,000      of Magnolia Bridge and City      On Schedule
Phase: Construction     Ice/Trident including various     On Budget
Start: 9/20/2009          buildings at T91              0 Change Orders
Completion: 3/30/2012                        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Construction is in progress.
5
Schedule                             4
Schedule extended to Q1 2012 to accommodate construction and     Millions 3
Dollars in 
site operations.                                          2
1
Budget
0
On budget                                       Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Risks                                  4
Contaminated material may be encountered throughout the            3
excavation process.                                   Millions
2
Budget Transfers
Dollars in    1
None
0
Initial   Change   Spent
Orders

Photo


SEAPORT

Port of Seattle 3Q 2011 Report  69

THIRD QUARTER REPORT, 2011
T-91 Roadway Pavement Project
Status Snapshot Prior Report
Project:   C800343                             Delayed Schedule 2Q 11
Budget: $982,000     Repave two main roadway        On Budget
Phase: Construction   intersections and the adjacent areas   0 Change Orders
Start: 12/18/09         west of the east guard shack.        Total Change Orders Amount:
Completion: 5/1/2011                         $0
Budget/Costs Incurred
Significant Developments
0.985
Port Construction Services completed construction in 2nd Quarter.
0.98
Project is being closed out.
0.975
0.97   Millions
Schedule                            0.965
Construction is complete.                                0.96  Dollars in 
0.955
0.95
Budget
Authorized  Forecasted Costs Incurred
Project is on budget.
Change Order                         Construction Costs
Construction was performed by Port Construction Services.
1
Risks                                 0.8
None                                  Millions 0.6
0.4
Budget Transfers
Dollars in   0.2
None
0
Initial   Change   Spent
Orders

Photo



SEAPORT

70  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
T-5 Crane Cable Reels
Status Snapshot Prior Report
Project:   C800349      Purchase Cable Reels for tenant.
Budget: $3,500,000                         Delayed Schedule 4Q 10
Phase: Design                            On Budget
Start: 05/04/10                                   0 Change Orders
Completion: 03/31/11                         Total Change Orders Amount:
0
Significant Developments
Budget/Costs Incurred
The cable reels have been delivered. Delivery of the support
materials has been extended into the first quarter of 2012 due to a
4
material change in the cable requested by the tenant.
3
Schedule                            Millions
2
On scheduled as updated last quarter. Installation is anticipated to
Dollars in   1
be completed in June 2012.
0
Budget                               Authorized Forecasted  Costs
Incurred
None
Change Order                         Construction Costs
Not Applicable
None
Risks                               Photo
Schedule
Budget Transfers
None




SEAPORT
Port of Seattle 3Q 2011 Report  71

THIRD QUARTER REPORT, 2011
T18 Fender Replacement
Project:   C800416      Replacement of 202 timber fender   Status Snapshot
Budget: $5,465,000      piles and their supporting members  On Schedule
Phase: Construction     along the face of the SSA crane    On Budget
Start: 02/07/2010         terminal.                   2 Change Orders
Completion: 03/15/2012                       Total Change Orders Amount:
$16,500
Significant Developments                    Budget/Costs Incurred
First phase of construction is complete. 91 timber fender piles were
7
replaced, and beneficial occupancy obtained for this phase on March     6
31, 2011.
Millions  5
4
Schedule                             3
2
Construction scheduled in two phases to accommodate permit       Dollars in 
1
windows and tenant operations. Resumption of construction of
0
second phase work scheduled to start in December 2011, all work to       Authorized  Forecasted Costs Incurred
be completed by March 2012.
Budget                            Construction Costs
Project is within the approved budget.                       None at this time
Change Order                         Photo
None this quarter
Risks
None this quarter
Budget Transfers
None



SEAPORT

72  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
East Marginal Way Grade Separation
Status Snapshot Prior Report
Project:   E102007      FAST Corridor funded project;     Delayed Schedule 2Q 11
Budget: $50,700,000     FHWA, State, City with Port      On Budget 2Q 11
Phase: Construction     commitment of $18,800,000. Scope  50 Change Orders
Start: 5/2006            is to construct grade separation in   Total Change Orders Amount:
Completion: Q4 2011     vicinity of T5 and T18 to minimize   $640,482
truck traffic/rail conflicts.
Budget/Costs Incurred
51
Significant Developments
50
Bridge opened for southbound traffic on October 21, 2011. Opening     49
for northbound traffic expected in mid-November, 2011.
Millions
48
47
Schedule                            Dollars in 46
Construction is 97% complete and scheduled completion is extended    45
to December 15, 2011 The overall program schedule remains as         Authorized Forecasted Costs Incurred
was reported in 4Q 09.
Budget                            Construction Costs
The overall program budget remains the same as reported in 4Q 09.
On future reports the budget that will be tracked will be the current        25
construction costs. The Budget status snapshot is On Budget          20
reflecting the active construction budget.                        Millions  15
Change Order                           10
Fifty change orders have been executed for a total net amount of      Dollars in   5
$640,482.                                         0
Initial   Change   Spent
Orders
Risks
Construction change orders could occur, which could increase cost
of construction.                                       Photo
Budget Transfers
New source of funds indicates that no budget transfers will be
required.

SEAPORT

Port of Seattle 3Q 2011 Report  73

THIRD QUARTER REPORT, 2011
Viaduct Construction Coordination
Project:   E104324,      Participate in the design &       Status Snapshot
E104535-38          construction of the bored tunnel,   On Schedule 3Q 11
Budget: $366,400       north & south portals, Central     On Budget 3Q 11
Phase: Implementation   Waterfront surface streets, and    0 Change Orders
Start: 1/1/2009          related projects to ensure adequate  Total Change Orders Amount:
connection to port facilities.         $0
Completion: 12/31/2018
Budget/Costs Incurred
Significant Developments
Port completed negotiating lease agreements with the State to allow    0.37
construction staging for bored tunnel to occur on port facilities at       0.365
T-46 and T-106. Port completed separate lease agreement with      0.36  Millions
tunnel contractor for use of T-25S site for concrete crushing
0.355
operation.
0.35
0.345   Dollars in 
Schedule
0.34
Bored tunnel environmental review process ended in August and         Authorized Forecasted Costs Incurred
State issued second Notice to Proceed to allow start of construction.
Stage 2 of Holgate to King Street (H2K) construction is ahead of
schedule. Stage 3 H2K expected to advertise for bids Spring 2012.   Construction Costs
None
Budget
Project is within budget, which was increased from $241,000 to
$366,400.
Change Order
Not applicable
Risks
Impacts due to construction mitigation and maintenance of traffic.
Budget Transfers
None

SEAPORT

74  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Street Vacations T5,18,105
Status Snapshot
On Schedule
Project: Capital &     Street vacation related real estate     On Budget
Expense         negotiations and agreements --T5,    0 Change Orders
104362, 104364, 104366 T18, and T105.               Total Change Orders Amount:
Budget: $1,500,000                         $0
Phase: Permitting
Start: June 2010                                 Budget/Costs Incurred
Completion: 2012
2
1.5
Significant Developments                     Millions
1
Finalized all agreements related to T-105 street vacations and
submitted package to Seattle DOT for their recommendation for City    Dollars in 0.5
Council final approval of street vacations at T-105. Moving along in
0
finalizing real estate agreements at T-18. T-5 negotiations are
Authorized  Forecasted Costs Incurred
pending completion of T-18 negotiations.
Schedule
Construction Costs
On Schedule                                 Not Applicable
Budget                            Photo
On Budget
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable


SEAPORT

Port of Seattle 3Q 2011 Report  75

THIRD QUARTER REPORT, 2011
T-18 Pile Cap Repair Pilot Project
Project:   E104559      T18 Pile Cap Repair Pilot Project    Status Snapshot
Budget: $300,000                          On Schedule 3Q 11
Phase: Planning                          On Budget 3Q 11
Start: 3/25/11                                    0 Change Orders
Completion: 12/31/12                        Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Design and permitting are complete and team is preparing for
Commission authorization of construction phase.                0.35
0.3
Schedule                            0.25 Millions 0.2
Project is on schedule for construction in early 2012.
0.15
0.1
Budget                             Dollars in 
0.05
Costs to date are lower than expected due to efficiencies in design       0
development.                                       Authorized Forecasted Costs Incurred
Change Order
Not applicable at this stage.                               Construction Costs
None
Risks
Risks include preventing deleterious materials from entering water
and managing project costs in order to stay within budget approved.
Budget Transfers
Not applicable at this stage.




SEAPORT

76  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Underdock Inspections
Project:   E104610-12    Underdock Inspections for T-5,     Status Snapshot
Budget: $1,250,000      T-18 and T-46            On Schedule 3Q 11
Phase: Planning                          On Budget 3Q 11
Start: 1/1/2011                                   0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Final report is complete at T-18 and draft final report is being
reviewed for T-46. Diving inspections and testing are underway at      1.4
T5 and T46.                                      1.2
Millions  1
Schedule                             0.8
0.6
Project is so far on schedule to complete dock condition
Dollars in 0.4                                                                               assessments by the end of 2011.
0.2
0
Budget                               Authorized Forecasted Costs Incurred
Budget was increased from $1,000,000 to $1,250,000 and is now on
target to complete within this amount.
Construction Costs
Change Order                         Not Applicable
Not applicable.
Risks
Schedule is now at risk if all work cannot be completed in 2011.
Budget Transfers
Budget is shared between four projects 104341 and 104610-104612.



SEAPORT

Port of Seattle 3Q 2011 Report  77

THIRD QUARTER REPORT, 2011
FT South Wall Reconstruction Phase IV
Project:   C800136      Completion of Fishermen's       Status Snapshot
Budget: $5,535,000      Terminal South Wall         Delayed Schedule
Phase: Construction     Reconstruction. Phase IV is located  On Budget
Start: 6/2009            along parcel currently leased by    8 Change Orders
Completion: 9/2011      FVO.                 Total Change Orders Amount:
$
Significant Developments                    Budget/Costs Incurred
All construction has now been completed and the project is in close-
6
out. PCS completed removal and replacement of apron pavement
5
due to excessive cracking and subsidence caused by compaction
4
grouting performed as part of major works scope.                Millions
3
Schedule                             2
Dollars in   1
Construction was completed by September 2011.
0
Authorized  Forecasted Costs Incurred
Budget
None this quarter
Construction Costs
Change Order
Approximately $300,000 for scope addition of sheet pile tie backs.        5
4
Risks
3
Successful installation of the sheet pile tie backs.
Millions
2
Budget Transfers                          Dollars in   1
None                                    0
Initial   Change   Spent
Orders

Photo


REAL ESTATE

78  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
FT C15 HVAC Improvements
Status Snapshot
Project:   C800137      Provide the preliminary planning,
Budget: $4,000,000      design, and construction for      Delayed Schedule
Phase: Design        replacing the FT C15 HVAC      On Budget
Start: 05/01/10          System.                   0 Change Orders
Completion: 12/31/2012                       Total Change Orders Amount:
0
Significant Developments
Budget/Costs Incurred
Contract for design services executed.
1
Schedule
0.8
Preliminary schematic is design due at the end of September.        Millions 0.6
Construction was originally scheduled for spring 2012 but will be
0.4
delayed until late summer/early fall 2012 because the procurement
of the designer took longer than anticipated.                     Dollars in 0.2
0
Authorized  Forecasted Costs Incurred
Budget
On budget
Construction Costs
Change Order                         Not Applicable
None
Risks
Further delays could cause construction to occur in winter (colder)
months.
Budget Transfers
None


REAL ESTATE


Port of Seattle 3Q 2011 Report  79

THIRD QUARTER REPORT, 2011
MIC Central Seawall Replacement
Status Snapshot
Delayed Schedule
Project:   C800175      Replacement of steel sheet pile
seawall between West Pier and     On Budget
Budget: $2,650,000
Central Pier at Maritime Industrial    4 Change Orders
Phase: Construction
Start: 9/2008            Center.                    Total Change Orders Amount:
$
Completion: 8/2011
Budget/Costs Incurred
Significant Developments
3
All construction has now been completed and the project is in closeout.
PCS completed removal and replacement of apron pavement      Millions 2
due to excessive cracking and subsidence caused by compaction
grouting performed as part of major works scope.                  1
Dollars in 
Schedule                             0
Authorized  Forecasted Costs Incurred
Construction was completed by August 2011.
Budget                            Construction Costs
None
1.8
Change Order                           1.7
1.6
None this quarter
1.5
Millions
1.4
Risks                                Dollars in  1.3
None this quarter                                          InitialChange OrdersSpent
Budget Transfers
None this quarter                                    Photo



REAL ESTATE

80  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
RE Maintenance Shop Solution
Project:   C800187      Marine Maintenance Solution CIP   Status Snapshot
Budget: $2,640,000      facilitates continued operations    On Schedule
Phase: Construction     from the existing shop location by   On Budget
Start: August 2010       funding the following five projects:   1 Change Orders
Completion: May 2012    MM Office Expansion; MM North-   Total Change Orders Amount:
end Office; MM Elec Upgrade; MM   1890
Roof Replacement; and MM
Kitchen Upgrade.             Budget/Costs Incurred
3
Significant Developments
The roof is under construction. Expect construction to be complete       2
by the end of November. Electrical equipment and materials have      Millions
been purchased. Expect final delivery by mid-December. Work has      1
begun.                                       Dollars in 
0
Schedule                               Authorized Forecasted Costs Incurred
The Office Expansion project is complete. The Northend Office is
substantially complete. Roof Replacement is expected to be
complete in November 2011. The Electrical Upgrade will be       Construction Costs
completed in Q1 2012. The Kitchen Upgrade is expected to be      None
complete by the end of Q2 2011.
Budget
Commission authorized a $340,000 increase in the CIP budget for a
total authorization of $2,640,000 on June 14, 2011.
Change Order
One for less that $2000 to install additional flashing.
Risks
Unforeseen existing roof conditions and weather may complicate the
roof replacement.
Budget Transfers
None

REAL ESTATE

Port of Seattle 3Q 2011 Report  81

THIRD QUARTER REPORT, 2011
FT NW Dock East Fender System Replacement
Project:   C800386      Replace existing timber fender     Status Snapshot
Budget: $3,750,000      system for the east section of the   On Schedule
Phase: Construction     NW Dock at Fishermen's Terminal  On Budget
Start: January 2010       including all new steel piling and    2 Change Orders
Completion: May 2011    associated fender system.       Total Change Orders Amount:
$48,757
Significant Developments                    Budget/Costs Incurred
All contractor work is complete and has been accepted. Project is in
4
close-out phase.
3
Schedule                            MillionsDollars in 
2
Project close-out will be completed during first half of 2012.
1
Budget
0
Total project budget is $3,750,000.                              Authorized  Forecasted Costs Incurred
Change Order
Two project change orders.                            Construction Costs
Risks                                 2.6
2.5
None
Millions  2.4
2.3
Budget Transfers
2.2
None
Dollars in   2.1
2
1.9
Initial   Change   Spent
Orders



REAL ESTATE

82  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Flight Information System (FIMS) II
Project: C101117        Procure, develop, and implement a  Status Snapshot
Budget: $5,400,000      FIMS system that includes       On Schedule
Phase:Design         replacement monitors, an airport   On Budget
Start: 5/4/2010           resource management system, and  0 Change Orders
Completion: 12/30/2012    a flexible digital signage system    Total Change Orders Amount:
capable of displaying flight         $0
information, visual paging, and
notifications.
Budget/Costs Incurred
Significant Developments                      6
5
Vendors selected for replacement software. Completed 60% design
4
on casework upgrades. Planning and design in progress.
3
in Millions
Schedule                             2
Dollars   1
On Schedule
0
Authorized  Forecasted   Costs
Budget                                      Incurred
On Budget
Construction Costs
Change Order                         Not Applicable in this phase
None
Risks
Aviation Operations resource availability may impact schedule during
implementation of resource management and flight information
display systems.
Budget Transfers
None


CORPORATE

Port of Seattle 3Q 2011 Report  83

THIRD QUARTER REPORT, 2011
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, and add service desk     0 Change Orders
Completion: 12/30/2012   module and wireless handheld    Total Change Orders Amount:
capabilities.                    $0

Significant Developments                    Budget/Costs Incurred
Major components of the program have been delivered including the
4
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of         3
Marine Maintenance and Aviation Maintenance Maximo systems in
2
September 2010. The smaller components of mobility enhancements   in Millions
and additional interfaces are in progress.                       Dollars  1
Schedule                             0
Authorized Forecasted   Costs
Prior Report - Several of the proposed new interfaces link the                        Incurred
Maximo system to the Peoplesoft Financials Procurement module.
Because of planned changes in the procurement process with the
Construction Costs
Peoplesoft Financials Upgrade project, the delivery of these
Not Applicable
interfaces will be delayed until after the completion of the upgrade
project.
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces and mobility enhancements.
Budget Transfers
None

CORPORATE
84  Port of Seattle 3Q 2011 Report

THIRDD QUARTER RREPORT, 2011
Airrline Acttivity Maanagemeent
Prooject: C8000222       Deevelopmentt of an airlinne activity   Statuss Snapshott
Buddget: $5000,000       maanagement system thaat       On Schedule
Phaase:Planning        inteegrates witth several PPort      On Budget
Start: 6/19/20011          sysstems to reeplace agingg reporting   0 Channge Orderss
Commpletion: 5/1/2013     sysstem and supply data for airline   Total CChange Ordders Amounnt:
acttivity fees.                    $0

Budgett/Costs Inccurred
Significant DDevelopmments
0.6
Reqquirements and designn in progresss.
0.5
Schhedule                            Millions 0.4
0.3
On SSchedule
0.2
Dollars in 
Buddget                             0.1
0
On BBudget
Authorized  F o recasted Costs I ncurred
Chaange Ordder
Nonne
Construuction Cossts
Rissks                               Not Appplicable
No ssignificant rrisks
Buddget Trannsfers
Nonne




CORRPORATEE

Port of Seattle 3Q 2011 Report  85

THIRD QUARTER REPORT, 2011
Ground Transportation Management System
Project: C800227        Procure and implement a Ground   Status Snapshot
Budget: $840,000       Transportation Management      Delayed Schedule     1Q 11
Phase: Close Out       System for tracking and billing     Under Budget
Start: 4/27/2010          ground transportation operators at   0 Change Orders
Completion: 12/15/2011    the airport.               Total Change Orders Amount:
$0
Significant Developments
Software deployed in early November.                     Budget/Costs Incurred
Schedule                             1
Prior Report - The system design phase took longer than anticipated    0.8
due to resource constraints and the resolution of system support       0.6
issues. To accommodate this delay and to best align project phases     Millions
0.4
with business operations, the project deployment has been delayed
Dollars in
6 months to mid-December 2011.                        0.2
0
Budget                               Authorized Forecasted Costs
Incurred
Under Budget - A significant portion of the vendor payments have
not yet been processed but the project is expected to complete
$150,000 under budget.                             Construction Costs
Not Applicable
Change Order
None
Risks
No significant risks
Budget Transfers
None



CORPORATE
86  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Port of Seattle Internet Redesign
Project: C800319        Create a new Internet web site, and  Status Snapshot Prior Report
Budget: $500,000       underlying infrastructure, with     Delayed Schedule     2Q 11
Phase:Implementation    dynamic content and interactive    On Budget
Start: 1/6/2009           communication tools such as blogs,  0 Change Orders
Completion: 12/30/2011    video, podcasts, discussion forums  Total Change Orders Amount:
and interactive maps.           $0
Significant Developments                    Budget/Costs Incurred
New website builds complete. Content migration is in progress.
0.52
Schedule                             0.5
Prior Report - Resource availability to migrate content as well as      0.48 Millions
additional time required to fully test the new site has delayed the
0.46
implementation to 4th Quarter 2011.
0.44  Dollars in 
Prior Report - The delay caused by the need to re-advertise the RFP   0.42
for an implementation vendor will delay the estimated completion to       Authorized Forecasted  Costs
2nd Quarter 2011.                                                 Incurred
Budget                            Construction Costs
On Budget                                  Not Applicable
Change Order
None
Risks
Significant amount work will be required to clean up the website
content from the previous site. Individuals across the Port are
working on this effort but it may require additional time to complete.
Budget Transfers
None


CORPORATE

Port of Seattle 3Q 2011 Report  87

THIRD QUARTER REPORT, 2011
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot
Budget: $1,525,000      costing systems with a common    Delayed Schedule
Phase:Implementation    enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: 9/30/2012                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Installation of the software in the Port environment has been
completed. Final configuration and interface development in           2
progress. Interface development in progress
1.5
Schedule
1
in Millions
Prior Report - Vendor did not deliver software per original contract
0.5
and project was put on-hold to evaluate alternatives. A decision was    Dollars 
made to continue with Skire in July 2010. The estimated completion      0
date at this time is September 2011 although there may be interim         Authorized  Forecasted Costs Incurred
deliveries prior to completion.
Configuration of the software took longer than anticipated due to the   Construction Costs
availability of resources and complexity of the software delaying the   Not Applicable
start of the interface development. The system is scheduled to be
deployed in May 2012 with several critical interfaces in place.
Budget
None
Change Order
None
Risks
See Schedule
Budget Transfers
None

CORPORATE
88  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot Prior Report
Budget: $800,000       increase functionality, and lower   Delayed Schedule    4Q 10
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 4/30/2012    records and document        Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
Sharepoint 2010 Upgrade has been completed. Design and
implementation of Sharepoint 2010 Records Center in progress.
1
Schedule                            0.8
Prior Report: Sharepoint 2010 implementation is dependent on the     0.6 Millions
completion of several infrastructure projects currently in progress      0.4
and requires additional time to complete the upgrade of existing
0.2  Dollars in 
sites. While Sharepoint 2010 will be available to departments
0
beginning in April 2011, the implementation of Sharepoint Records
Authorized Forecasted   Costs
Center will not be complete until December 2011. The full project is                  Incurred
estimated to be completed in April 2012.
Budget                            Construction Costs
Not Applicable
On Budget
Change Order
None
Risks
Scope of Sharepoint 2010 upgrade may require additional funding to
complete migration activities.
Budget Transfers
None

CORPORATE

Port of Seattle 3Q 2011 Report  89

THIRD QUARTER REPORT, 2011
Business Continuity
Project: C800326        Acquire new backup and storage   Status Snapshot Prior Report
Budget: $1,760,000      software and hardware that will    Delayed Schedule     1Q 11
Phase:Close Out       facilitate business continuity in the  On Budget
Start: 6/23/2009          event of a disaster            0 Change Orders
Completion: 10/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Completed installation and data migration to the new High Capacity   Budget/Costs Incurred
Network Storage System and Backup File Share.
1.8
Schedule                            1.75
1.7
Prior Report - A small number of remaining components are
1.65
dependent on the design of another project. This will delay the final
in Millions 1.6
delivery of this project until October 2011.                       1.55  Dollars 
1.5
Prior Report - Insufficient power in the data center required           1.45
unplanned infrastructure upgrades for the new High Capacity            Authorized  Forecasted Costs Incurred
Realtime Storage Device. The new device is estimated to be online
in October 2010 and final project completion is estimated in April
2011, a 6 month delay from the original schedule.               Construction Costs
Not Applicable
Budget
On Budget
Change Order
None
Risks
No significant risks
Budget Transfers
None


CORPORATE

90  Port of Seattle 3Q 2011 Report

THIRDD QUARTER RREPORT, 2011
Proopworkss Upgradde
Prooject: C8000328       Uppgrade the pproperty maanagementt  Statuss Snapshott
Buddget: $4500,000       sysstem, Propwworks, used by      On Schedule
Phaase: Impleementationn    Avviation Propperties and Real Estatee  On Budget
Start: 3/1/2011           orgganizationss.               0 Channge Orderss
Commpletion: 7/30/20122                         Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Aviaation implemmentation inn progress. Real Estatte/Seaport upgrade    Budgett/Costs Inccurred
will ffollow.
0.5
Schhedule                            0.4
On SSchedule                                 0.3
Millions
0.2
Buddget
0.1  Dollars in
On BBudget
0
Authorized Foreca s ted  Costs
Chaange Ordder                                  Incurred
Nonne
Construuction Cossts
Rissks
Not Appplicable
No ssignificant rrisks
Buddget Trannsfers
Nonne




CORPORATTE

Port of Seattle 3Q 2011 Report  91

THIRD QUARTER REPORT, 2011
Time Clock System
Project:C800387        Procure and implement a Time    Status Snapshot
Budget:$840,000       Clock System to accurately capture  On Schedule
Phase:Planning        and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion:7/30/2012     Aviation Security and Airport      Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
System configuration and interface development in progress
0.4
Schedule                            0.3
On Schedule
0.2
in Millions
Budget                             0.1 Dollars 
On Budget
0
Authorized Forecasted  Costs
Change Order                                   Incurred
None
Construction Costs
Risks                               Not Applicable
No significant risks at this time.
Budget Transfers
None




CORPORATE

92  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Peoplesoft Financials Upgrade
Project: C800392        Upgrade of Peoplesoft Financials   Status Snapshot Prior Report
Budget: $5,000,000      hardware and software         Delayed Schedule
Phase:Planning                            On Budget
Start: 9/28/2010                                 0 Change Orders
Completion: 12/31/2013                         Total Change Orders Amount:
$0
Significant Developments
An implementation vendor was selected via a competitive         Budget/Costs Incurred
procurement but we were unsuccessful in negotiating an acceptable
6
contract. Work is in progress to minimize risk to the overall project.
5
4
Schedule
Millions 3
Prior Report - Because of resource constraints during the year-end
2
process, the next optimum window of opportunity for the upgrade      Dollars in 1
begins in mid-2012. This will delay the project one year. In the
0
interim, steps are being taken to minimize risk to the overall project
Authorized Forecasted   Costs
and resolve procurement issues.                                       Incurred
Budget
Construction Costs
On Budget                                  Not Applicable
Change Order
None
Risks
Significant resources will be required across multiple organizations
which may delay other technology projects.
Budget Transfers
None


CORPORATE

Port of Seattle 3Q 2011 Report  93

THIRD QUARTER REPORT, 2011
Police Records Management System
Project: C800393        Procure and implement a       Status Snapshot
Budget: $1,300,000      replacement Police Records      On Schedule
Phase:Planning        Management System         On Budget
Start: 10/10/2010                                0 Change Orders
Completion: 1/31/2012                         Total Change Orders Amount:
$0

Budget/Costs Incurred
Significant Developments
1.4
Negotiating contract with vendor
1.2
1
Schedule                             0.8
On Schedule                                  in Millions 0.6
Dollars 0.4
0.2
Budget
0
On Budget                                      Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable in the phase
Risks
Contract negotiation is taking significantly longer than planned and
may delay completion.
Budget Transfers
None



CORPORATE

94  Port of Seattle 3Q 2011 Report

THIRD QUARTER REPORT, 2011
Upgrade to Windows 7 and Office 2010
Project: C800395        Upgrade Port workstations to     Status Snapshot
Budget: $500,000       Windows 7 and Microsoft Office    On Schedule
Phase: Close Out       2010.                  On Budget
Start: 9/17/2010                                 0 Change Orders
Completion: 9/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Portwide workstation upgrade to Windows 7 and Microsoft Office     Budget/Costs Incurred
2010 complete.
0.6
Schedule                            0.5
On Schedule                                  0.4
0.3
Budget                            0.2
0.1
On Budget
0
Authorized Forecasted  Costs
Change Order                                   Incurred
None
Construction Costs
Risks
Not Applicable
Due to aging, incompatible software still required on some
workstations, not all assets will be updated at the close of the
project. As the application issues are resolved, the associated assets
will be upgraded.
Budget Transfers
None



CORPORATE

Port of Seattle 3Q 2011 Report  95

THIRDD QUARTER RREPORT, 2011
CUUSE Migrration
Prooject: C8000481       Miggrate the AAirport Common-Use   Statuss Snapshott
Buddget: $4855,000       Paassenger Prrocessing SSystem,    On Schedule
Phaase:Planning        CUUSE, from aa virtual to aa physical   Under Budget
Start: 6/19/20011          based infrastrructure           0 Channge Orderss
Commpletion: 2/29/20122                         Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Harddware purcchased and software innstalled in test environnment.     Budgett/Costs Inccurred
Testting in proggress.
0.6
Schhedule                             0.5
On SSchedule                                  0.4
0.3
in Millions
Buddget                             0.2
Dollars 0.1
On BBudget
0
Authorized  F o recasted Costs I ncurred
Chaange Ordder
Nonne
Rissks
Construuction Cossts
No ssignificant rrisks                                      Not Appplicable
Buddget Trannsfers
Nonne




CORPORATTE

96  Port of Seattle 3Q 2011 Report

THIRDD QUARTER RREPORT, 2011
Maaintenance Planning Sooftware
Prooject: C8000501       Proocure and iimplement        Statuss Snapshott
Buddget: $4022,000       Maaintenance Planning aand      On Schedule
Phaase:Planning        Sccheduling sooftware thaat integratess  Under Budget
Start: 6/26/20011          witth our Asseet Managemment       0 Channge Orderss
Commpletion: 5/30/20122    sysstem, Maximo.            Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Vendor has been selectedd via a commpetitive proocess.            Budgett/Costs Inccurred
Schhedule                            0.5
On SSchedule                                  0.4
0.3
Buddget
in Millions0.2
On BBudget                                  Dollars 0.1
Chaange Ordder                          0
A uthorized Fore c asted  Costs
Nonne                                              Incurre d
Rissks
No ssignificant rrisks                                      Construuction Cossts
Not Appplicable
Buddget Trannsfers
Nonne





CORRPORATE

Port of Seattle 3Q 2011 Report  97

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.