6b

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      6b 
Date of Meeting    October 25, 2011 

DATE:    October 14, 2011 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    David Soike, Director, Aviation Facilities and Capital Program 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Vertical Conveyance (Elevator) Modernization Project at Seattle-Tacoma
International Airport (CIP # C800251). 
Amount of This Request: $2,991,850    Source of Funds: Airport Development Fund and
Existing Revenue Bonds 
Total Project Cost: $11,120,000 
ACTION REQUESTED: 
Request Port Commission authorization to (1) prepare full design documents; (2) authorize Port
Construction Services (PCS) to perform Regulated Material Management (RMM) design and 
monitoring; and (3) bid and award a major construction contract for RMM abatement in existing
elevator shafts and related spaces for the Vertical Conveyance (Elevator) Modernization Project,
Aero Phase I Project (CIP# C800251) at Seattle-Tacoma International Airport (Airport) for
$2,991,850. The total project cost is $11,120,000. 
SYNOPSIS: 
The Airport has developed a renewal and replacement program for both the elevators and
escalators throughout the Main Terminal and Satellites. Many of the elevators and escalators are
over 40 years old and are at the end of their service lives. The Vertical Conveyance
Modernization, Aero Phase I project, one of four individual projects in this program, will
incorporate complete elevator modernization upgrades for eight existing traction elevators and
for the addition of hydraulic oil cooling units to eleven existing hydraulic elevators in the Main
Terminal. The design work for this project will be accomplished utilizing a previously
authorized IDIQ contract. The total project cost is $11,120,000 (including $1,346,850 expense).
This request is to complete design of this elevator modernization project and to authorize the first
construction contract to remove regulated materials from all of these elevator shafts. Staff will
return in the spring to request the remaining funds and authorization to advertise and award the
follow-on construction contract for upgrading the elevators. The Port is evaluating whether it
will utilize a project labor agreement (PLA) for the RMM abatement work and/or the follow-on
elevator construction contract.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
October 14, 2011 
Page 2 of 6 
BACKGROUND: 
In 2000/2001 an airport-wide elevator modernization program was planned as part of the Airport
Modernization Program. However, the events of September 11, 2001, forced the Airport to
significantly scale back those plans. Of the 79 escalators and 80 elevators in the Airport 
terminal, only 12 elevators and six escalators have been modernized. Since 2001, additional
elevators and escalators have been identified for modernization or upgrades due to the increased
time in service. Currently the Terminal Escalator Modernization project ($55,000,000
authorized February 1, 2011) is modernizing 42 existing escalators throughout the Main
Terminal and South Satellite and installing two new escalators in the South Satellite. This
project (Aero Phase 1- $11,120,000) will modernize eight elevators and overhaul the hydraulics
of 11 existing elevators, which were all identified as the most critical to upgrade quickly. The
follow-on projects for next year (Aero Phase 2 - $17,227,000 and Non-Aero Phase 1 - 
$9,806,000) will modernize an additional 15 elevators and 12 escalators. After all of the above
projects are completed, 19 escalators and 34 elevators will remain at the terminal that have not
been upgraded; however, they are all less than 20 years old and have expected service lives of
five years or more remaining. The two follow-on projects for next year may be modified to
install new elevators or escalators for the South Satellite Federal Inspection Services mid-term
improvements and changes proposed by Alaska Air Group for the C Concourse, both of which
are now under study. 
The elevators included in this project were installed in 1970 and 1971. Due to their age and
technology, the controls, drives and door actuators of these elevators have become uneconomical
to maintain. In addition, the replaced systems, i.e., new motors and controls, would be more
efficient and meet current energy codes, resulting in energy savings. 
Elevator #               Location                   Action 
SSAF          South Satellite  Freight           Modernize 
SSB          South Satellite  Passenger           Modernize 
SSC          South Satellite  Passenger           Modernize 
MT-2        Main Terminal  South/Center          Modernize 
MT-6        Main Terminal  North/Central         Modernize 
MT-7          Main Terminal  North           Modernize 
C-4        Main Terminal  End of Concourse C         Modernize 
NSCF         North Satellite  Freight           Modernize 
C-2             Concourse C, Gate C-2           Hydraulic Cooling 
B        Main Terminal, between Ckpts #1 & #2      Hydraulic Cooling 
J, K, L        Main Terminal  International Carriers       Hydraulic Cooling 
MT-20, MT-30,     Main Terminal  Glass Elevators       Hydraulic Cooling 
MT-40, MT-50 
D1         Concourse D Alaska Board Room       Hydraulic Cooling 
MT-9       Main Terminal, North STS Station      Hydraulic Cooling

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
October 14, 2011 
Page 3 of 6 
PROJECT DESCRIPTION/SCOPE OF WORK: 
Project Statement: 
This project will provide complete modernization of the eight elevators listed above. The 
comprehensive Port of Seattle elevator modernization program includes the following objectives: 
Improve overall system reliability and performance by providing efficient microprocessor
logic for elevator dispatch and individual motor control. 
Replace aged components to ensure 20+ years of reliable service without the need for
additional investments besides normal maintenance costs. 
Provide Firefighters' operation to comply with current life safety code requirements. 
Upgrade existing car and hoist way door equipment to provide safe and reliable
operation. 
Upgrade elevator car and corridor pushbuttons and signal fixtures to comply with current
requirements of the Americans with Disabilities Act (ADA). 
No "worn" parts will be retained. All installed equipment will be replaced with new
items. 
Upgrade existing building conditions to comply with current National, State and City
elevator safety codes and building code requirements. 
Remove regulated materials (Asbestos Fireproofing) to eliminate the cost and litigation
risk of ongoing hazardous material containment and clean-up protocol requirements in
the elevator shafts. 
Work with building officials to accommodate code-required upgrades to structural
seismic and shaft wall fire rating performance criteria. 
Provide components that reduce overall energy consumption. 
Connect to the existing Port elevator/escalator monitoring system, LiftNet, for quick
response in case of failure. 
Project Objectives: 
1.  Improve reliability of elevators to handle current and future passenger loads. 
2.  Provide a safe and reliable delivery route for concessionaires at both South and North
Satellites. 
3.  Improve passenger travel at South Satellite and Main Terminal by installing new ADA-
compliant fixtures and signage. 
4.  Improve International arrivals passenger travel at South Satellite within the FIS area for
those passengers unable to use the existing escalators or stairs. 
Scope of Work: 
Develop infrastructure to modernize eight existing elevators and retrofit hydraulic oil cooling
systems for 11 existing hydraulic elevators. Infrastructure development will, at a minimum,
include: 
1.  Site preparation for installation of elevators and oil cooling systems. 
2.  Removal of regulated materials as required. 
3.  Installation of electrical power and control systems. 
4.  Installation of communication system.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
October 14, 2011 
Page 4 of 6 
5.  Installation of elevator and oil cooling equipment. 
6.  Installation and revisions to fire sprinkler systems. 
7.  Structural, electrical and mechanical revisions to the base building. 
8.  Commissioning of elevator systems. 
9.  Testing of installed elevator systems. 
10. Closeout of completed project. 
STRATEGIC OBJECTIVES: 
Ensure Airport and Seaport Vitality 
The project provides enhanced capacity and flexibility in critical terminal infrastructure, both for
airline customers and for the Airport's concessionaire customers at both the South and North
Satellites. This project supports the Airport strategy that provides world-class facilities that
anticipate and provide for the needs of travelers and customers. 
Exhibit Environmental Stewardship through Our Actions 
This project is in alignment with the Port's goal of improving the long-term sustainability of its
facilities and operations. This project has a generally positive effect on the environment to the
extent that modernized elevators will reduce Airport reliance on less energy efficient vertical
conveyance alternatives and will allow more efficient movement of passengers and retail
product. Passengers and tenants will benefit from faster, more reliable elevators. 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary           Capital      Expense     Total 
Original Budget                         $10,160,000   $ 960,000  $11,120,000 
Budget increase (decrease)                  -$ 386,850   $ 386,850  $ 0 
Revised Budget                        $ 9,773,150   $1,346,850  $11,120,000 
Previous Authorizations                    $ 0 
Current request for authorization               $ 1,645,000   $1,346,850  $ 2,991,850 
Total Authorizations, including this request        $ 1,645,000   $1,346,850  $ 2,991,850 
Remaining budget to be authorized             $ 8,128,150   $ 0  $ 8,128,150 

Project Cost Breakdown  RMM Expense    This Request   Total Project 
Construction costs (RMM)                  $1,230,000    $1,230,000 
Sales tax (RMM)                      $ 116,850    $ 116,850 
Total                                   $1,346,850    $1,346,850

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
October 14, 2011 
Page 5 of 6 
Project Cost Breakdown - Capital          This Request   Total Project 
Construction costs                        $ 0   $ 6,350,000 
Sales tax                                 $ 0    $ 603,250 
Outside professional services                  $1,045,000   $ 1,045,000 
Aviation PMG and other soft costs              $ 600,000   $ 1,774,900 
Total                                   $1,645,000   $ 9,773,150 
Totals: Capital and Expense                 $2,991,850   $11,120,000 
Source of Funds 
This project (CIP # C800251) was included in the 2011-15 capital budget and plan of finance as
a business plan prospective project. The funding source will be existing revenue bonds. 
Expense funds (Airport Development Fund) will be used for the RMM abatement major
construction contract, and supporting/monitoring work to be performed by Port Construction
Services. 
Financial Analysis 
CIP Category 
Renewal/Enhancement 
Project Type              Infrastructure Upgrade 
Risk adjusted Discount rate     N/A 
Key risk factors             N/A 
Project cost for analysis        $9,773,150 
Business Unit (BU)          Terminal Cost Center 
Effect on business performance  NOI after depreciation will increase 
IRR/NPV             N/A 
CPE Impact             Will increase CPE by $.04 by 2014. However, no
change to business plan forecast since this project
was included. The expense costs will cause CPE to
increase on a one-time basis by $.08 spread over two
years (approximately $.04 in 2012 and 2013) 
There are no anticipated increases in annual elevator O&M costs associated with this project.
ECONOMIC IMPACTS: 
The Port will spend less maintenance funds on emergency and/or urgent repairs to existing
vertical conveyance equipment. 
ENVIRONMENTAL SUSTAINABILITY/COMMUNITY BENEFITS: 
There are significant benefits with reductions in handling of concessionaire's retail product on
the ramp, as they will be able to use freight elevators, in lieu of service elevators or freight
elevators that are not co-located where their retail product is stored. Reduced ramp vehicular
traffic will result in lower fuel consumption and therefore less carbon air emissions.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
October 14, 2011 
Page 6 of 6 
TRIPLE BOTTOM LINE SUMMARY: 
This project will provide tangible improvements to the Airport's vertical circulation capability. 
Passengers will be able to depend on reliable vertical circulation means to safely and quickly
move between floors in the South Satellite, Concourse C and Main Terminal. In addition, the
modernized freight elevators will allow goods to be reliably delivered to the concession storage
areas, and safely and efficiently retrieved by concession tenants when needed. Reduced freight
and service use of passenger elevators in the North and South Satellite will also enhance
passenger travel experiences. 
PROJECT SCHEDULE: 
(For the Capital Funded Major Construction Contract) 
Commission Authorization to Start Design           October 2011 
Start Design                            November 2011 
Design Complete                        June 2012 
Commission Authorization to Bid and Increase Budget    June 2012 
Bid Advertisement                       July 2012 
Commission Authorization to Award              August 2012 
Construction Start                         October 2012 
Construction Complete                     December 2013 
(For the Expense funded RMM Major Construction Contract) 
Commission Authorization to Bid and Increase Budget    October 2011 
Design Start                            October 2011 
Design Complete                        November 2011 
Bid Advertisement                       November 2011 
Commission Authorization to Award (if necessary)     December 2011 
Construction Start                         January 2012 
Construction Complete                     August 2013 
ALTERNATIVES CONSIDERED/RECOMMENDED ACTION: 
Alternative 1: The age and their obsolete technology require these elevators to be modernized to
current standards. This is the recommended alternative.
Alternative 2: The "Do Nothing" alternative results in continued customer service disruptions
and increased maintenance costs. Many parts are no longer available and have to be custom
manufactured, where possible. At some point in time, even custom fabricated replacement parts
will not be available, and the elevators will be modernized using maintenance funds, all at a
greater cost than proceeding with a designed and competitively bid modernization project. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
None. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
Map  Key Plan, Vertical Conveyance Modernization, Aero Phase 1

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.