Item No.      Se

Date of Meeting  September 27, 2011
MEMORANDUM

'
DATE:      September 12, 2011

TO:        Tay Yoshitani, Chief Executive Officer

FROM:     Ralph Graves, Managing Director, Capital Development Division (15528

Ref:         Port of Seattle Resolution 3628, Para. 4.2.3.7

SUBJECT:    DECLARATION OF CRITICAL WORK SITUATION

This memorandum serves as formal notification that in accordance with Resolution 3628, Section
4.2.3.7, a Critical Work situation was declared on September 12, 2011 to facilitate the Terminal 86 Grain
Facility Modernization Phase-2 Project. This declaration requests additional funding authorization to
support the increased cost of labor, materials and equipment to complete the work.

Proiect Background Information:

The Phase 2 Modernization Project consists of two parts:

0  Equipment Upgrades on Towers 2, 3, & 5. American Construction is performing this work under
Major Construction Contract MC-0316888.
0  Structural Strengthening of Towers 2, 3 & 5. This is self-performed labor provided by Port
Construction Services (PCS).

Both portions of work were originally intended to be completed within a planned Terminal 86 Facility
shut-down scheduled to begin on August 20, 2011 and continue through September 20, 2011. The
project authorization on May 3, 2011 for Terminal 86 Facility Modernization brought the total project
authorization to $2,900,000. Significant changes since the authorization include:
1)  City of Seattle Department of Planning and Development (DPD) permit process took longer
than anticipated,
2)  DPD permit conditions resulted in a significant amount of additional structural steel
materials and associated labor,
3)  Only one bidder responded to an advertisement for installation of tower scaffolding, the
lone bid was higher than the anticipated bid amount,
4) The recent International Longshore and Warehouse Union (lLWU) labor issue delayed work
resulting in a work acceleration to recover schedule.
Situational Information:

After review of 60% design documents it was determined that in order to complete the work on
schedule, the structural strengthening phase would need to begin earlier than the shutdown period
scheduled for August 20 thru September 20. In support of this effort, arrangements were made with
the tenant (Louis Dreyfus Corporation) to allow PCS crews to begin work in May of 2011. Because of
strict safety regulations imposed while loading grain ships, the tenant placed a condition that all hot
work (welding, grinding, and burning) be done only during facility shift changes, limiting the actual work
on each tower to 2-3 hours per day. Work progressed on schedule through the months of May, June,
and July, as crews worked around the scheduling limitations.

In early August the tenant informed PCS that because of delayed grain deliveries several longer windows
of working opportunity would be available. Accordingly, PCS increased their work force earlier than
expected and also extended the work shifts to include daily and weekend overtime to guarantee
completion.

The revised and increased weekly wage expenditure, if carried through the end of the shutdown period,
would exceed the PCS authorization. On or about September 1St the project delivery team (Seaport
Project Management (SPM), Construction Management (CM), & PCS) discussed the project needs and
considered the additional requirements (Materials, Scaffolding, Labor and Change Orders). ln-depth
reviews were conducted the subsequent week. Staff determined that the overall project budget was
insufficient to complete on time and within scope.

Conclusion:

Staff recommends continuing to use PCS resources to complete the Tower Structural Strengthening, and
to continue with the Major Works Equipment Upgrades including change orders to the original scope of
work. Completion for the Small and Major works portions of the work will remain on schedule for
September 20th 2011.

Staff is confident that with the approval of requested $180,000 additional project funding, the Phase 2
Modernization Project can be completed successfully and delivered to the tenant by September 20,
2011.

Respectfully, Port Staff recommends an additional request of $180,000 to accommodate all known
project concerns.
.1
1/1/5")7"
REQUESTED:      "m 

'
DECLARED:

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.