5b

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5b 
Date of Meeting   September 12, 2011 
DATE:    September 2, 2011 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Peter Garlock, Chief Information Officer 
SUBJECT:  Century Link Optical Ethernet Connectivity Master Contract 
FOUR YEAR AMOUNT: $990,000    SOURCE OF FUNDS: ICT Expense
Budget 
Amount of This Request: $0 
ACTION REQUESTED: 
Request authorization for the Chief Executive Officer to execute appropriate contract
documents with Century Link (previously Qwest) to continue Qwest Metropolitan 
Optical Ethernet (QMOE) services until December 31, 2015, at a cost not to exceed 
$990,000. 
SYNOPSIS: 
Qwest/Century Link Metropolitan Optical Ethernet (QMOE) provides the wide area
network connectivity for the Port of Seattle locations. 
BACKGROUND: 
QMOE provides the Port's wide area network. It connects all port locations to our
primary and secondary data centers in order to provide IT services, including application
access, file and printing services, voice connectivity, internet access, and other
miscellaneous IT functions. Qwest (recently purchased by Century Link) utilizes fiber
optic cables for the connections. 
The Port first deployed QMOE in 2006. At the time Qwest was the only provider
capable of meeting the Port's needs at an acceptable cost. The original five-year contract
expired in early 2011. We have recently completed negotiations with Qwest/Century
Link that will allow us to consolidate agreements, increase bandwidth and reduce costs
by approximately 20% compared to our original Qwest agreement. 
The new Port agreement with Qwest/Century Link will be established through
Washington State's Department of Information Services (DIS) contract with Century

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
September 2, 2011 
Page 2 of 2 
Link/Qwest. DIS conducts competitive procurements and enters into contracts with
multiple agencies enabling them to secure lower prices than available to individual state 
agencies or local governments. 
SOURCE OF FUNDS: 
Payments to Century Link for 2011 are already included in the Information and
Communications Technology (ICT) expense budget. Payments for future years will be
included in future ICT annual expense budgets. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
None.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.