7c Report

Item Number: 7c_Report
Meeting Date: Sep. 12, 2011


Commission Staff Brieng
Capital Improvement Projects
Second Quarter Report 2011

This page intentionally left blank









ii  Port of Seattle 2Q 2011 Report

Port of Seattle
Capital Improvement Project Report
Second Quarter 2011
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the statue of the Port's capital projects.
Background
During 2010 the Port plans to invest over $378,000,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 2Q 2011 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ...............................................7-8 .......... ...............
C102030 ...............Stormwater Management Program .......................9 ...........
C102163................Main Terminal Baggage Screening ...................10-11 ........ ...................................
C102334 ...............Water System Isolation Valve Upgrade ................12 ..........
C102573 ...............Airf eld Pavement Replacement ...........................13 ..........
C800019 ...............Loading Bridge Utilities .........................................14 .......... ...............
C800034 ...............North Expressway Relocation ..............................15 .......... ...............
C800061 ...............Main Terminal South Low Voltage ........................16 .......... ...............
C800071 ...............Consolidated Warehouse .....................................17 ..........  ...............
C800105 ...............Airport Owned Gate Infrastructure .......................18 ..........
C800107 ...............C4 UPS System Improvements ............................19 .......... ...............
C800109 ...............Garage Escalator & "A" Elevator Upgrade ...........20 .......... ...............
C800112................Runway 16C/34C Panel/Joint Sealant .................21 ..........
C800144 ...............Security CCTV System Improvements.................22 .......... ...............
C800147 ...............Concessions Unit Readiness Program ................23 .......... ...............
C800148 ...............GML Arrivals Hall Concessions ...........................24 .......... ...............
C800167 ...............Runway 16L/34R Reconstruction.........................25 .......... .................................. .......................................... 
C800170 ...............Connect C1 BHS to C88 BHS ..............................26 ........................................ ...................................... 
C800174................FIS - New Primary Inspection Booths ..................27 ........................................
C800203 ...............Common Use Lounge Remodel ...........................28 ..........
C800237 ...............Terminal Escalators Modernization ......................29 .......... ...............
C800238 ...............Central Plant Pre-Conditioned Air ........................30 .......... ..................................................... 
C800253 ...............Parking System Replacement ..............................31 ........................................ 
C800254 ...............Aircraft RON Parking Post Off ce Site..................32 ........................................ 
C800274 ...............8th Floor Weather Proof ng ..................................33 .......... 
C800276 ...............Common Use Equipment Expansion (CUSE) ......34 ..........
C800331 ...............Communication Cable Add To MT, D, CTE ..........35 ..........
C800334 ...............Two new CTE Freight Elevators ...........................36 ..........
C800335 ...............EGSE Electrical Charging Stations ...................37-38........
C800336 ...............South Satelite Delta Sky Club Extension .............39 ........................................ 
C800360 ...............Roof Replacement Program .................................40 ..........
C800374 ...............Claim Device 14 and Lower Inland .......................41 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ...............................42 ..........
C800406 ...............RW 16C/34C Reconstruction Design ...................43 ..........



2  Port of Seattle 2Q 2011 Report

C800412 ...............South Satellite Concessions Project ....................44 ..........
C800420 ...............Additional Air f eld Mitigations at Tyee ..................45 ..........
C800426 ...............FIS Improvement - Phase I ...................................46 ..........
C800455 ...............Concourse D Common Use Environment ............47 ........................................
C800457 ...............EGSE Rolling Stock ..............................................48 ..........
C800466 ...............South Satellite - Additional Gate Lobby ................49 ..........
C800467 ...............PLB Replacement .................................................50 .......... 
C800469 ...............Water System Isolation Valve - Airf eld ................51 ..........
C800471 ...............Security Checkpoint Optimization ........................52 ..........
C800472 ...............Exterior Gate Improvements ................................53 ..........
C800474 ...............Airport Signage .....................................................54 .......... 
Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................55 .......... ...............
C200015 ...............3rd Runway Residential Acquisition .....................56 ......................... ...................................... 
C200042 ...............Highline Community College Noise Insulation .....57 .......... ...............
C200048 ...............Home Insulation Retrof t .......................................58 ..........  ...............
C200093 ...............Single Family Home Sound Insulation .................59 ..........
C800046 ...............Street Vacations  Des Moines Creek 1 ..............60 ........................................
C800146 ...............RMU/Kiosk Concession Program ........................61 ........................................ 
C800150 ...............Burien Commercial Property Acquisition .............62 .......... ...............
C800154 ...............Tenant Reimbursement ........................................63 .......... 
C800354 ...............Paint Stripper Equipment ......................................64 ........................................ 
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C102451 ................T-115 Dock Reconstruction...................................65 .......... ............... ....................
C800114................P-66 Bag. Corridor & Pass. Screening ................66 .......... ...............
C800121 ...............T-18 S. Fendering .................................................67 ..........
C800133 ..............T-86 Grain Facility Modernization (Phase I) ........68 ..........
C800165 ..............Seaport Security Grant Round 7 .........................69 ..........
C800182 ...............NH Island Mooring Dolphins (4) ...........................70 ..........
C800183 ...............P91 Fender System Upgrade ...............................71 ..........



Port of Seattle 2Q 2011 Report  3

C800264 ...............T-10 Interim Redevelopment.................................72 .......... ...............
C800298 ...............T-91 Watermain Replacement ..............................73 ..........
C800343 ...............T-91 Roadway Pavement .....................................74 ........................................ 
C800349 ...............T-5 Crane Cable Reels .........................................75 ..........
C800416 ...............T-18 Fender Replacement ....................................76 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................77 ..........
E104324 ................Viaduct Construction Coordination ......................78 ..........
E104362 et al ........Street Vacations T-5/18/105 .................................79 ..........
E104559................T-18 Pile Cap Repair Pilot Project ........................80 ..........
E104610 ................Underdock Inspections .........................................81 .......... 
Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800070 ...............T-102 HVAC Renewal/Replacement ....................82 .......... ...............
C800136 ...............FT South Wall Reconstruction Phase VI ..............83 ..........
C800137 ...............FT C15 HVAC Improvements ...............................84 ..........
C800175 ...............MIC Central SeaWall Replacement ......................85 ..........
C800187 ...............RE Maintenance Shop Solutions..........................86 ..........
C800386 ...............FT NW Dock E. Fender System Replacement.....87 ..........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ....................88 ..........
C800003...............Maximo Enterprise Implementation......................89 .......... ...............
C800222 ...............Airline Activity Management .................................90 ..........
C800227 ...............Ground Transportation Management System ......91 ........................................ 
C800319...............Port of Seattle Internet Redesign.........................92 ........................................
C800321 ...............Enterprise Project Cost Management ..................93 .......... ...............
C800322 ...............Records and Document Management .................94 ........................................ 
C800326 ...............Business Continuity ..............................................95 .......... .............................. 
C800328 ...............Propworks Upgrade ..............................................96 .......... 
C800387 ...............Time Clock System ...............................................97 ..........
C800392 ...............PeopleSoft Financial Upgrade ..............................98 ........................................


4  Port of Seattle 2Q 2011 Report

C800393 ...............Police Records Management System ..................99 ..........
C800395 ...............Upgrade to Windows 7 & Off ce 2010..................100 ......... 
C800397 ...............Port Contractor Roster and Bid Management .....101 .........
C800481 ...............CUSE Migration ...................................................102 ......... 
C800501 ...............Maintenance Planning System ............................103 .........

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
Previously Reported
No Diamond  On Budget or On Schedule












Port of Seattle 2Q 2011 Report  5

SSECOND QUUARTER REPPORT, 2011
3rdd Runwaay Progrram
Status Snapshot
On Schedule
Prooject: C0000683,       Thee 3rd Runwway Programm
On Buddget
C0001138, C0001175,      connstructed a new 8,5000 foot long
3 Changge Orders
C0001331, C0001751,      runnway, conneecting taxiwways, and
Total Change Ordeers Amount:
C0001760, C1000172      relaated infrasttructure.
$190,0000.00
Buddget: $932,408,802
Phaase: Consstruction                       Budgett/Costs Inccurred
Start: 05/27/1997
1200
Commpletion: 12/31/20111
1000
Millions800
Significant DDevelopmments                    600
400
The 2010 consstruction contract workk is complette except foor the in-     Dollars in 
200
streaam work that will be coompleted inn 2011. The remainingg tasks on
0
this project incllude: contrract in-streaam work, Allaska Mainttenance
Au thorized  Forecas t ed Costs Incurred
Buildding demolition, minorr in-stream work to adddress tempporal
impaacts, and PPond M moddifications.
Schhedule                           2010 Coontract Connst. Costs
Bidss were openned on April 12, 2011 for the Ponnd M Modifications. .
1
Notice to proceeed was givven to Northhwest Consstruction forr Pond M
Moddifications oon June 3, 22011. In the thirt quarrter of 2011, Alaska      0.8
Mainntenance BBuilding demmolition prooject will reqquest the auuthority to    Millions 0.6
adveertise for coonstruction from the Port Commisssion. Connstruction      0.4
is noow scheduled to start in the fourth quarter of 2011.              Dollars in  0.2
0
Buddget
InitialChange Orde r sSpent
The project foreecast is witthin the appproved budgget and autthorization.
Chaange Ordder
Photo
Nonne this quarter
Rissks
Nonne
Buddget Trannsfers
Nonne this quarter

AIRRPORT
6  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Rental Car Facility
Status Snapshot Prior Report
Delayed Schedule 4Q 08
Project:   C100266,     The program will construct a       On Budget
C102167, C800032     consolidated rental car facility (RCF)  928 Change Orders
Budget: $419,306,000   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $10,038,778
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.          Budget/Costs Incurred
Significant Developments                     500
400
RCF construction is nearly 93 percent complete. Permanent power is
estimated to be in August, after which commissioning starts.          Millions300
Completing interior finishes in the Customer Service Building and on     200
each floor plate. Completing work in all four quick turnaround areas.     Dollars in 100
Averaging around 135 workers daily. Site work is nearing completion
0
and landscaping has begun. Little progress made on Contractor and       Authorized Forecasted Costs Incurred
sub claims. BMF and wash buildings taking shape with installation of
tilt-up panels and roof. Backfilling site and CNG underground utilities
with contractor meeting schedule milestones. ORI construction      Construction Costs
continues on the bridge demolition for widening and seismic upgrade
column wraps. Revisions to Host Rd and the Airport ground
300
transportation lots complete. Final paving to occur in August. Main
250
Terminal Improvements awarded contract to Skanska. Gillig is
Millions  200
currently manufacturing the first bus.
150
100
Schedule                             Dollars in  50
The revised program schedule remains on-track for spring 2012
0
completion. RCF scheduled completion is November 2011. Tenant
InitialChange OrdersSpent
work to be completed early 2012. BMF scheduled completion is
March 2012. ORI scheduled completion is December 2011 (except
for signage activation). MTI will start construction early September    Photo
with completion early 2012. Bus delivery planned for 4Q 2011.
Budget
Customer Facility Charge revenues continue to increase slightly
each month, trending over $1,000,000 above projections. The
program forecast is within the approved budget and authorization. 
Change Order
172 change orders were issued this quarter in the amount of
$1,482,257.
Port of Seattle 2Q 2011 Report  7

Risks
For RCF: impacts to schedule due to changes and contractor performance, claims submitted by
prime contractor and one subcontractor; quality issues; and site congestion.
For ORI: unforeseen conditions; coordination with RCF contractor and site congestion.
For BMF: multiple subcontractor congestion within building space; utility connections; and completion
of aggressive construction schedule to support spring 2012 opening.
Budget Transfers
Several this quarter transferring budget from Unallocated Program Contingency to ORI construction
contingency and RCF construction management.
Cost Growth of Construction
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - Cumulative change order percentage through this quarter is 21.4%. Primary
reasons for these changes are unknown conditions and contaminated materials.
Bus Maintenance Facility - Cumulative change order percentage through this quarter is <0.3%.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative change order percentage through
this quarter is 19.4%. Primary reason for changes is the removal of contaminated soils and
associated impacts. This work and the final contract reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  Cumulative change order percentage
through this quarter is 170.5%. Primary reasons for changes are for additional contractor
management, estimating, scheduling and bidding effort for cost estimate reconciliation,
constructability reviews and value engineering beyond the extent of the original scope to validate
project costs and support the rental car companies and the Port on final approval of the project. This
work and the final contract reconciliation is complete.


AIRPORT

8  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Stormwater Management Program
Project:   C102030,    The program achieves permit       Status Snapshot
C800026, C800030     requirements and makes the Airport a  On Schedule
Budget: $50,347,234   leader in stormwater management by  On Budget
Phase: Construction   construction of flow control, water    0 Change Orders
Start: 06/11/2002       quality treatment and low stream flow   Total Change Orders Amount:
mitigation facilities.                  $0
Completion: 12/31/2011
Budget/Costs Incurred
Significant Developments
The stormwater program (C102030) is in its adaptive management     100
phase under which additional or upgraded water quality treatment
80
facilities are being implemented based on the stricter effluent         Millions 60
standards of the new stormwater National Pollutant Discharge
Dollars in 
Elimination System (NPDES) permit. Contractor work has been       40
completed to beneficial occupancy on stormwwater quality treatment    20
upgrades at four project sites.
0
Authorized  Forecasted Costs Incurred
Schedule
The new stormwater NPDES permit became effective April 1, 2009.
Current adaptive management projects will be completed during     Construction Costs
2011, and possibly additional projects through 2014 depending on
water quality monitoring results. The stormwater (C800026) and       1.2
sanitary sewer (C800030) pipeliner projects, which are not part of       1
adaptive management, have been deferred until the second half of     Millions 0.8
2011, or later.                                            0.6
0.4
Budget                             Dollars in 0.2
The project forecast is within the approved budget and authorization.     0
Initial    Change Orders    Spent
Change Order
None
Risks
Additional adaptive management facilities or upgrades may be
required beyond those currently being planned, depending upon
future water quality monitoring results.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 2Q 2011 Report  9

SECOND QUARTER REPORT, 2011
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $223,533,540   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget   4Q 09
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
Significant Developments
235
The C-1 baggage handling/screening system has been placed into     230
revenue service for the Alaska Air Group. The C-1 Lid Replacement    Millions 225
is the only work remaining on this project.
220
215
Schedule                            Dollars in 
210
The project was delayed approximately two years from the original
Authorized  Forecasted Costs Incurred
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope
changes. Turner Construction demobilized on May 31, 2009. The
Construction Costs
GCCM construction contract with Turner Construction has been
closed. The remaining fire sprinkler and fire proofing work was
200
completed.
150
Budget                             Millions 100
The project forecast is within the approved budget and authorization.
50
Dollars in 
Change Order                           0
Initial  Change Orders  Spent
665 Change Orders have been issued on this project.
Risks                               Photo
None
Budget Transfers
None this quarter



10  Port of Seattle 2Q 2011 Report

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated as they were unable to meet the
project schedule requirements. The remaining work was rebid in the fall of 2006. Alaska Airlines
asked that we include the BHS work within the 2-step ticket counter project; which increased the
amount of BHS work in the bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.












AIRPORT

Port of Seattle 2Q 2011 Report  11

SECOND QUARTER REPORT, 2011
Water System Isolation Valve Upgrade
Status Snapshot
On Schedule
Project:   C102334      This project replaces isolation     On Budget
Budget: $704,000       valves on the aging water       0 Change Orders
Phase: Design        distribution system, necessary for   Total Change Orders Amount:
Start: 10/01/2010         isolating portions of the system in    $0
Completion: 12/31/2011   the event of breaks, leaks, or tieins.
Budget/Costs Incurred
0.8
Significant Developments
0.6
The project is currently in design. Port Construction Services has      Millions
pre-ordered the valves and associated fittings.                   0.4
Schedule
Dollars in 0.2
0
The project is currently on schedule.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time
Budget Transfers
None this quarter



AIRPORT

12  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Airfield Pavement Replacement
Project:   C102573      The project is intended to be a     Status Snapshot
Budget: $30,800,000     multi-year pavement replacement   On Schedule
Phase: Construction     program to replace some of the    On Budget
Start: 05/02/2010         worst pavement and joint seal on    0 Change Orders
Completion: 12/31/2016   the airfield.              Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Bids were opened on April 14, 2011. Gary Merlino Construction was
35
the selected bidder.
30
25
Schedule                            Millions 20
The contractor is scheduled to begin work on June 13, 2011. The      15
construction work in 2011 will be the initial phase of a multi-year       Dollars in  10
pavement replacement program scheduled from 2011 to 2015.        5
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget.
Construction Costs
Change Order
None                                    5
4
Risks
3
Any delay will put project out of typical construction window.
Millions
2
Budget Transfers                          Dollars in   1
None this quarter                                        0
Initial   Change   Spent
Orders

Photo

AIRPORT

Port of Seattle 2Q 2011 Report  13

SECOND QUARTER REPORT, 2011
Loading Bridge Utilities
Project:   C800019   This project will upgrade all Port-       Status Snapshot Prior Report
Budget: $12,883,000  owned loading bridges to the same     Delayed Schedule    2Q 09
Phase: Design     standards, including 400Hz power and   On Budget
potable water. It will reduce air
Start: 06/28/2007                                 0 Change Orders
emissions, improve energy efficiency
Completion:                              Total Change Orders Amount:
and save money for the airlines.        $0
12/31/2013
Budget/Costs Incurred
Significant Developments                     14
The scope of this project has been increased to include two          12
additional gates (B-1 and B-5), and to increase the number of 400 Hz   Millions 10
8
generators from two to three at the South Satellite to service 787s in
6
the future. The project will be redesigned to include the new scope.
Dollars in   4
2
Schedule
0
The schedule has been delayed due to the new scope additions.         Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
None
Risks
Airport Operations at certain gates could be impacted during the
construction phase of the project. The Ports power centers might
need to upgraded to support the Pre-Conditioned Air, Electrical
Ground Support Equipment, and Loading Bridge Utilities projects.
Budget Transfers
From C102166 (Aeronautical Renewal/Replacement) $3,498,000

AIRPORT


14  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
North Expressway Relocation
Project:   C800034
The project is a collaboration       Status Snapshot
Budget: $110,347,700    between the Port and Sound     Delayed Schedule
Phase: Construction     Transit. It reconstructs the North   On Budget
Start: 07/27/2004         Airport Expressway and brought    210 Change Orders
Completion: 07/31/2012   light rail to the Airport.         Total Change Orders Amount:
$8,111,265
Significant Developments
Budget/Costs Incurred
The work in the main contract for reconstruction of the North Airport
Expressway and light rail transit components is complete. The        115
intelligent transportation management system is complete. A final
110
contract to complete paving, landscaping, the north entry art          Millions
features, and other miscellaneous work is nearing completion.        105
Schedule                            Dollars in 100
The main contract reached substantial completion in August 2008      95
and plant establishment was completed in December 2010. A           Authorized Forecasted Costs Incurred
contract for final paving, landscaping, and reclamation is underway 
and is planned to be complete in mid 2011 due to a couple of
differing site issues, followed by a first year plant establishment      Construction Costs
period to be complete in early 2012. The landscaping was delayed
and is in the first-year plant establishment period.                  120
100
Budget                             Millions 80
The project forecast is within the approved budget and authorization.    60
40
Change Order                          Dollars in 20
Four change orders were issued this quarter in the amount of          0
$18,350.                                            Initial  Change Order  Spent
Risks
None identified at this time.                                Photo
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 2Q 2011 Report  15

SECOND QUARTER REPORT, 2011
Main Terminal South Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
0 Change Orders
Start: 06/28/2007      equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD    Main Terminal.
$0
Significant Developments                    Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. Additional scope of work is being added due to increased     2
electrical loads and site conditions. The 90% design review          Millions 1.5
documents are being submitted for review, comments, prepare Asset
1
Acquisition Planning, revise implementation schedule, update        Dollars in 0.5
existing project notebook, and to re-assess the budget.
0
Schedule                               Authorized Forecasted Costs Incurred
The project was reactivated on June 24, 2009 and is in the process
of determining the scope of work, schedule and final design budget.
Expect to remobilize the design consultant in the fourth quarter 2011.  Construction Costs
Not Applicable
Budget
Photo
The project forecast is being analyzed due to changes in electrical
load requirements but it has been determined that Commission
approved for design funds will delay the start of the final 100%
design.
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area of the Main Terminal is a 24/7/365 operation.
Sequencing of this work is critical and electrical power has to be
maintained without interruptions.
Budget Transfers
None this quarter
16  Port of Seattle 2Q 2011 ReportAIRPORT

SECOND QUARTER REPORT, 2011
Consolidated Warehouse
Project:   C800071     This project will construct a 50,000    Status Snapshot Prior Report
Budget: $9,237,000     square foot warehouse for storage   Ahead of Schedule    3Q 09
Phase: Close Out     and inventory management of spare  On Budget
Start: 06/27/2006       parts for the Aviation Maintenance    34 Change Orders
Department.
Completion: 02/15/2010                       Total Change Orders Amount:
$770,658
Significant Developments                    Budget/Costs Incurred
The project is complete and in close out, with the building open for
use and in operation. The final invoice was submitted but has not       9.4
been paid due to incomplete as-built drawings.                   9.3
Millions 9.2
Schedule
9.1
The project was completed ahead of schedule.
Dollars in   9
Budget                             8.9
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Construction Costs
None this quarter
6
Risks
The final as-built drawings have not been received.                Millions  4
Dollars in 
Budget Transfers                           2
None this quarter.
0
Initial  Change Orders  Spent
Cost of Construction Growth
CO's exceeding 10% were due to the following:
1. Soil and foundation changes due to the site being an old,        Photo
unconsolidated fill of unknown material;
2. Perceived market conditions during bidding, structural mezzanine
was deleted. The bid climate changes allowed the mezzanine to
be installed; and
3. Pallet racks were anticipated to be a Port purchase and install.
The purchasing officer recommended the contractor purchase and
install as a CO.

AIRPORT
Port of Seattle 2Q 2011 Report  17

SECOND QUARTER REPORT, 2011
Airport Owned Gate Infrastructure
Project:   C800105      This project purchases and
Budget: $6,000,000      replaces passenger loading bridges  Status Snapshot
On Schedule
Phase: Construction     (PLB) at gates throughout the
On Budget
Start: 07/24/2007         airport. The project is being
performed in phases.           0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The PLBs for Gates B5 and S10 have been purchased. The work at
Gate B5 will be completed by October 31, 2011. The work at Gate
7
S10 will be completed by November 30, 2011. The design only for      6
the Gate S3 PLB replacement will be completed by December 31,
Millions  5
2011.                                         4
3
Schedule                            Dollars in  2
1
The project is currently on schedule.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

18  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
C4 UPS System Improvements
Project:   C800107    Project will replace existing          Status Snapshot Prior Report
Budget: $2,336,000   Uninterruptible Power Supply (UPS)    Delayed Schedule 1Q 09
Phase: Construction  System, including batteries, with a new  On Budget
Start: 06/28/2007      new system located in the Airport      0 Change Orders
Completion: TBD     Combined Communications and      Total Change Orders Amount:
Command Center (C4).           $0
Significant Developments                    Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. Additional scope of work is being added due to increased     2
electrical loads and site conditions. The 90% design review          Millions 1.5
documents are being submitted for review, comments, prepare Asset
1
Acquisition Planning, revise implementation schedule, update        Dollars in 0.5
existing project notebook, and to re-assess the budget.
0
Schedule                               Authorized Forecasted Costs Incurred
The project was reactivated on June 24, 2009 and is in the process
of determining the scope of work, schedule and final design budget.
Expect to remobilize the design consultant in the fourth quarter 2011.  Construction Costs
Not Applicable
Budget
The project forecast is being analyzed due to changes in electrical
load requirements but it has been determined that Commission
approved for design funds will delay the start of the final 100%
design.
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as 
this is specialized equipment and due to the complexity and requires
rigorous testing during the commissioning phase.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 2Q 2011 Report  19

SECOND QUARTER REPORT, 2011
Garage Escalator & A-Bank Elevator Upgrade
Project:   C800109    This project renews aging elevators    Status Snapshot Prior Report
Budget: $5,815,000    and escalators in the Airport Parking   Delayed Schedule    3Q 10
Phase: Construction   Garage to provide reliable vertical    On Budget
Start: 09/11/2007       transportation to customers for years   23 Change Orders
Completion: 10/31/2011  to come.                 Total Change Orders Amount:
$219,523
Significant Developments                    Budget/Costs Incurred
Contractor work on all six Garage Escalators is complete, except for
8
installation of monitoring software and an additional minor electrical
upgrade that was determined to be necessary. All escalators are       6
operational. The A-Bank elevator work was completed in 2010.       Millions
4
Schedule                            Dollars in  2
Contractor work is scheduled to be completed in August 2011.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
4
None this quarter
3
Risks
2
Millions
None identified at this time.
Dollars in   1
Budget Transfers
0
None this quarter                                         Initial  Change Order  Spent


AIRPORT


20  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot
The scope of work will remove and   On Schedule
Project:   C800112      replace the pavement and joint seal  On Budget
in areas on Runway 16C-34C.
Budget: $4,161,623                         0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 02/26/2008                                 $0.00
Completion: 09/01/2012
Significant Developments                    Budget/Costs Incurred
The 2012 runway 16C/34C panel replacement project is requesting      6
from the Port Commission to use previously authorized funds and
5
retaining $1,400,000 for this project on July 26, 2011.
Millions  4
3
Schedule
2
Design efforts for 2012 contract would start in the third quarter of       Dollars in  1
2011.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None this quarter
Risks                               Photo
No risks have been identified at this time.
Budget Transfers
To C102166 (Aeronautical Renewal/Replacement)   $1,488,377



AIRPORT

Port of Seattle 2Q 2011 Report  21

SECOND QUARTER REPORT, 2011
Security CCTV System Improvements
Project:   C800144      This project will install          Status Snapshot Prior Report
Budget: $2,037,591      approximately 70 new cameras for  Delayed Schedule 3Q 09
Phase: Implementation   TSA and integrate existing Airport   On Budget
Start: 9/11/2007          camera networks which contain     0 Change Orders
Completion: 05/31/2010   over 800 cameras.          Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The project is in the process of purchasing additional data storage.
2.06
2.04
Schedule                            2.02
Project substantial completion occurred in March 2010.             Millions 2
1.98
1.96
Budget                             1.94 Dollars in 
1.92
The project forecast is within the approved budget and authorization.
1.9
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable
Construction Costs
Risks                               Not Applicable
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

22  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Concessions Unit Readiness Project
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Design        previously vacated or slated to be   On Budget
Start: 08/26/2008         vacated to Port standards for use    0 Change Orders
Completion: 06/30/2013   as specialty concession space.    Total Change Orders Amount:
$0
Significant Developments
This project received Commission authorization in September 2010   Budget/Costs Incurred
to design and build concession spaces in two locations. Design of
these two locations is complete. Staff will request Commission        2.5
authorization on August 9, 2011 to design/construct two additional       2
locations.                                             Millions 1.5
Schedule                             1
Dollars in 
The construction phase has been restructured and re-sequenced,      0.5
with the intent to maximize the timing for new Concessions           0
opportunities. The project was put on hold until the prioritization           Authorized  Forecasted Costs Incurred
decisions were made by Aviation Business Development.
Budget                            Construction Costs
The project forecast is within the approved budget. Authorization of   Not Applicable
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2011 Report  23

SECOND QUARTER REPORT, 2011
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot  Prior Report
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule 1Q 11
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,000
project includes installing three      0 Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new     $0
Completion: 07/01/2012   approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
1.2
The design for utilities was previously completed in 2009 but put on      1
hold due to market conditions. Plans for the new food-beverage       Millions 0.8
concession are now proceeding with design to restart and be         0.6
updated based on current conditions.
0.4
Dollars in 0.2
Schedule
0
The project schedule was delayed due to the pending decision by         Authorized Forecasted Costs Incurred
the Business Development Group to proceed with the
concessionaire. Design for the food/beverage concession is planned
to begin in the third quarter 2011 with project completion in mid-      Construction Costs
2012. The demand for retail merchandizing units is still under       Not applicable
evaluation.
Photo
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter

AIRPORT
24  Port of Seattle 2Q 2011 Report

SSECOND QUUARTER REPPORT, 2011
Runway 166L/34R RReconsttruction
Prooject: C8000167       Thee scope of this projectt includes
Status SSnapshot
Buddget: $60,257,357     thee complete reconstructtion of
Phaase: Close Out      Runway 16L/334R (the eaastern    On Scheedule
Start: 02/26/22008        runnway) and rreplacemennt of aging  Under BBudget
infrrastructure.                  26 Channge Orders
Commpletion: 12/31/20009                     Total Chhange Ordeers Amount:
$2,528,2214.29
Significant DDevelopmments
Runnway 16L/344R Reconstruction prooject includees reconstrruction of
11,9900 foot runnway and portions of fiive taxiways. The consstruction   Budget//Costs Incuurred
was completedd on Septemmber 25, 20009 and re-opened on
100
September 26, 2009 on scchedule.
80
Schhedule                            Millions 60
40
The runway waas re-openeed on scheddule on Sepptember 266, 2009.
The project is bbeing closed out. Thiss is the last report.              Dollars in  20
0
Buddget                              A uthorized For ecasted Costs I n curred
The project foreecast is witthin the appproved budgget and autthorization.
The project antticipates retturning appproximately $200,000 nnext      Construuction Costs
quarrter.
60
Chaange Ordder
50
No cchange orders have beeen executted during this period.           Millions 40
30
Rissks
20
No rrisk have beeen identifieed at this time.                        Dollars in   10
0
Buddget Trannsfers                            InitialChange O rdersSpent
Nonne this quarter.
Photo


AIRRPORT

Port of Seattle 2Q 2011 Report  25

SECOND QUARTER REPORT, 2011
Connect C1 BHS to C88 Baggage Handling
System
This project connects the C1       Status Snapshot  Prior Report
Project:   C800170      baggage handling system (BHS) to  Delayed Schedule 3Q 10
the C88 BHS. It installs two High-   Under Budget
Budget: $3,032,000
Speed Diverters plus additional     9 Change Orders
Phase: Close Out      baggage conveyor length that will   Total Change Orders Amount:
Start: 8/30/2009          connect the two C1 sortation loops   $214,502
Completion: 3/31/2011    to the C88 BHS.
Budget/Costs Incurred
3.2
Significant Developments
3
The project is complete and in close out. This will be the last
quarterly report for this project.                                Millions 2.8
2.6
Schedule                            Dollars in 2.4
The project was complete as of March 31, 2011.
2.2
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
The project anticipates returning savings after close out is complete.   Construction Costs
Change Order                           1.5
We added the computer upgrades to the scope of the project as
requested by Alaska Airlines.                              Millions  1
Risks                                 0.5
Dollars in 
None identified at this time.
0
Budget Transfers                             InitialChange OrdersSpent
None this quarter
Cost of Construction Growth
The 17.74% growth on the project resulted from the request by
Alaska to upgrade the C92 computers to mitigate issues with sorting
the baggage and related interruptions to airline activities.

AIRPORT

26  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Federal Inspection Services - New Primary
Inspection Booths
This project will replace existing     Status Snapshot
Project:   C800174      primary inspection booths for      Delayed Schedule
Customs and Border Protection in   On Budget
Budget: $2,000,000
the International Arrivals Federal    0 Change Orders
Phase: Construction     Inspection Services (FIS) facility in  Total Change Orders Amount:
Start: 7/27/2010          the South Satellite.             $0
Completion: 9/8/2011
Budget/Costs Incurred
Significant Developments
The first phase of the new booths is complete and operational. The     2.5
second phase is under construction.                          2
Millions 1.5
Schedule
1
The project was delayed by approximately two months due to a
Dollars in 0.5
delay in contractor badging.
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2011 Report  27

SECOND QUARTER REPORT, 2011
Common Use Lounge Remodel
Project:   C800203      This project will relocate the Port's   Status Snapshot
Budget: $971,000       common-use lounge from the     On Schedule
Phase: Design        mezzanine level to the departure   On Budget
Start: 03/01/2011         level of the South Satellite.        0 Change Orders
Completion: 02/28/2012   Improvements consist of new     Total Change Orders Amount:
finishes, new furnishings and other   $0
minor cosmetic improvements.
Budget/Costs Incurred
Significant Developments
1.2
The 90% design has been submitted for review.                  1
Schedule                            Millions 0.8 Dollars in 
0.6
Design is scheduled to complete in August 2011. The project will be     0.4
advertised and awarded in Fall 2011. Construction is currently        0.2
scheduled to begin in Fall 2011 and complete early 2012.            0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will    Construction Costs
be requested when the design and bid documents are completed.    Not Applicable
Change Order
None
Risks
None identified at this time
Budget Transfers
None this quarter



AIRPORT

28  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Terminal Escalators Modernization
Project:   C800237      This project will replace 42       Status Snapshot Prior Report
Budget: $46,230,292     escalators in the Main Terminal,    Ahead of Schedule 1Q 11
Phase: Design        Concourse B, and South Satellite.   On Budget
Start: 11/02/2007         In addition, two new escalators will   3 Change Orders
Completion: 07/01/2013   be installed at the South Satellite.   Total Change Orders Amount:
$213,000
Significant Developments                    Budget/Costs Incurred
This is a design-build contract. The contractor is in the final stages
60
of design. Construction is scheduled to start in the third quarter 2011
50
in the Main Terminal, Concourse B, and the communications room of
Millions 40
the South Satellite.
30
Schedule                             20
Dollars in  10
The project is currently ahead of schedule.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
The project budget was reduced by $7,500,000 in the first quarter    Construction Costs
2011 to reflect the competitive pricing by the contractor in its price
proposal.                                           20
15
Change Order
10
Millions
Three change orders have been approved for energy-saving sleep
mode sensors in the escalators, shared project partnering facilitation,    Dollars in  5
and design/purchase for relocated electrical panels.
0
Initial    Change Order    Spent
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 2Q 2011 Report  29

SECOND QUARTER REPORT, 2011
Central Plant Pre-Conditioned Air
Project:   C800238     This project will provide a centralized  Status Snapshot Prior Report
Budget: $40,010,000    pre-conditioned air plant, associated  Delayed Schedule 3Q 09
Phase: Design       heating and cooling piping systems,   Forecast Overrun
Start: 06/15/2009       and jet bridge terminal air handling    30 Change Orders
Completion: 12/10/2012  units to serve airplanes with heating   Total Change Orders Amount:
and cooling while at the gates.       $529,596
Significant Developments
The contractor is installing equipment foundations in the Central     Budget/Costs Incurred
Terminal Basement, and piping and electrical conduit at the South
Satellite, Concourse B and Concourse C.                     50
40
Schedule
30
The design process took longer than anticipated and the project is      in Millions 20
approximately two months behind the original schedule.            Dollars  10
Budget                             0
Authorized  Forecasted Costs Incurred
The project budget is forecast to exceed the approved budget by
$3,525,000. In March 2011, the Port received additional Voluntary
Airport Low Emissions (VALE) grant money from the FAA in the
Construction Costs
amount of $3,612,679 for Concourse D and North Satellite.
30
Change Order
25
Twenty seven change orders were issued this quarter for a total of
$511,596.                                       Millions 20
15
10
Risks                                Dollars in  5
The design schedule had to be accelerated in order to meet VALE
0
grant submission dates, which could impact the number of change
InitialChange OrdersSpent
orders and design modifications. The design consultant has
improved response time on Requests for Information and Submittal
review. However, engineering review is still critical as site conditions
required piping design changes. The design review and changes are
happening concurrently with the contractor work. Actual Regulated
Materials Management costs for work at South Satellite are below
estimated budget.
Budget Transfers
None this quarter.

AIRPORT
30  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Parking System Replacement
Project:   C800253      This project replaces the current    Status Snapshot
Budget: $9,777,000      Parking Revenue Control System,   Delayed Schedule
Phase: Construction     which manages parking access    On Budget
Start: 04/06/2010         and revenue collection in the      0 Change Orders
Completion: 03/31/2012   Airport's Main Parking Garage.    Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Project design is complete. Commission authorization of system
acquisition funding and authority to advertise occurred during March     12
2011. The project was advertised in April 2011. Three parking         10
revenue control system manufacturers offered competitive          Millions 8
proposals. After a competitive process, Scheidt-Bachmann was        6
chosen.                                        4
Dollars in   2
Schedule                             0
This project was advertised in April 2011. Installation of the system        Authorized  Forecasted Costs Incurred
was delayed and is scheduled to occur first quarter 2012. The
installation was delayed approximately three months to avoid
conflicts during the holiday rush period.                       Construction Costs
None this quarter
Budget
Photo
The project forecast is within the approved budget and authorization.
Change Order
No change orders were issued this quarter.
Risks
This project schedule is aggressive.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2011 Report  31

SSECOND QUUARTER REPPORT, 2011
Airrcraft ROON Parkking USPPS Site
Statuss Snapshott Prior Reportt
Delayeed Schedulee     1QQ 11
Prooject: C8000254       Thiis project wwill prepare the site forr
On Buddget
Buddget: $43,900,000     thee constructioon of Hardsstands for
0 Channge Orders
Phaase: Desiggn        usee as Remaiin Overnighht (RON)
Total CChange Ordders Amounnt:
Start: 08/26/22008        parrking of airccraft at the AAir Mail
$0
Center site.
Commpletion: 12/31/20114
Budget//Costs Incuurred
Significant DDevelopmments
50
The temporary lease with the United States Posstal Servicee (USPS)
40
for the Air Mail Center sitee ended in JJanuary 20011. Designn efforts for
the ddemolition of the Air MMail Center including thhe design fofor minimal    Millions 30
site improvemeents allowinng for tempoorary uses and amenitties, and     20
15%% hardstandd design staarted in Summmer 20100. Hazardouus        Dollars in  10
mateerial removval will be inncluded as a part of the demolitioon contract.
0
A uthorized  For ecasted Costs I n curred
Schhedule
Authhorization oof construction fundingg and authoority to awarrd for
consstruction is scheduled for July 26, 2011. Abbatement annd       Construuction Costs
demmolition of thhe USPS Building is sccheduled too start in thee fourth    Not Applicable
quarrter of 20111. Proposed constructtion of a peermanent haardstand is
scheeduled to begin the seecond quartter of 2013.                Photo
Buddget
The project foreecast is witthin the appproved budgget.
Chaange Ordder
Nonne
Rissks
Exteent of asbesstos in the USPS Buildding may afffect the prooject cost.
Buddget Trannsfers
Nonne this quarter

AIRRPORT

32  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
8th Floor Weatherproofing
Status Snapshot
On Schedule
Project:   C800274      This project includes removal and   On Budget
Budget: $13,050,000     replacement of the floor covering   0 Change Orders
Phase: Construction     system on the 8th floor of the STIA  Total Change Orders Amount:
Start: 03/23/2010         parking garage and repair or       $0
Completion: 03/31/2013   replacement of expansion joints
and flashings.                Budget/Costs Incurred
14
Significant Developments                     12
The design consultant issued a conditions assessment report based    Millions 10
8
Dollars in 
on forensic testing procedures outlining the cause and severity of
6
structural cracking in the 8th floor parking deck. Design is complete.
4
2
Schedule                             0
The delivery of design by the consultant was delayed to the second        Authorized Forecasted Costs Incurred
quarter of 2011, with bid advertisement in third quarter 2011, and
construction during the fall of 2011 and summer of 2012. Substantial
completion is still on schedule.                             Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.  Photo
Change Order
None
Risks
This is a weather-dependent project.
Budget Transfers
From C800153 (Non-Aero Renewal/Replacement)     $50,000


AIRPORT

Port of Seattle 2Q 2011 Report  33

SECONDD QUARTER RREPORT, 2011
Common UUse Equuipment Expanssion (CUUSE)
Prooject:  C800276C          This project innstalls flexibble       Statuss Snapshott
Buddget: $3,0090,000     passenger processing        On Schedule
Phaase: Desiggn        infrastructure and equipmment at thee  On Budget
Start: 09/01/22009         airrline gates aat some Soouth       0 Channge Orderss
Commpletion: 12/31/20111   Saatellite and CConcourse A gates,   Total CChange Ordders Amounnt:
as well as at tthe former Delta       $0
loccation.
Budgett/Costs Inccurred
Significant DDevelopmments
4
Casework for thhis project has been bbid separateely at the reequest of
3
Deltta Air Lines and is anticipated to bbe installedd in Septemmber 2011.    Millions
The designers for the remmaining scoppe are deveeloping the 90%        2
desiign documeents.
Dollars in   1
Schhedule                             0
The project is sstill trackingg a few weeeks behind schedule ddue to a         A uthorized Fore c asted Costs Incu r red
longger than antticipated duuration for ccontract neggotiation. HHowever,
the ddesign teamm anticipatees recovering this timee during dessign and
the pproject should be commpleted on ttime.                    Construuction Cossts
Not Appplicable
Buddget
The project foreecast is witthin the appproved budgget. Authorrization of
consstruction funding and aauthority too advertise ffor construcction will
be requested wwhen the deesign and bbid documents are commpleted.
Chaange Ordder
Nonne
Rissks
Nonne identifiedd at this timee
Buddget Trannsfers
Nonne this quarter

AIRRPORT

34  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Communications Cable Additions to MT, D, CTE
Project:   C800331      Addition of copper and fiber cabling  Status Snapshot
Budget: $377,000       to create a redundant pathway    On Schedule
Phase: Construction     throughout the Central Terminal    On Budget
Start: 08/11/2011         and Main Terminal             0 Change Orders
Completion: 12/31/2011   Communications Rooms.       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
Commission Authorization to construct was received May 3, 2011.      0.4
0.3
Schedule                            Millions
Schedule is on track with the schedule as presented to Commission.    0.2
Dollars in 0.1                                                                               Budget
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT

Port of Seattle 2Q 2011 Report  35

SECOND QUARTER REPORT, 2011
Two New CTE Freight Elevators
Status Snapshot
Project:   C800334      Provide two new freight elevators   On Schedule
Budget: $6,664,000      to support concession operations in  On Budget
Phase: Design        the Central Terminal/Pacific      0 Change Orders
Start: 08/05/2011         Marketplace.                Total Change Orders Amount:
Completion: 07/31/2011                       $0
Budget/Costs Incurred
Significant Developments                      7
The project will begin design in third quarter 2011.                  6
Millions  5
4
Dollars in 
Schedule
3
The project is scheduled to complete design in first quarter 2012.        2
Construction is anticipated to commence in forth quarter 2012.         1
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.    Construction Costs
Not Applicable
Change Order
None
Risks
There is a potential risk due to unknown conditions where the freight
elevator foundations will be constructed, i.e., outside of the Central
Terminal building envelope.
Budget Transfers
None this quarter


AIRPORT

36  Port of Seattle 2Q 2011 Report

SECONDD QUARTER RREPORT, 2011
Eleectrical GGround Supporrt Equipmment (EGSE)
Eleectrical CCharge Stationss
Statuss Snapshott
Prooject:  C800335C          Airrport-wide eelectrical chharging     On Schedule
Buddget: $14,410,000     sysstem for eleectrical grouund      On Budget
Phaase: Desiggn        support equippment (EGSSE) at the   0 Channge Orderss
Start: 10/26/22010         Cooncourses aand the Norrth and     Total CChange Ordders Amounnt:
Commpletion: 4/30/20133    Soouth Satellittes.           $0
Significant DDevelopmments                   Budgett/Costs Inccurred
The Port receivved manufaacturer's ressponse to the Requesst for         20
Inforrmation for EGSE batttery chargeers and an aanalysis waas
commpleted in Juune 2011. TThe projectt team is cuurrently prepparing a      15
Reqquest for Prooposal to solicite bids to prepurchhase the EGGSE        Millions
10
batteery chargerrs in order tto completee the 100% design. Thhere are
diffeerent types of battery cchargers onn the markeet and the tyype of       Dollars in  5
batteery chargerr selected wwill have a ssignificant impact on hhow the
0
desiign is impleemented and the project overall costs. A Serrvice
Authorized  F o recasted Costs I ncurred
Agreeement withh the Consuultant was eexecuted aand the site walks are
commplete. Withh the information deriveed from thee site walk, the projectt
teamm is now in the process of preparring the scoope of work, budget,
Construuction Cossts
impllementationn schedule, and Projecct Notebookk.
Not Appplicable
Schhedule
The project teaam is in the process off developingg the implementation
scheedule.
Buddget
The project foreecast is witthin the appproved budgget. Authorization for
the cconstruction funding aand authoritty to advertise for consstruction
will bbe requesteed when the design annd bid docuuments are
commpleted.




Port of Seattle 2Q 2011 Report  37

Chaange Ordder
Nonne
Rissks
Riskks include: Late execution of agreeements beetween Portt and Airlinee Carrier CConsortium; and
Cooordination wwith other airfield projeccts and Airlline Realignnment proggram.
Buddget Trannsfers
Nonne this quarter.









AIRRPORT

38  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
South Satellite Delta Sky Club Expansion
Status Snapshot Prior Report
Delayed Schedule 1Q 11
Project:   C800336     Construction of a new 6,800 square   On Budget
Budget: $8,930,000    foot Sky Club lounge on the roof of   0 Change Orders
Phase: Construction   the South Satellite for Delta Air Lines.  Total Change Orders Amount:
Start: 06/01/2010                                 $0
Completion: 08/30/2011
Budget/Costs Incurred
Significant Developments
10
The Port has requested additional authorization and funds for the
8
increased club size and for unanticipated structural conditions at roof
level that have added significant Port scope to the project. Delta's       6  Millions
contractor is working on interior finishes.                         4
Dollars in   2
Schedule
0
Construction work is well underway and the completion date remains
Authorized  Forecasted Costs Incurred
August 2011.
Budget                            Construction Costs
The project forecast for the current scope has increased and is within  Not Applicable
the approved budget and authorization.
Change Order
None
Risks
The Port's scope and costs could still increase beyond current
authorization as change orders are negotiated and costs split
between Delta and the Port.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2011 Report  39

SECOND QUARTER REPORT, 2011
Roof Replacement Program
Status Snapshot
On Schedule
Project:   C800360      Remove and replace the roofing    On Budget
Budget: $2,640,000      systems on the south and central   0 Change Orders
Phase: Construction     sections of the Main Terminal. The  Total Change Orders Amount:
Start: 4/25/2010          new roofing systems will achieve    $0
Completion: 10/31/2011   LEED credits and are Energy Star
rated. This project is part of a      Budget/Costs Incurred
multi-phased program.
3
2.5
Significant Developments
2
Design and bid document preparation is complete and the          Millions
1.5
construction contract was awarded to Cobra in May 2011.
1
Dollars in 0.5
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                           1.2
1
None
0.8
Risks                                 0.6
Millions
0.4
None at this time                                       Dollars in  0.2
Budget Transfers                           0
InitialChange OrdersSpent
None this quarter



AIRPORT

40  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Claim Device 14 & Lower Inbound
Project:   C800374      This project will replace the slope-   Status Snapshot
Budget: $3,900,000      plate bag claim device 14 and     On Schedule
Phase: Design        associated controls, in addition to   On Budget
Start: 04/01/2011         removing the lower feed conveyor   0 Change Orders
Completion: 05/31/2012   and replacing it with a new      Total Change Orders Amount:
overhead feed.               $0
Budget/Costs Incurred
Significant Developments                      5
The project team has started the design for this project. We           4
anticipate the design being complete this fall.                    Millions 3
2
Schedule                            Dollars in  1
The project is currently on schedule.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be    Construction Costs
requested when the design and bid documents are completed.      Not Applicable
Change Order
None
Risks
None
Budget Transfers
None



AIRPORT

Port of Seattle 2Q 2011 Report  41

SECOND QUARTER REPORT, 2011
Baggage Handling System (C22-C1, MK1, and
TC3)
This project will replace the ticket    Status Snapshot
Project:   C800382      counter (TC3) conveyors and      On Schedule
declines, reroute the conveyors of   On Budget
Budget: $5,335,000
the C-22 system and connect it to   0 Change Orders
Phase: Design        the C-1 screening system, replace  Total Change Orders Amount:
Start: 03/01/2011         the existing makeup (MK1) device,   $0
Completion: 05/31/2013   and install a new odd size baggage
system.                  Budget/Costs Incurred
6
Significant Developments                      5
This project was authorized March 1, 2011. The design consultant     Millions 4
finalized design of TC3 conveyor system. Design on the remainder of    3
the project will continue through third quarter 2011. The project team     2
is working with the Central Procurement Office to purchase the        Dollars in  1
equipment for TC3. Port Construction Services will start demolishing     0
the TC3 conveyors in the third quarter 2011.                       Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule.                        Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time
Budget Transfers
None this quarter

AIRPORT

42  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
RW16C/34C Reconstruction Design
Project:   C800406      This project will produce the 60%   Status Snapshot
Budget: $669,000       design for the runway 16C/34C    On Schedule
Phase: Design        reconstruction. The design will    On Budget
Start: 05/04/2010         include utilities, runway status      0 Change Orders
Completion: TBD       lights, and other scope items     Total Change Orders Amount:
related to the project.             $0
Significant Developments                    Budget/Costs Incurred
The 60% design was issued in December 2010. Incorporation of
0.8
comments on the 60% design work is completed.
0.6
Schedule                            MillionsDollars in 
0.4
Staff will return to Commission for authorization of the remaining
design funds in late 2014 or early 2015. The forecast will be          0.2
reassessed when staff returns to the Commission for authorization of
0
the final design funds.
Authorized  Forecasted Costs Incurred
Budget
The Port Commission authorized $669,000 on May 4, 2010. The     Construction Costs
current forecast for 60% design is within the approved budget and    Not Applicable
authorization. Any potential savings will be returned.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2011 Report  43

SECOND QUARTER REPORT, 2011
South Satellite Concessions Project
Project:   C800412      This project will demolish and      Status Snapshot
Budget: $1,872,739      relocate the existing duty free shop,  On Schedule
Phase: Design        electric/communications to support  On Budget
Start: 01/01/2011         a temporary duty free location, and   0 Change Orders
Completion: 03/31/2012   construct a new food and beverage  Total Change Orders Amount:
shell space in the South Satellite at   $0
Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                      2
The project received Commission Authorization to design on March     1.5
8, 2011. Design procurement is underway.                    Millions
1
Schedule                            Dollars in 0.5
Design is three months behind schedule based on contract
0
negotiations. The project is in the process of determining if a
Authorized  Forecasted Costs Incurred
recovery schedule is possible.
Budget
Construction Costs
The project forecast is within the approved budget. Authorization of   Not Applicable
construction funding and authority to award for construction will be
requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

44  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Additional Airfield Mitigation at Tyee
Project:   C800420      The project will design and       Status Snapshot
Budget: $800,000       complete the Tyee Golf Course    On Schedule
Phase: Design        Area Mitigation which includes    On Budget
Start: 02/08/2011         removing a culvert, new wetland    0 Change Orders
Completion: 03/30/2012   planting, updating existing wetlands  Total Change Orders Amount:
to environmental permit standards,   $0
and installing a temporary irrigation
system.                  Budget/Costs Incurred
1
Significant Developments
0.8
The Port Commission authorized $109,000 of design funds on
February 8, 2011.                                    Millions 0.6
0.4
Schedule                            Dollars in 0.2
In August 2011, the project will request authority to advertise for
0
construction from the Port Commission. Construction is scheduled
Authorized  Forecasted Costs Incurred
to begin in December 2011.
Budget                            Construction Costs
The project forecast is within the approved budget. Authorization for  Not Applicable
construction funding and authority of award for construction will be
requested when the design and bid documents are completed.      Photo
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2011 Report  45

SECOND QUARTER REPORT, 2011
Federal Inspection Service Improvements -
Phase 1
Improvements to the Federal      Status Snapshot
Project:   C800426      Inspection Service area at the     On Schedule
South Satellite to remedy queuing   On Budget
Budget: $31,700,000
pinch points and add additional     0 Change Orders
Phase: Design        passenger processing capacity.    Total Change Orders Amount:
Start: 04/01/2011                                 $0
Completion: 05/31/2013
Budget/Costs Incurred
Significant Developments                     35
Procurement for a design consultant is in progress.                30
Millions 25
Schedule                             20
15
This project is currently projected to complete on schedule.
Dollars in  10
5
Budget                             0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time
Budget Transfers
None this quarter



AIRPORT

46  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Concourse D Common Use Environment
Project:   C800455      This project installs a common-use  Status Snapshot
Budget: $4,250,000      environment at all gates on      On Schedule
Phase: Design        Concourse D. Scope includes new  On Budget
Start: 03/01/2011         communications infrastructure,     0 Change Orders
Completion: 06/31/2012   casework built to a new Airport    Total Change Orders Amount:
standard, new carpet, wall        $0
coverings and task lighting.
Budget/Costs Incurred
Significant Developments
5
The 90% design is complete and a new casework standard has been
4
developed. The project team created a full size mock-up of the new    Millions 3
casework to work out the final design details and ensure they
function as intended.                                     2
Dollars in   1
Schedule
0
Design began in March 2011 and will now be complete in late            Authorized Forecasted Costs Incurred
September 2011. The decision to construct a casework mock-up
added time to the design schedule. Advertisement for construction is
scheduled for late Fall 2011 and will be awarded to a contractor in    Construction Costs
early 2012. Construction is now anticipated to be complete in June   Not Applicable
2012.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 2Q 2011 Report  47

SECONDD QUARTER RREPORT, 2011
Eleectrical GGround Supporrt Equipmment (EGSE)
Rolling Stoock
The Port of Seattle will pprocure andd   Statuss Snapshott
Prooject:  C800457C          deploy the initial fleet of EGSE.    On Schedule
This fleet will be comprissed of       On Budget
Buddget: $30,000,000
approximatelyy 334 baggage tugs,   0 Channge Orderss
Phaase: Desiggn        192 belt loadeers, 71 pusshback    Total CChange Ordders Amounnt:
Start: 0/26/20010         traactors, and 92 other pieeces of     $0
Commpletion: 04/30/20113   groound suppoort.
Budgett/Costs Inccurred
Significant DDevelopmments
The Port is in thhe process of solicitingg bid propoosals for thee EGSE       35
Rolling Stock aand the clossing date is scheduled for Augustt 5, 2011.      30
Millions 25
20
Schhedule
15
The Port is schheduled to aanalyze thee bid propossals and suubmit the
Dollars in  10
resuults to the AAirline Carrieers. Once tthe Carrierss provide thhe Port withh     5
the llist of required equipmment, the Poort staff will present ressults to        0
Authorized  F o recasted Costs I ncurred
Commmission annd secure aapproval to proceed too issue multtiple
purcchase orderrs to the rollling stock uusing the $55,000,000 GGrant
Cleaan Cities funds that waas previoussly secured..
Buddget                           Construuction Cossts
The project foreecast is witthin the appproved budgget. Commmission     Not Appplicable
authhorization foor the remaaining fundinng and authhorization too purchasee
the eequipment will be requuested early in the thirrd quarter 22011.
Chaange Ordder
Nonne
Rissks
Poteential risks due to late execution oof agreemeents betweeen the Port
and Airline Carrrier Consorrtium, and ccoordination with otheer airfield
projeects and Aiirline Realiggnment proogram.
Buddget Trannsfers
Nonne this quarter

AIRRPORT

48  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
South Satellite - Additional Gate Lobby
Project:   C800466      Demolition of glass partitions,      Status Snapshot
Budget: $1,257,000      restrooms, relocation of gate     On Schedule
Phase: Design        podiums new flooring, ceilings and  On Budget
Start: 11/01/2010         infrastucture to provide additional    0 Change Orders
Completion: 03/31/2011   gate lobby in the South Satellite.   Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Commission Authorization for design and removal of glass panels
was received in November 2010. Design procurement is underway.    1.4
1.2
1
Schedule                            Millions 0.8
Project design is currently three month behind schedule based on      0.6
negotiations with designer. The project is in the process of           Dollars in 0.4
determining if a recovery schedule is possible.                   0.2
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
Construction Costs
requested when the design and bid documents are completed.
Not Applicable
Change Order
None.
Risks
None identified at this time.
Budget Transfers



AIRPORT

Port of Seattle 2Q 2011 Report  49

SECOND QUARTER REPORT, 2011
Passenger Loading Bridge Replacement
Project:   C800467      This project entails Passenger     Status Snapshot
Budget: $14,850,000     Loading Bridge (PLB)         On Schedule
Phase: Design        replacements associated with the   On Budget
Start: 04/12/2011         one-time airline realignment (AR).   0 Change Orders
Completion: 04/30/2012   The work will take place at      Total Change Orders Amount:
Concourse D, Concourse B and    $0
North Satellite.
Budget/Costs Incurred
Significant Developments
20
Design for the first bid package (Gates D1-D3) is at 90%. Additional
refubishment work will take place at Concourse D, Gates B7 and B9     15
are added; the North Satellite gates have been deleted.            Millions
10
Schedule                            Dollars in  5
The project is currently on schedule.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will    Construction Costs
be requested when the design and bid documents are completed.    Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

50  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Water System Isolation Valve Upgrade - Airfield
Project:   C800469      The water distribution system at the
Budget: $1,443,000      Airport is almost 40 years old. This  Status Snapshot
Phase: Construction     project will replace and add      On Schedule
Start: 11/15/2010         additional water valves in several    On Budget
Completion: 12/31/2011   strategic locations to prevent     0 Change Orders
possible outages.              Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
On November 15, 2010, Commission authorized dividing the Water     2
System Isolation Valve Upgrade project into two projects, Airfield and
1.5
Non-Airfield. The Port Commission authorization to advertise was on   Millions
March 1, 2011. The water valves have been delivered. Construction     1
work started on June 13th.
Dollars in 0.5
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not applicable
be requested when the design and bid documents are completed.
Change Order                         Photo
None
Risks
The replacement valve sizes were taken from 25-40 year old
documents.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 2Q 2011 Report  51

SECOND QUARTER REPORT, 2011
Security Checkpoint Optimization
Project:   C800471      This project supports TSA initiative  Status Snapshot
Budget: $430,000       to accomodate emerging       On Schedule
Phase: Close Out      technologies. Major elements were  On Budget
Start: 8/15/10           new electrical infrastructure to      0 Change Orders
Completion: 12/31/10    checkpoints and minor relocation of  Total Change Orders Amount:
lanes for installation of Advanced    $0
Imaging Technology (AIT) units.
Budget/Costs Incurred
Significant Developments                     0.44
Project is substantially complete; remaining work includes installing
0.42
additional electrical outlets.                                   Millions
0.4
Schedule
0.38  Dollars in 
The remaining outlet installation is scheduled to be completed by
October 31, 2011.                                   0.36
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT


52  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Exterior Gate Improvements (Airline
Realignment)
This project will install new fuel pits   Status Snapshot
Project:   C800472      and aircraft docking systems at     On Schedule
exterior gates for the airline         On Budget
Budget: $2,650,000
reallocation program.            0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 06/01/2011                                 $0
Completion: 10/31/2012
Budget/Costs Incurred
Significant Developments                      3
2.5
The design phase has started.
Millions  2
Schedule                             1.5
1
The project is currently on schedule.                          Dollars in 0.5
Budget                             0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.    Construction Costs
Not Applicable
Change Order
None
Risks
If proposed future gate locations for the airlines change, it could
impact the project schedule and budget.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 2Q 2011 Report  53

SECOND QUARTER REPORT, 2011
Airport Signage (Airline Realignment)
Project:   C800474      The project will provide airport     Status Snapshot
Budget: $646,000       directional signage for the airline   On Schedule
Phase: Design        reallocation program.         On Budget
Start: 06/01/2011                                 0 Change Orders
Completion: 04/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
A Request for Qualifications was issued for a signage design         0.7
services contract.                                       0.6
0.5
0.4
Schedule
in Millions 0.3
The project is currently on schedule.
Dollars 0.2
0.1
Budget                             0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
54  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Highline School Noise Insulation
Project:   C200007      Highline School Insulation        Status Snapshot Prior Report
Budget: $101,797,000    Agreement will provide funding for  Delayed Schedule 4Q 10
Phase: Construction     sound mitigation for 15 schools that  On Budget
Start: 03/23/1999         are impacted by aircraft noise from   0 Change Orders
Completion: 11/30/2021   Sea-Tac Airport.            Total Change Orders Amount:
$0
Significant Developments
The insulation of seven schools has been completed and no more    Budget/Costs Incurred
are scheduled until 2012.
120
100
Schedule
Millions 80
Port funding is authorized and will be available when the matching
60
funds are provided by the FAA, the State of Washington, and the
40
Highline School District. The schedule for state funding is not known.    Dollars in  20
The district's schedule is dependent on obtaining general election
0
bonds at various intervals.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Not applicable
Risks
None identified at this time
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2011 Report  55

SECONDD QUARTER RREPORT, 2011
3rd Runwayy Resideential Accquisitioon
Prooject:  C200015C          Accquire singlee/multi-family       Statuss Snapshott Prior Report
Buddget: $34,340,000     ressidences located in thee noise-    On Schedule
Phaase: Close Out      impacted 3rd RRunway fligght path in   Under Budget   2Q 11
Start: 05/27/1999         thee City of Buurien to commply with    0 Channge Orderss
Commpletion: 12/31/20111   FAAA noise exxposure andd safety    Total CChange Ordders Amounnt:
reggulations.                  $0
Significant DDevelopmments                   Budgett/Costs Inccurred
The final of threee phases is completee. All 58 of tthe propertties have
50
beenn acquired and the ressidents reloocated to quuieter neighhborhoods.
40
The apartment building prroperty has been demoolished. Onne
remaining single property was determmined by thhe King Couunty        Millions 30
Superior Court to be comppatible landd use and wwill not be aacquired.      20
Thiss will be thee last quarteerly report ffor this projeect.
Dollars in  10
0
Schhedule
Authorized  F o recasted Costs I ncurred
The project is ccomplete. DDemolition of the remaaining strucctures
begaan during thhe first quarter of 20111. Site resttoration is ccomplete.
Construuction Cossts
Buddget                           Not Appplicable
The project foreecast is witthin the appproved budgget and autthorization.
Savings will bee returned foor this projeect.                       Photo
Chaange Ordder
Not Applicable
Rissks
No ssignificant rrisks identiffied.
Buddget Trannsfers
Nonne this quarter


AIRRPORT
56  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $10,822,000     Insulation Agreement will provide   Delayed Schedule 4Q 10
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      0 Change Orders
Completion: 10/01/2011   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
$0
Significant Developments
Thirteen of the 22 eligible buildings have been sound insulated by    Budget/Costs Incurred
the college.
12
Schedule                             10
Building #9 construction was completed in the first quarter of 2011,     Millions 8
with some remaining punchlist items. The schedules for the           6
remaining buildings are dependent on state funding.                4
Dollars in   2
Budget                             0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
the remaining project budget will be requested for one building at a
time from the Commission in the future when schedule is
determined.                                     Construction Costs
Not Applicable
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed. The Port is working with the College to determine
estimates for the remaining college buildings that have not been
completed.
Budget Transfers
None this quarter.

AIRPORT

Port of Seattle 2Q 2011 Report  57

SECOND QUARTER REPORT, 2011
Home Insulation Retrofit
Project:   C200048      This project includes storm window  Status Snapshot Prior Report
Budget: $5,344,000      retrofit of previously insulated     Delayed Schedule 4Q 10
Phase: Construction     homes.                On Budget
Start: 01/11/2005                                 0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The Port is researching remaining eligible homes to continue with
insulation retrofit and storm window retrofit.                       6
5
Schedule                             4
Two homes are in the process and reviewing list for qualified homes.     Millions 3
2
Budget                             Dollars in 1
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable
Construction Costs
Risks                               Not Applicable
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter




AIRPORT

58  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot Prior Report
Budget: $4,947,395      that are within the 1998 65 decibel  On Schedule
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Sixteen homes are in process of receiving sound insulation; nineteen
6
homes are on the waiting list for the next group.
5
4
Schedule                            Millions
3
This project is currently on schedule.
2
Dollars in   1
Budget
0
The project forecast is within approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable                                     Construction Costs
Not Applicable
Risks
The ability to accomplish the insulation is dependent on
homeowner's schedules, willingness to sign an aviation easement
and obtain a subordination agreement from their lender, and
structural integrity of the home.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2011 Report  59

SECOND QUARTER REPORT, 2011
Street Vacations - Des Moines Creek 1
Project:   C800046    Purchase the City of Des Moines-      Status Snapshot
Budget: $3,850,000   owned streets in the Des Moines Creek  Delayed Schedule
Phase: Implementation Business Park site that are surrounded  On Budget
Start: 10/01/2008      by Port-owned property. This        0 Change Orders
Completion: 12/31/2011 acquisition will enable the Port to     Total Change Orders Amount:
develop the business park site.        $0
Significant Developments                    Budget/Costs Incurred
Closing on the large majority of the streets with the City of Des
3.86
Moines occurred in March 2011. One small parcel must still be
3.84
acquired from the Washington State Department of Transportation
(WSDOT).                                3.82 MillionsDollars in 
3.8
Schedule
3.78
Final acquisition of the WSDOT parcel is expected to be completed
3.76
by December 31, 2011, which is a delay due to a delay in acquisition
Authorized  Forecasted Costs Incurred
approval by WSDOT.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Not applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
60  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
RMU/Kiosk Concession Program
Project:   C800146    The project will provide design and     Status Snapshot Prior Report
Budget: $1,209,000   fabrication of eight Retail         Delayed Schedule 3Q 10
Phase: Construction   Merchandising Units (RMUs); provide   On Budget
Start: 11/20/2007      power, communications, and data to    0 Change Orders
Completion: 06/30/2011 sixteen RMU locations; and install floor-  Total Change Orders Amount:
mounted receptacles for the utilities to    $0
allow easy connection points as well as
flexibility for future utilization.
Budget/Costs Incurred
1.4
Significant Developments
1.2
All RMU utility installations are complete, and considered
Millions  1
substantially complete. The remaining tasks include purchasing and     0.8
installing the RMU kiosk units.                               0.6
Dollars in 0.4
Schedule                             0.2
0
The project is on hold until the prioritization decisions are made by
Authorized  Forecasted Costs Incurred
the Port's Business Development group, related to the procurement
of the RMUs.
Construction Costs
Budget
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 2Q 2011 Report  61

SECOND QUARTER REPORT, 2011
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot Prior Report
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule    2Q 10
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   0 Change Orders
Completion: 12/31/2013   owned properties.           Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The Sunnydale sub-station was purchased from Seattle City Light on
3.5
July 25, 2011. The last anticipated acquisition will be the street
3
vacation of 12th Place S. in Burien, Washington.
Millions 2.52
Schedule                             1.5
It is anticipated that the street vacation will occur in the 2012-2013      Dollars in  1
time frame.                                         0.5
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

62  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Tenant Reimbursement
Status Snapshot
Project:   C800154    Build out of spaces for new and      On Schedule
Budget: $4,709,577    existing tenants. If more than a "basic  On Budget
0 Change Orders
Phase: Construction   finish" condition space is built for the
tenant, the tenant is required to       Total Change Orders Amount:
Start: 08/14/2007
reimburse the Port for the cost of the   $0
Completion: 03/31/2012
work beyond this "basic finish". These
reimbursements are allowed under    Budget/Costs Incurred
the guidelines described in the
"Tenant Reimbursement Policy".        5
4
Significant Developments                     Millions 3
Dollars in 
There were no tenant reimbursements during the second quarter of
2
2011. Delta cancelled their 2011 tenant reimbursement project that
1
was planned for second quarter in the Ticket Lobby. Future tenant
projects will likely be part of the Airline Realignment over the next        0
few years, so this CIP will have limited activity, being limited to            Authorized  Forecasted Costs Incurred
tenants not impacted by the Realignment.
Schedule                           Construction Costs
Schedules vary to meet the tenant's needs.                  Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 2Q 2011 Report  63

SECOND QUARTER REPORT, 2011
Paint Striper Equipment
Project:   C800354      Via a competitive process,       Status Snapshot Prior Report
Budget: $420,000       purchase one Truck Chassis     Delayed Schedule 1Q 11
Phase: Implementation   Mounted Airless Application Paint   On Budget
Start: 09/01/2010         Striping Unit for the Airport. This    0 Change Orders
Completion: 10/31/2011   requested paint striper equipment   Total Change Orders Amount:
is necessary to meet operational,    $0
safety and regulatory requirements.
Budget/Costs Incurred
Significant Developments
The contract has been advertised and bid opening date was in        0.5
March.                                       0.4
Millions 0.3
Schedule
0.2
The equipment is expected to be in service in the third quarter of       Dollars in 0.1
2011.
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

64  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
T-115 Dock Reconstruction
Status Snapshot Prior Report
Project:   C102451      Upgrade three areas of existing    Delayed Schedule 4Q 08
Budget: 31,541,577      1200 ft dock, upgrade Berth 1 and  Forecast Overrun 1Q 08
Phase: Construction     improve 15 acres of uplands for    29 Change Orders
Start: 7/03             tug/barge cargo operations.       Total Change Orders Amount:
Completion: 12/31/09                        $1,748,865
Significant Developments                    Budget/Costs Incurred
As previously reported, construction was completed in 2Q 2010 with    31.6
tenant beneficial occupancy at the end of April 2010. Final contract     31.4
negotiations were completed during 2Q 2011. Project Close out has
31.2  Millions
begun and this will be the final report.
31
Schedule                            30.8 Dollars in 
Authorized  Forecasted Costs Incurred
No change this quarter
Budget                            Construction Costs
No change this quarter
30
Change Order                           20
No change this quarter
10
Millions
Risks                                Dollars in  0
InitialChange OrdersSpent
None
Budget Transfers                         Photo
None
Cost Growth of Construction
No change from prior report, cost growth remains at 17.4 percent.


SEAPORT


Port of Seattle 2Q 2011 Report  65

SECOND QUARTER REPORT, 2011
P66 Bag. Corridor & Pass. Screening
Project:   C800114      Provide baggage and passenger    Status Snapshot Prior Report
Budget: $2,087,000      screening improvements at P66 to  Delayed Schedule 4Q 09
Phase: Construction     accommodate larger cruise vessels  On Budget
Start: 1/1/2008          with 300-400 more passengers per   0 Change Orders
Completion: 6/15/2011    sailing.                Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
CIP Projects are complete.
2.5
2
Schedule
Millions 1.5
None
1
Budget                             Dollars in 0.5
None                                   0
Authorized  Forecasted   Costs
Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None
Budget Transfers
None




SEAPORT

66  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Terminal 18 South Fender Improvements
Status Snapshot Prior Report
Project:   C800121      Replace 800' of deteriorated fender  On Schedule 4Q 10
system at the south end of        On Budget
Budget: $3,300,000
Phase: Design        Terminal 18.             4 Change Orders
Total Change Orders Amount:
Start: 3/26/08                                    $51,000
Completion: 3/31/11
Budget/Costs Incurred
Significant Developments
4
Construction is complete. 800' of the fender system has been
3
replaced by Manson Construction. Beneficial occupancy was given    Millions
on March 31, 2011. This will be the final report.                    2
1
Schedule                            Dollars in 
0
No change from last report. Construction began in December 2010,        Authorized Forecasted Costs Incurred
with berth available for use in March 2011.
Budget                            Construction Costs
Project is within the approved budget. Favorable bids allowed the    None at this time
project to be completed under the authorized amount.
Photo
Change Order
None this quarter
Risks
None this quarter
Budget Transfers
None



SEAPORT

Port of Seattle 2Q 2011 Report  67

SECOND QUARTER REPORT, 2011
T-86 Grain Facility Modernization           Status Snapshot Prior Report
On Schedule
Modernize and replace aging grain   On Budget
Project:   C800133      facility equipment/controls for $5M   1 Change Orders
by 12/31/2011 to maximize       Total Change Orders Amount:
Budget: $2,900,000
operational efficiencies and allow    $33,123.00
Phase: Construction     continuation of uninterrupted grain
Start: 2/21/2010          terminal operations.           Budget/Costs Incurred
Completion: 12/30/2011
4
3
Significant Developments                     Millions 2
Phase-1 - project is complete.                               1
Dollars in   0
Phase-2 - has been advertised and awarded. Equipment Fabrication       Authorized Forecasted Costs Incurred
complete with installation components to accommodate the tenant
2011 shutdown schedule for Q3 2011.
Construction Costs
Schedule
3
Phase-2 - delayed due to tenant revised shutdown schedule. Overall
Project remains on schedule. (Shutdown will occur in Q3 2011).       Millions  2
Dollars in 
Budget                              1
None
0
InitialChange OrdersSpent
Change Order
Phase-1 $33,123                                Photo
Risks
None
Budget Transfers
None


SEAPORT

68  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Seaport Security Grant Round 7
Project:   C800165      Seaport Security Grant Round 7    Status Snapshot
Budget: $2,283,090                         On Schedule 4Q 11
Phase: Construction                        On Budget
Start: March 2007                                0 change Orders
Completion: Dec 2010                        Total Change Orders Amount:
Significant Developments                    Budget/Costs Incurred
Design complete and project out to bid.
2.5
Schedule                             2
Project was delayed during design but construction is expected to      Millions 1.5
start late November or early December and completed in 6 to 8        1
weeks (weather dependent).                            Dollars in 0.5
0
Budget
Authorized  Forecasted Costs Incurred
On budget
Change Order                         Construction Costs
None                                 Not Applicable
Risks
Bids will come in higher than estimated.
Budget Transfers
None




SEAPORT
Port of Seattle 2Q 2011 Report  69

SECOND QUARTER REPORT, 2011
North Harbor Island Mooring Dolphins (4)
Project:   C800182      Replace four barge mooring      Status Snapshot
Budget: $2,350,000      dolphins at the north end of Harbor  On Schedule
Phase: Design        Island.                Under Budget
Start: 07/05/09                                   2 Change Orders
Completion: 3/31/11                         Total Change Orders Amount:
$28,000
Significant Developments                    Budget/Costs Incurred
Construction was completed by Northwest Marine Construction.
2.5
Berths are currently operational. This will be the final report.
2
Schedule                            Millions 1.5
Project completed on schedule within the 2010-11 permit fish          1
window. Beneficial occupancy attained on March 31, 2011.          Dollars in 0.5
0
Authorized  Forecasted Costs Incurred
Budget
Favorable bids indicate the project should complete under the
authorized amount.                                 Construction Costs
None
Change Order
None                                 Location
North Harbor Island
Risks
None                                 Photo
Budget Transfers
None



SEAPORT
70  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
P91 Fender System Upgrade
Project:   C800183      Upgrades to the vessel berths of    Status Snapshot
Budget: $5,700,000      P91 to better accommodate cruise  On Schedule
Phase: Design        ships and also serve the other    On Budget
Start: 01/31/10          industrial customers who utilize the   0 Change Orders
Completion: 04/30/2012   berths and adjacent dock/apron    Total Change Orders Amount:
areas on P91 for less than $6M by   $0
spring 2011.
Budget/Costs Incurred
Significant Developments
Final design is complete, bidding expected Q3 2011.               2.5
2
Schedule                            Millions 1.5 Dollars in 
Phase I construction by Port Construction Services started in
1
January 2011, completed in March 2011. Full replacement is to be
0.5
completed by April 2012.
0
Budget                               Authorized Forecasted Costs Incurred
Project is within approved budget.
Change Order                         Construction Costs
None
None this quarter
Risks
None this quarter
Budget Transfers
None



SEAPORT

Port of Seattle 2Q 2011 Report  71

SECOND QUARTER REPORT, 2011
T-10 Interim Redevelopment
Status Snapshot Prior Report
Project:   C800264      Redevelop site, complete with new  Delayed Schedule 4Q 11
Budget: $7,205,000      stormwater treatment facilities,    On Budget
Phase: Construction     outfall, yard lighting, security fence,  0 Change Orders
Start: 03/22/08          and paving to support terminal     Total Change Orders Amount:
Completion: 12/31/2011   related activities.           0
Budget/Costs Incurred
Significant Developments
8
Building permit received from the City of Seattle. Major construction
6
contract advertised and contract awarded to IMCO General
Construction. Construction contract executed on May 12th and         4  Millions
submittal reviews are underway. Seaport Maintenance is cleaning
up/preparing site for construction. Onsite construction will begin       Dollars in  2
early July.                                                0
Authorized  Forecasted Costs Incurred
Schedule
Construction completion is scheduled for 4Q 2011, unchanged from
Construction Costs
last quarter's report.
8
Budget
6
Low bid tracked well with Engineer's Estimate. Project is on budget.    Millions
4
Change Order
Dollars in    2
None
0
Risks                                   Initial Change Spent
Orders
Potential major unforeseen underground obstructions may be found
at this superfund site and significantly more runoff may occur that
must be treated and discharged to the sanitary sewer system during   Photo
construction. Both could significantly increase construction costs
and lengthen construction schedule.
Budget Transfers
None

SEAPORT

72  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
T-91 Watermain Replacement
Project:   C800298      Replace water main in the vicinity   Status Snapshot Prior Report
Budget: $4,255,000      of Magnolia Bridge and City      On Schedule
Phase: Construction     Ice/Trident including various     On Budget
Start: 9/20/2009          buildings at T91              0 Change Orders
Completion: 12/30/2011                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Construction is in progress.
5
Schedule                             4
On schedule                                    Millions 3
2
Budget                             Dollars in  1
On budget
0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks
4
Contaminated material may be encountered throughout the
excavation process.                                     3
Millions
Budget Transfers                           2
None
Dollars in    1
0
Initial   Change   Spent
Orders

Photo


SEAPORT

Port of Seattle 2Q 2011 Report  73

SECOND QUARTER REPORT, 2011
T-91 Roadway Pavement Project
Project:   C800343                             Status Snapshot Prior Report
Budget: $982,000     Repave two main roadway        Delayed Schedule 2Q 11
Phase: Construction   intersections and the adjacent areas   On Budget
Start: 12/18/09         west of the east guard shack.        0 Change Orders
Completion: 5/1/2011                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Commission approved additional $87,000 construction funding and
1
brought the total project authorization to $982,000. Port
Construction Services completed all work and returned the roadways   0.95
to service prior to the 2011 cruise season. Project is being closed      MillionsDollars in 
0.9
out.
0.85
Schedule
0.8
Construction is complete.
Authorized  Forecasted Costs Incurred
Budget
Project is on budget.                                   Construction Costs
Not Applicable
Change Order
Port Construction Services performed work.                  Photo
Risks
None
Budget Transfers
None



SEAPORT
74  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
T-5 Crane Cable Reels
Status Snapshot Prior Report
Project:   C800349      Purchase Cable Reels for tenant.
Budget: $3,500,000                         Delayed Schedule 4Q 10
Phase: Design                            On Budget
Start: 05/04/10                                   0 Change Orders
Completion: 03/31/11                         Total Change Orders Amount:
0
Significant Developments
Budget/Costs Incurred
The cable reels have been purchased. Delivery of the materials
remains at the end of September 2011.
4
Schedule                             3
Millions
The schedule remains as reported in the 4Q10 report               2
Dollars in                                                                              Budget                                                                     1
None                                   0
Authorized  Forecasted    Costs
Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
Schedule                                   Photo
Budget Transfers
None




SEAPORT

Port of Seattle 2Q 2011 Report  75

SECOND QUARTER REPORT, 2011
T18 Fender Replacement
Project:   C800416      Replacement of 202 timber fender   Status Snapshot
Budget: $5,465,000      piles and their supporting members  On Schedule
Phase: Construction     along the face of the SSA crane    On Budget
Start: 02/07/2010         terminal.                   2 Change Orders
Completion: 03/15/2012                       Total Change Orders Amount:
$16,500
Significant Developments                    Budget/Costs Incurred
First phase of construction is complete. 91 timber fender piles were
7
replaced, and beneficial occupancy obtained for this phase on March     6
31, 2011.                                          5
4
Schedule
Millions
3
Construction scheduled in two phases to accommodate permit       Dollars in  2
1
windows and tenant operations. Resumption of construction of
0
second phase work scheduled to start in December 2011, all work to       Authorized  Forecasted Costs Incurred
be completed by March 2012.
Budget
Construction Costs
Project is within the approved budget.                       None at this time
Change Order                         Photo
None this quarter
Risks
None this quarter
Budget Transfers
None



SEAPORT

76  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
East Marginal Way Grade Separation
Status Snapshot Prior Report
Project:   E102007      FAST Corridor funded project;     Delayed Schedule 2Q 11
Budget: $50,700,000     FHWA, State, City with Port      On Budget 2Q 11
Phase: Construction     commitment of $18,800,000. Scope  36 Change Orders
Start: 5/2006            is to construct grade separation in   Total Change Orders Amount:
Completion: Q4 2011     vicinity of T5 and T18 to minimize   $444,696
truck traffic/rail conflicts.
Budget/Costs Incurred
60
Significant Developments
50
Bridge substructure is complete and the superstructure concrete       Millions 40
decking is at 95% complete. Drainage facilities at 95% complete.       30
20
Schedule                            Dollars in 10
Construction is 85% complete and scheduled completion is           0
September 15, 2011. Schedule may potentially be extended to          Authorized Forecasted  Costs
Incurred
October 31 due to roadway channelization changes. The overall
program schedule remains as was reported in 4Q 09.
Construction Costs
Budget
25
The overall program budget remains the same as reported in 4Q 09.
20
On future reports the budget that will be tracked will be the current
construction costs. The Budget status snapshot is On Budget          15
reflecting the active construction budget.
Millions
10
Dollars in    5
Change Order
0
Thirty six change orders have been executed for a total net amount         Initial Change Spent
of $444,696.                                               Orders
Risks                               Photo
Construction change orders could occur, which could increase cost
of construction.
Budget Transfers
New source of funds indicates that no budget transfers will be
required.

SEAPORT

Port of Seattle 2Q 2011 Report  77

SECOND QUARTER REPORT, 2011
Viaduct Construction Coordination
Project:   E104324,      Participate in the design &       Status Snapshot
E104535-38          construction of the bored tunnel,   On Schedule 2Q 11
Budget: $241,000       north & south portals, Central     On Budget 2Q 11
Phase: Implementation   Waterfront surface streets, and    0 Change Orders
Start: 1/1/2009          related projects to ensure adequate  Total Change Orders Amount:
connection to port facilities.         $0
Completion: 12/31/2018
Budget/Costs Incurred
Significant Developments
Port is negotiating lease agreements with the State to allow          0.28
construction staging for bored tunnel to occur on port facilities at       0.27
T-46 and T-106.                                    0.26  Millions
0.25
Schedule
0.24
Bored tunnel and north and south portal schedules are dependent on   0.23  Dollars in 
environmental review process, expected to end on August 17, 2011.    0.22
Stage 2 of Holgate to King Street construction is ahead of schedule.        Authorized  Forecasted Costs Incurred
Budget
Project is within budget                                 Construction Costs
None
Change Order
Not applicable
Risks
There might be impacts due to construction mitigation and
maintenance of traffic. A nine-day closure of central Viaduct is
scheduled for late October 2011.
Budget Transfers
None

SEAPORT


78  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Street Vacations T5,18,105
Status Snapshot
On Schedule
Project: Capital &     Street vacation related real estate     On Budget
Expense         negotiations and agreements --T5,    0 Change Orders
104362, 104364, 104366 T18, and T105.               Total Change Orders Amount:
Budget: $1,500,000                         $0
Phase: Permitting
Start: June 2010                                 Budget/Costs Incurred
Completion: Feb 2012
2
1.5
Significant Developments                     Millions
1
Moving along in finalizing real estate agreements for T-105 and T-18,
and T-105 package of agreements will be ready for Commission      Dollars in 0.5
approval in the 3rd quarter of this year.
0
Authorized  Forecasted Costs Incurred
Schedule
On Schedule
Construction Costs
Budget                            Not Applicable
On Budget
Photo
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable


SEAPORT

Port of Seattle 2Q 2011 Report  79

SECOND QUARTER REPORT, 2011
T-18 Pile Cap Repair Pilot Project
Project:   E104559      T18 Pile Cap Repair Pilot Project    Status Snapshot
Budget: $50,000                           On Schedule 2Q 11
Phase: Planning                          On Budget 2Q 11
Start: 3/25/11                                    0 Change Orders
Completion: 12/31/12                        Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Project is in design phase and team is incorporating information
gained from a similar project that was completed in 2002 by Port of    0.006
Tacoma.                                  0.005
0.004
Schedule                            Millions
0.003
Project is on schedule for construction in early 2012.              0.002
0.001   Dollars in 
Budget
0
Costs to date are lower than expected due to efficiencies in design         Authorized  Forecasted Costs Incurred
development.
Change Order                         Construction Costs
Not applicable at this stage.                               None
Risks
Risk and opportunity assessment was completed and team is
moving forward with mitigation plan for issues of high probability and
impacts such as containment of concrete during demolition.
Budget Transfers
Not applicable at this stage.


SEAPORT

80  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Underdock Inspections
Project:   E104610-12    Underdock Inspections for T-5,     Status Snapshot
Budget: $1,000,000      T-18 and T-46            On Schedule 2Q 11
Phase: Planning                          On Budget 2Q 11
Start: 1/1/2011                                   0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Inspections complete at T-18 and final report is being developed.
T-46 inspections are complete with exception of underwater diving.     0.8
Schedule                             0.6
Millions
Project is on schedule to complete dock condition assessments by      0.4
the end of 2011.
Dollars in 0.2
Budget                              0
Authorized  Forecasted Costs Incurred
Budget is restricted to $1,000,000 and currently on target to
complete within this amount.
Change Order                         Construction Costs
Not Applicable
Not applicable.
Risks
Cost is only risk. If work cannot be completed within $1,000,000,
scope will be cut to manage accordingly.
Budget Transfers
Budget is shared between four projects 104341 and 104610-104612.



SEAPORT

Port of Seattle 2Q 2011 Report  81

SECOND QUARTER REPORT, 2011
T 102 HVAC Renewal/Replacement
Project:   C800070      Replace HVAC System at all four   Status Snapshot Prior Report
Budget: $1,425,000      buildings at the Harbor Marina    Delayed Schedule 4Q 2010
Phase: Construction     Conference Center          On Budget
Start: 10/2/2005                                  0 Change Orders
Completion: 9/1/2011                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Remaining units were installed in Q1 2011. Punch list items and
1.45
final inspection was completed July 26, 2011. Project will close
1.4
pending final invoice from Contractor
1.35  Millions
Schedule                             1.3
Expect total project completion in Q4 2011.                    1.25  Dollars in 
1.2
Budget                               Authorized Forecasted  Costs
Incurred
Anticipate approximately $65,000 of approved budget to remain after
all invoices are paid.
Construction Costs
Change Order
0.4
None
0.3
Risks
0.2    Millions
None
Dollars in   0.1
Budget Transfers                           0
Initial   Change   Spent
None
Orders



REAL ESTATE

82  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
FT South Wall Reconstruction Phase IV
Project:   C800136      Completion of Fishermen's       Status Snapshot
Budget: $5,535,000      Terminal South Wall         Delayed Schedule
Phase: Construction     Reconstruction. Phase IV is located  On Budget
Start: 6/2009            along parcel currently leased by    1 Change Orders
Completion: 9/2011      FVO.                 Total Change Orders Amount:
$300K
Significant Developments                    Budget/Costs Incurred
Completion of the seawall apron area compaction grouting has been
6
suspended pending the installation of seawall tie backs to prevent
5
any further deflection in the previously installed steel sheet piles.
4
Additionally, the existing project area asphalt pavement will need to     Millions
3
be removed and replaced due to excessive cracking and subsidence
as a result of the compaction grouting performed to date.             2
Dollars in   1
Schedule                             0
Authorized  Forecasted Costs Incurred
Construction is scheduled to be completed by September 2011.
Budget
Construction Costs
None this quarter
5
Change Order
4
Approximately $300,000 for scope addition of sheet pile tie backs.      Millions  3
Risks                                  2
Successful installation of the sheet pile tie backs.                  Dollars in   1
0
Budget Transfers                             Initial Change Spent
Orders
None

Photo


REAL ESTATE

Port of Seattle 2Q 2011 Report  83

SECOND QUARTER REPORT, 2011
FT C15 HVAC Improvements
Status Snapshot
Project:   C800137      Provide the preliminary planning,
Budget: $4,000,000      design, and construction for      Delayed Schedule
Phase: Design        replacing the FT C15 HVAC      On Budget
Start: 05/01/10          System.                   0 Change Orders
Completion: 12/31/2012                       Total Change Orders Amount:
0
Significant Developments
Budget/Costs Incurred
Contract for design services executed.
1
Schedule
0.8
Design behind schedule by 6-8 weeks.                      Millions 0.6
0.4
Budget
Dollars in 0.2
On budget
0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
Contract negotiations took longer than anticipated and schedule
must be adjusted.
Budget Transfers
None




REAL ESTATE
84  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
MIC Central Seawall Replacement
Status Snapshot
Delayed Schedule
Project:   C800175      Replacement of steel sheet pile
On Budget
Budget: $2,650,000      seawall between West Pier and
0 Change Orders
Phase: Construction     Central Pier at Maritime Industrial
Start: 9/2008            Center.                    Total Change Orders Amount:
$0
Completion: 6/2011
Budget/Costs Incurred
Significant Developments
3
Major works construction has been completed. Removal and
replacement of the existing project area asphalt pavement by PCS     Millions 2
will now be required due to the excessive cracking and subsidence
that has occurred as a result of the completed compaction grouting      1
work.                                           Dollars in 
0
Authorized  Forecasted Costs Incurred
Schedule
Construction is scheduled to be complete by August 2011.
Construction Costs
Budget
1.8
None
1.7
Change Order                          Millions 1.6
1.5
None this quarter
1.4
Dollars in   1.3
Risks
InitialChange OrdersSpent
None this quarter
Budget Transfers                        Photo
None this quarter



REAL ESTATE

Port of Seattle 2Q 2011 Report  85

SECOND QUARTER REPORT, 2011
RE Maintenance Shop Solution
Project:   C800187      Marine Maintenance Solution CIP   Status Snapshot
Budget: $2,640,000      facilitates continued operations    On Schedule
Phase: Construction     from the existing shop location by   On Budget
Start: January 2008       funding the following five projects:   0 Change Orders
Completion: Dec 2008    MM Office Expansion; MM North-   Total Change Orders Amount:
end Office; MM Elec Upgrade; MM   0
Roof Replacement; and MM
Kitchen Upgrade.             Budget/Costs Incurred
3
Significant Developments
2.5
The major construction contract for the roof replacement has been
Millions  2
executed.
1.5
1
Schedule                            Dollars in 0.5
The Office Expansion project is complete. The Northend Office is       0
substantially complete. Roof Replacement is expected to be            Authorized Forecasted  Costs
Incurred
complete in November 2011. The Electrical Upgrade and the
Kitchen Upgrade are expected to be complete by the end of Q4
2011.                                       Construction Costs
None
Budget
Commission authorized a $340,000 increase in the CIP budget for a
total authorization of $2,640,000 on June 14, 2011.
Change Order
None
Risks
Unforeseen existing roof conditions and weather may complicate the
roof replacement.
Budget Transfers
None

REAL ESTATE

86  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
FT NW Dock East Fender System Replacement
Project:   C800386      Replace existing timber fender     Status Snapshot
Budget: $3,750,000      system for the east section of the   On Schedule
Phase: Construction     NW Dock at Fishermen's Terminal  On Budget
Start: January 2010       including all new steel piling and    2 Change Orders
Completion: May 2011    associated fender system.       Total Change Orders Amount:
$48,757
Significant Developments                    Budget/Costs Incurred
All contractor work is complete and has been accepted. Project is in
4
close-out phase.
3
Schedule                            MillionsDollars in 
2
Project close-out will be completed approximately October 2011.
1
Budget
0
Total project budget is $3,750,000.                              Authorized  Forecasted Costs Incurred
Change Order
Two project change orders.                            Construction Costs
Risks                                 2.6
2.5
None
Millions  2.4
2.3
Budget Transfers
2.2
None
Dollars in   2.1
2
1.9
Initial   Change   Spent
Orders



REAL ESTATE

Port of Seattle 2Q 2011 Report  87

SECOND QUARTER REPORT, 2011
Flight Information System (FIMS) II
Project: C101117        Procure, develop, and implement a  Status Snapshot
Budget: $5,400,000      FIMS system that includes       On Schedule
Phase:Design         replacement monitors, an airport   On Budget
Start: 5/4/2010           resource management system, and  0 Change Orders
Completion: 12/30/2012    a flexible digital signage system    Total Change Orders Amount:
capable of displaying flight         $0
information, visual paging, and
notifications.
Budget/Costs Incurred
Significant Developments
6
Vendor selected for a replacement resource management system.
5
Evaluating proposals for the replacement flight information display
4
system. Design in progress.
3
in Millions
Schedule                             2
Dollars   1
On Schedule
0
Authorized  Forecasted   Costs
Budget                                       Incurred
On Budget
Construction Costs
Change Order                         Not Applicable in this phase
None
Risks
Aviation Operations resource availability may impact schedule during
implementation of resource management and flight information
display systems.
Budget Transfers
None


CORPORATE

88  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, and add service desk     0 Change Orders
Completion: 12/30/2012   module and wireless handheld    Total Change Orders Amount:
capabilities.                    $0
Significant
Developments                        Budget/Costs Incurred
Major components of the program have been delivered including the
4
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of
3
Marine Maintenance and Aviation Maintenance Maximo systems in
September 2010. The smaller components of mobility enhancements    2
in Millions
and additional interfaces are in progress.
Dollars   1
Schedule                             0
Authorized Forecasted   Costs
Prior Report - Several of the proposed new interfaces link the
Incurred
Maximo system to the Peoplesoft Financials Procurement module.
Because of planned changes in the procurement process with the
Peoplesoft Financials Upgrade project, the delivery of these        Construction Costs
interfaces may be delayed until after the completion of the upgrade   Not Applicable
project. Due to resource constraints, the delivery of the mobility
enhancements will be completed in June 2011.
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces and mobility enhancements.
Budget Transfers
None
CORPORATE
Port of Seattle 2Q 2011 Report  89

SECONDD QUARTER RREPORT, 2011
Airrline Acttivity Maanagemeent
Prooject: C8000222       Deevelopmentt of an airlinne activity   Statuss Snapshott
Buddget: $5000,000       maanagement system thaat       On Schedule
Phaase:Planning        inteegrates witth several PPort      Under Budget
Start: 6/19/20011          sysstems to reeplace agingg reporting   0 Channge Orderss
Commpletion: 5/1/2013     sysstem and supply data for airline   Total CChange Ordders Amounnt:
acttivity fees.                    $0

Budgett/Costs Inccurred
Significant DDevelopmments
0.6
Reqquirements in progresss.
0.5
Schhedule                            0.4
0.3
On SSchedule                                  in Millions
0.2
Dollars 
Buddget                             0.1
0
On BBudget
A uthorized For e casted   Cost s
Incurr e d
Chaange Ordder
Nonne
Construuction Cossts
Rissks                               Not Appplicable
No ssignificant rrisks
Buddget Trannsfers
Nonne




CORRPORATEE

90  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Ground Transportation Management System
Project: C800227        Procure and implement a Ground   Status Snapshot Prior Report
Budget: $840,000       Transportation Management      Delayed Schedule     1Q 11
Phase: Implementation    System for tracking and billing     On Budget
Start: 4/27/2010          ground transportation operators at   0 Change Orders
Completion: 12/15/2011    the airport.               Total Change Orders Amount:
$0
Significant Developments
Software installation and configuration in progress.               Budget/Costs Incurred
Schedule                             1
Prior Report - The system design phase took longer than anticipated    0.8
due to resource constraints and the resolution of system support       0.6
issues. To accommodate this delay and to best align project phases     Millions
0.4
with business operations, the project deployment has been delayed
Dollars in 0.2
6 months to mid-December 2011.
0
Budget                               Authorized Forecasted Costs Incurred
On Budget
Change Order                         Construction Costs
Not Applicable
None
Risks
No significant risks
Budget Transfers
None



CORPORATE

Port of Seattle 2Q 2011 Report  91

SECOND QUARTER REPORT, 2011
Port of Seattle Internet Redesign
Project: C800319        Create a new Internet web site, and  Status Snapshot
Budget: $500,000       underlying infrastructure, with     Delayed Schedule
Phase:Planning        dynamic content and interactive    On Budget
Start: 1/6/2009           communication tools such as blogs,  0 Change Orders
Completion: 12/30/2011    video, podcasts, discussion forums  Total Change Orders Amount:
and interactive maps.           $0
Significant Developments                    Budget/Costs Incurred
New website builds complete. Content migration is in progress.
0.6
Schedule                            0.5
0.4
Resource availability to migrate content as well as additional time
0.3
required to fully test the new site has delayed the implementation to     in Millions
0.2
4th Quarter 2011.
0.1  Dollars 
Prior Report - The delay caused by the need to re-advertise the RFP    0
Authorized Forecasted   Costs
for an implementation vendor will delay the estimated completion to
Incurred
2Q 2011.
Budget                            Construction Costs
Not Applicable
On Budget
Change Order
None
Risks
Significant amount work will be required to clean up the website
content from the previous site. Individuals across the Port are
working on this effort but it may require additional time to complete.
Budget Transfers
None

CORPORATE

92  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot Prior Report
Budget: $1,525,000      costing systems with a common    Delayed Schedule
Phase:Implementation    enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: 9/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Installation of the software in the Port environment has been
completed. Final configuration and interface development in           2
progress.
1.5
Schedule
Millions  1
Prior Report - Vendor did not deliver software per original contract
and project was put on-hold to evaluate alternatives. A decision was    Dollars in 0.5
made to continue with Skire in July 2010. The estimated completion      0
date at this time is September 2011 although there may be interim         Authorized  Forecasted Costs Incurred
deliveries prior to completion.
Budget                            Construction Costs
None                                 Not Applicable
Change Order
None
Risks
See Schedule
Budget Transfers
None



CORPORATE
Port of Seattle 2Q 2011 Report  93

SECOND QUARTER REPORT, 2011
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot Prior Report
Budget: $800,000       increase functionality, and lower   Delayed Schedule    4Q 10
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 4/30/2012    records and document        Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
Sharepoint 2010 Upgrade has been completed. Design and
implementation of Sharepoint 2010 Records Center in progress.
1
Schedule                            0.8
Prior Report: Sharepoint 2010 implementation is dependent on the     0.6 Millions
completion of several infrastructure projects currently in progress      0.4
and requires additional time to complete the upgrade of existing
0.2  Dollars in 
sites. While Sharepoint 2010 will be available to departments
0
beginning in April 2011, the implementation of Sharepoint Records
Authorized Forecasted   Costs
Center will not be complete until December 2011. The full project is                  Incurred
estimated to be completed in April 2012.
Budget                            Construction Costs
Not Applicable
On Budget
Change Order
None
Risks
Scope of Sharepoint 2010 upgrade may require additional funding to
complete migration activities.
Budget Transfers
None

CORPORATE

94  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Business Continuity
Project: C800326        Acquire new backup and storage   Status Snapshot Prior Report
Budget: $1,760,000      software and hardware that will    Delayed Schedule     1Q 11
Phase:Implementation    facilitate business continuity in the  On Budget
Start: 6/23/2009          event of a disaster            0 Change Orders
Completion: 10/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Completed installation and data migration to the new High Capacity   Budget/Costs Incurred
Network Storage System. Delivery of remaining components on
schedule to complete project.                              1.8
1.75
Schedule                             1.7
1.65
Prior Report - A small number of remaining components are
in Millions 1.6
dependent on the design of another project. This will delay the final     1.55  Dollars 
delivery of this project until October 2011.                        1.5
1.45
Prior Report - Insufficient power in the data center required              Authorized  Forecasted Costs Incurred
unplanned infrastructure upgrades for the new High Capacity
Realtime Storage Device. The new device is estimated to be online
in October 2010 and final project completion is estimated in April     Construction Costs
2011, a 6 month delay from the original schedule.               Not Applicable
Budget
On Budget
Change Order
None
Risks
No significant risks
Budget Transfers
None

CORPORATE

Port of Seattle 2Q 2011 Report  95

SECONDD QUARTER RREPORT, 2011
Proopworkss Upgradde
Prooject: C8000328       Uppgrade the pproperty maanagementt  Statuss Snapshott
Buddget: $4500,000       sysstem, Propwworks, used by      On Schedule
Phaase: Impleementationn    Avviation Propperties and Real Estatee  On Budget
Start: 3/1/2011           orgganizationss.               0 Channge Orderss
Commpletion: 7/30/20122                         Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Aviaation implemmentation inn progress. Real Estatte/Seaport upgrade    Budgett/Costs Inccurred
will ffollow.
0.5
Schhedule                            0.4
On SSchedule                                  0.3
0.2  in Millions
Buddget
0.1  Dollars 
On BBudget
0
A u thorized Foreca s ted  Costs
Chaange Ordder                                   Incurred
Nonne
Construuction Cossts
Rissks
Not Appplicable
No ssignificant rrisks
Buddget Trannsfers
Nonne




CORPORATTE

96  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Time Clock System
Project:C800387        Procure and implement a Time    Status Snapshot
Budget:$840,000       Clock System to accurately capture  On Schedule
Phase:Planning        and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion:7/30/2012     Aviation Security and Airport      Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
System configuration and interface development in progress
0.4
Schedule                            0.3
On Schedule
0.2
in Millions
Budget                             0.1 Dollars 
On Budget
0
Authorized Forecasted   Costs
Change Order                                   Incurred
None
Construction Costs
Risks                               Not Applicable
No significant risks at this time.
Budget Transfers
None




CORPORATE

Port of Seattle 2Q 2011 Report  97

SECOND QUARTER REPORT, 2011
Peoplesoft Financials Upgrade
Project:C800392        Upgrade of Peoplesoft Financials   Status Snapshot
Budget:$5,000,000       hardware and software        Delayed Schedule
Phase:Planning                            On Budget
Start: 9/28/2010                                 0 Change Orders
Completion:12/31/2013                        Total Change Orders Amount:
$0
Significant Developments
An implementation vendor was selected via a competitive         Budget/Costs Incurred
procurement but we were unsuccessful in negotiating an acceptable
6
contract.
5
4
Schedule
3
Because of resource constraints during the year-end process, the      in Millions
2
next optimum window of opportunity for the upgrade begins in mid-     Dollars  1
2012. This will delay the project one year. In the interim, steps are
0
being taken to minimize risk to the overall project and resolve
Authorized  Forecasted Costs Incurred
procurement issues.
Budget
Construction Costs
On Budget                                  Not Applicable
Change Order
None
Risks
Significant resources will be required across multiple organizations
which may delay other technology projects.
Budget Transfers
None


CORPORATE

98  Port of Seattle 2Q 2011 Report

SECOND QUARTER REPORT, 2011
Police Records Management System
Project: C800393        Procure and implement a       Status Snapshot
Budget: $1,300,000      replacement Police Records      On Schedule
Phase:Planning        Management System         On Budget
Start: 10/10/2010                                0 Change Orders
Completion: 1/31/2012                         Total Change Orders Amount:
$0

Budget/Costs Incurred
Significant Developments
1.4
Negotiating contract with selected vendor.
1.2
1
Schedule                             0.8
On Schedule                                  in Millions 0.6
Dollars 0.4
0.2
Budget
0
On Budget                                      Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable in the phase
Risks
No significant risks identified at this time
Budget Transfers
None




CORPORATE

Port of Seattle 2Q 2011 Report  99

SECOND QUARTER REPORT, 2011
Upgrade to Windows 7 and Office 2010
Project: C800395        Upgrade Port workstations to     Status Snapshot
Budget: $500,000       Windows 7 and Microsoft Office    On Schedule
Phase: Implementation    2010.                 On Budget
Start: 9/17/2010                                 0 Change Orders
Completion: 9/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Upgrade of Port workstations in progress.                    Budget/Costs Incurred
Schedule                            0.6
0.5
On Schedule
0.4
Budget                             0.3
in Millions
0.2
On Budget
0.1  Dollars 
Change Order                          0
Authorized Forecasted  Costs
None                                            Incurred
Risks
Construction Costs
Due to aging, incompatible software still required on some         Not Applicable
workstations, not all assets will be updated at the close of the
project. As the application issues are resolved, the associated assets
will be upgraded.
Budget Transfers
None



CORPORATE

100  Port of Seattle 2Q 2011 Report

SECONDD QUARTER RREPORT, 2011
Port Contrractor Rooster & Bid Mannagement
Prooject: C8000397      Develoop and impplement a siingle Port   Statuss Snapshott Prior Reporrt
Buddget: $4500,000     Roster & Bid Sysstem that reeplaces the  Delayeed Schedulee     4Q 10
Phaase: Closee Out     functioonality of thhree rosterss, supports   On Budget
Start: 1/26/20010        new CCentral Proccurement OOffice      0 Channge Orderss
Commpletion: 5/30/2011  processses , and ssimplifies thhe process  Total CChange Ordders Amounnt:
for Port vendors.                  $0
Significant DDevelopmments
Budgett/Costs Inccurred
Neww system deeployed andd in-use by external veendors.
Schhedule                            0.5
0.4
Prior Report: SSeveral channges were suggested during the testing
0.3
phasse that will require an additional 33 months too complete,, test, and
0.2
deplloy.                                              Millions
0.1
Dollars in 0
Buddget                              Aut t horized Foreca s ted Costs
Incurred
On BBudget
Chaange Ordder                         Construuction Cossts
Nonne                                 Not Appplicable
Rissks
No ssignificant rrisks
Buddget Trannsfers
Nonne




CORPORATTE
Port of Seattle 2Q 2011 Report  101

SECONDD QUARTER RREPORT, 2011
CUUSE Migrration
Prooject: C8000481       Miggrate the AAirport Common-Use   Statuss Snapshott
Buddget: $4855,000       Paassenger Prrocessing SSystem,    On Schedule
Phaase:Planning        CUUSE, from aa virtual to aa physical   Under Budget
Start: 6/19/20011          based infrastrructure           0 Channge Orderss
Commpletion: 2/29/20122                         Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Archhitecture deesign in progress.                           Budgett/Costs Inccurred
Schhedule                             0.6
0.5
On SSchedule
Millions 0.4
Buddget                             0.3
0.2
On BBudget                                  Dollars in 0.1
Chaange Ordder                           0
Authorized  F o recasted Costs I ncurred
Nonne
Rissks
No ssignificant rrisks                                      Construuction Cossts
Not Appplicable
Buddget Trannsfers
Nonne





CORPORATTE

102  Port of Seattle 2Q 2011 Report

SECONDD QUARTER RREPORT, 2011
Maaintenance Planning Sooftware
Prooject: C8000501       Proocure and iimplement        Statuss Snapshott
Buddget: $4022,000       Maaintenance Planning aand      On Schedule
Phaase:Planning        Sccheduling sooftware thaat integratess  Under Budget
Start: 6/26/20011          witth our Asseet Managemment       0 Channge Orderss
Commpletion: 5/30/20122    sysstem, Maximo.            Total CChange Ordders Amounnt:
$0
Significant DDevelopmments
Vendor has been selectedd via a commpetitive proocess.            Budgett/Costs Inccurred
Schhedule                            0.5
On SSchedule                                  0.4
0.3
Buddget
in Millions0.2
On BBudget                                  Dollars 0.1
Chaange Ordder                          0
A uthorized Fore c asted  Costs
Nonne                                              Incurre d
Rissks
No ssignificant rrisks                                      Construuction Cossts
Not Appplicable
Buddget Trannsfers
Nonne





CORRPORATEE
Port of Seattle 2Q 2011 Report  103

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.