7a supp

Item No: ________7a_supp___________ 
Date of Meeting: __August 23, 2011__ 
RCF Construction 
August 1, 2011 





July 1, 2011

RCF Construction 

RCF Employee Parking Light Poles and Traffic            RCF QTA #1 Fuel Dispensing Equipment 
Coating 





CNG Equipment Racks  Foreground 
BMF Building  Background 
SR 99 Bridge Sidewalk and Guardrail Demolition        2

Rental Car Facility Program 
Contract - Status Summary 

Base Contract       Revised         Additional Costs *          Unallocated       Billed to date
Amount                                        Balance       (as of July, 2011) 
In review **   Executed 
Consolidated Rental Car Facility 
Total Construction Costs  $224,837,739     $211,421,525        $315,412 $207,233,622         $3,872,491         $204,390,465 
Construction Contingency Summary 
Non Suspension Contract Changes    $5,953,159      $17,031,082      $13,688,321  $11,330,664       ($7,987,903)          $8,183,469 
Suspension Related Contract Changes                $16,800,000         89,202   $8,640,600        $8,070,198          $8,648,096 
$3,954,786 
Off Site Roads 

Construction Contract Amount    $7,627,485                            $7,627,485             $0          $4,935,261 
Construction Contingency    $1,087,000     $2,707,000        $485,513.40 $2,020,727.55         200,762.50           $1,483,583 

Bus Maintenance Facility 
Construction Contract Amount   $13,086,444                           $13,139,159             $0          $3,992,439 
Construction Contingency    $1,611,000                     $113,891     $52,715         $1,444,394            $10,192

NOTE: * updated as of August 11, 2011 
** includes costs in dispute for entitlement or quantum 
3

RCF GC/CM Project Construction Contingency Trending to Date 
$40,000,000

$35,000,000

$30,000,000

$25,000,000

$20,000,000

$15,000,000

$10,000,000

$5,000,000

$0


Construction Contingency Budget                        Executed Suspension + Non-Suspension Change Orders
Suspension Change Orders                           Total Executed Change Orders + In Review

RCF Program Construction Contingency Trending to Date Summary 
(RCF, ORI and BMF) 
$45,000,000
$40,000,000
$35,000,000
$30,000,000
$25,000,000
$20,000,000
$15,000,000
$10,000,000
$5,000,000
$-

Construction Contingency Budget       Executed Change Orders       Total Executed Change Order + In Review

Consolidated Rental Car Facility 
Program Costs as of 8/16/2011 
Project       6/30/09     2/2/10        Approved   Pending     Remaining   Expended to  Forecast to
Budget     Authorization   Transfers/  Transfers/    Contingency  Date       complete 
Trends     Trends 
RCF        $350,772,000   $350,772,000  $20,301,264   $13,777,523    $3,954,786   $301,651,702   $351,102,000 
BMF       $28,282,000   $28,282,000  ($1,847,285)    $113,891   $1,444,394   $8,449,615   $26,382,000 
ORI         $19,542,000    $19,542,000  ($1,208,273)     $485,513     $200,760   $10,541,994    $17,853,000 
MTI        $3,383,000    $3,383,000   ($675,000)        $0    $159,000    $385,869    $2,708,000 
Buses       $17,327,000    $16,000,000  ($4,911,269)        $0    $219,897    $134,643   $12,415,731 
Unallocated
$0            $0   $8,765,269                  $8,765,269           $0           $0 
Contingency 
Total       $419,306,000   $417,979,000  $20,424,706   $14,376,927   $14,744,106  $321,163,823  $410,460,731

6

SEATTLE-TACOMA INTERNATIONAL AIRPORT
CFC REVENUE FORECAST TO ACTUAL COMPARISON
JUN YTD 2011

$147.5 
CUMULATNE CFC REVENUES       )'
AS or SEP 2012           I
.
$142.5                                                                                      RIGONBOFEASIBIEWN
$146.6 M          x

$137.5 

$132.5 

$127.5 
MILLIONS  $122.5 
$117.5 
IN
REVENUES$112.5 $107.5 
CFC  $102.5  '
$97.5 

$92.5 

$87.5 

$82.5 
'Jan1o Feb10 Mano Apno'Mayio Jun10' Juno'Augw Sep10 Oct10 Nov10 Dec10 Jan11 Feb11Mar11 Apr11 May11 Jm11 m1 Aug111Sep11 0cm Nov11Dec11jJa'r121Feb12 W12 Apr121May12.Jun12 Ju|12 Aug12 Sep12
-01- FORECAST 83.6  84.9. 862  87.7113  91.2  93.4  96.1  99.0  101.3 103.3 104.8 1062 107.6 108.9 110.4 112.0 113.9 116.1 118811216 124.0 126.0 127.5 129111306 132.0 133811357337] 140.2 143.3'1466
IACTUALS  83.7  84.6  86.6  882  89.9  912  93.9  96.4  98.7 101.8 103.9 105.5 107.0 108.5 110.0 111.6 113.3 116.0       1                1         1
'               '

Notes:
The forecast is from the Ricondo Feasibility Analysis which was the basis for the RCF bond issuance                                                                 7 7
No interest proceeds are reected in actuals shown above

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.