7a supp
Item No: ___________7a_supp________ Date of Meeting: __July 26, 2011__ RCF Construction July 1, 2011 June 3, 2011 RCF Construction RCF South Slope Landscaping RCF Striping of West Drive Lanes Level 4 BMF Bldg. Structural Steel & Joist Erection ORI: Light Pole Foundation Augering at SR 518 2 Rental Car Facility Program Contract - Status Summary Base Contract Revised Additional Costs * Unallocated Billed to date Amount Balance (as of May.2011) In review ** Executed Consolidated Rental Car Facility Total Construction Costs $224,837,739 $211,421,525 $1,506,948 $203,131,319 $6,783,258 $209,004,666 Construction Contingency Summary Non Suspension Contract Changes $5,953,159 $17,031,082 $13,605,923 $10,613,544 ($7,188,385) $7,795,523 Suspension Related Contract Changes $16,800,000 89,202 $8,640,600 $8,070,198 $8,644,612 $7,665,135 Off Site Roads Construction Contract Amount $7,627,485 $7,627,485 $0 $4,323,305 Construction Contingency $1,087,000 $2,707,000 $381,370 $1,830,637 495,093 $1,322,796 Bus Maintenance Facility Construction Contract Amount $13,086,444 $13,096,444 $0 $2,903,864 Construction Contingency $1,611,000 $131,739 $34,287 $1,444,974 $3,949,293 NOTE: * updated as of July 12, 2011 ** includes costs in dispute for entitlement or quantum 3 RCF GC/CM Project Construction Contingency Trending to Date $40,000,000 $35,000,000 $30,000,000 $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 $0 Construction Contingency Budget Executed Suspension + Non-Suspension Change Orders Suspension Change Orders Total Executed Change Orders + In Review 4 RCF Program Construction Contingency Trending to Date (RCF, ORI and BMF) $45,000,000 $40,000,000 $35,000,000 $30,000,000 $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 $- Construction Contingency Budget Executed Change Orders Total Executed Change Order + In Review 5 Consolidated Rental Car Facility Program Costs as of 7/18/2011 Project 6/30/09 2/2/10 Approved Pending Remaining Expended to Forecast to Budget Authorization Transfers/ Transfers/ Contingency Date complete Trends Trends RCF $350,772,000 $350,772,000 $19,584,144 $13,695,125 $7,665,071 $297,727,539 $351,102,000 BMF $28,282,000 $28,282,000 ($1,890,000) $176,736 $1,424,264 $7,238,133 $26,382,000 ORI $19,542,000 $19,542,000 ($1,398,363) $381,370 $494,993 $10,288,610 $17,853,000 MTI $3,383,000 $3,383,000 $0 ($675,000) $159,000 $60,030 $2,708,000 Buses $17,327,000 $16,000,000 ($4,911,269) $0 $219,897 $133,958 $12,415,731 Unallocated $0 $0 $8,090,269 $675,000 $8,765,269 $0 $0 Contingency Total $419,306,000 $417,979,000 $19,474,781 $14,253,231 $18,728,494 $315,448,270 $410,460,731 6 SEATTLE-TACOMA INTERNATIONAL AIRPORT CFC REVENUE FORECAST TO ACTUAL COMPARISON MAY YTD 2011 $147.5 CUMULATIVE CFC REVENUES '3' AS OF SEP 2012 ' X $142.5 RICONDO FEASIBILITY ANALYSIS $146.6 M I $137.5 $132.5 $127.5 MILLIONS $122.5 IN $117.5 REVENUES $112.5 $107.5 CFC $102.5 $97.5 $92.5 $87.5 $82.5 Jan10 Feb10 Mar10 Apr10 May 10 Jun10 Ju|10 Aug10 Sep10 Oct10 Nov10 Doc 10 Jan" Feb'It Mar11 Apr11 May11 Jun11 Jul" Aug" Sop11 Oct11 Nov11 D0011 Jan12 Fcb12 Mar12 Apr12 May12 Jun12 Ju|12 Aug12 Scp12 i I ' ' ' ' ' I ' ' ' ' ' ' ' . ' ' ' ' -"- FORECAsT' 83.6 84.9 862 87.7 893 91.2 93.4 961 99.0 '1013' 103.3 104.8 1062 107.6 1089 1104' 1120 113.9. 1161 116.8 121.6 1240' 1260 1275 1291 130.6 132.0 133.8 1357 137.7 1402' 143.3 1466 -IScncs2 837 84.6 866 88.2 699 912 939 964 98.7 1018 103.9 1055 1070 108.5 1100 111.6 11327 Notes: The forecast is from the Ricondo Feasibility Analysis which wasthe basis forthe RCF bond issuance 7 7 No interest proceeds are reected in actuals shown above
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.