5i

PORT OF SEATTLE 
MEMORANDUM 

COMMISSION AGENDA           Item No.:        5i 
ACTION ITEM 
Date of Meeting:        June 14, 2011 
DATE:    June 6, 2011 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:    Peter Garlock, Chief Information Officer 
SUBJECT:  Maintenance Planning and Scheduling Software Project 

Amount of This Request:  $402,000   Source of Funds:  Airport Development Fund 67%
General Fund 33% 
State and Local Taxes Paid:  $16,000 
Total Project Cost:  $402,000 
ACTION REQUESTED: 
Request authorization for the Chief Executive Officer to approve all work and contracts, 
including executing and amending any and all necessary contracts and service directives for the
Maintenance Planning and Scheduling Software Project in an amount not to exceed $402,000.
An estimated annual increase of $25,000 will be included in the Information and
Communications Technology (ICT) operating budget for software license and maintenance
agreements. 
SYNOPSIS: 
The Maintenance organizations in the Aviation and Real Estate divisions both strive to meet an
industry best practice goal of keeping preventive maintenance at 80% of the total maintenance
actions performed on Port facilities and assets, which helps prolong the life of these investments. 
Planning and scheduling preventive maintenance is a challenging undertaking when performed
using manual methods. This project will competitively procure and implement an automated
maintenance planning and scheduling software system that integrates with the Port's asset
management system, Maximo. 
Maintenance Planning and Scheduling software can automate preventive maintenance workload
scheduling and reduce manual efforts by as much as 15%. 
This project was approved by the Information & Communication Technology (ICT) Governance
Board on April 6, 2011.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 6, 2011 
Page 2 of 4 
BACKGROUND: 
The Aviation Maintenance Work Management function was created in 2006 as part of an 
ongoing continuous process improvement effort to align the maintenance department with
industry best practices for facilities maintenance. The Marine Maintenance organization
followed with a similar effort in 2008. Across both organizations, seven Maintenance Planners
now actively plan and schedule crew work. 
An effective maintenance work plan involves several components, including long-range
planning, scheduling and communication of shutdown or outages, establishing weekly preventive
maintenance schedules and daily work plans. Each week, planners in both organizations team up
with foremen or crew chiefs to evaluate and prioritize work, coordinate resources, and schedule
tasks. For Aviation Maintenance, this manual, time-intensive effort is estimated to consume
nearly 40% of a Foreman's time each week. 
PROJECT JUSTIFICATION: 
The estimated 15% reduction in manual effort to automate preventive maintenance workload
scheduling using Maintenance Planning and Scheduling software will allow the maintenance
organizations to focus more on maintenance management and unscheduled outages. Other
benefits include the following: 
Foremen and Crew Chiefs are able to spend more time on training, supervising, and
quality control. 
Better communication with tenants and internal business partners on work order progress. 
Adjustments to the schedule and notifications can occur more quickly. 
Alternative plans and "what if" scenarios can be easily evaluated. 
PROJECT STATEMENT AND OBJECTIVES: 
Project Statement: 
Purchase an automated maintenance workload scheduling and planning software tool through a
competitive procurement process and integrate it with our existing asset management software,
Maximo. 
Project Objectives: 
Improve efficiency of maintenance planning to help achieve a preventive maintenance goal
of 80% of total maintenance actions. 
Improve communication of maintenance schedules to tenants and internal business partners. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
The scope of work includes the competitive procurement, implementation, testing, and training
of maintenance planning and scheduling software that integrates with the Port of Seattle asset

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 6, 2011 
Page 3 of 4 
management system, Maximo. The system will be used by the Aviation Maintenance and Marine
Maintenance organizations. 
Schedule: 
Commission Approval                                 May 2011 
Procurement Complete                              September 2011 
Implementation Complete                                 July 2012 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary: 
Original Budget                                         $402,000 
Budget Increase                                              $0 
Revised Budget                                            $0 
Previous Authorizations this CIP                                    $0 
Current request for authorization                                 $402,000 
Total Authorizations, including this request                          $402,000 
Remaining budget to be authorized                                  $0 
Project Cost Breakdown: 
Port of Seattle Labor or Contracted Services                         $140,000 
Software License                                        $170,000 
Vendor Services                                         $15,000 
Sales tax                                                   $16,000 
Contingency  20%                                     $61,000 
Total                                                    $402,000 
Budget Status and Source of Funds: 
Project costs are estimated to be $402,000. This project was originally budgeted as an aviation
small capital project for Aviation Maintenance only. Marine Maintenance has now joined the
project increasing both the project scope and required budget. Upon Commission Authorization,
the $402,000 project budget will be transferred from the Services Technology Small Capital CIP
# C800012 into a new CIP. 
Financial Analysis and Summary: 
CIP Category                     Renewal/Enhancement 
Project Type                       Technology 
Risk adjusted Discount rate             7% 
Key risk factors                      N/A 
Project cost for analysis                 $402,000

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 6, 2011 
Page 4 of 4 
Business Unit (BU)                  AV Maintenance/Marine Maintenance 
Effect on business performance          N/A 
5 Year NPV                    N/A 
CPE Impact                     Included in business plan forecast 
Lifecycle Cost and Savings: 
An annual increase of $25,000 is estimated for software license and maintenance agreements and
will be included in the ICT operating budget. 
ECONOMIC IMPACTS AND BUSINESS PLAN OBJECTIVES:
Proceeding with this project is essential to achieve Aviation and Marine Maintenance business
goals of 80% preventive maintenance and 20% repair maintenance. 
STRATEGIC OBJECTIVES: 
This project supports the following Port's strategic objectives: 
Ensure Airport and Seaport vitality by ensuring effective utilization of our resources and that
systems are operating efficiently and safely. 
Be a "high performance organization" by striving for industry best practices and comparing 
measures of our own performance to those of other leading institutions. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
The following alternatives were considered. 
1.  Procure and implement Maintenance Planning and Scheduling Software: The
implementation of Maintenance Planning and Scheduling software that integrates with
our asset management system, Maximo, will increase efficiency necessary to achieve
business goals for preventive maintenance. This is the recommended alternative. 
2.  Continue with manual planning and scheduling processes: The amount of time required
to manually complete planning and scheduling activities is an inefficient use of
management time and will prevent the achievement of business goals for preventive 
maintenance. This is not the recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None 
PREVIOUS COMMISSION ACTION OR BRIEFING: 
None

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.