7a Supp
Item No: 7a_Supp Date: March 8, 2011 Capital Improvement Projects Fourth Quarter Report 2010 Commission Briefing 1 Capital Improvement Projects Overall Status of Projects 85 Total Projects in report 45 Projects that are within or ahead of target schedule and budget 39 Projects that have either target schedule or budget off 1 Project has both schedule and budget off 2 Capital Development Division Aviation Projects Capital Improvement Projects Fourth Quarter Report 2010 3 Aviation Project Overall Status 27 projects are within target budget and schedule 23 projects are either over budget or have delayed schedule 4 Aviation Quarterly Variance Update includes 50 projects 43 of the projects have no reportable variances for this quarter 2 projects with favorable variances (budget and/or schedule) 5 projects with reportable variances (projected late completion and/or forecast overruns) 5 Projects with Favorable Variances Consolidated Warehouse Under Budget The project returned a savings of approximately $63,000 and is anticipating returning additional savings after closeout. The final invoice was submitted but has not been paid due to incomplete as-built drawings. Alaska Air 2 Step Ticket Counter Under Budget The Port has reached a final agreement with Alaska Airlines to reconcile the reimbursable amount. $1.5 million was received from Alaska. The project will return over $6.8 million from the project at final closeout. 6 Projects with Reportable Variances Loading Bridge Utilities Forecast Overrun The scope of this project has been increased to include two additional gates (B-1 and B-5), and to increase the number of 400 Hz generators from two to three at the South Satellite to service 787s in the future. The project will have to be redesigned to include the new scope. Connect C1 BHS to C88 BHS Schedule Delay The scope of this project has been increase, per Alaska Airlines request, to add computer programming upgrades to the baggage handling computers. This will delay the project completion date by two months. South Satelite Delta Sky Club Extension Schedule Delay The tenant's delayed decision on the increased size of the club has pushed Delta's substantial completion out by two months. . 7 Construction Contract Growth that Exceeds 10% No new reportable projects. 8 Capital Development Division Seaport Projects Capital Improvement Projects Fourth Quarter Report 2010 9 Seaport Project Overall Status 12 Projects are within or ahead of target budget and schedule 5 Projects have either target schedule or budget off 1 Project has both target schedule and budget off 10 Seaport Quarterly Variance Update includes 18 projects There are no new reportable variances for either budget or schedule 11 Construction Contract Growth that Exceeds 10% No new reportable projects 12 Capital Development Division Real Estate Projects Capital Improvement Projects Fourth Quarter Report 2010 13 Real Estate Project Overall Status 3 Projects are within or ahead of target budget and schedule 2 Projects have either target schedule or budget off 14 Real Estate Quarterly Variance Update includes 5 projects There are no new reportable variances for either budget or schedule 15 Construction Contract Growth that Exceeds 10% No Real Estate projects exceed 10% in construction change orders 16 Project Status Total CIPs Managed by CDD 100% 90% 80% Project Distribution per Quarter 70% 60% 50% 40% 30% 20% 10% 0% 4Q09 Report 1Q10 Report 2Q10 Report 3Q10 Report 4Q10 Report Both Schedule and Budget off 2 2 3 1 1 Either Budget or Schedule off 30 27 27 28 30 On Schedule/On Budget 37 39 43 45 42 17 Corporate Division Projects Information and Communications Technology Capital Projects Fourth Quarter Report 2010 1818 Corporate Overall Status 5 projects are within target budget and schedule 1 project is under budget and behind schedule 6 projects are behind schedule but within budget 1919 ICT Quarterly Variance Update includes 12 projects 2 projects have a reportable variance for this quarter 10 projects have no reportable variances for this quarter 20 Projects with Reportable Schedule Variance Sharepoint Records and Document Management Sharepoint 2010 implementation is dependent on the completion of several infrastructure projects currently in progress and requires additional time to complete the upgrade of existing sites. While Sharepoint 2010 will be available to departments beginning in April 2011, the implementation of Sharepoint Records Center will not be complete until December 2011. The full project is estimated to be completed in April 2012. Port Contractor Roster and Bid Management Several changes were suggested during the testing phase that will require an additional 3 months to complete, test, and deploy. 21 Construction Contract Growth that Exceeds 10% No ICT projects exceed 10% in construction change orders 22
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.