7a Report

Item Number: 7a_Report
Meeting Date: March 8, 2011


Commission Staff Brieng
Capital Improvement Projects
Fourth Quarter Report 2010

This page intentionally left blank









ii  Port of Seattle 4Q 2010 Report

Port of Seattle
Capital Improvement Project Report
Fourth Quarter 2010
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the statue of the Port's capital projects.
Background
During 2010 the Port plans to invest over $329,000,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 4Q 2010 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................5 ........... 
C100266 et al .......Rental Car Facility ............................................... 6-7.......... ...............
C102030 ...............Stormwater Management Program .......................8 ........... ................................................................................
C102038 ...............Apron Pavement Rehabilitation 3 ........................9 ........... .............................. 
C102163................Main Terminal Baggage Screening ................... 10-11 ........ ...................................
C102334 ...............Water System Isolation Valve Upgrade ................12 ..........
C102573 ...............Aireld Pavement Replacement ...........................13 ..........
C102744................2nd Floor Tenant Improvements ...........................14 .......... ...............
C800019 ...............Loading Bridge Utilities .........................................15 .......... ............... ...................................... 
C800034 ...............North Expressway Relocation ..............................16 .......... ...............
C800036 ...............Parking Garage 4th Floor Improvements .............17 ..........
C800042 ...............Aircraft Rescue Fire Fighting Station Upgrade ....18 .......... ...............
C800061 ...............Main Terminal South Low Voltage ........................19 .......... ...............
C800071 ...............Consolidated Warehouse .....................................20 .......... ............... ...................................... 
C800095 ...............Alaska Air 2 Step Ticket Counter..........................21 .......... ............... ...................................... 
C800105 ...............Airport Owned Gate Infrastructure .......................22 ..........
C800107 ...............C4 UPS System Improvements ............................23 .......... ...............
C800109 ...............Garage Escalator & "A" Elevator Upgrade ...........24 .......... ...............
C800112................Runway 16C/34C Panel/Joint Sealant .................25 .......... ...............
C800144 ...............Security CCTV System Improvements.................26 .......... ...............
C800146 ...............RMU/Kiosk Concession Program ........................27 .......... ..............................  ........................................
C800147 ...............Concessions Unit Readiness Program ................28 .......... ...............
C800148 ...............GML Arrivals Hall Concessions ...........................29 .......... ...............
C800167 ...............Runway 16L/34R Reconstruction.........................30 .......... .................................. ............................................
C800170 ...............Connect C1 BHS to C88 BHS ..............................31 .......... ..............................
C800174................FIS - New Primary Inspection Booths ..................32 ..........
C800237 ...............Terminal Escalators Modernization ......................33 .......... ...............
C800238 ...............Central Plant Pre-Conditioned Air ........................34 .......... ...............
C800253 ...............Parking System Replacement ..............................35 .......... .............................. 
C800254 ...............Aircraft RON Parking Post Ofce Site..................36 ..........
C800274 ...............8th Floor Weather Proong ..................................37 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......38 ..........
C800335 ...............EGSE Electrical Charging Stations ......................39 ..........
C800336 ...............South Satelite Delta Sky Club Extension .............40 .......... ..............................
C800360 ...............Roof Replacement Program .................................41 ..........
C800406 ...............RW 16C/34C Reconstruction Design ...................42 ..........
C800457 ...............EGSE Rolling Stock ..............................................43 ..........
C800469 ...............Water System Isolation Valve - Aireld ................44 ..........


2  Port of Seattle 4Q 2010 Report

C800471 ...............Security Checkpoint Optimization ........................45 ..........
Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C102396 ...............Fire Vehicles .........................................................46 ..........
C200007...............Highline School Noise Insulation ..........................47 .......... ...............
C200015 ...............3rd Runway Residential Acquisition .....................48 ......................... 
C200042 ...............Highline Community College Noise Insulation .....49 .......... ...............
C200048 ...............Home Insulation Retrot .......................................50 .......... ...............
C200093 ...............Single Family Home Sound Insulation .................51 ..........
C800046 ...............Street Vacations  Des Moines Creek 1 ..............52 .......... ..............................
C800150 ...............Burien Commercial Property Acquisition .............53 .......... ...............
C800154 ...............Tenant Reimbursement ........................................54 ..........
C800354 ...............Paint Stripper Equipment ......................................55 .......... ..............................
C800381 ...............28th Ave Property Acquistion ...............................56 .......... ...............
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C102451 ................T-115 Dock Reconstruction...................................57 .......... ............... ....................
C800085 ...............T-30/T-91 Program ............................................58-59 ....... ............... ....................
C800114................P-66 Bag. Corridor & Pass. Screening ................60 .......... ...............
C800121 ...............T-18 S. Fendering .................................................61 .......... ...............
C800123 ...............T-5 Crane Spreader Replacement .......................62 .......... ...............
C800133 .............. T-86 Grain Facility Modernization (Phase I) ........63 ..........
C800182 ...............NH Island Mooring Dolphins (4) ...........................64 ..........
C800183 ...............P91 Fender System Upgrade ...............................65 ..........
C800264 ...............T-10 Interim Redevelopment.................................66 .......... ...............
C800298 ...............T-91 Watermain Replacement ..............................67 ..........
C800343 ...............T-91 Roadway Pavement .....................................68 .......... .............................. 
C800347 ...............T-46 Upgrade Yard Lighting .................................69 ..........
C800349 ...............T-5 Crane Cable Reels .........................................70 ..........
C800416 ...............T-18 Fender Replacement ....................................71 ..........
WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................72 ..........
E103705 et al ........T-46 ZPMC Gearboxes ........................................73 ..........


Port of Seattle 4Q 2010 Report  3

E103835 et al ........T-5/T-18 Maintenance Dredging ...........................74 .......... ...................................
E104362 et al ........Street Vacations T-5/18/105 .................................75 ..........
Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800070 ...............T-102 HVAC Renewal/Replacement ....................76 .......... ...............
C800136 ...............FT South Wall Reconstruction Phase VI ..............77 ..........
C800137 ...............FT C15 HVAC Improvements ...............................78 ..........
C800175 ...............MIC Central SeaWall Replacement ......................79 ..........
C800386 ...............FT NW Dock E. Fender System Replacement.....80 ..........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ....................81 ..........
C800003...............Maximo Enterprise Implementation......................82 .......... ...............
C800227 ...............Ground Transportation Management System ......83 ..........
C800319............... Port of Seattle Internet Redesign.........................84 .......... .............................. 
C800320 ...............External Sharepoint ..............................................85 .......... .............................. ....................
C800321 ...............Enterprise Project Cost Management ..................86 .......... ...............
C800322 ...............Records and Document Management .................87 .......... ..............................
C800326 ...............Business Continuity ..............................................88 .......... .............................. 
C800387 ...............Time Clock System ...............................................89 ..........
C800392 ...............PeopleSoft Financial Upgrade ..............................90 ..........
C800393 ...............Police Records Management System ..................91 ..........
C800395 ...............Upgrade to Windows 7 & Ofce 2010...................92 ..........
C800397 ...............Port Contractor Roster and Bid Management ......93 ..........
Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
Previously Reported
No Diamond  On Budget or On Schedule

4  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
3rd Runway Program
Status Snapshot
On Schedule
Project: C000683,       The 3rd Runway Program
On Budget
C001138, C001175,      constructed a new 8,500 foot long
3 Change Orders
C001331, C001751,      runway, connecting taxiways, and
Total Change Orders Amount:
C001760, C100172      related infrastructure.
$190,000.00
Budget: $932,408,802
Phase: Construction                       Budget/Costs Incurred
Start: 05/27/1997
1200
Completion: 12/31/2011
1000
Millions800  Dollars in 
Significant Developments                    600
400
Remaining 2009 contract work for pond netting has been completed.
200
The 2010 construction contract work was completed except for the
0
in-stream work that will be completed in 2011.
Authorized   Forecasted  Costs Incurred
Schedule
The remaining tasks on this project include: 2010 contract in-stream
work, Alaska Maintenance Building demolition, minor in-stream work  2010 Contract Const. Costs
to address temporal impacts, and Pond M modifications.
1
Budget                             0.8
0.6
The project forecast is within the approved budget and authorization.   Millions
0.4
Change Order                          Dollars in  0.2
Three change orders were executed this quarter totaling $190,000.      0
One change order involved an extension of the contract time of 353        InitialChange OrdersSpent
days.
Risks
Photo
Hazardous materials in caulk may delay the demolition of the Alaska
Maintenance Building.
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 4Q 2010 Report  5

FOURTH QUARTER REPORT, 2010
Rental Car Facility
Status Snapshot Prior Report
Delayed Schedule 4Q 08
Project:   C100266,     The program will construct a       On Budget
C102167, C800032     consolidated rental car facility (RCF)  653 Change Orders
Budget: $419,306,000   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $6,713,485
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.          Budget/Costs Incurred
Significant Developments                     500
400
Construction continues progressing well on all aspects of the RCF.
The entire concrete structure is complete. The Customer Service       Millions300
Building is fully enclosed to the weather and interior work is well        200
underway. Construction continues on all four quick turnaround areas,    Dollars in 100
though No. 1 and 2 are nearing completion. Averaging around 200      0
workers daily. One subcontractor is making claims they've been          Authorized Forecasted Costs Incurred
significantly impacted. BMF contract was awarded and contractor
working on early submittals. The ORI construction continues with
both the S160th St revisions and new access ramp to the Airport     Construction Costs
Expressway ramp to SR518 fairly complete. Work is underway on
the bridge widening and strengthening. Main Terminal Improvements     300
60% design review is complete and working toward 90%. Gillig is
250
currently manufacturing the first bus.
Millions  200
150
Dollars in 
Schedule
100
The revised program schedule remains on-track for spring 2012        50
completion. BMF scheduled completion is March 2012. ORI           0
scheduled completion is December 2011. Bus delivery planned for          InitialChange OrdersSpent
4Q 2011.
Budget                            Photo
Customer Facility Charge revenues have increased slightly and the
trend is improving slightly with the economy. The program forecast is
within the approved budget and authorization.
Change Order
115 change orders were issued this quarter in the amount of
$1,109,582.


6  Port of Seattle 4Q 2010 Report

Risks
For RCF: impacts to schedule due to changes and contractor performance, claims submitted by one
subcontractor; multiple subcontractors working in same location; quality issues; control of onsite
stormwater; and site congestion.
For ORI: weather; traffic control; and site congestion.
For BMF: weather; material deliveries; and completion of aggressive construction schedule to support
spring 2012 opening.
Budget Transfers
None this quarter
Cost Growth of Construction
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative change order percentage through
this quarter is 19.4%. Primary reason for changes is the removal of contaminated soils and
associated impacts. This work and the final contract reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  Cumulative change order percentage
through this quarter is 170.5%. Primary reasons for changes are for additional contractor
management, estimating, scheduling and bidding effort for cost estimate reconciliation,
constructability reviews and value engineering beyond the extent of the original scope to validate
project costs and support the rental car companies and the Port on final approval of the project. This
work and the final contract reconciliation is complete.




AIRPORT
Port of Seattle 4Q 2010 Report  7

FOURTH QUARTER REPORT, 2010
Stormwater Management Program
Project:   C102030,    The program achieves permit       Status Snapshot Prior Report
C800026, C800030     requirements and makes the Airport a  On Schedule
Budget: $52,347,234   leader in stormwater management by  Under Budget   1Q 10
Phase: Construction   construction of flow control, water    0 Change Orders
Start: 06/11/2002       quality treatment and low stream flow   Total Change Orders Amount:
mitigation facilities.                  $0
Completion: 12/31/2011
Budget/Costs Incurred
Significant Developments
The stormwater program (C102030) is in its adaptive management     100
phase under which additional or upgraded water quality treatment
80
facilities are being implemented based on the stricter effluent         Millions 60
standards of the new stormwater National Pollutant Discharge
Elimination System (NPDES) permit. Designs were completed for      40
water quality treatment upgrades at four project sites; contractor bids    Dollars in  20
are anticipated in January 2011.
0
Authorized  Forecasted Costs Incurred
Schedule
The new stormwater NPDES permit became effective April 1, 2009.
Current adaptive management projects will be constructed during    Construction Costs
2011, and possibly additional projects through 2014 depending on    No active construction
water quality monitoring results. The stormwater (C800026) and     contract at this time.
sanitary sewer (C800030) pipeliner projects, which are not part of
adaptive management, have been deferred until 2011, or later.
Budget
The project forecast is within the approved budget and authorization.
During the first quarter of 2011 approximately $2,000,000 of budget
will be returned to savings.
Change Order
None
Risks
Additional adaptive management facilities or upgrades may be
required beyond those currently being planned, depending upon
future water quality monitoring results.
Budget Transfers
None this quarter
AIRPORT
8  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Apron Pavement Rehabilitation
Project:   C102038      Multiyear airfield pavement       Status Snapshot Prior Report
Budget: $14,998,000     replacement program. This is a    Ahead of Schedule 3Q 10
Phase: Close Out      continuation of a program for the   Under Budget   3Q 10
Start: 01/14/2003         removal and replacement of aged   2 Change Orders
Completion: 07/09/2010   airfield apron pavement started in   Total Change Orders Amount:
1994.                    $232,732.84
Budget/Costs Incurred
Significant Developments
The apron pavement rehabilitation portion of the contract was        16.5
finished on July 9, 2010.
16
15.5  Millions
Schedule
15
Contract closeout is in progress.
14.5  Dollars in 
Budget                             14
The project forecast is within the approved budget and authorization.       Authorized Forecasted Costs Incurred
Any potential savings will be returned once the project is closed out.
Change Order                         2010 Contract 1
Construction Costs
One change order was executed during this period. None involved
extension of the contract time.
3.5
3
Risks
2.5
No risks have been identified at this time.                       Millions  2
1.5
Budget Transfers                          Dollars in  1
0.5
None this quarter.                                        0
InitialChange OrdersSpent

Photo


AIRPORT
Port of Seattle 4Q 2010 Report  9

FOURTH QUARTER REPORT, 2010
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $223,538,762   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget   4Q 09
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
Significant Developments
235
The C-1 baggage handling/screening system has been placed into     230
revenue service for the Alaska Air Group. All work was completed.     Millions 225
220
Schedule
Dollars in 215
The project was delayed approximately two years from the original
210
completion date due to replacement of the original baggage
Authorized  Forecasted Costs Incurred
subcontractor, changing TSA requirements and other scope
changes. Turner Construction demobilized on May 31, 2009. The
GCCM construction contract with Turner Construction has been
Construction Costs
closed. The remaining fire sprinkler and fire proofing work was
completed.
200
Budget                              150
Millions
The project forecast is within the approved budget and authorization.     100
50
Change Order                          Dollars in 
0
665 Change Orders have been issued on this project.
Initial  Change Orders  Spent
Risks
None                                 Photo
Budget Transfers
None this quarter



10  Port of Seattle 4Q 2010 Report

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated as they were unable to meet the
project schedule requirements. The remaining work was rebid in the fall of 2006. Alaska Airlines
asked that we include the BHS work within the 2-step ticket counter project; which increased the
amount of BHS work in the bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.












AIRPORT

Port of Seattle 4Q 2010 Report  11

FOURTH QUARTER REPORT, 2010
Water System Isolation Valve Upgrade
Status Snapshot
On Schedule
Project:   C102334      This project replaces isolation     On Budget
Budget: $704,000       valves on the aging water       0 Change Orders
Phase: Design        distribution system, necessary for   Total Change Orders Amount:
Start: 10/01/2010         isolating portions of the system in    $0
Completion: 12/31/2011   the event of breaks, leaks, or tieins.
Budget/Costs Incurred
0.8
Significant Developments
On November 15, 2010, Commission authorized dividing the Water     0.6
System Isolation Valve Upgrade project into two projects, Airfield and    Millions
0.4
Non-Airfield. The project is currently in design. The Port
Construction Services group determined that the valves can be pre-    Dollars in 0.2
ordered using a State Contract.
0
Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
From C800469 (Water Sys Isolation Valve - Airfield)  $1,443,000



AIRPORT
12  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Airfield Pavement Replacement
Project:   C102573      The project is intended to be a     Status Snapshot
Budget: $30,800,000     multi-year pavement replacement   On Schedule
Phase: Design        program to replace some of the    On Budget
Start: 05/02/2010         worst pavement and joint seal on    0 Change Orders
Completion: 12/31/2016   the airfield.              Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The 90% design for the South Satellite Slot Drain/Apron
35
Replacement will be completed in January 2011.
30
25
Schedule                            Millions 20
The construction work in 2011 will be the initial phase of a multi-year     15
pavement replacement program scheduled from 2011 to 2015.       Dollars in  10
5
Budget                             0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Not Applicable
Change Order
None                                 Photo
Risks
Any delay will put project out of typical construction window.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 4Q 2010 Report  13

FOURTH QUARTER REPORT, 2010
2nd Floor Tenant Improvements
Project:   C102744      This project constructs a shell     Status Snapshot Prior Report
Budget: $377,864       space for new tenant offices and   Delayed Schedule 1Q 10
Phase: Construction     provides utility pathways to the    On Budget
Start: 08/22/2006         shell space and makes code       0 Change Orders
Completion: (See       improvements to adjacent lobby    Total Change Orders Amount:
and corridors.                 $0
C800249)
Significant Developments                    Budget/Costs Incurred
Project construction activities were waiting for one project element,
0.6
completion of tenant office build out and relocation of current tenant
0.5
offices. This element of work has now been determined to be
0.4
unnecessary and the project is now complete. This will be the final
0.3
quarterly report for this project.                                in Millions
0.2
Dollars 0.1
Schedule
0
The project is now complete.                                 Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

14  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Loading Bridge Utilities
Project:   C800019   This project will upgrade all Port-       Status Snapshot Prior Report
Budget: $9,385,000   owned loading bridges to the same     Delayed Schedule    2Q 09
Phase: Design     standards, including 400Hz power and   Forecast Overrun
potable water. It will reduce air
Start: 06/28/2007                                 0 Change Orders
emissions, improve energy efficiency
Completion: TBD                           Total Change Orders Amount:
and save money for the airlines.        $0
Budget/Costs Incurred
Significant Developments
The scope of this project has been increased to include two          14
additional gates (B-1 and B-5), and to increase the number of 400 Hz    12
generators from two to three at the South Satellite to service 787s in    Millions 10
8
Dollars in 
the future. The project will have to be redesigned to include the new
6
scope, and the project will have to return to the Investment
4
Committee to approve the new scope and budget.
2
0
Schedule
Authorized  Forecasted Costs Incurred
The schedule has been delayed due to the new scope additions.
Budget                            Construction Costs
The budget forecast will be increased to accommodate the new     Not Applicable
scope and the new soft cost markups currently being used.
Change Order
None
Risks
Airport Operations is in the process of identifying the additional
scope necessary and a revised cost estimate is being developed.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2010 Report  15

FOURTH QUARTER REPORT, 2010
North Expressway Relocation
Project:   C800034
The project is a collaboration      Status Snapshot  Prior Report
Budget: $110,347,700    between the Port and Sound     Delayed Schedule 1Q 10
Phase: Construction     Transit. It reconstructs the North   On Budget
Start: 07/27/2004         Airport Expressway and brings light  200 Change Orders
Completion: 03/31/2012   rail to the Airport.           Total Change Orders Amount:
$7,973,721
Significant Developments
Budget/Costs Incurred
The work in the main contract includes reconstruction of the North
Airport Expressway and light rail transit components. This work is      115
complete. The intelligent transportation management system has
110
been implemented. A final contract to complete paving, landscaping,    Millions105
the north entry art features, and other miscellaneous work is
underway.                                     100
Dollars in  95
Schedule
90
The main contract reached substantial completion in August 2008         Authorized Forecasted Costs Incurred
and plant establishment was completed in December 2010. A
contract for final paving, landscaping, and reclamation is underway
and is planned to be complete in early 2011, followed by a first year   Construction Costs
plant establishment period to be complete in early 2012.
120
Budget                             100
The project forecast is within the approved budget and authorization.    Millions 80
60
Change Order                          40
Dollars in 
Seven change orders were issued this quarter in the amount of        20
($1,377,213).                                        0
Initial    Change Order    Spent
Risks
None identified at this time.
Budget Transfers                        Photo
None this quarter


AIRPORT
16  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Parking Garage 4th Floor Improvements
Project:   C800036
The project includes the design and  Status Snapshot
Budget: $9,131,000      construction of a pedestrian bridge  On Schedule
Phase: Construction     and a walkway from Sound      On Budget
Start: 02/14/2006         Transit's Airport Station to the      56 Change Orders
Completion: 12/31/2009   Terminal.               Total Change Orders Amount:
$177,015
Significant Developments
Budget/Costs Incurred
The project was delivered in two contracts: the pedestrian bridge
between the Airport Station and the Parking Garage, and a walkway    9.2
on the 4th floor of the garage between the pedestrian bridge and        9
northernmost sky bridge to the main terminal. Both contracts are       Millions 8.8
complete and opened in conjunction with Sound Transit's Airport       8.6
Station on December 19, 2009.
8.4
Dollars in 8.2
Schedule
8
The Multiple User Flight Information Display System (MUFIDS) is         Authorized Forecasted Costs Incurred
being installed in the Airport Station with completion to occur First
Quarter of 2011. This work was scheduled to minimize disruption to
passenger traffic through the light rail station during the holidays.     Construction Costs
Budget                              4
The project forecast is within the approved budget and authorization.      3
Millions   2
Change Order
None this quarter                                       1
Dollars in 
0
Risks                                   Initial Change Orders Spent
None
Budget Transfers                        Photo
None this quarter


AIRPORT
Port of Seattle 4Q 2010 Report  17

FOURTH QUARTER REPORT, 2010
Aircraft Rescue & Fire Fighting Station Upgrade
Project:   C800042      Upgrade the Sea-Tac International   Status Snapshot Prior Report
Budget: $4,972,000      Airport Aircraft Rescue & Fire     Delayed Schedule 1Q 09
Phase: Close Out      Fighting (ARFF) station to meet    On Budget
Start: 06/13/2006         current Airport needs and comply    26 Change Orders
Completion: 01/31/2010   with current safety codes.       Total Change Orders Amount:
$173,099
Significant Developments                    Budget/Costs Incurred
Port Construction Services is installing additional pick points on the
5.2
training tower. Altering the grade of the asphalt around it has proved
more complex than originally anticipated and too cost prohibitive to      5
proceed with at this time.                                  Millions 4.8
4.6
Schedule                            Dollars in 
4.4
The project and punchlist are now substantially complete.
4.2
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None this quarter
3
Risks                                2.5
None at this time                                      Millions 2
1.5
Budget Transfers
Dollars in   1
None this quarter                                      0.5
0
Initial    Change Order    Spent



AIRPORT

18  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Main Terminal South Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
0 Change Orders
Start: 06/28/2007      equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD    Main Terminal.
$0
Significant Developments                    Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. The Port is in the process of finalizing and executing a        2
Service Agreement (SA) to finish the design. The SA with Scope of     Millions 1.5
Work and Level of Effort are in the negotiation phase with
1
Consultant.                                        Dollars in 0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
The project was reactivated on June 24, 2009 and is in the process
of determining the scope of work, schedule and final design budget.
Expect to remobilize the Design Consultant in the first quarter 2011.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.  Photo
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area of the Main Terminal is a 24/7/365 operation and
sequencing of this work is critical and electrical power has to be
maintained without interruptions.
It is not known when the construction will proceed. There may be an
impact on project costs due to changes in market conditions at that
time.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 4Q 2010 Report  19

FOURTH QUARTER REPORT, 2010
Consolidated Warehouse
Project:   C800071     This project will construct a 50,000    Status Snapshot Prior Report
Budget: $9,237,000     square foot warehouse for storage   Ahead of Schedule    3Q 09
Phase: Close Out     and inventory management of spare  Under Budget
Start: 06/27/2006       parts for the Aviation Maintenance    34 Change Orders
Department.
Completion: 02/15/2010                       Total Change Orders Amount:
$770,658
Significant Developments                    Budget/Costs Incurred
The project is complete and in close out, with the building open for
use and in operation. The final invoice was submitted but has not       9.4
been paid due to incomplete as-built drawings.                   9.3
Millions 9.2
Schedule                             9.1
9
The project was completed ahead of schedule.
Dollars in 8.9
8.8
Budget                             8.7
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Construction Costs
None this quarter
6
Risks
The final as-built drawings have not been received.                Millions  4
Budget Transfers                           2
To C800152 (Non Aeronatical New Projects)       $63,000       Dollars in 
0
Initial  Change Orders  Spent
Cost of Construction Growth
CO's exceeding 10% were due to the following:
1. Soil and foundation changes due to the site being an old,        Photo
unconsolidated fill of unknown material;
2. Perceived market conditions during bidding, structural mezzanine
was deleted. The bid climate changes allowed the mezzanine to
be installed; and
3. Pallet racks were anticipated to be a Port purchase and install.
The purchasing officer recommended the contractor purchase and
install as a CO.

AIRPORT
20  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Alaska Air 2-Step Ticket Counter
Project:   C800095      This project provides Port of      Status Snapshot Prior Report
Budget: $10,707,000     Seattle support for Alaska Airlines'  Delayed Schedule 1Q 08
Phase: Close Out      2-step ticket counter projects (the   Under Budget
Start: 04/11/2006         "Airport of the Future"). The work   0 Change Orders
Completion: 02/13/2009   includes: asbestos abatement;    Total Change Orders Amount:
concessions relocations; and      $0
related building modifications.
Budget/Costs Incurred
Significant Developments
12
The onsite work is complete. The Port has reached a final agreement
10
with Alaska Airlines to reconcile the reimbursable amount. This will
be the last quarterly report for this project.                        Millions 8
6
Schedule                             4
Dollars in   2
The project work is complete.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
The project will return savings at closeout.                     Construction Costs
Not Applicable
Change Order
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 4Q 2010 Report  21

FOURTH QUARTER REPORT, 2010
Airport Owned Gate Infrastructure
Project:   C800105      This project purchases and
replaces passenger loading bridges  Status Snapshot
Budget: $6,000,000
On Schedule
Phase: Construction     at gates throughout the airport. The
On Budget
Start: 07/24/2007         project is being performed in
phases.                  0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project was presented to the Commission in July 2010 for
authorization of the remainder of the budget. Currently, the team is in
7
the process of procuring a design firm.                         6
5
Schedule                            Millions 4
Dollars in 
3
The remainder of the project will be completed in 2011.
2
1
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
22  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
C4 UPS System Improvements
Project:   C800107    Project will replace existing UPS      Status Snapshot Prior Report
Budget: $2,336,000   System, including batteries, with a new  Delayed Schedule 1Q 09
Phase: Construction  new system located in the Airport     On Budget
Start: 06/28/2007      Combined Communications and       0 Change Orders
Completion: TBD     Command Center (C4).          Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. The Port is in the process of finalizing and executing a        2
Service Agreement to finish the design. The Service Agreement with    Millions 1.5
Scope of Work and Level of Effort are in the negotiation phase with
1
Consultant.                                        Dollars in 0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
The project was reactivated on June 24, 2009 and is in the process
of determining the scope of work, schedule and final design budget.
Expect to remobilize the Design Consultant late in first quarter of
2011.                                       Construction Costs
Not Applicable
Budget
Photo
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions.
It is not known when the construction will proceed as this is
specialized equipment and complex and requires rigorous testing
during the commissioning phase.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2010 Report  23

FOURTH QUARTER REPORT, 2010
Garage Escalator & A-Bank Elevator Upgrade
Project:   C800109    This project renews aging elevators    Status Snapshot Prior Report
Budget: $5,815,000    and escalators in the Airport Parking   Delayed Schedule    3Q 10
Phase: Construction   Garage to provide reliable vertical    On Budget
Start: 09/11/2007       transportation to customers for years   23 Change Orders
Completion: 10/31/2011  to come.                 Total Change Orders Amount:
$219,523
Significant Developments                    Budget/Costs Incurred
Separate construction contracts were used for the A-Bank Elevators
8
and Garage Escalators. All contractor work on the elevators is
complete. The construction contract for the escalator work was        6
executed and a notice to proceed was given to the contractor.        Millions
4
Schedule
Dollars in  2
Contractor site work on the Garage Escalators will start in early
February 2011 and is expected to be complete by June. Schedule      0
was delayed due to time required to complete the competition waiver       Authorized Forecasted Costs Incurred
process.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
3
The project returned $1,500,000 of budget in Third Quarter of 2010.
2.5
Change Order                          Millions 2
Dollars in 
1.5
None this quarter.
1
0.5
Risks
0
None identified at this time.
Initial    Change Order    Spent
Budget Transfers
To C800152 (Non Aeronautical New Projects)       $1,500,000


AIRPORT

24  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot Prior Report
The scope of work will remove and   Ahead of Schedule 3Q 10
Project:   C800112      replace the pavement and joint seal  On Budget
in areas on Runway 16C-34C.
Budget: $5,650,000                         2 Change Orders
Phase: Close Out                          Total Change Orders Amount:
Start: 02/26/2008                                 $232,732.84
Completion: 09/03/2010
Significant Developments                    Budget/Costs Incurred
The 2010 construction project was completed on September 3, 2010.    6
5
Schedule
Millions  4
The contract is in the closeout process.                         3
2
Budget                             Dollars in  1
The project forecast is within the approved budget and authorization.     0
Any potential savings will be returned once the project has been          Authorized  Forecasted Costs Incurred
closed out.
Change Order                         2010 Contract 1
One change order was executed during this period. None involved   Construction Costs
extension of the contract time.
3.5
3
Risks
Millions  2.5
No risks have been identified at this time.                         2
1.5
Budget Transfers                          Dollars in  1
0.5
None this quarter.
0
InitialChange OrdersSpent

Photo


AIRPORT
Port of Seattle 4Q 2010 Report  25

FOURTH QUARTER REPORT, 2010
Security CCTV System Improvements
Project:   C800144      This project will install          Status Snapshot Prior Report
Budget: $2,037,591      approximately 70 new cameras for  Delayed Schedule 3Q 09
Phase: Implementation   TSA and integrate existing Airport   On Budget
Start: 9/11/2007          camera networks which contain     0 Change Orders
Completion: 03/31/2010   over 800 cameras.          Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
No additional funding is being provided for this project by TSA.
2.06
Finalizing remaining work for the remaining budget, which includes
2.04
installing additional cameras and purchasing additional data storage.    2.02
Millions  2
Schedule                            1.98
1.96
Project substantial completion occurred in March 2010.            1.94  Dollars in 
1.92
1.9
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable                                     Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

26  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
RMU/Kiosk Concession Program
Project:   C800146    The project will provide design and     Status Snapshot Prior Report
Budget: $1,209,000   fabrication of eight Retail         Delayed Schedule 3Q 10
Phase: Construction   Merchandising Units (RMUs); provide   Under Budget       2Q 10
Start: 11/20/2007      power, communications, and data to    0 Change Orders
Completion: 06/30/2011 sixteen RMU locations; and install floor-  Total Change Orders Amount:
mounted receptacles for the utilities to    $0
allow easy connection points as well as
flexibility for future utilization.
Budget/Costs Incurred
Significant Developments
1.4
All RMU utility installations are complete. The remaining tasks         1.2
include purchasing and installing the RMU kiosk units. The originally     1
agreed upon amount of $240,000 is being transferred to the          0.8
Business Sponsor so that they may procure the kiosk units. This      in Millions 0.6
allows for a return of funds in the amount of approximately $400,000.    Dollars 0.4
0.2
0
Schedule
Authorized  Forecasted Costs Incurred
The project is on hold until the prioritization decisions are made by
the Port's Business Development group, related to the procurement
of the RMUs.                                    Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
The project anticipates a savings of approximately $400,000 once
closeout is complete.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2010 Report  27

FOURTH QUARTER REPORT, 2010
Concessions Unit Readiness Project
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Design        previously vacated or slated to be   On Budget
Start: 08/26/2008         vacated to Port standards for use    0 Change Orders
Completion: 06/30/2013   as specialty concession space.    Total Change Orders Amount:
$0
Significant Developments
This project received Commission authorization in September 2010   Budget/Costs Incurred
to design and build concession spaces in two locations. Design of
these two locations is complete and construction is scheduled to       2.5
begin in February 2011.                                 2
1.5
Schedule
in Millions  1
The construction phase has been restructured and re-sequenced,
Dollars 
with the intent to maximize the timing for new Concessions           0.5
opportunities. The project was put on hold until the prioritization         0
decisions were made by Aviation Business Development.              Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
28  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot  Prior Report
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule 4Q 09
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,000
project includes installing three      0 Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      $0
Completion: 12/31/2011   approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
1.2
The 100% design is complete.                            1
0.8
Schedule
Millions 0.6
The project completion is dependent upon selection of a tenant by      0.4
Aviation Business Development for a new concession in the GML      Dollars in 0.2
Arrivals Hall.                                               0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not applicable
None
Photo
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 4Q 2010 Report  29

FOURTH QUARTER REPORT, 2010
Runway 16L/34R Reconstruction
The scope of this project includes   Status Snapshot  Prior Report
Project: C800167
On Schedule
Budget: $60,466,538     the complete reconstruction of
Phase: Close Out      Runway 16L/34R (the eastern    Under Budget   3Q 10
runway) and replacement of aging  26 Change Orders
Start: 02/26/2008
infrastructure.                 Total Change Orders Amount:
Completion: 12/31/2009                      $2,528,214.29
Significant Developments
Runway 16L/34R Reconstruction project includes reconstruction of   Budget/Costs Incurred
11,900 foot runway and portions of five taxiways. The construction
100
was completed on September 25, 2009 and re-opened on
80
September 26, 2009 on schedule.
Millions 60
Schedule                             40
The runway was re-opened on schedule on September 26, 2009.     Dollars in  20
The project is being closed out.                              0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order
60
No change orders have been executed during this period.            50
Millions  40
Risks                                 30
No risk have been identified at this time.                         20
Dollars in   10
Budget Transfers                           0
From CIP C800167 (Runway 16L/34R Reconstruction) $6,420,000        InitialChange OrdersSpent

Photo


AIRPORT

30  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Connect C1 BHS to C88 BHS
Project:   C800170      This project connects the C1      Status Snapshot
Budget: $3,032,000      baggage handling system (BHS) to  Delayed Schedule
Phase: Construction     the C88 BHS. It installs two High-  On Budget
Start: 8/30/2009          Speed Diverters plus additional     0 Change Orders
Completion: 3/31/2011    baggage conveyor length that will   Total Change Orders Amount:
connect the two C1 sortation loops   $0
to the C88 BHS.
Budget/Costs Incurred
Significant Developments
3.5
The Port executed the construction contract on July 12, 2010. The
3
contractor duration is 180 days. The contractor has mobilized and is
Millions 2.5                                                                                  on site. The contractor has completed about 65% of the required            2
contract work. We anticipate a change order to add computer         1.5
programming upgrades to the baggage handling computers. This      Dollars in  1
work is per Alaska Airlines request and was not in the original scope.    0.5
0
Schedule                               Authorized Forecasted Costs Incurred
Currently the project is scheduled to be completed by March 31
2011. This is due to the potential added scope.
Construction Costs
Budget
1.4
The project forecast is within the approved budget and authorization.     1.2
1
Change Order                          Millions 0.8
0.6
None this quarter
Dollars in   0.4
0.2
Risks
0
None identified at this time.                                      InitialChange OrdersSpent
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 4Q 2010 Report  31

FOURTH QUARTER REPORT, 2010
FIS - New Primary Inspection Booths
Project:   C800174      This project will replace existing    Status Snapshot
Budget: $2,000,000      primary inspection booths for     On Schedule
Phase: Design        Customs and Border Protection in   On Budget
Start: 7/27/2010          the International Arrivals Federal    0 Change Orders
Completion: 6/1/2011    Inspection Services (FIS) facility in  Total Change Orders Amount:
the South Satellite.              $0
Budget/Costs Incurred
Significant Developments
2.5
The purchase bid was awarded for fabrication and delivery of booths.
2
The design is nearing 100% completion.                     Millions 1.5 Dollars in 
Schedule                             1
The project is currently on schedule                          0.5
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

32  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Terminal Escalators Modernization
Project:   C800237      This project will replace 42       Status Snapshot Prior Report
Budget: $55,000,000     escalators in the Main Terminal,    Ahead of Schedule 3Q 09
Phase: Design        Concourse B, and South Satellite.   On Budget
Start: 11/02/2007         In addition, two new escalators will   0 Change Orders
Completion: 12/31/2013   be installed at the South Satellite.   Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
This project was formerly entitled "Renew/Replace 42 Escalators & 2
60
New Escalators". Proposals were received from four firms on
50
September 9, 2010. The proposals have been evaluated. Interviews
40
with the four firms were conducted in October 2010. Best and Final
30
Offers were received on December 9, 2010. Selection
Millions
recommendation and Commission authorization are scheduled for      20
Dollars in 
early 2011. The project is utilizing the design-build contracting         10
method to accelerate the overall project schedule.                 0
Authorized  Forecasted Costs Incurred
Schedule
The schedule reflects an expedited design-build procurement as well
as an accelerated construction duration with a tentative completion   Construction Costs
date in 2013.                                       Not Applicable
Budget
The project forecast is within the approved budget. Authorization for
construction funding will be requested as part of the Commission
authorization process.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2010 Report  33

FOURTH QUARTER REPORT, 2010
Central Plant Pre-Conditioned Air
Project:   C800238     This project will provide a centralized  Status Snapshot Prior Report
Budget: $40,600,000    pre-conditioned air plant, associated  Delayed Schedule 3Q 09
Phase: Design       heating and cooling piping systems,   On Budget
Start: 06/15/2009       and jet bridge terminal air handling    0 Change Orders
Completion: 12/10/2012  units to serve airplanes with heating   Total Change Orders Amount:
and cooling while at the gates.       $0
Significant Developments
The contract was awarded to Lydig Construction Inc. on September   Budget/Costs Incurred
13, 2010, after obtaining an $18,000,000 Voluntary Airport Low
Emissions (VALE) grant from the FAA. Notice to proceed was issued    50
and the Contractor is starting project layout and investigation.          40
30
Schedule
in Millions 20
The design process took longer than anticipated and the project is      Dollars  10
approximately two months behind the original schedule.
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                   30
25
Risks
Millions  20
The design schedule had to be accelerated in order to meet VALE       15
grant submission dates, which could impact the number of change       10
orders. The design consultant is having trouble meeting the contract    Dollars in   5
submittal review schedule and is at risk if their delays cause the Port
0
of Seattle any claims. Additionally, the Regulated Materials
InitialChange OrdersSpent
Management costs are higher than originally estimated.
Budget Transfers
None this quarter


AIRPORT

34  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Parking System Replacement
Project:   C800253      This project replaces the current    Status Snapshot Prior Report
Budget: $9,777,000      Parking Revenue Control System,   Delayed Schedule 3Q 10
Phase: Design        which manages parking access    On Budget
Start: April 6, 2010       and revenue collection in the      0 Change Orders
Completion: 12/31/2011   Airport's Main Parking Garage.    Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The schedule has been revised to complete the design and to
advertise in the first quarter of 2011. Construction of the system will     12
occur during 2011 and early 2012. The Port received 90% design      10
documents during December 2010.                       Millions 8
6
Schedule
4
The project is adhering to its revised recovery schedule, which        Dollars in  2
reduced the completion delay from three months to one month.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
system acquisition funding and authority to advertise for a parking    Construction Costs
revenue control system replacement will occur during the first quarter  None this quarter
of 2011.
Photo
Change Order
No change orders were issued this quarter.
Risks
This project schedule is aggressive.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2010 Report  35

FOURTH QUARTER REPORT, 2010
Aircraft RON Parking USPS Site
Status Snapshot
On Schedule
Project: C800254        This project will prepare the site for
On Budget
Budget: $43,900,000     the construction of Hardstands for
0 Change Orders
Phase: Design        use as Remain Overnight (RON)
Total Change Orders Amount:
Start: 04/05/2009        parking of aircraft at the Air Mail
$0
Center site.
Completion: 06/30/2013
Significant Developments                   Budget/Costs Incurred
Completed the lease buyout negotiation with the United States        50
Postal Service (USPS) and lease termination in February 2010. The
40
temporary lease with the USPS for the Air Mail Center site will end
in January 2011. Design efforts for the demolition of the Air Mail       Millions 30
Center including the design for minimal site improvements allowing     20
for temporary uses and amenities, and 15% hardstand design        Dollars in  10
started in Summer 2010.
0
Authorized  Forecasted Costs Incurred
Schedule
Abatement and demolition of the USPS Building is scheduled to
start third quarter of 2011. Proposed construction of a permanent    Construction Costs
hardstand is scheduled to begin the second quarter of 2012.       Not Applicable
Budget                           Photo
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested following the review of the proposal documents.
Change Order
None
Risks
Extent of asbestos in the USPS Building may affect the project cost.
Budget Transfers
None this quarter

AIRPORT
36  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
8th Floor Weatherproofing
Project:   C800274      This project includes removal and   Status Snapshot
Budget: $13,000,000     replacement of the floor covering   On Schedule
Phase: Design        system on the 8th floor of the STIA  On Budget
Start: 03/23/2010         parking garage and repair or       0 Change Orders
Completion: 03/31/2013   replacement of expansion joints    Total Change Orders Amount:
and flashings.                 $0
Budget/Costs Incurred
Significant Developments
Design began during the fourth quarter of 2010. The design          14
12
consultant engaged in forensic testing procedures to ascertain the
cause and severity of structural cracking in the 8th floor parking deck.    Millions 10
8
Preliminary results were positive, although there is certain damage
6
that will need to be addressed.
Dollars in   4
2
Schedule                             0
The current plan is to complete the design in the first quarter of 2011,       Authorized  Forecasted Costs Incurred
to advertise in the second quarter of 2011, and to construct during
the summers of 2011 and 2012.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will    Photo
be requested when the design and bid documents are completed.
Change Order
None
Risks
This is a weather-dependent project.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2010 Report  37

FOURTH QUARTER REPORT, 2010
Common Use Equipment Expansion (CUSE)
Project:   C800276      This project installs flexible       Status Snapshot
Budget: $3,090,000      passenger processing         On Schedule
Phase: Design        infrastructure and equipment at the  On Budget
Start: 09/01/2009         airline gates at some South       0 Change Orders
Completion: 12/31/2011   Satellite and Concourse A gates,   Total Change Orders Amount:
as well as at the former Delta       $0
location.
Budget/Costs Incurred
Significant Developments
4
Design consultant service agreement is nearly complete.
3
Millions
Schedule
2
The project is on schedule.
Dollars in   1
Budget                             0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

38  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations
Status Snapshot
Project:   C800335      Airport-wide electrical charging     On Schedule
system for electrical ground        On Budget
Budget: $14,410,000
support equipment (EGSE) at the   0 Change Orders
Phase: Design
Start: 10/26/2010         Concourses and the North and     Total Change Orders Amount:
Completion: 4/30/2013    South Satellites.            $0
Budget/Costs Incurred
Significant Developments
Completed site walks and identified charger locations and number of    20
charging stations for Alaska, Horizon, Delta and Southwest Airlines.
15
In the process of negotiations with the Consultant to define the scope   Millions
of work and the budget for 20% schematic design.                10
Dollars in   5
Schedule
The EGSE program was reactivated late in fourth quarter of 2010       0
and the project team is in process of determining the scope of work,        Authorized  Forecasted Costs Incurred
schedule and final design budget. Expect to remobilize the Design
Consultant in the first quarter of 2011.
Budget                            Construction Costs
The project forecast is within the approved budget. Authorization for  Not Applicable
the construction funding and authority to advertise for construction
will be requested when the design and bid documents are
completed.
Change Order
None
Risks
Late execution of agreements between Port and Airline Carrier
Consortium. Coordination with other airfield projects and Airline
Realignment program.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2010 Report  39

FOURTH QUARTER REPORT, 2010
South Satellite Delta Sky Club Expansion
Status Snapshot
Delayed Schedule
Project:   C800336     Construction of a new 6,800 square   On Budget
Budget: $5,440,000    foot Sky Club lounge on the roof of   0 Change Orders
Phase: Design       the South Satellite for Delta Air Lines.  Total Change Orders Amount:
Start: 06/01/2010                                 $0
Completion: 06/30/2011
Budget/Costs Incurred
Significant Developments
6
Tenant has increased the size of the club on the roof and is           5
developing a cost estimate for the additional work. Delta's contractor
4
is proceeding with work on the ramp and concourse level. The        Millions
3
increased size results in additional Port work for removal of
2
asbestos.                                        Dollars in  1
0
Schedule
Authorized  Forecasted Costs Incurred
Construction work has begun. The tenant's delayed decision on the
increased size of the club has pushed Delta's substantial completion
out to June 2011.                                   Construction Costs
Not Applicable
Budget
The project forecast for the current scope is within the approved
budget and authorization. The impacts of the addition to the club is
yet unknown.
Change Order
None
Risks
With the increased size of the club, the Port's scope and costs may
increase beyond current authorization.
Budget Transfers
None this quarter


AIRPORT
40  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Roof Replacement Program
Status Snapshot
Project:   C800360      Remove and replace the roofing    On Schedule
Budget: $2,640,000      systems on the south and central   On Budget
Phase: Design        sections of the Main Terminal. The  0 Change Orders
Start: 4/25/2010          new roofing systems will achieve    Total Change Orders Amount:
Completion: 12/20/2010   LEED credits and are Energy Star   $0
rated. This project is part of a
multi-phased program.          Budget/Costs Incurred
3
Significant Developments
2.5
Design and bid document preparation is complete. Commission       Millions 2
authorization to advertise for construction was received in November
1.5
2010. Advertisement is scheduled for February 2011 in order to meet
1
the most timely bid period for reasonable bids. Bid opening is         Dollars in 0.5
anticipated in March 2011.
0
Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None at this time
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2010 Report  41

FOURTH QUARTER REPORT, 2010
RW16C/34C Reconstruction Design
Project:   C800406      This project will produce the 60%   Status Snapshot
Budget: $669,000       design for the runway 16C/34C    On Schedule
Phase: Design        reconstruction. The design will    On Budget
Start: 05/04/2010         include utilities, runway status      0 Change Orders
Completion: TBD       lights, and other scope items     Total Change Orders Amount:
related to the project.             $0
Significant Developments                    Budget/Costs Incurred
The 60% design was issued in December 2010. Design review is
0.8
underway and then the project will be archived until the design
resumes in 2014.                                   0.6
Millions
0.4
Schedule
Staff will return to Commission for authorization of the remaining       Dollars in 0.2
design funds in late 2014 or early 2015.
0
Authorized  Forecasted Costs Incurred
Budget
The Port Commission authorized $669,000 on May 4, 2010. The
current forecast for 60% design is within the approved budget and    Construction Costs
authorization. The forecast will be reassessed when staff returns to   Not Applicable
the Commission for authorization of the final design funds.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
42  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Electrical Ground Support Equipment (EGSE)
Rolling Stock
The Port of Seattle will procure and   Status Snapshot
Project:   C800457      deploy the initial fleet of EGSE.     On Schedule
This fleet will be comprised of       On Budget
Budget: $30,000,000
approximately 334 baggage tugs,   0 Change Orders
Phase: Design        192 belt loaders, 71 pushback    Total Change Orders Amount:
Start: 0/26/2010          tractors, and 92 other pieces of     $0
Completion: 04/30/2013   ground support.
Budget/Costs Incurred
Significant Developments
The Port of Seattle, in conjunction with the Airline Carriers, is          35
proceeding with developing an Invitation to Bid for the EGSE vehicle     30
25
fleet. The Airlines Carriers (Alaska, Horizon, and American) have      Millions 20
provided the Port with EGSE vehicle specifications and a list of
15
vendors.
Dollars in  10
5
Schedule                             0
The EGSE program was reactivated late in the first quarter of 2010        Authorized  Forecasted Costs Incurred
and project team is in the process of finalizing the Invitation to Bid,
which will be issued by March 31, 2011.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget. Authorization for
the remaining funding and authorization to purchase the equipment
will be requested once the proposals have been evaluated, and the
Airline Carrier Consortium has reviewed and selected the equipment.
A Department of Energy Grant will be used to offset the total cost of
the EGSE initial fleet.
Change Order
None.
Risks
Potential risks due to late execution of agreements between Port of
Seattle and Airline Carrier Consortium, and coordination with other
airfield projects and Airline Realignment program.
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 4Q 2010 Report  43

FOURTH QUARTER REPORT, 2010
Water System Isolation Valve Upgrade - Airfield
Project:   C800469      The water distribution system at the
Budget: $1,443,000      Airport is almost 40 years old. This
Phase: Design        project will replace and add      Status Snapshot
Start: 11/15/2010         additional water valves in several    On Schedule
Completion: 12/31/2011   strategic locations to prevent     On Budget
possible outages.              0 Change Orders
Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
On November 15, 2010, Port of Seattle Commission authorized
dividing the Water System Isolation Valve Upgrade project into two      2
projects, Airfield and Non-Airfield. The Airfield Water System
1.5
Isolation Valve Upgrade is in design. The 90% review comments are    Millions
due in February 2011.                                  1
Schedule                            Dollars in 0.5
Bid advertisement is anticipated to be March 8, 2011.               0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization for
the construction funding and authority to advertise for construction    Construction Costs
will be requested when the design and bid documents are         Not applicable
completed.
Change Order                         Photo
None
Risks
The replacement valve sizes were taken from 25-40 year old
documents.
Budget Transfers
None this quarter

AIRPORT

44  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Security Checkpoint Optimization
Project:   C800471      This project supports TSA initiative  Status Snapshot
Budget: $430,000       to accomodate emerging       On Schedule
Phase: Close Out      technologies. Major elements were  On Budget
Start: 8/15/10           new electrical infrastructure to      0 Change Orders
Completion: 12/31/10    checkpoints and minor relocation of  Total Change Orders Amount:
lanes for installation of Advanced    $0
Significant           Imaging Technology (AIT) units.
Budget/Costs Incurred
Developments
Construction activities were timed to allow the North Checkpoint to      0.5
0.45
open in time for holiday travel. Terrazzo repairs, and punchlist work      0.4
continued through the end of December.                     Millions 0.35
0.3
Dollars in    0.25
Schedule                             0.2
0.15
The project is complete and in closeout.                        0.1
0.05
0
Budget                                Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
This project was originally a Small Capital Project, but exceeded the
$300,000 limitation. It was authorized as a Major Construction       Construction Costs
Project at $430,000 by Commission Action on November 30, 2010,   Not Applicable
and the budget was increased at that time.
Change Order
None
Risks
None identified at this time
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2010 Report  45

FOURTH QUARTER REPORT, 2010
Fire Vehicles
Project:   C102396      Purchase of fire vehicles according  Status Snapshot
Budget: $1,369,000      to the Fire Department Vehicle    On Schedule
Phase: Implementation   Replacement Master Plan. Includes  On Budget
Start: 11/16/2008         purchase of an ARFF vehicle and   0 Change Orders
Completion: 7/31/2009    medical aid unit vehicle.        Total Change Orders Amount:
$0
Significant Developments
The ARFF vehicle contract has been executed.               Budget/Costs Incurred
The Medical Aid Unit contract has been executed; the Aid vehicle will    1.5
be in service beginning July 2010.
1
This will be the last quarterly report for this project.                   Millions
0.5
Schedule                            Dollars in
The project is on schedule.                                 0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
46  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Highline School Noise Insulation
Project:   C200007      Highline School Insulation        Status Snapshot Prior Report
Budget: $101,797,000    Agreement will provide funding for  Delayed Schedule 3Q 09
Phase: Construction     sound mitigation for 15 schools that  On Budget
Start: 03/23/1999         are impacted by aircraft noise from   0 Change Orders
Completion: 11/30/2021   Sea-Tac Airport.            Total Change Orders Amount:
$0
Significant Developments
The insulation of seven schools has been completed and no more    Budget/Costs Incurred
are scheduled until 2012.
120
100
Schedule
80
Port funding is authorized and will be available when the matching
60
funds are provided by the FAA, the State of Washington, and the      in Millions
40
Highline School District. The schedule for state funding is not known.    Dollars  20
The district's schedule is dependent on obtaining general election
0
bonds at various intervals.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Not applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2010 Report  47

FOURTH QUARTER REPORT, 2010
3rd Runway Residential Acquisition
Project:   C200015      Acquire single/multi-family        Status Snapshot Prior Report
Budget: $34,340,000     residences located in the noise-    Delayed Schedule 1Q 10
Phase: Close Out      impacted 3rd Runway flight path in  On Budget
Start: 05/27/1999         the City of Burien to comply with    0 Change Orders
Completion: TBD       FAA noise exposure and safety    Total Change Orders Amount:
regulations.                   $0
Significant Developments                    Budget/Costs Incurred
The final of three phases is complete. 58 of 59 properties have been    60
acquired and the residents relocated to quieter neighborhoods. The
apartment building property settled in mediation. One remaining       40
single property was determined by the court to be compatible land      Millions
use and will not be acquired.                               20
Dollars in  0
Schedule
Authorized  Forecasted Costs Incurred
The project is currently on schedule. Demolition of the remaining
structures will begin during the first quarter of 2011.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Photo
Change Order
Not Applicable
Risks
No significant risks identified.
Budget Transfers
None this quarter



AIRPORT
48  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $10,822,000     Insulation Agreement will provide   Delayed Schedule 1Q 08
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      0 Change Orders
Completion: 10/01/2011   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
$0
Significant Developments
Twelve of the 22 eligible buildings have been sound insulated by the  Budget/Costs Incurred
college.
12
Schedule                             10
Building #9 is under construction and is anticipated to be complete      8
the first quarter of 2011. The schedules for the remaining buildings      6
in Millions
are dependent on state funding.                             4
Dollars   2
Budget                             0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
the remaining project budget will be requested for one building at a
time from the Commission in the future when schedule is
determined.                                     Construction Costs
Not Applicable
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed. The Port is working with the College to determine
estimates for the remaining college buildings that have not been
completed.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2010 Report  49

FOURTH QUARTER REPORT, 2010
Home Insulation Retrofit
Project:   C200048      This CIP includes two projects that   Status Snapshot Prior Report
Budget: $5,344,000      provide either re-insulation or repair  Delayed Schedule 4Q 09
Phase: Construction     of previously insulated homes due  On Budget
Start: 01/11/2005         to safety issues.              0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The Port is researching remaining eligible homes to continue with
insulation retrofit and storm window retrofit .                       6
5
Schedule                             4
The project will commence upon Job Order Contract approval.         Millions 3
2
Budget                             Dollars in 1
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable
Construction Costs
Risks                               Not Applicable
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter.




AIRPORT

50  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot
Budget: $2,450,000      that are within the 1998 65 decibel  On Schedule
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   0 Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Nine homes are in process and there are 19 on the waiting list for the
6
next group.
5
Millions  4
Schedule
3
This project is on schedule.
2
Dollars in   1
Budget
0
The project forecast is within approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable                                     Construction Costs
Not Applicable
Risks
The ability to accomplish the insulation is dependent on
homeowner's schedules, willingness to sign an aviation easement
and obtain a subordination agreement from their lender, and
structural integrity of the home.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 4Q 2010 Report  51

FOURTH QUARTER REPORT, 2010
Street Vacations - Des Moines Creek 1
Project:   C800046    Purchase the City of Des Moines-      Status Snapshot
Budget: $3,850,000   owned streets in the Des Moines Creek  Delayed Schedule
Phase: Implementation Business Park site that are surrounded  On Budget
Start: 10/01/2008      by Port-owned property. This        0 Change Orders
Completion: 6/30/2011  acquisition will enable the Port to     Total Change Orders Amount:
develop the business park site.        $0
Significant Developments                    Budget/Costs Incurred
Per the Port's agreement with the City of Des Moines, the amount
3.86
owed the City has been deposited into an escrow account pending
3.84
satisfaction of all the conditions required for closing.
3.82  Millions
Schedule                             3.8
Waiting on FAA approval. Expect to close the streets owned by the    3.78  Dollars in 
City of Des Moines by the end of March 2011. Final acquisition is
3.76
expected to be completed by June 30, 2011.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Not applicable.
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

52  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot Prior Report
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule    2Q 10
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   0 Change Orders
Completion: 12/31/2011   owned properties.           Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The Burien Seventh Day Adventists Church and School were
3.5
acquired December 31, 2008. Next acquisitions are for the
3
Sunnydale Substation and a street vacation in Burien.
Millions 2.52
Schedule                             1.5
Properties are purchased as Commission authorization is received.     Dollars in  1
The program is expected to be complete in 2011. The last parcel to     0.5
0
be acquired is tied to the North East Redevelopment Area (NERA)
Authorized  Forecasted Costs Incurred
project which is a joint effort with the city of Burien. They will not be
ready to vacate the street until 2011.
Budget                            Construction
Not Applicable
The project forecast is within the approved budget.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 4Q 2010 Report  53

FOURTH QUARTER REPORT, 2010
Tenant Reimbursement
Project:   C800154    Build out of spaces for new and      Status Snapshot
Budget: $4,709,577    existing tenants. If more than a "basic  On Schedule
finish" condition space is built for the    On Budget
Phase: Construction
tenant, the tenant is required to       0 Change Orders
Start: 08/14/2007
reimburse the Port for the cost of the   Total Change Orders Amount:
Completion: 03/31/2012
work beyond this "basic finish". These   $0
reimbursements are allowed under
the guidelines described in the       Budget/Costs Incurred
"Tenant Reimbursement Policy".
5
Significant Developments                      4
There were no tenant reimbursements during the fourth quarter of      Millions 3
2010. The Airport is, however, working to revise the Tenant
2
Reimbursement Guidelines in coordination with the Airlines.          Dollars in  1
Completion of revised Reimbursement Guidelines is anticipated
during the first quarter of 2011.                                0
Authorized  Forecasted Costs Incurred
Schedule
Schedules vary to meet the tenant's needs.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
54  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Paint Striper Equipment
Project:   C800354      Via a competitive process,       Status Snapshot
Budget: $420,000       purchase one Truck Chassis     Delayed Schedule
Phase: Implementation   Mounted Airless Application Paint   On Budget
Start: 09/01/2010         Striping Unit for the Airport. This    0 Change Orders
Completion: 10/31/2011   requested paint striper equipment   Total Change Orders Amount:
is necessary to meet operational,    $0
safety and regulatory requirements.
Budget/Costs Incurred
Significant Developments
The contract has been advertised and bid opening date is March 11,    0.5
2011.                                         0.4
Millions 0.3
Schedule
0.2
The equipment is expected to be in service in the third quarter of       Dollars in 0.1
2011.
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 4Q 2010 Report  55

FOURTH QUARTER REPORT, 2010
28th Ave Property Acquisition
Project:   C800381      Acquire by purchase two King     Status Snapshot Prior Report
Budget: $1,455,000      County Parcels 042204-9218 &    Ahead of Schedule 3Q 10
Phase: Implementation   042204-9139. Demolish the      On Budget
Start: 5/4/2010          improvements on the Property and   0 Change Orders
Completion: 11/31/2010   restore it in accordance with the    Total Change Orders Amount:
Interlocal Agreement.           $0
Budget/Costs Incurred
Significant Developments
1.456
The project is complete. This will be the last quarterly report on this
1.454
CIP.
1.452   Millions
Schedule                             1.45
The project was completed ahead of schedule.                 1.448  Dollars in 
1.446
Budget
Authorized  Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
None identified at this time
Budget Transfers
None this quarter



AIRPORT

56  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
T-115 Dock Reconstruction
Status Snapshot Prior Report
Project:   C102451      Upgrade three areas of existing    Delayed Schedule 4Q 08
Budget: 31,541,577      1200 ft dock, upgrade Berth 1 and  Forecast Overrun 1Q 08
Phase: Construction     improve 15 acres of uplands for    29 Change Orders
Start: 7/03             tug/barge cargo operations.       Total Change Orders Amount:
Completion: 12/31/09                        $1,748,865
Significant Developments                    Budget/Costs Incurred
Construction was completed in 2Q 2010. The Tenant began using      32
Berth 1 at the end of April 2010. Final contract negotiations will
31.5
extend into 1Q 2011.                                  Millions 31
Schedule                            30.5
Dollars in 
Project finalization is expected to move from 4Q 2010 to 1Q 2011.      30
Authorized  Forecasted Costs Incurred
Budget
No change this quarter.
Construction Costs
Change Order                           30
A change order was approved for unexpected difficulties in driving
20
pipe and sheet pile caused by unanticipated underwater            Millions
obstructions. However, project is expected to stay within the           10
approved budget.
Dollars in    0
Risks                                   InitialChange OrdersSpent
None
Photo
Budget Transfers
None
Cost Growth of Construction
No change from last report, cost growth remains at 17.4 percent.


SEAPORT

Port of Seattle 4Q 2010 Report  57

FOURTH QUARTER REPORT, 2010
Terminal 30/Terminal 91 Program
Project:   C800085      Redevelop Terminals 25/28/30 into  Status Snapshot
Budget: $121,525,000    one combined container facility.    On Schedule
Phase: Construction     Relocation of the existing T-30    On Budget
Start: 10/02/07          Cruise operations into a new facility  129 Change Orders
Completion: 04/30/11    at T-91, and related facility      Total Change Orders Amount:
improvements and berth dredging.   $6,581,000
Significant Developments                    Budget/Costs Incurred
T-91: Canopy lighting/power receptacle and fence design is
125
complete and scheduled for installation. Welcome Figures Artist has
begun carving the art piece. The Graphic Artist selection process is     120
ongoing.                                        Millions
115
Schedule
110  Dollars in 
T-91: Canopy electrical/lighting and fence installation work are the
remaining work elements to be completed under the December 2009   105
Commission authorization. The remaining work is currently             Authorized Forecasted Costs Incurred
scheduled to be completed by end of 1Q 2011 and will be ready for
the new cruise season. Terminal's public arts component is ongoing
and scheduled to be completed in late 2011.                  Construction Costs
100
T-30: T-30 components of the Program are in closeout and will no
longer be included in quarterly reports as previously reported.          80
Millions  60
Dollars in 
Budget
40
The budget remains stable. Current program budget is $121,500,000
20
and the forecast is $113,500,000.
0
Change Order                             InitialChange OrdersSpent
There were no change orders this quarter. Major construction
contracts have been partially closed out.                     Photo
Risks
T-91: None. Facility is in operation.
T-30: None. Facility is in operation.


58  Port of Seattle 4Q 2010 Report

Budget Transfers
There were no budget transfers in or out of the program.
Cost Growth of Construction
T-91 Cruise Terminal Upgrade  MC-0314783  The major
construction contract is in closeout.
T-30 Upgrade  MC-103326  The major construction contract is in
closeout.
The cost growth of construction remains as reported in
4Q 09 for both contracts.









SEAPORT

Port of Seattle 4Q 2010 Report  59

FOURTH QUARTER REPORT, 2010
P66 Bag. Corridor & Pass. Screening
Project:   C800114      Provide baggage and passenger    Status Snapshot Prior Report
Budget: $2,087,000      screening improvements at P66 to  Delayed Schedule 3Q 09
Phase: Construction     accommodate larger cruise vessels  On Budget
Start: 1/1/2008          with 300-400 more passengers per   0 Change Orders
Completion: 3/31/2011    sailing.                Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
One project remains in this CIP, an elevator upgrade.
2.5
Schedule                             2
Construction is underway and on-schedule with an anticipated        1.5
completion date of March 2011.                           in Millions 1
Dollars 0.5
Budget
0
None
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
The biggest risk is that there may be unforeseen conditions that
could possibly delay the project and conflict with the cruise schedule.
Budget Transfers
None




SEAPORT
60  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Terminal 18 South Fender Improvements
Status Snapshot Prior Report
Project: C800121        Replace 800' of deteriorated fender
On Schedule 4Q 09
Budget: $3,300,000      system at the south end of
Under Budget
Phase: Design        Terminal 18.
0 Change Orders
Start: 3/26/08                                   Total Change Orders Amount:
Completion: 3/31/11                         $0
Budget/Costs Incurred
Significant Developments
3.5
Contract awarded for replacement of 800' of the fender system to       3
Millions 2.5                                                                                             Manson Construction.  Notice to Proceed to the contractor given on
2
12/10/2010. Demolition of the existing fender has begun.
1.5
Dollars in   1
Schedule                             0.5
0
No change from last report. Construction began in December 2010,
Authorized   Forecasted  Costs Incurred
with berth available for use in March 2011.
Budget
Construction Costs
Project within approved budget. Favorable bids indicate the project
None at this time
should complete under the authorized amount.
Photo
Change Order
None this quarter
Risks
None this quarter
Budget Transfers
None



SEAPORT

Port of Seattle 4Q 2010 Report  61

FOURTH QUARTER REPORT, 2010
T-5 Crane Spreader Replacement          Status Snapshot Prior Report
Delayed Schedule 1Q 10
Project:   C800123      To replace two crane cargo       On Budget
Budget: $525,000       spreader beams that are beyond   0 Change Orders
Phase: Construction     their useful life. Spreader beams   Total Change Orders Amount:
Start: 10/24/06          are terminal equipment used to     $0
Completion: 3/31/09     move containers to and from ships
and trucks.                  Budget/Costs Incurred
0.54
0.53
Significant Developments                     Millions
Spreader Beams were delivered 3Q 2010. Beams were in operation    0.52
during the 4Q 2010. This is the last report.                      0.51  Dollars in 
0.5
Schedule
Authorized  Forecasted Costs Incurred
Project is closed and scheduled to be retired.
Budget                            Construction Costs
On budget
0.5
Change Order                           0.4
0.3
None
0.2
Millions
Risks                                Dollars in  0.1
None                                    0
Initial Change Orders Spent
Budget Transfers
None                                 Photo




SEAPORT

62  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
T-86 Grain Facility Modernization           Status Snapshot Prior Report
On Schedule
Modernize and replace aging grain   On Budget
Project:   C800133      facility equipment/controls for $5M   1 Change Orders
by 12/31/2011 to maximize       Total Change Orders Amount:
Budget: $2,500,000
operational efficiencies and allow    $33,123.00
Phase: Construction     continuation of uninterrupted grain
Start: 2/21/2010          terminal operations.           Budget/Costs Incurred
Completion: 11/30/2011
3

2
Significant Developments                     Millions
Phase-1 portion of the project is complete. Final close out            1
procedures are in process.                               Dollars in 
0
Phase-2 portion of the project has been advertised; however, the         Authorized Forecasted Costs Incurred
advertisement was cancelled due to tenant shutdown schedule
concerns for Q2 2011. Staff has separated the equipment
Fabrication and Installation components to accommodate the tenant   Construction Costs
2011 shutdown schedule. Tenant will notify staff when the shutdown  Not Applicable
period will occur.
Photo
Schedule
Phase-2 project delayed due to tenant shutdown schedule.
(Expected shutdown is between Q2 2011 and Q3 2011).
Budget
None
Change Order
Phase-1 $33,123
Risks
None
Budget Transfers
None

SEAPORT
Port of Seattle 4Q 2010 Report  63

FOURTH QUARTER REPORT, 2010
North Harbor Island Mooring Dolphins (4)
Project:   C800182      Replace four barge mooring      Status Snapshot
Budget: $2,350,000      dolphins at the north end of Harbor  On Schedule
Phase: Design        Island.                Under Budget
Start: 07/05/09                                   0 Change Orders
Completion: 3/31/11                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Contract awarded for replacement of the dolphins to Northwest
2.5
Marine Construction. Notice to Proceed was given to the contractor
2
on November 3, 2010. Demolition scheduled to begin in January.
1.5  Millions
1
Schedule
0.5
Project is still on schedule to be completed within the 2010-11 permit    Dollars in 
0
fish window. Beneficial occupancy expected by March 31, 2011.
Authorized  Forecasted    Costs 
Incurred
Budget
Favorable bids indicate the project should complete under the
authorized amount.                                 Construction Costs
None
Change Order
None                                 Location
North Harbor Island
Risks
Photo
Contractor schedule remains very tight.
Budget Transfers
None



SEAPORT

64  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
P91 Fender System Upgrade
Project:   C800183      Upgrades to the vessel berths of    Status Snapshot
Budget: $2,125,000      P91 to better accommodate cruise  On Schedule
Phase: Design        ships and also serve the other    On Budget
Start: 01/31/10          industrial customers who utilize the   0 Change Orders
Completion: 04/30/2012   berths and adjacent dock/apron    Total Change Orders Amount:
areas on P91 for less than $6M by   $0
spring 2011.
Budget/Costs Incurred
Significant Developments
Design is complete for Phase I construction consisting of the          2.5
replacement of 15 piles to strengthen the facility for the 2011-12        2
cruise season. Remaining design is underway.                 Millions 1.5
1
Schedule
Dollars in 0.5
Phase I construction is scheduled to start in January 2011, complete
by April 2011. Full replacement is to be completed by April 2012.        0
Authorized  Forecasted Costs Incurred
Budget
Project is within approved budget.
Construction Costs
Change Order                         None at this time
None this quarter
Risks
None this quarter
Budget Transfers
None



SEAPORT

Port of Seattle 4Q 2010 Report  65

FOURTH QUARTER REPORT, 2010
T-10 Interim Redevelopment
Status Snapshot Prior Report
Project:   C800264      Funding is to develop full project
Budget: $980,000       scope and design of utilities to    Delayed Schedule 2Q 10
Phase: Design        support terminal related activities.   On Budget
Start: 03/22/08          Primary focus is the design of the    0 Change Orders
Completion: 11/30/2009   storm water drainage system and   Total Change Orders Amount:
the paving, lighting and fencing.     0
Significant Developments
Budget/Costs Incurred
As noted previously, revised design and permit documents were
submitted to the City, State and Federal Agencies. Staff continues to     8
work on addressing permit requirements with the EPA and
6
Department of Natural Resources. We expect to receive the permit in
1Q 2011
Millions  4
2
Schedule                            Dollars in 
The scheduled completion remains at 3Q 2011.                 0
Authorized  Forecasted Costs Incurred
Budget
Staff will return to Commission for additional construction          Construction Costs
authorization 1Q 2011. The permit conditions will increase the      Not Applicable
environmental reserve costs. The condition of zero storm and
ground water discharge from the site during construction is the most   Photo
significant cost impact.
Change Order
None
Risks
Schedule delays
Budget Transfers
None


SEAPORT

66  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
T-91 Watermain Replacement
Project:   C800298      Replace water main in the vicinity   Status Snapshot Prior Report
Budget: $4,255,000      of Magnolia Bridge and City      On Schedule
Phase: Construction     Ice/Trident including various     On Budget
Start: 9/20/2009          buildings at T91              0 Change Orders
Completion: 12/30/2011                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Commission approved project to move forward. Construction is now
5
in progress.
4
Schedule                            Millions 3
Dollars in 
On schedule                                    2
1
Budget
0
On budget
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
Contaminated material may be encountered throughout the        Photo
excavation process.
Budget Transfers
None



SEAPORT

Port of Seattle 4Q 2010 Report  67

FOURTH QUARTER REPORT, 2010
T-91 Roadway Pavement Project
Project:   C800343                             Status Snapshot Prior Report
Budget: $895,000     Repave two main roadway        Delayed Schedule 2Q 10
Phase: Design       intersections and the adjacent areas   On Budget
Start: 12/18/09         west of the east guard shack.        0 Change Orders
Completion: 5/1/2011                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
PCS completed Phase 1 paving work (area along the east portal
1
under the Magnolia Bridge) and continued to work on the remaining
construction phases. Construction activities have been carefully       0.8
coordinated with those from the Water Main Project team to          Millions 0.6
maximize construction efficiency.
0.4
Dollars in 0.2
Schedule
0
Construction is on schedule and will be fully completed by the 2011
Authorized  Forecasted Costs Incurred
Cruise season.
Budget
Construction Costs
Project is currently on budget.                             Not Applicable
Change Order                         Photo
None
Risks
Phase 1 paving work has gone well but because paving work is
weather dependent, there could be potential weather related delays.
Also, the conditions of remaining existing underground vaults and
utilities within the project area cannot be accurately assessed until
they are fully exposed after construction starts.
Budget Transfers
None

SEAPORT

68  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
T46 Upgrade Yard Lighting
Status Snapshot
Project:   C800347      Purchase and Engineering support  On Schedule
Budget: $680,000       for installation of energy saving    On Budget
Phase: Design        yard lighting and equipment, as    0 Change Orders
Start: 08/25/09          part of T46 lease negotiation.      Total Change Orders Amount:
$0
Completion: 12/31/2010
Budget/Costs Incurred
Significant Developments
0.69
Procurement complete, this will be the last regular report on this
0.68
project. A final status report will be provided upon tenant installation.
0.67  Millions
0.66
Schedule
0.65
On schedule
0.64  Dollars in 
0.63
Budget
Authorized  Forecasted Costs Incurred
No change
Change Order                         Construction Costs
None                                 Not Applicable
Risks                               Photo
None
Budget Transfers
None




SEAPORT

Port of Seattle 4Q 2010 Report  69

FOURTH QUARTER REPORT, 2010
T-5 Crane Cable Reels
Status Snapshot
Project:   C800349      Purchase Cable Reels for tenant.
Budget: $3,500,000                         Delayed Schedule
Phase: Design                            On Budget
Start: 05/04/10                                   0 Change Orders
Completion: 03/31/11                         Total Change Orders Amount:
0
Significant Developments
Budget/Costs Incurred
Commission approved funding for the Project on May 4, 2010. The
technical specification was completed 4Q 2010. The request for
5
quote will be issued in 1Q 2011.
4
Schedule                            Millions 3
Dollars in 
Delivery of material delayed six months.                        2
1
Budget
0
None                                    Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
Schedule                                   Photo
Budget Transfers
None




SEAPORT

70  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
T18 Fender Replacement
Project:   C800416      Replacement of 200 timber fender   Status Snapshot
Budget: $5,465,000      piles and their supporting members  On Schedule
Phase: Construction     along the face of the SSA crane    On Budget
Start: 02/07/2010         terminal.                   0 Change Orders
Completion: 03/15/2012                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Contract awarded to General Construction. Notice to Proceed was
7
given to the contractor on November 2, 2010. Demolition scheduled     6
to begin in January.
Millions  5
4
Schedule                             3
2
Construction scheduled in two phases to accommodate permit       Dollars in 
1
windows and tenant operations. First phase scheduled to start in
0
January 2011, second phase to be completed by March 2012.
Authorized  Forecasted Costs Incurred
Budget
Project is within the approved budget.                       Construction Costs
None at this time
Change Order
None this quarter                                    Photo
Risks
None this quarter
Budget Transfers
None



SEAPORT

Port of Seattle 4Q 2010 Report  71

FOURTH QUARTER REPORT, 2010
East Marginal Way Grade Separation
Project:   E 102007      FAST Corridor funded project;     Status Snapshot Prior Report
Budget: $50,700,000     FHWA, State, City with Port      On Schedule 4Q 10
Phase: Construction     commitment of $18,800,000. Scope  On Budget 4Q 10
Start: 5/2006            is to construct grade separation in   10 Change Orders
Completion: Q3 2011     vicinity of T5 and T18 to minimize   Total Change Orders Amount:
truck traffic/rail conflicts.            $411,876
Budget/Costs Incurred
Significant Developments
60
Bridge substructure complete and span girders were placed early      50
February 2011. Utility installation includes large stormwater quality
vault.
Millions 40
30
20
Schedule                            Dollars in 10
Construction is 60% complete and scheduled completion remains      0
September 1, 2011. The overall program schedule remains as was        Authorized Forecasted Costs Incurred
reported in 4Q 09. The Schedule status snapshot is On Schedule
reflecting the current construction schedule.
Construction Costs
Budget
The overall program budget remains the same as reported in 4Q 09.     25
On future reports the budget that will be tracked will be the current       20
construction costs. The Budget status snapshot is On Budget         Millions 15
reflecting the active construction budget.
10
Change Order                          Dollars in  5
Ten change orders have been executed for a total net amount of        0
$411,876.                                          InitialChange OrdersSpent
Risks
Construction change orders could occur, which could increase cost   Photo
of construction.
Budget Transfers
New source of funds indicates that no budget transfers will be
required.

SEAPORT
72  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Terminal 46 ZPMC Gearboxes
Project:   Expense      Implementation of contingency     Status Snapshot
103705,103706,103707    plans to keep the three port owned  On Schedule
Budget: $1,227,000      ZPMC cranes located at Terminal   On Budget
Phase: Construction     46 operating while cause of the    0 Change Orders
Start: 8/22/2007          failing gearboxes is investigated    Total Change Orders Amount:
$0
Completion: 12/31/09*
Budget/Costs Incurred
Significant Developments
1.4
ZPMC sent letter to manufacturer of gearbox to replace all
1.2
gearboxes with new redesigned gearboxes. Continued efforts to        1
work with manufacturer to resolve, will be managed as an operating    Millions 0.8
expense, as such the gear boxes will no longer appear in quarterly     0.6
reports.                                              Dollars in 0.4
0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
Contingency plans were implemented through December 2008 as
spare parts were received and stored for future use when another
failure occurs. Monitoring of gearbox vibrations and oil quality occurs
Construction Costs
on a quarterly basis.
No Major Construction
Contracts
Budget
Budget remains unchanged from the 2Q 10 Report. Annual operating
expenses are $25,000 for quarterly monitoring and $90,000 for      Photo
potential gearbox replacement labor.
Change Order
None this quarter
Risks
Additional gearbox failures would result in further disruptions to
operations.
Budget Transfers
None

SEAPORT
Port of Seattle 4Q 2010 Report  73

FOURTH QUARTER REPORT, 2010
T5 Maintenance Dredging
Project:   Expense   Mechanically dredge up to 3,000 cy of   Status Snapshot
103835           sediment at T-5 and dispose of      On Schedule
Budget: $1,980,000   dredged material at approved upland   On Budget
Phase: Construction  disposal sites; conduct environmental   0 Change Orders
Start: Feb 2008       testing, permitting, and design work for   Total Change Orders Amount:
T-5 maintenance dredging          $0
Completion: Feb 2011
Budget/Costs Incurred
Significant Developments                     2.5
Construction began in December as planned.                   2
Millions 1.5   Dollars in 
Schedule
1
On schedule
0.5
Budget                             0
On budget                                       Authorized Forecasted Costs Incurred
Change Order
Construction Costs
Not applicable
Not Applicable
Risks
Photo
Not applicable
Budget Transfers
Not applicable




SEAPORT

74  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Street Vacations T5,18,105
Status Snapshot
On Schedule
Project: Expense     Street vacation related real estate     On Budget
104362, 104364, 104366 negotiations and agreements --T5,     0 Change Orders
Budget: $1,500,000   T18, and T105.              Total Change Orders Amount:
Phase: Permitting                         $0
Start: June 2010
Completion: Feb 2012                        Budget/Costs Incurred
2
Significant Developments                     1.5
Not applicable                                       Millions
1
Schedule                            Dollars in 0.5
On Schedule
0
Authorized  Forecasted Costs Incurred
Budget
On Budget
Construction Costs
Change Order                         Not Applicable
Not applicable
Photo
Risks
Not applicable
Budget Transfers
Not applicable



SEAPORT

Port of Seattle 4Q 2010 Report  75

FOURTH QUARTER REPORT, 2010
T 102 HVAC Renewal/Replacement
Project:   C800070      Replace HVAC System at all four   Status Snapshot Prior Report
Budget: $1,425,000      buildings at the Harbor Marina    Delayed Schedule 4Q 08
Phase: Construction     Conference Center          On Budget
Start: 10/2/2005                                  0 Change Orders
Completion: 3/1/2011                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Six of the remaining seven HVAC units have been installed and
1.45
booked. The last unit will be installed in Q1 2011.
1.4
Schedule                            1.35 Millions
Installation will be complete by Q1 2011.                       1.3
1.25  Dollars in 
Budget
1.2
Anticipate approximately $80,000, of approved budget, remaining
Authorized  Forecasted Costs Incurred
after all invoices are paid.
Change Order                         Construction Costs
None
0.4
Risks
0.3
None                                  Millions
0.2
Budget Transfers
Dollars in   0.1
None
0
Initial Change Orders Spent



REAL ESTATE

76  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
FT South Wall Reconstruction Phase IV
Project:   C800136      Completion of Fishermen's       Status Snapshot
Budget: $5,535,000      Terminal South Wall         On Schedule
Phase: Construction     Reconstruction. Phase IV is located  On Budget
Start: 6/2009            along parcel currently leased by    0 Change Orders
Completion: 6/2011      FVO.                 Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
IMCO (general contractor) ordered steel sheet piling from
6
manufacturer and has been making submittals to the Port as
5
required prior to NTP being issued. Geotechnical consultant service
4
directives have been finalized for necessary upcoming construction     Millions
3
monitoring.
2
Dollars in 
Schedule                             1
0
NTP anticipated to be issued in January 2011.
Authorized  Forecasted Costs Incurred
Budget
None this quarter                                    Construction Costs
$15,000
Change Order
None this quarter                                    Photo
Risks
None this quarter
Budget Transfers
None



REAL ESTATE

Port of Seattle 4Q 2010 Report  77

FOURTH QUARTER REPORT, 2010
FT C15 HVAC Improvements
Status Snapshot
Project:   C800137      Provide the preliminary planning,
Budget: $4,000,000      design, and construction for      Delayed Schedule
Phase: Design        replacing the FT C15 HVAC      On Budget
Start: 05/01/10          System.                   0 Change Orders
Completion: 12/31/2012                       Total Change Orders Amount:
0
Significant Developments
Budget/Costs Incurred
Design consultant selected and contract negotiations in progress.
1
Schedule
0.8
Design behind schedule by 6 weeks.                       Millions 0.6
0.4
Budget
Dollars in 0.2
On budget
0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
Contract negotiations must proceed quickly in order to meet
schedule.
Budget Transfers
None




SEAPORT
78  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
MIC Central Seawall Replacement
Project:   C800175      Replacement of steel sheet pile    Status Snapshot
Budget: $2,650,000      seawall between West Pier and    On Schedule
Phase: Construction     Central Pier at Maritime Industrial   On Budget
Start: 9/2008            Center.                    0 Change Orders
Completion: 6/2011                          Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
MCO (general contractor) ordered steel sheet piling from
3
manufacturer and has been making submittals to the Port as
2.5
required prior to NTP being issued. Geotechnical consultant service
2
directives have been finalized for necessary upcoming construction     Millions
1.5
monitoring.
1
Dollars in 
Schedule                             0.5
0
NTP anticipated to be issued in January 2011.
Authorized  Forecasted Costs Incurred
Budget
None this quarter                                    Construction Costs
$20,000
Change Order
None this quarter                                    Photo
Risks
None this quarter
Budget Transfers
None this quarter



REAL ESTATE

Port of Seattle 4Q 2010 Report  79

FOURTH QUARTER REPORT, 2010
FT NW Dock East Fender System Replacement
Project:   C800386      Replace existing timber fender     Status Snapshot
Budget: $3,750,000      system for the east section of the   On Schedule
Phase: Construction     NW Dock at Fishermen's Terminal  On Budget
Start: January 2010       including all new steel piling and    0 Change Orders
Completion: April 2011   associated fender system.       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Construction contract was executed. Contractor mobilized on site
4
and started work.
3
Schedule                            Millions
2
Site construction work started in mid January 2011 and will be
completed by the end of April 2011.                         Dollars in  1
0
Budget
Authorized  Forecasted Costs Incurred
Total project budget is $3,750,000.
Change Order                         Construction Costs
No construction change orders to date.
2.5
Risks                                 2
In-water pile replacement work must be completed by April 15, 2011     1.5
to comply with anticipated permit requirements.
Millions
1
Budget Transfers                          Dollars in  0.5
None                                   0
InitialChange OrdersSpent



REAL ESTATE

80  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Flight Information System (FIMS) II
Project: C101117        Procure, develop, and implement a  Status Snapshot
Budget: $5,400,000      FIMS system that includes       On Schedule
Phase:Design         replacement monitors, an airport   On Budget
Start: 5/4/2010           resource management system, and  0 Change Orders
Completion: 12/30/2012    a flexible digital signage system    Total Change Orders Amount:
capable of displaying flight         $0
information, visual paging, and
notifications.
Budget/Costs Incurred
Significant Developments
6
Evaluating vendor proposals for a replacement resource
5
management system. Planning and software architecture design in
progress. Casework design contract $50,000 more than anticipated    Millions 4
3
but overage can be accomodated with budgeted contingency.
2
Dollars in   1
Schedule
0
On Schedule
Authorized  Forecasted Costs Incurred
Budget
On Budget                                  Construction Costs
Not Applicable in the phase
Change Order
None
Risks
Aircraft activity feeds will be requested from every airline in the new
industry standard format. There is a risk that not all airlines will
initially agree to this request causing a schedule delay.
Budget Transfers
None


CORPORATE

Port of Seattle 4Q 2010 Report  81

FOURTH QUARTER REPORT, 2010
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, add service desk module   0 Change Orders
Completion: 12/30/2012   and wireless handheld capabilities.  Total Change Orders Amount:
$0
Significant Developments
Major components of the program have been delivered including the  Budget/Costs Incurred
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of         4
Marine Maintenance and Aviation Maintenance Maximo systems in
3
September 2010. The smaller components of mobility enhancements
and additional interfaces are in progress.                        2
in Millions
Schedule                            Dollars  1
Prior Report - Several of the proposed new interfaces link the          0
Maximo system to the Peoplesoft Financials Procurement module.        Authorized Forecasted Costs Incurred
Because of planned changes in the procurement process with the
Peoplesoft Financials Upgrade project, the delivery of these
interfaces may be delayed until after the completion of the upgrade   Construction Costs
project. Due to resource constraints, the delivery of the mobility      Not Applicable
enhancements will be completed in June 2011.
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces and mobility enhancements.
Budget Transfers
None

CORPORATE
82  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Ground Transportation Management System
Project: C800227        Procure and implement a Ground   Status Snapshot
Budget: $840,000       Transportation Management      On Schedule
Phase: Planning        System for tracking and billing     On Budget
Start: 4/27/2010          ground transportation operators at   0 Change Orders
Completion: 6/30/2011    the airport.               Total Change Orders Amount:
$0
Significant Developments
Vendor selected through competitive procurement. Project kickoff    Budget/Costs Incurred
completed in mid-November 2010. Working on requirements and
design.                                            1
0.8
Schedule
0.6
On Schedule                                   Millions
0.4
Dollars in 0.2
Budget
0
On Budget
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No significant risks
Budget Transfers
None




CORPORATE

Port of Seattle 4Q 2010 Report  83

FOURTH QUARTER REPORT, 2010
Port of Seattle Internet Redesign
Project: C800319        Create a new Internet web site, and  Status Snapshot Prior Report
Budget: $500,000       underlying infrastructure, with     Delayed Schedule     2Q 10
Phase:Planning        dynamic content and interactive    On Budget
Start: 1/6/2009           communication tools such as blogs,  0 Change Orders
Completion: 6/30/2011    video, podcasts, discussion forums  Total Change Orders Amount:
and interactive maps.           $0
Significant Developments                    Budget/Costs Incurred
Vendor selected to lead requirements and development of new Port
0.6
of Seattle website. Contract signed in late January 2011.
0.5
Schedule                            Millions 0.4
0.3
Prior Report - The delay caused by the need to re-advertise the RFP
0.2
for an implementation vendor will delay the estimated completion to     Dollars in 
2nd quarter 2011.                                     0.1
0
Budget                               Authorized Forecasted Costs Incurred
On Budget
Change Order                         Construction Costs
Not Applicable
None
Risks
No significant risks identified
Budget Transfers
None



CORPORATE

84  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
External Sharepoint
Project: C800320        Implement External Microsoft     Status Snapshot Prior Report
Budget: $500,000       Sharepoint Services to support    Delayed Schedule     1Q 10
Phase:Implementation    application consolidation, customer  Under Budget
Start: 1/6/2009           collaboration, and system        0 Change Orders
Completion: 2/1/2011     integration opportunities.        Total Change Orders Amount:
$0
Significant Developments
Project was put on hold by ICT Management to evaluate security     Budget/Costs Incurred
issues and potential solutions identified during architecture             Dollars [Thousands)
600
development. After evaluation, a lower-cost solution utilizing a
500
hosted sharepoint environment has been selected that will meet the
400
current needs for the Port Internet Redesign and other external
projects.                                               300
200
Schedule                             100
Solution is in progress and will be ready for deployment in February      0
Authorized    Forecasted   Costs incurred
2011.
Budget                            Construction Costs
This solution can be delivered at a lower-cost than the original       Not Applicable
proposed solution resulting in an estimated 50% under-run of
$250,000.
Change Order
None
Risks
No significant risks
Budget Transfers
None


CORPORATE

Port of Seattle 4Q 2010 Report  85

FOURTH QUARTER REPORT, 2010
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot Prior Report
Budget: $1,525,000      costing systems with a common    Delayed Schedule
Phase:Planning        enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: 9/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Configuration workshops and prototyping have been completed.     Budget/Costs Incurred
Next phase includes the installation of the software in the Port
environment and interface development.                      2
1.5
Schedule
Prior Report - Vendor did not deliver software per original contract       Millions 1
and project was put on-hold to evaluate alternatives. A decision was
Dollars in 0.5
made to continue with Skire in July 2010. The estimated completion
date at this time is September 2011 although there may be interim      0
deliveries prior to completion.                                   Authorized Forecasted Costs Incurred
Budget
Construction Costs
None
Not Applicable
Change Order
None
Risks
See Schedule
Budget Transfers
None



CORPORATE
86  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot
Budget: $800,000       increase functionality, and lower   Delayed Schedule
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 4/30/2012    records and document        Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
Incorporating upgrade to Sharepoint 2010 because of significant
improvements in Records Management features.
1
Schedule                             0.8
Sharepoint 2010 implementation is dependent on the completion of     Millions 0.6
several infrastructure projects currently in progress and requires       0.4
additional time to complete the upgrade of existing sites. While        Dollars in 0.2
Sharepoint 2010 will be available to departments beginning in April
0
2011, the implementation of Sharepoint Records Center will not be
Authorized  Forecasted Costs Incurred
complete until December 2011. The full project is estimated to be
completed in April 2012.
Budget                            Construction Costs
Not Applicable
On Budget
Change Order
None
Risks
Scope of Sharepoint 2010 upgrade may require additional funding to
complete migration activities.
Budget Transfers
None

CORPORATE

Port of Seattle 4Q 2010 Report  87

FOURTH QUARTER REPORT, 2010
Business Continuity
Project: C800326        Acquire new backup and storage   Status Snapshot Prior Report
Budget: $1,760,000      software and hardware that will    Delayed Schedule
Phase:Implementation    facilitate business continuity in the  On Budget
Start: 6/23/2009          event of a disaster            0 Change Orders
Completion: 4/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Completed installation and data migration to the new High Capacity   Budget/Costs Incurred
Network Storage System. Delivery of remaining components on
schedule to complete project.                               2
1.5
Schedule
Previous Report - Insufficient power in the data center required         Millions 1
unplanned infrastructure upgrades for the new High Capacity
Dollars in 0.5
Realtime Storage Device. The new device is estimated to be online
in October 2010 and final project completion is estimated in April        0
2011, a 6 month delay from the original schedule.                    Authorized  Forecasted Costs Incurred
Budget
On Budget                                  Construction Costs
Not Applicable
Change Order
None
Risks
No significant risks
Budget Transfers
None



CORPORATE

88  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Time Clock System
Project:C800387        Procure and implement a Time    Status Snapshot
Budget:$840,000       Clock System to accurately capture  On Schedule
Phase:Planning        and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion:7/30/2012     Aviation Security and Airport      Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
Contract completed with vendor for product and implementation
0.4
services.
0.3
Schedule
0.2
On Schedule                                  in Millions
Dollars 0.1
Budget
0
On Budget                                      Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No significant risks at this time.
Budget Transfers
None




CORPORATE

Port of Seattle 4Q 2010 Report  89

FOURTH QUARTER REPORT, 2010
Peoplesoft Financials Upgrade
Project:C800392        Upgrade of Peoplesoft Financials   Status Snapshot
Budget:$5,000,000       hardware and software        On Schedule
Phase:Planning                            On Budget
Start: 9/28/2010                                 0 Change Orders
Completion:12/31/2012                        Total Change Orders Amount:
$0
Significant Developments
Implementation vendor has been selected. Contract negotiation in    Budget/Costs Incurred
progress.
6
5
Schedule
4
On Schedule
Millions 3
2
Budget                             Dollars in 1
On Budget
0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
Significant resources will be required across multiple organizations
which may delay other technology projects.
Budget Transfers
None




CORPORATE

90  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Police Records Management System
Project: C800393        Procure and implement a       Status Snapshot
Budget: $1,300,000      replacement Police Records      On Schedule
Phase:Planning        Management System         On Budget
Start: 10/10/2010                                0 Change Orders
Completion: 1/31/2012                         Total Change Orders Amount:
$0

Budget/Costs Incurred
Significant Developments
1.4
RFP requirements complete. Advertising in January 2011.
1.2
1
Schedule                             0.8
Millions
On Schedule                                   0.6
Dollars in 0.4
0.2
Budget
0
On Budget                                      Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable in the phase
Risks
No significant risks identified at this time
Budget Transfers
None




CORPORATE

Port of Seattle 4Q 2010 Report  91

FOURTH QUARTER REPORT, 2010
Upgrade to Windows 7 and Office 2010
Project: C800395        Upgrade Port workstations to     Status Snapshot
Budget: $500,000       Windows 7 and Microsoft Office    On Schedule
Phase: Implementation    2010.                 On Budget
Start: 9/17/2010                                 0 Change Orders
Completion: 9/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Completed planning and procurement of vendor implementation     Budget/Costs Incurred
services.
0.6
Schedule                             0.5
0.4
On Schedule
Millions 0.3
Budget                             0.2
Dollars in 0.1
On Budget
0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
No significant risks
Budget Transfers
None




CORPORATE

92  Port of Seattle 4Q 2010 Report

FOURTH QUARTER REPORT, 2010
Port Contractor Roster & Bid Management
Project: C800397      Develop and implement a single Port   Status Snapshot
Budget: $450,000     Roster & Bid System that replaces the  Delayed Schedule
Phase: Design       functionality of three rosters, supports   On Budget
Start: 1/26/2010        new Central Procurement Office      0 Change Orders
Completion: 5/30/2011  processes , and simplifies the process  Total Change Orders Amount:
for Port vendors.                  $0
Significant Developments
Budget/Costs Incurred
Completed development on initial requirements. Working on
suggested changes identified during test phase.                 0.5
0.4
Schedule                            Millions 0.3
Several changes were suggested during the testing phase that will     0.2
require an additional 3 months to complete, test, and deploy.         Dollars in 0.1
0
Budget
Authorized  Forecasted Costs Incurred
On Budget
Change Order                         Construction Costs
Not Applicable
None
Risks
No significant risks
Budget Transfers
None




CORPORATE

Port of Seattle 4Q 2010 Report  93

94  Port of Seattle 4Q 2010 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.