7b Report

Item Number: 7b_Report
Meeting Date: September 7, 2010


Commission Staff Brieng
Capital Improvement Projects
Second Quarter Report 2010

This page intentionally left blank









ii  Port of Seattle 2Q 2010 Report

Port of Seattle
Capital Improvement Project Report
Second Quarter 2010
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the statue of the Port's capital projects.
Background
During 2009 the Port plans to invest over $600 million to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 11 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
maritime transportation facilities and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 2Q 2010 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................5 ........... 
C100266 et al .......Rental Car Facility ............................................... 6-7.......... ...............
C102030 ...............Stormwater Management Program .......................8 ........... ................................................................................
C102038 ...............Apron Pavement Rehabilitation 3 ........................9 ...........
C102163................Main Terminal Baggage Screening ................... 10-11 ........ ...................................
C102744................2nd Floor Tenant Improvements ...........................12 .......... ...............
C800019 ...............Loading Bridge Utilities .........................................13 .......... ...............
C800020 ...............Trash Handling & Recycling System ....................14 .......... .................................. .......................................... 
C800034 ...............North Expressway Relocation ..............................15 .......... ...............
C800036 ...............Parking Garage 4th Floor Improvements .............16 ..........
C800042 ...............Aircraft Rescue Fire Fighting Station Upgrade ....17 .......... ...............
C800061 ...............Main Terminal South Sub Low Volt ......................18 .......... ...............
C800071 ...............Consolidated Warehouse .....................................19 .......... ...............
C800095 ...............Alaska Air 2 Step Ticket Counter..........................20 .......... ...............
C800105 ...............Airport Owned Gate Infrastructure .......................21 ..........
C800107 ...............C4 UPS System Improvements ............................22 .......... ...............
C800109 ...............Garage Escalator & "A" Elevator Upgrade ...........23 .......... ...............
C800112................Runway 16C/34C Panel/Joint Sealant .................24 ..........
C800144 ...............Security CCTV System Improvements.................25 .......... ...............
C800146 ...............RMU/Kiosk Concession Program ........................26 .......... ..............................  ...................................... 
C800147 ...............Concessions Unit Readiness Program ................27 .......... ...............
C800148 ...............GML Arrivals Hall Concessions ...........................28 .......... ...............
C800157 ...............Concessions Flooring ...........................................29 .......... ............... ...................................... 
C800167 ...............Runway 16L/34R Reconstruction.........................30 .......... ................. .......................................... 
C800170 ...............Connect C1 BHS to C88 BHS ..............................31 ..........
C800237 ...............Renew/Replace 42 Escalators .............................32 .......... ...............
C800238 ...............Central Plant Pre-Conditioned Air ........................33 .......... ...............
C800239 ...............Fire Piping .............................................................34 .......... ..............................  ........................................
C800249 ...............2nd Floor HVAC ....................................................35 ..........
C800253 ...............Parking System Replacement ..............................36 ..........
C800254 ...............Aircraft RON Parking Post Ofce Site..................37 ..........
C800274 ...............8th Floor Weather Proong ..................................38 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......39 ..........
C800336 ...............South Satelite Delta Sky Club Extension .............40 ..........
C800360 ...............Roof Replacement Program .................................41 ..........
C800406 ...............RW 16C/34C Reconstruction Design ...................42 ..........



2  Port of Seattle 2Q 2010 Report

Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C102396 ...............Fire Vehicles .........................................................43 ..........
C200007...............Highline School Noise Insulation ..........................44 .......... ...............
C200015 ...............3rd Runway Residential Acquisition .....................45 ......................... 
C200037 ...............FAR Part 150 Mobile Home Park Acquisition ......46 .......... ...............
C200042 ...............Highline Community College Noise Insulation .....47 .......... ...............
C200048 ...............Home Insulation Retrot .......................................48 .......... ...............
C200093 ...............Single Family Home Sound Insulation .................49 ..........
C800046 ...............Street Vacations  Des Moines Creek 1 ..............50 .......... ...............
C800150 ...............Burien Commercial Property Acquisition .............51 .......... ...............
C800154 ...............Tenant Reimbursement ........................................52 ..........
C800381 ...............28th Ave Property Acquistion ...............................53 ..........
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000579 ...............Alaskan Way St Vacation and Public Access ......54 .......... ...............
C102451 ................T-115 Dock Reconstruction...................................55 .......... ............... ....................
C800085 ...............T-30/T-91 Program ............................................56-57 ....... ............... ....................
C800114................P-66 Bag. Corridor & Pass. Screening ................58 .......... ...............
C800121 ...............T-18 S. Fendering .................................................59 .......... ...............
C800123 ...............T-5 Crane Spreader Replacement .......................60 .......... ...............
C800182 ...............NH Island Mooring Dolphins (4) ...........................61 ..........
C800264 ...............T-10 Interim Redevelopment.................................62 .......... ...............
C800273 ...............T-91 Mobile Gangways .........................................63 ..........
C800343 ...............T-91 Road Pavement Entry & Guard Shack ........64 .......... ..............................
C800347 ...............T-46 Upgrade Yard Lighting .................................65 ..........
C800349 ...............T-5 Crane Cable Reels .........................................66 ..........
WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................67 .......... ............... ....................
E103705 et al ........T-46 ZPMC Gearboxes ........................................68 ..........
E103835 et al ........T-5/T-18 Maintenance Dredging ...........................69 .......... ...................................
E104011 et al ........T-25/P-28/T-46 Barge Layberth Improvements ...70 ..........
E104362 et al ........Street Vacations T-5/18/105 .................................71 ..........
Multiple Expense ..Water/Sewer Meter Upgrade ................................72 ..........


Port of Seattle 2Q 2010 Report  3

Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C001706 et al........SBM Renewal and Replacement .........................73 .......... ...............
C800070 ...............T-102 HVAC Renewal/Replacement ....................74 .......... ............... .................. 
C800125 ...............C15 Sewer Line Upgrades ....................................75 .......... ...................................
C800133 .............. T-86 Grain Facility Modernization (Phase I) ........76 ..........
C800136 ...............FT South Wall Reconstruction Phase VI ..............77 ..........
C800175 ...............MIC Central SeaWall Replacement ......................78 ..........
C800298 ...............T-91 Watermain Replacement ..............................79 ..........
C800386 ...............FT NW Dock E. Fender System Replacement.....80 ..........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ....................81 ..........
C800003...............Maximo Enterprise Implementation......................82 .......... ...............
C800227 ...............Ground Transportation Management System ......83 ..........
C800319............... Port of Seattle Internet Redesign.........................84 .......... ..............................
C800320 ...............External Sharepoint ..............................................85 .......... .............................. 
C800321 ...............Enterprise Project Cost Management ..................86 .......... ...............
C800322 ...............Records and Document Management .................87 .......... .............................. 
C800326 ...............Business Continuity ..............................................88 .......... ..............................
C800387 ...............Time Clock System ...............................................89 ..........
C800397 ...............Port Roster ............................................................90 ..........
Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
Previously Reported
No Diamond  On Budget or On Schedule



4  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
3rd Runway Program
Status Snapshot
On Schedule
Project: C000683,       The 3rd Runway Program will
On Budget
C001138, C001175,      construct a new 8,500 foot long
0 Change Orders
C001331, C001751,      dependent runway, connecting
Total Change Orders Amount:
C001760, C100172      taxiways, and related infrastructure.
$0.00
When complete the 3rd Runway
Budget: $931,940,984
will significantly reduce weather-
Phase: Construction                       Budget/Costs Incurred
related delays.
Start: 05/27/1997
1200
Completion: 12/31/2011
1000
Millions800
Significant Developments                     600
400
2010 construction contract's bid opening was on June 10, 2010 with
200
SCI Infrastructure, LLC as the apparent low bidder at $939,725.       Dollars in 
0
Site preparation and utility work will continue as planned.
Authorized  Forecasted   Costs 
Commission authorized deferral of Pond M to 2011 contract.                        Incurred
Schedule
2010 Contract Const. Costs
The 2010 construction contract work is to start in August and be
completed in the fall.
1
0.8
Budget
0.6
To date, $615,388,000 of construction has been completed on the
Millions
0.4
overall program.
Dollars in   0.2
Change Order                           0
Zero change orders have been executed during this period.             InitialChange OrdersSpent
Risks
No risks were identified at this time.                         Photo
Budget Transfers
None

AIRPORT

Port of Seattle 2Q 2010 Report  5

SECOND QUARTER REPORT, 2010
Rental Car Facility
Status Snapshot Prior Report
Delayed Schedule 4Q 08
Project:   C100266,     The program will construct a       On Budget
C102167, C800032     consolidated rental car facility (RCF)  463 Change Orders
Budget: $419,306,000   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $10,244,906
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.          Budget/Costs Incurred
500
Significant Developments                     400
Construction is progressing well on all aspects of the RCF. Concrete    Millions300
work for three (of six) sections are complete to the fifth floor and        200
work on the Customer Service Building has begun. Steel for the high    Dollars in 100
canopy roof has been erected (the topping off ceremony was held on
0
July 14, 2010). All but one retaining wall is complete. Construction
Authorized  Forecasted Costs Incurred
continues on all four quick turnaround areas (QTA's). All utilities
within the building footprint are complete. Averaging 230 workers
daily, increasing to 260 workers for concrete work. All conforming
Construction Costs
design change and but one suspension claims are complete.
Completed the design for the BMF and are preparing for
250
advertisement next quarter assuming an accelerated construction
200
schedule. Awarded the ORI to MidMountain Construction Company
on May 28, 2010 with $3,200,000 in savings due to the low bid.        Millions 150
Awarded the bus purchase to Gillig on June 15, 2010 with            100
$3,600,000 in savings due to the low bid.                      Dollars in  50
0
Schedule
Initial  Change Orders  Spent
Revised the program schedule due to BMF delays; remains on-track
for spring 2012 completion. ORI construction anticipated to start
next quarter. BMF construction anticipated to start 4th quarter 2010.
BUs delivery planned for 4th quarter 2011.                    Photo
Budget
Customer Finance Charge (CFC) revenues continue to run lower
than planned due to the economy. The program forecast is within the
approved budget and authorization.
Change Order
114 change orders were issued this quarter in the amount of
($4,732,532).
6  Port of Seattle 2Q 2010 Report

Risks
For RCF, potential risks include claims, multiple subcontractors
working in same location, quality issues, control of onsite
stormwater and site congestion. Turner changed key on-site
management positions resulting in improved performance. For
ORI, compressed construction schedule due to design delays.
For BMF, completion of aggressive design and accelerated
construction schedules to support spring 2012 opening.
Budget Transfers
None this quarter
Cost Growth of Construction
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On
June 30, Commission authorized the $32,000,000 suspension
impact including a $6,973,300 budget increase and an increase
in change order limit from 10% to 18% requiring Commission
notification.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative
change order percentage through this quarter is 19.4%. Primary
reason for changes is the removal of contaminated soils and
associated impacts. This work and the final contract
reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280 
Cumulative change order percentage through this quarter is
170.5%. Primary reasons for changes are for additional
contractor management, estimating, scheduling and bidding
effort for cost estimate reconciliation, constructability reviews and
value engineering beyond the extent of the original scope to
validate project costs and support the rental car companies and
the Port on final approval of the project. This work and the final
contract reconciliation is complete.


AIRPORT

Port of Seattle 2Q 2010 Report  7

SECOND QUARTER REPORT, 2010
Stormwater Management Program
Project:   C102030,    The program achieves permit       Status Snapshot Prior Report
C800026, C800030     requirements and makes the Airport a  On Schedule
Budget: $58,447,234   leader in stormwater management by  Under Budget   1Q 10
Phase: Construction   construction of flow control, water    No Change Orders
Start: 06/11/2002       quality treatment and low stream flow   Total Change Orders Amount:
mitigation facilities.                  N/A
Completion: 12/31/2011
Significant Developments                    Budget/Costs Incurred
The stormwater program (C102030) is in its adaptive management
100
phase under which additional or upgraded water quality treatment
facilities are being implemented based on the stricter effluent          80
standards of the new stormwater National Pollutant Discharge        Millions 60
Elimination System (NPDES) permit. Water quality treatment         40
upgrades at three project sites are in the 90% design review phase     Dollars in  20
and will be constructed in 2011.
0
Schedule                               Authorized Forecasted Costs Incurred
The new stormwater NPDES permit became effective April 1, 2009.
Current adaptive management projects will be designed and
Construction Costs
constructed during the 2010 to 2011 period, and possibly additional
No active construction
projects through 2014 depending on water quality monitoring results.
contract at this time.
The stormwater (C800026) and sanitary sewer (C800030) pipeliner
projects, which are not part of adaptive management, have been
deferred until later in 2010 or 2011.
Budget
The project forecast is within the approved budget and authorization.
Approximately $6,100,000 will be returned to savings next quarter.
Change Order
None
Risks
Additional adaptive management facilities or upgrades may be
required beyond those currently being planned, depending upon
future water quality monitoring results.
Budget Transfers
None this quarter
AIRPORT
8  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Apron Pavement Rehabilitation - 3
Project:   C102038      Multiyear airfield pavement       Status Snapshot
Budget: $16,100,000     replacement program. This is a    On Schedule
Phase: Construction     continuation of a program for the   On Budget
Start: 01/14/2003         removal and replacement of aged   0 Change Orders
Completion: 12/31/2010   airfield apron pavement started in   Total Change Orders Amount:
1994.                    $0
Budget/Costs Incurred
Significant Developments
Approximately 70 concrete panels will be replaced in the 2010 Apron    17
Replacement Contract. This work is part of a contract awarded to      16
Gary Merlino Construction and construction is underway.           Millions 15
Schedule                             14
The apron pavement rehabilitation portion of the contract was         Dollars in  13
finished in second week of July.                             12
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
2010 Contract 1
Change Order                         Construction Costs
None
1.2
1
Risks
Millions  0.8
No risks have been identified at this time.
0.6
0.4
Budget Transfers                          Dollars in  0.2
None this quarter.
0
InitialChange OrdersSpent

Photo

AIRPORT


Port of Seattle 2Q 2010 Report  9

SECOND QUARTER REPORT, 2010
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $230,538,762   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget   4Q 09
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
Significant Developments
235
The C-1 baggage handling/screening system has been placed into     230
revenue service for the Alaska Air Group. The only remaining work is    Millions 225
to relocate some fire sprinklers and to repair/replace fire proofing
220
material displaced from the main structural elements of the bagwell.
Dollars in 215
Schedule                            210
Authorized  Forecasted Costs Incurred
The project was delayed approximately two years from the original
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope
Construction Costs
changes. Turner Construction demobilized on May 31, 2009. The
GCCM construction contract with Turner Construction has been
200
closed. The remaining fire sprinkler and fire proofing work is
scheduled for completion by year end.                         150
Millions  100
Budget
50
The project forecast is within the approved budget and authorization.    Dollars in 
The project is anticipating a return of $8,000,000 of budget.             0
Initial  Change Orders  Spent
Change Order
665 Change Orders have been issued on this project.
Photo
Risks
Risks include recent TSA changes in certification requirements and
whether they will be imposed retroactively.
Budget Transfers
None this quarter


10  Port of Seattle 2Q 2010 Report

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was
terminated as they were unable to meet the project schedule
requirements. The remaining work was rebid in the fall of 2006.
Alaska Airlines asked that we include the BHS work within the 2-
step ticket counter project; which increased the amount of BHS
work in the bidding (attracting more competition), and eliminated
the issues with having two different BHS subcontractors in the
same work area.











AIRPORT

Port of Seattle 2Q 2010 Report  11

SECOND QUARTER REPORT, 2010
2nd Floor Tenant Improvements
Project:   C102744      This project constructs a shell     Status Snapshot Prior Report
Budget: $377,864       space for new tenant offices and   Delayed Schedule 1Q 10
Phase: Construction     provides utility pathways to the    On Budget
Start: 08/22/2006         shell space and makes code       No Change Orders
Completion: (See       improvements to adjacent lobby    Total Change Orders Amount:
and corridors.                 N/A
C800249)
Significant Developments                    Budget/Costs Incurred
Project construction activities are substantially complete except for
0.6
one project element, which is awaiting completion of tenant office
0.5
build out and relocation of current tenant offices. The remaining
0.4
portion of the work will be completed after the 2nd Floor HVAC
Upgrades project (C800249). The tenant project to build out the       Millions 0.3
0.2
office space is nearing completion.                           Dollars in 0.1
Schedule                             0
Authorized  Forecasted Costs Incurred
The remaining work is now scheduled for late 2010.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None.
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

12  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Loading Bridge Utilities
Project:   C800019   This project will upgrade all Port-       Status Snapshot Prior Report
Budget: $9,385,000   owned loading bridges to the same     Delayed Schedule    2Q 09
Phase: Design     standards, including 400Hz power and   On Budget
potable water. It will reduce air
Start: 06/28/2007                                 No Change Orders
emissions, improve energy efficiency
Completion: TBD                           Total Change Orders Amount:
and save money for the airlines.        N/A
Budget/Costs Incurred
Significant Developments
The project has been re-initiated and the design team has re-started     10
with a site walk of the existing conditions and for coordination with       8
other projects.                                          Millions 6
Schedule                             4
The current schedule will be updated once the design team has       Dollars in  2
completed survey of the exisiting conditions, determined which         0
drawings require changes/updates.                            Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None
Risks
The project budget could increase, due to the design being placed
on hold and restarting at 90% and potential increases in the
construction market.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2010 Report  13

SECOND QUARTER REPORT, 2010
Trash Handling & Recycling System
Project:   C800020    To improve trash handling and       Status Snapshot
Budget: $1,612,000    recycling operations and to meet     On Schedule
Phase: Close Out    future trash volume demands;      Under Budget
Start: 04/22/2008      decentralize tenant trash disposal and   9 Change Orders
Completion: 02/28/2010 recycling; and centralize airline trash   Total Change Orders Amount:
disposal and recycling.             $28,468
Significant Developments                    Budget/Costs Incurred
Project is now complete except for close out. All major airlines are
2
utilizing the six new sites. Each site has one trash and one recycling
compactor and all compactors are remotely monitored and emptied     1.5
when they are nearing 100% full.                           MillionsDollars in 
1
Schedule
0.5
Project close out is under way.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
The project is anticipating a savings of approximately $200,000 after  Construction Costs
closeout.
0.35
Change Order                           0.3
None                                  Millions 0.25
0.2
Dollars in 
0.15
Risks
0.1
None identified at this time.                                  0.05
0
Budget Transfers                             Initial Change Orders Spent
None this quarter
Cost of Construction Growth                  Photo
Three electrical changes during construction affected the project's
costs. At Concourse D, the home run conduit proposed for re-use
did not exist in the field, so the project installed new conduit; the
Ethernet converters specified for the fiber conversion were changed
to analog to accommodate the Port's existing communication
system; and fusible disconnect switches were added at all twelve
trash compactors for safety and maintenance reasons.
AIRPORT
14  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
North Expressway Relocation
Project:   C800034
The project is a collaboration      Status Snapshot  Prior Report
Budget: $110,347,700    between the Port and Sound     Delayed Schedule 1Q 10
Phase: Construction     Transit. It reconstructs the North   On Budget
Start: 07/27/2004         Airport Expressway and brings light  187 Change Orders
Completion: 03/31/2012   rail to the Airport.           Total Change Orders Amount:
$9,300,934
Significant Developments
Budget/Costs Incurred
The work in the main contract includes reconstruction of the North
Airport Expressway and included light rail transit components. This     115
work is complete. The intelligent transportation management system    110
has been implemented. A final contract to complete paving,         Millions105
landscaping, the north entry art features, and other miscellaneous      100
work has been awarded and is underway.
95
Dollars in  90
Schedule
85
The main contract reached substantial completion in August 2008         Authorized Forecasted Costs Incurred
and only plant establishment remains. A contract for final paving,
landscaping, and reclamation is underway and is planned to be
complete in early 2011, followed by a first year plant establishment
period to be complete in early 2012.                        Construction Costs
Budget                              150
The project forecast is within the approved budget and authorization.
Millions  100
Change Order
50
No change orders were issued this quarter.                    Dollars in 
0
Risks                                   Initial Change Orders Spent
None identified at this time.
Budget Transfers                        Photo
To C800036 (Parking Garage 4th Floor Improvements)   $140,000


AIRPORT

Port of Seattle 2Q 2010 Report  15

SECOND QUARTER REPORT, 2010
Parking Garage 4th Floor Improvements
Project:   C800036
The project includes the design and  Status Snapshot
Budget: $9,131,000      construction of a pedestrian bridge  On Schedule
Phase: Construction     and a walkway from Sound      On Budget
Start: 02/14/2006         Transit's Airport Station to the      51 Change Orders
Completion: 12/31/2009   Terminal.               Total Change Orders Amount:
$258,642
Significant Developments
Budget/Costs Incurred
The project was delivered in two contracts: the pedestrian bridge
between the Airport Station and the Parking Garage, and a walkway    9.5
on the 4th floor of the garage between the pedestrian bridge and
9
northernmost sky bridge to the main terminal. Both contracts are       Millions
substantially complete and opened in conjunction with Sound         8.5
Transit's Airport Station on December 19, 2009.
Dollars in   8
Schedule
7.5
Punch list work is complete for the walkway and the pedestrian           Authorized Forecasted Costs Incurred
bridge. Multiple User Flight Information Display System (MUFIDS)
will be installed in the third quarter of 2010.
Construction Costs
Budget
4
The project forecast is within the approved budget and authorization.
3
Change Order
2
18 change orders were issued for the walkway this quarter in the
Millions
amount of ($16,486).                                    1
Dollars in 
0
Risks                                   Initial Change Orders Spent
None
Budget Transfers                        Photo
From C800034 (North Expressway Relocation)     $140,000


AIRPORT

16  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Aircraft Rescue & Fire Fighting Station Upgrade
Project:   C800042      Upgrade the Sea-Tac International   Status Snapshot Prior Report
Budget: $4,972,000      Airport Aircraft Rescue & Fire     Delayed Schedule 1Q 09
Phase: Close Out      Fighting (ARFF) station to meet    On Budget
Start: 06/13/2006         current Airport needs and comply    26 Change Orders
Completion: 01/31/2010   with current safety codes.       Total Change Orders Amount:
$173,099
Significant Developments                    Budget/Costs Incurred
Contractor has returned and completed waterproofing of training
5.2
tower.
5
Schedule                            Millions 4.8
The project and punchlist are now substantially complete.           4.6
Dollars in 4.4
Budget                             4.2
The project forecast is within the approved budget and authorization.     4
Authorized  Forecasted Costs Incurred
Change Order
Two change orders were issued this quarter in the amount of
$24,228.                                      Construction Costs
Risks                                 3
Contractor and Port costs to perform tower waterproofing may
2
exceed the amount originally budgeted for this scope.              Millions
1
Budget Transfers                          Dollars in 
None this quarter                                       0
Initial  Change Orders  Spent



AIRPORT

Port of Seattle 2Q 2010 Report  17

SECOND QUARTER REPORT, 2010
Main Terminal South Sub Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
No Change Orders
Start: 06/28/2007      equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD    Main Terminal.
NA
Significant Developments
Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
and building codes, the design phase changed from 100% to 90%      2.5
complete. Port staff is in the process of reviewing the Consultant's
2
proposed Service Agreement and Service Directive, and should be
completed in the 3Q 2010.                              Millions 1.5
1
Schedule                            Dollars in 0.5
The project was reactivated on June 24, 2009 and is in the process      0
of determining the scope of work, schedule and final design budget.
Authorized  Forecasted Costs Incurred
Expect to remobilize the Design Consultant late in the 3Q 2010.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order                         Photo
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area of the Main Terminal is a 24/7/365 operation and
sequencing of this work is critical and electrical power has to be
maintained without interruptions.
It is not known when the construction will proceed. There may be an
impact on project costs due to changes in market conditions at that
time.
Budget Transfers
None this quarter.
AIRPORT
18  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Consolidated Warehouse
Status Snapshot Prior Report
Project:   C800071   This project will construct a 50,000     Ahead of Schedule     3Q 09
On Budget
Budget: $9,300,000   square foot warehouse for storage and
Phase: Close Out    inventory management of spare parts   34 Change Orders
for the Aviation Maintenance          Total Change Orders Amount:
Start: 06/27/2006                                 $770,658
Completion: 2/15/2010 Department.
Budget/Costs Incurred
Significant Developments
The project is complete and in close out, with the building open for      9.4
use and in operation. The architect will submit the final as-built        9.3
drawings in August 2010.                               Millions 9.29.1
9
Schedule
Dollars in 8.9
The project was completed ahead of schedule.                  8.8
8.7
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Seven change orders were issued this quarter in the amount of
6
$68,517.
Millions   4
Risks
None                                    2
Dollars in 
Budget Transfers                           0
Initial  Change Orders  Spent
None this quarter
Cost of Construction Growth
Photo
Project anticipated CO's exceeding 10% due to the following:
1. Soil and foundation changes due to the site being an old,
unconsolidated fill of unknown material;
2. Perceived market conditions during bidding, structural mezzanine
was deleted. The bid climate changes allowed the mezzanine to
be installed; and
3. Pallet racks were anticipated to be a Port of Seattle purchase and
install. The purchasing officer recommended the contractor
purchase and install as a CO.
AIRPORT
Port of Seattle 2Q 2010 Report  19

SECOND QUARTER REPORT, 2010
Alaska Air 2-Step Ticket Counter
Project:   C800095      This project provides Port of      Status Snapshot Prior Report
Budget: $10,707,000     Seattle support for Alaska Airlines'  Delayed Schedule 1Q 08
Phase: Close Out      2-step ticket counter projects (the   On Budget
Start: 04/11/2006         "Airport of the Future"). The work   No Change Orders
Completion: 02/13/2009   includes: asbestos abatement;    Total Change Orders Amount:
concessions relocations; and      N/A
related building modifications.
Budget/Costs Incurred
Significant Developments
12
The onsite work is complete. The Port is meeting with Alaska         10
Airlines to reconcile the reimbursable amount.                   Millions 8
6
Schedule
4
The project work is complete.                              Dollars in  2
0
Budget                               Authorized Forecasted Costs Incurred
The project could incur additional costs over the current budget for
Port performed tasks which will be reimbursed by Alaska Airlines.
After reimbursement, the anticipated forecast is within the approved   Construction Costs
budget and authorization.                              Not Applicable
Change Order
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

20  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Airport Owned Gate Infrastructure
Project:   C800105      This project purchases and
Status Snapshot
Budget: $6,000,000      replaces loading bridges at gates
On Schedule
Phase: Construction     throughout the airport.
On Budget
Start: 07/24/2007                                 No Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
The project will be going to the Commission for the remainder of the
budget in July.                                          7
6
Schedule                            Millions 5
4
The remainder of the project will be completed in 2011.
3
2
Budget                             Dollars in 
1
The project forecast is within the approved budget. The current        0
authorization is for $4,337,000. The remaining budget of $1,663,000       Authorized  Forecasted Costs Incurred
will be presented to the Commission for authorization in July 2010.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2010 Report  21

SECOND QUARTER REPORT, 2010
C4 UPS System Improvements
Project:   C800107    Project will replace existing UPS      Status Snapshot Prior Report
Budget: $2,336,000   System, including batteries, with a new  Delayed Schedule 1Q 09
Phase: Construction  new system located in the Airport     On Budget
Start: 06/28/2007      Combined Communications and       No Change Orders
Completion: TBD     Command Center (C4).          Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. Port staff is in the process of reviewing the Consultant's       2
proposed Service Agreement and Service Directive, and should be     Millions 1.5
completed in the second quarter of 2010.
1
Dollars in 0.5
Schedule
0
The project was reactivated on June 24, 2009 and is in the process
Authorized  Forecasted Costs Incurred
of determining the scope of work, schedule and final design budget.
Expect to remobilize the Design Consultant late in the third quarter of
2010.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Photo
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions.
It is not known when the construction will proceed as this is
specialized euipment and complex and requires rigorous testing
during the commissioning phase.
Budget Transfers
None this quarter
AIRPORT
22  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Garage Escalator & A-Bank Elevator Upgrade
Project:   C800109    This project renews and replaces     Status Snapshot
Budget: $7,315,000    aging elevators and escalators in the   Delayed Schedule
Phase: Construction   Parking Garage to provide reliable    On Budget
Start: 09/11/2007       vertical transportation to customers for  17 Change Orders
Completion: 02/28/2011  years to come.              Total Change Orders Amount:
$143,640
Significant Developments                    Budget/Costs Incurred
A-Bank consists of seven elevators. Four elevators are in service.
8
Project duration was extended to early August to implement change
7
orders regarding upgrades to machine room lighting and to install
6
new safety devices. A sole source contractor acquisition was         5
approved for the garage escalator project; contract is currently in        4
Millions
preparation.                                          3
Dollars in   2
Schedule                             1
0
Substantial completion and in-service of all A-Bank elevator work is
Authorized  Forecasted Costs Incurred
scheduled for early August 2010. Change order work will occur
during July. The garage escalator construction contract is expected
to be executed in early August with project duration of approximately
Construction Costs
10 months.
2.5
Budget
2
The project forecast is within the approved budget and authorization.    Millions 1.5
Dollars in 
1
Change Order
0.5
Change orders were issued this quarter for new electrical panel in
0
the machine room; new light fixtures in the machine room; and cover
Initial  Change Orders  Spent
for the HVAC water containment pan.
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 2Q 2010 Report  23

SECOND QUARTER REPORT, 2010
Runway 16C/34C Panel/Joint Sealant
Replacement
The scope of work will remove and   Status Snapshot
Project:   C800112      replace the pavement and joint seal  On Schedule
in areas on Runway 16C-34C.     On Budget
Budget: $5,650,000
0 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 02/26/2008                                 $0
Completion: 12/31/2010
Budget/Costs Incurred
Significant Developments
This work is part of a contract awarded to Gary Merlino Construction     6
and construction is underway. Approximately 170 concrete panels      5
will be replaced.                                         Millions 4
3
Schedule                             2
Dollars in 
The 2010 project has started construction in July and is scheduled to     1
be complete this year.                                    0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
2010 Contract 1
Change Order                         Construction Costs
None
2
Risks                                 1.5
Millions
No risks have been identified at this time.                         1
Budget Transfers                          Dollars in  0.5
None                                    0
InitialChange OrdersSpent

Photo


AIRPORT

24  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Security CCTV System Improvements
Project:   C800144      This project will install          Status Snapshot Prior Report
Budget: $2,037,591      approximately 70 new cameras for  Delayed Schedule 3Q 09
Phase: Implementation   TSA and integrate existing Airport   On Budget
Start: 9/11/2007          camera networks which contain     No Change Orders
Completion: 03/31/2010   over 800 cameras.          Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The final cut overs are complete. The Port and TSA are evaluating
2.05
follow on work.
2
Schedule                            1.95 Millions
Project completion occurred in March 2010.                    1.9
1.85  Dollars in 
Budget
1.8
The project forecast is within the approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable
Construction Costs
Risks                               Not Applicable
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 2Q 2010 Report  25

SECOND QUARTER REPORT, 2010
RMU/Kiosk Concession Program
Project:   C800146   The project will: Provide design and     Status Snapshot Prior Report
Budget: $1,209,000   fabrication of eight Retail Merchandising  Delayed Schedule 4Q 09
Phase: Construction  Units (RMUs); provide power,       Under Budget
Start: 11/20/2007     communications, and data to the sixteen  No Change Orders
Completion: 2/29/2010 RMU locations; and install floor-mounted  Total Change Orders Amount:
receptacles for the utilities to allow easy   N/A
connection points to the sixteen RMUs,
as well as flexibility for future utilization.   Budget/Costs Incurred
1.4
Significant Developments
1.2
All RMU utility installations are complete. The remaining tasks
Millions  1
include purchasing and installation of the RMU kiosk units.           0.8
0.6
Schedule                            Dollars in 0.4
0.2
The project is on hold until the prioritization decisions are made by
0
the Port's Business Development group, related to the procurement
Authorized  Forecasted Costs Incurred
of the RMUs.
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
The project anticipates a savings of approximately $700,000 once    Not Applicable
closeout is complete.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

26  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Concessions Unit Readiness Project
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Design        previously vacated or slated to be   On Budget
Start: 08/26/2008         vacated to Port standards for use    No Change Orders
Completion: 06/30/2013   as specialty concession space.    Total Change Orders Amount:
N/A
Significant Developments
The Business Development Group is requesting Commission       Budget/Costs Incurred
authorization in August to construct a portion of the units.
2.5
Schedule                             2
The construction phase has been restructured and re-sequenced,      1.5
with the intent to maximize the timing for new Concessions           Millions
1
opportunities. The project was put on hold until the prioritization
Dollars in
decisions were made by the Port's Business Development group.      0.5
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 2Q 2010 Report  27

SECOND QUARTER REPORT, 2010
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot  Prior Report
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule 4Q 09
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,000
project includes installing three      No Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      N/A
Completion: 12/31/2011   approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
1.2
The 100% design is complete.                            1
0.8
Schedule
0.6
in Millions
The project completion is dependent upon issuance of a Request for    0.4
Proposal by the Aviation Business Development Group for a new      Dollars 0.2
concession in the Arrivals Hall.                               0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                 Not applicable
Risks                               Photo
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter.



AIRPORT

28  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Concessions Flooring
Project:   C800157      This project replaces flooring in     Status Snapshot Prior Report
Budget: $2,182,000      North and South Satellite food    Delayed Schedule 2Q 09
Phase: Close Out      courts.                Under Budget
Start: 07/24/2007                                 19 Change Orders
Completion: 08/05/2009                       Total Change Orders Amount:
$238,589
Budget/Costs Incurred
Significant Developments
All work is completed. This will be the last quarterly report for this       2.5
project.
2
Millions 1.5
Schedule
Dollars in 
1
The project is complete.
0.5
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
The project will be returning a savings of approximately $400,000.
Construction Costs
Change Order
1.5
Four change orders issued this quarter closing out previously issued
Not to Exceed change orders resulted in a net decrease of $31,573.
1
Risks
Millions
0.5
None identified at this time.                                  Dollars in 
0
Budget Transfers                             Initial Change Orders Spent
None this quarter
Cost of Construction Growth                  Photo
Structural deficiencies were encountered during the demolition
phase. Changes in phasing and materials were required to expedite
curing and allow tenants to stay open during construction. Varying
site conditions required additional demolition, regulated materials
removal, and restoration of existing conditions.

AIRPORT
Port of Seattle 2Q 2010 Report  29

SECOND QUARTER REPORT, 2010
Runway 16L/34R Reconstruction
Status Snapshot
Project: C800167        The scope of this project includes
On Schedule
Budget: $73,490,000     the complete reconstruction of
Phase: Close Out      Runway 16L/34R (the eastern     Under Budget
runway) and replacement of aging   26 Change Orders
Start: 02/26/2008
infrastructure.                  Total Change Orders Amount:
Completion: 12/31/2009                       $2,528,214.29
Significant Developments                    Budget/Costs Incurred
Runway 16L/34R Reconstruction project includes reconstruction of    100
11,900 foot runway and portions of five taxiways. The construction     80
was completed on September 25, 2009 and re-opened on         Millions 60
September 26, 2009 on schedule. Seeding of slopes completed.      40
Dollars in  20
Schedule                             0
Authorized  Forecasted Costs Incurred
The runway was re-opened on schedule on September 26, 2009
and contract closeout will continue through 2010.
Budget                           Construction Costs
The project forecast is within the approved budget and authorization.
60
It is anticipated that the project will return a savings of approximately
50
$6,600,000.
Millions  40
30
Change Order
20
No change orders have been executed during this period.          Dollars in  10
0
Risks                                   Initial Change Orders Spent
No risk have been identified at this time.
Budget Transfers                        Photo
None



AIRPORT

30  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Connect C1 BHS to C88 BHS
Project:   C800170      This project connects the C1      Status Snapshot
Budget: $3,032,000      baggage handling system (BHS) to  On Schedule
Phase: Construction     the C88 BHS. It installs two High-  On Budget
Start: 8/30/2009          Speed Diverters plus additional     No Change Orders
Completion: 12/31/2010   baggage conveyor length that will   Total Change Orders Amount:
connect the two C1 sortation loops   N/A
to the C88 BHS.
Budget/Costs Incurred
Significant Developments
3.5
The 100% design is complete. The project received Commission
3
authorization for construction funding on March 23, 2010. The project
was advertised and bids were recieved on May 27, 2010. A total of     Millions 2.5
2
Dollars in 
five contractor submitted bids for the project. The Port is working on     1.5
award and execution of the contract.                          1
0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
Currently the project is on schedule.
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2010 Report  31

SECOND QUARTER REPORT, 2010
Renew/Replace 42 Escalators & 2 New
Escalators
This project will replace 42         Status Snapshot  Prior Report
Project:   C800237      escalators in the Main Terminal,    Ahead of Schedule 3Q 09
Concourse B, and South Satellite.   On Budget
Budget: $55,000,000
In addition, two new escalators will   No Change Orders
Phase: Design        be installed at the South Satellite.   Total Change Orders Amount:
Start: 11/02/2007                                 N/A
Completion: 12/31/2013
Budget/Costs Incurred
Significant Developments
60
Request for Qualifications was issued on May 19, 2010. Six firms      50
submitted Statement of Qualifications. The selection of the finalists
40
is scheduled to be issued in early July 2010 with the issuance of the    Millions
30
Request for Proposals to the finalists later in July 2010. The project
20
is utilizing the design-build contracting method to accelerate the       Dollars in  10
overall project schedule.
0
Authorized  Forecasted Costs Incurred
Schedule
The schedule has been updated to reflect an expedited design-build
procurement as well as an accelerated construction duration with a   Construction Costs
resultant tentative completion date in 2013.                    Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested following the review of the proposal documents and
selection of a firm.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
32  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Central Plant Pre-Conditioned Air
Project:   C800238     This project will provide a centralized  Status Snapshot Prior Report
Budget: $40,600,000    pre-conditioned air plant, associated  Delayed Schedule 3Q 09
Phase: Design       heating and cooling piping systems,   On Budget
Start: 06/15/2009       and jet bridge terminal air handling    No Change Orders
Completion: 12/10/2012  units to serve airplanes with heating   Total Change Orders Amount:
and cooling while at the gates.       N/A
Significant Developments
The design documents were completed. Commission approved     Budget/Costs Incurred
advertising for bids. The project was advertised on June 4, 2010.
50
Contractor interest was very high; over 50 participants attended the
pre-bid meeting.                                      40
30
Schedule
in Millions 20
The design process took longer than anticipated and the project is      Dollars  10
approximately two months behind for completing the construction
documents; however, we coordinated closely with the FAA to make      0
sure we were still on track to receive the necessary funding. We          Authorized  Forecasted Costs Incurred
anticipate bids in early July of 2010.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
Not applicable
Authorization of construction funding and authority to advertise for
construction was authorized by the Commission on May 11, 2010.
Change Order
None
Risks
FAA funding is pending the final application. The grant is part of the
Voluntary Airport Low Emissions (VALE) program. The project will
not move forward without the grant.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 2Q 2010 Report  33

SECOND QUARTER REPORT, 2010
Fire Piping Upgrades - Main Terminal
Project:   C800239      This project will upgrade the Main   Status Snapshot Prior Report
Budget: $1,450,000      Terminal fire piping to restore     Ahead of Schedule    4Q 09
Phase: Close Out      system reliability and provide full   Under Budget   4Q 09
Start: 09/23/2008         monitoring capability with the fire    1 Change Orders
Completion: 03/24/2010   alarm system.             Total Change Orders Amount:
($10,000)
Significant Developments                    Budget/Costs Incurred
Project is complete and in close out. Substantial completion was
issued on March 24, 2010.                               2
1.5
Schedule                            Millions
1
The construction was completed ahead of schedule. The fire piping
contractor identified efficiencies and performed the work accordingly.    Dollars in 0.5
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
It is anticipated that this project will have a future savings of
approximately $800,000.
Change Order                         Construction Costs
None                                   0.3
0.2
Risks                                Millions 0.1
None identified at this time.
0
Budget Transfers                          Dollars in     Initial Change Orders Spent
0.1
None this quarter



AIRPORT
34  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
2nd Floor HVAC Upgrades
Project:   C800249      Construct a new Heating        Status Snapshot
Budget: $1,700,000      Ventilating and Air-Conditioning    On Schedule
Phase: Close Out      (HVAC) air supply duct system to   On Budget
Start: 03/25/2008         the north side of the second floor of  15 Change Orders
Completion: 04/09/2010   the central main terminal       Total Change Orders Amount:
administration building and the      $114,331
concessions located directly below
on the ticketing level.            Budget/Costs Incurred
Significant Developments
1.72
Construction was completed on April 9, 2010.                   1.7
1.68
Schedule                            1.66 Millions
1.64
The project is in close-out phase.
1.62  Dollars in 
1.6
Budget
1.58
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Fifteen change orders were issued this quarter.                Construction Costs
1
Risks
0.8
None identified at this time.                                  Millions 0.6
Dollars in 
Budget Transfers                           0.4
0.2
None this quarter
0
Initial  Change Orders  Spent
Cost of Construction Growth
The project scope required the installation of supply and return air
ducts for the 2nd floor offices in the Old Administration Building at
STIA. Change orders were required to correct varying design and
site conditions discovered during the contract submittal, demolition
and installation processes. Change orders were negotiated and
issued covering time and scope to redesign the supports for the
ductwork, address the changed site conditions for the return air duct
and add temporary HVAC to the Host offices.

AIRPORT

Port of Seattle 2Q 2010 Report  35

SECOND QUARTER REPORT, 2010
Parking System Replacement
Project:   C800253      This project replaces the current    Status Snapshot
Budget: $9,777,000      Parking Revenue Control System,   On Schedule
Phase: Design        which manages parking access    On Budget
Start: April 6, 2010       and revenue collection in the      No Change Orders
Completion: 12/15/2011   Airport's Main Parking Garage.    Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
Project notebook was completed and presented to the Investment
Committee. Commission approved moving to the design phase on     12
April 6th. Currently in contract negotiations with design services        10
consultant. Current plan is to complete design in 2010, bid the
project during December 2010, and construct the system during       Millions 8
Dollars in 
6
2011.
4
2
Schedule
0
The project is approximately 3 weeks behind schedule due to
Authorized  Forecasted Costs Incurred
protracted consultant scope and fee negotiations.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order                         Photo
No change orders were issued this quarter.
Risks
This project has an aggressive schedule.
Budget Transfers
None this quarter



AIRPORT

36  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Aircraft RON Parking USPS Site
This project will prepare the site for   Status Snapshot
Project: C800254
the construction of Hardstands for    On Schedule
Budget: $43,900,000                        On Budget
Phase: Design        use as Remain Overnight (RON)
Start: 04/05/2009        parking of aircraft at the Air Mail     No Change Orders
Center site.                   Total Change Orders Amount:
Completion: 06/30/2013                       N/A
Significant Developments
Budget/Costs Incurred
Completed the lease buyout negotiation with the United States
Postal Service (USPS) and is scheduled for lease termination in
50
2010. A new one year lease with Customs and Border Protection
40
will extend into 2011. Design efforts for the demolition of the Air
Mail Center including the design for minimal site improvements       Millions 30
allowing for temporary uses and amenities, and 15% design will start    20
in Summer 2010.                                 Dollars in  10
0
Schedule
Authorized  Forecasted Costs Incurred
Abatement and demolition of the USPS Building is scheduled to
start second quarter of 2011. No current time frame for construction
of a permanent hardstand has been set.
Construction Costs
Budget                           Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested following the review of the proposal documents and
selection of a firm.
Change Order
None
Risks
Extent of asbestos in USPS Building could affect cost.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 2Q 2010 Report  37

SECOND QUARTER REPORT, 2010
8th Floor Weatherproofing
Project:   C800274      This project includes removal and   Status Snapshot
Budget: $13,000,000     replacement of the floor covering   On Schedule
Phase: Design        system on the 8th floor of the STIA  On Budget
Start: 03/23/2010         parking garage and repair or       No Change Orders
Completion: 03/31/2013   replacement of expansion joints    Total Change Orders Amount:
and flashings.                 N/A
Budget/Costs Incurred
Significant Developments                     14
Currently negotiating scope and fee with the consultant for design      12
services. Design will be underway this quarter.                   Millions 10
8
6
Schedule
Dollars in   4
Current plan is to complete design in 2010, bid in first quarter 2011      2
and construct during the spring/summer of 2011 and 2012.           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
No change orders were issued this quarter.
Photo
Risks
This is a weather-dependent project.
Budget Transfers
None this quarter



AIRPORT

38  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Common Use Equipment Expansion (CUSE)
Project:   C800276      This project installs flexible       Status Snapshot
Budget: $3,090,000      common use facilities at some    On Schedule
Phase: Design        South Satellite and Concourse A   On Budget
Start: 09/01/2009         gates, as well as at Delta's former   No Change Orders
Completion: 12/31/2011   (pre-NWA merger) ticket counters.  Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Procurement of the design consultant continues. Commission
3.5
Authorization for procurement of an IDIQ contract will be requested
3
on August 3, 2010.
Millions 2.52
Schedule                             1.5
The project is on schedule.                                Dollars in  1
0.5
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2010 Report  39

SECOND QUARTER REPORT, 2010
South Satellite Delta Sky Club Expansion
Project:   C800336     Construction of a new 6,800 square   Status Snapshot
Budget: $5,440,000    foot Sky Club lounge on the roof of   On Schedule
Phase: Design       the South Satellite for Delta Air Lines.  On Budget
Start: 06/01/2010                                 No Change Orders
Completion: 04/30/2011                       Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
The Port of Seattle and Delta Air Lines are negotiating tenant
reimbursement amounts for the shell scope. The tenant designer is      6
resolving permit comments.                              5
Schedule                            Millions 4
3
Construction work is scheduled to begin in the summer of 2010 and     2
to be complete by spring 2011.                            Dollars in  1
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

40  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Roof Replacement Program
Project:   C800360      Remove and replace the roofing    Status Snapshot
Budget: $2,640,000      systems on the south and central   On Schedule
Phase: Design        sections of the Main Terminal. The  On Budget
Start: 4/25/2010          new roofing systems will achieve    No Change Orders
Completion: 12/20/2010   LEED credits and are Energy Star   Total Change Orders Amount:
rated. This project is part of a      N/A
multi-phased program.
Budget/Costs Incurred
Significant Developments
3
Design and bid document preparation is underway.               2.5
2
Schedule                            Millions
1.5
The project is on schedule.                                 1
Dollars in 0.5
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None at this time
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 2Q 2010 Report  41

SECOND QUARTER REPORT, 2010
RW16C/34C Reconstruction Design
Project:   C800406      This project will produce the 60%   Status Snapshot
Budget: $669,000       design for the runway 16C/34C    On Schedule
Phase: Design        reconstruction. The design will    On Budget
Start: 05/04/2010         include utilities, runway status      0 Change Orders
Completion: TBD       lights, and other scope items     Total Change Orders Amount:
related to the project.             $0
Significant Developments                    Budget/Costs Incurred
Preliminary design is underway.
0.8
Schedule
Millions 0.6                                                                              The 60% design will be completed in 2010, followed by the
0.4
remaining 40% design in 2015. Schedule for the design is as
follows: 15% design in July with 30% design complete in September    Dollars in 0.2
and 60% design completed by December.
0
Authorized  Forecasted Costs Incurred
Budget
Port Commission approved $669,000 on May 4, 2010. Port staff will
return to Commission in late 2014 or early 2015 to request funds for   Construction Costs
the final 40% design. The forecast will be reassessed at that time.    Not applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None



AIRPORT

42  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Fire Vehicles
Project:   C102396      Purchase of fire vehicles according  Status Snapshot
Budget: $1,369,000      to the Fire Department Vehicle    On Schedule
Phase: Implementation   Replacement Master Plan. Includes  On Budget
Start: 11/16/2008         purchase of an ARFF vehicle and   No Change Orders
Completion: 7/31/2009    medical aid unit vehicle.        Total Change Orders Amount:
N/A
Significant Developments
The ARFF vehicle contract has been executed.               Budget/Costs Incurred
The Medical Aid Unit contract has been executed; the Aid vehicle will    1.5
be in service beginning July 2010.
Millions  1
Schedule
The project is on schedule.                                0.5
Dollars in 
Budget                             0
The project forecast is within the approved budget.                   Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 2Q 2010 Report  43

SECOND QUARTER REPORT, 2010
Highline School Noise Insulation
Project:   C200007      Highline School Insulation        Status Snapshot Prior Report
Budget: $101,797,000    Agreement will provide funding for  Delayed Schedule 3Q 09
Phase: Construction     sound mitigation for 15 schools that  On Budget
Start: 03/23/1999         are impacted by aircraft noise from   No Change Orders
Completion: 11/30/2021   Sea-Tac Airport.            Total Change Orders Amount:
N/A
Significant Developments
The insulation of seven schools has been completed and no more    Budget/Costs Incurred
are scheduled until 2012.
120
100
Schedule
80
Port funding is authorized and will be available when the matching
60
funds are provided by the state and school district. The schedule for     Millions
40
state funding is not known. The district's schedule is also dependent    Dollars in 20
on obtaining general election bonds at various intervals.
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
Not applicable                                      Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

44  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
3rd Runway Residential Acquisition
Project:   C200015    Acquire single/multi-family residences   Status Snapshot Prior Report
Budget: $34,340,000   located in the noise-impacted 3rd     Delayed Schedule    1Q 10
Runway flight path in the City of Burien
Phase: Close Out                          On Budget
to comply with FAA noise exposure
Start: 05/27/1999                                 No Change Orders
and safety regulations.
Completion: TBD                           Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The final of three phases is complete. 56 of 59 properties have been
50
acquired and the residents relocated to quieter neighborhoods. Two
40
properties (one single family residence and one 16-unit apartment     Millions 30
complex) have been forwarded to our outside legal counsel for
20
acquisition via the mediation and/or condemnation process.
Dollars in  10
Condemnation proceedings for a third property have been
suspended. Timing of the remaining three properties is dependent on    0
Authorized  Forecasted Costs Incurred
the legal process. Abatement and demolition of vacant homes
continues.
Schedule
Construction Costs
The project end date is delayed due to the pending court cases and
Not Applicable
dependent on the length of time the property condemnation process.
This does not affect airport or 3rd Runway operations.
Budget                            Photo
The project forecast is within the approved budget and authorization.
Change Order
Not Applicable
Risks
No significant risks identified.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 2Q 2010 Report  45

SECOND QUARTER REPORT, 2010
FAR Part 150 Mobile Home Park Acquisition
Project:   C200037     Acquisition of mobile and         Status Snapshot Prior Report
Budget: $52,306,110    manufactured home parks, and     Ahead of Schedule    1Q 10
Phase: Close Out     relocation of the tenants, to reduce   On Budget
Start: 02/12/2002       the number of people living in mobile   No Change Orders
homes within high noise areas.
Completion: 06/17/2010                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
All mobile home units have been purchased. Demolition and site
52.5
restoration is 100% complete.
52
Schedule                            Millions
51.5
All tenants have been successfully relocated to quieter
neighborhoods.                                   Dollars in  51
50.5
Budget
Authorized  Forecasted Costs Incurred
The total budget increases for the life of this program are
approximately 2.55% above the 2001 forecast for this Capital
Improvement Project.
Construction Costs
Change Order                         Not Applicable
Not Applicable
Photo
Risks
Regulated materials abatement and demolition costs could be higher
than anticipated.
Budget Transfers
None this quarter



AIRPORT

46  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $10,822,000     Insulation Agreement will provide   Delayed Schedule 1Q 08
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      No Change Orders
Completion: 10/01/2011   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
N/A
Significant Developments
Twelve of the 22 eligible buildings have been sound insulated by the  Budget/Costs Incurred
college.
12
Schedule                             10
Building #9 will be under construction during the summer of 2010      Millions 8
and is anticipated to be complete 1st Quarter 2011. The schedules      6
for the remaining buildings are dependent on state funding.           4
Dollars in   2
Budget                             0
The project forecast is within the approved budget. We will complete       Authorized  Forecasted Costs Incurred
noise audits on each of the remaining buildings that have not been
reconstructed to see if in the future any will be eligible for FAA grant
funds. Authorization of the remaining project budget will be
requested for one building at a time from the Commission in the     Construction Costs
future when schedule is determined.                       Not Applicable.
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed. The Port is working with the College to determine
estimates for the remaining college buildings that have not been
completed.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 2Q 2010 Report  47

SECOND QUARTER REPORT, 2010
Home Insulation Retrofit
Project:   C200048      This CIP includes two projects that   Status Snapshot Prior Report
Budget: $5,344,000      provide either re-insulation or repair  Delayed Schedule 4Q 09
Phase: Construction     of previously insulated homes due  On Budget
Start: 01/11/2005         to safety and condensation issues.   No Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
The Port is researching remaining eligible homes to continue with
insulation retrofit.                                              6
5
Schedule                            Millions 4
The project will commence upon review of remaining homes.          3
2
Budget                             Dollars in  1
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable
Risks                               Construction Costs
Not Applicable
There is potential liability associated with egress safety issues.
Budget Transfers
None



AIRPORT

48  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot
Budget: $2,450,000      that are within the 1998 65 decibel  On Schedule
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   No Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Seven homes are in process and there are 28 on the waiting list for
3
the next group.
2.5
2
Schedule                            Millions
1.5
This project is on schedule.
1
Dollars in 0.5
Budget
0
The project forecast is within approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable                                     Construction Costs
Not Applicable
Risks
The ability to accomplish the insulation is dependent on
homeowner's schedules, willingness to sign an aviation easement,
and structural integrity of the home.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2010 Report  49

SECOND QUARTER REPORT, 2010
Street Vacations - Des Moines Creek 1
Project:   C800046    Purchase the City of Des Moines-      Status Snapshot Prior Report
Budget: $3,850,000   owned streets in the Des Moines Creek  Delayed Schedule 1Q 10
Phase: Implementation Business Park site that are surrounded  On Budget
Start: 10/01/2008      by Port-owned property. This        No Change Orders
Completion: 12/31/2010 acquisition will enable the Port to     Total Change Orders Amount:
develop the business park site.        N/A
Significant Developments                    Budget/Costs Incurred
Per the Port of Seattle's agreement with the City of Des Moines, the
3.86
amount owed the City has been deposited into an escrow account
3.84
pending satisfaction of all the conditions required for closing.
3.82  Millions
Schedule                             3.8
Acquisition is expected to be completed by December 31, 2010. The   3.78  Dollars in 
Port is still negotiating the agreement with the City of Des Moines,
3.76
which we expect to complete before the end of the year.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Not applicable.
Risks
The original conditions required for closing--most notably, the Des
Moines City Council's approval of the developer's master plan--
cannot be met now that the developer selected for the project
withdrew from ground lease negotiations. The Port anticipates
revising its existing agreement with the City to reflect a new
approach to developing the site.
Budget Transfers
None this quarter

AIRPORT

50  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   No Change Orders
Completion: 12/31/2011   owned properties.           Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The Burien Seventh Day Adventists Church and School were
3.5
acquired December 31, 2008. Next acquisitions are for the
3
Sunnydale Substation and a street vacation in Burien.
Millions 2.52
Schedule                             1.5
Properties are purchased as Commission authorization is received.     Dollars in  1
The program is now expected to be complete in 2011. The last       0.5
0
parcel to be acquired is tied to the North East Redevelopment Area
Authorized  Forecasted Costs Incurred
(NERA) project which is a joint effort with the city of Burien. They will
not be ready to vacate the street until next year.
Budget                            Construction
Not Applicable
The project forecast is within the approved budget.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2010 Report  51

SECOND QUARTER REPORT, 2010
Tenant Reimbursement
Project:   C800154    Build out of spaces for new and      Status Snapshot
Budget: $4,709,577    existing tenants. If more than a "basic  On Schedule
finish" condition space is built for the    On Budget
Phase: Construction
tenant, the tenant is required to       No Change Orders
Start: 08/14/2007
reimburse the Port for the cost of the   Total Change Orders Amount:
Completion: 03/31/2012
work beyond this "basic finish". These   N/A
reimbursements are allowed under
the guidelines described in the       Budget/Costs Incurred
"Tenant Reimbursement Policy".
5
Significant Developments                      4
Port had no tenant reimbursement activity in the 2nd Quarter of 2010.    Millions 3
2
Schedule                            Dollars in  1
Schedules vary to meet the tenant's needs.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order                         Not Applicable.
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

52  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
28th Ave Property Acquisition
Project:   C800381      Acquire by purchase two King     Status Snapshot
Budget: $1,455,000      County Parcels 042204-9218 &    On Schedule
Phase: Implementation   042204-9139. Demolish the      On Budget
Start: 5/4/2010          improvements on the Property and   No Change Orders
Completion: 12/31/2010   restore it in accordance with the    Total Change Orders Amount:
Interlocal Agreement.           N/A
Budget/Costs Incurred
Significant Developments
1.5
Property has been acquired and RMM assessment completed.
1.45
Schedule                            Millions
1.4
On-schedule for demolition and restoration
1.35  Dollars in 
Budget
1.3
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Risks
N/A
None identified at this time
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 2Q 2010 Report  53

SECOND QUARTER REPORT, 2010
Alaskan Way St Vacation and Public Access
Project:   C000579      Scope includes all public access    Status Snapshot Prior Report
Budget: $1,036,000      improvements at multiple sites and  Delayed Schedule 2Q 08
Phase: Planning       fees as required by the City of    On Budget
Start: 1996             Seattle in order to vacate Alaskan   No Change Orders
Completion: 2011       Way South at T-30 site.        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Project continues to be on hold by the City pending closure of all
1.2
other previous street vacations. The original authorizations date back
1
to 1998 and 1999. When the City is ready to move forward with this
0.8
project, staff will return to Commission for new authorizations. This     Millions
0.6
will be the last report on the current authorized project. Reporting will
0.4
resume when Commission approves the project again in the future.     Dollars in 0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
No changes this quarter.
Budget
Construction Costs
No changes this quarter. Plan is to get new authorizations for future  None
work pursuant to Resolution 3605.
Photo
Change Order
Not Applicable
Risks
Risks have not changed from 3Q 2008.
Budget Transfers
Not Applicable


SEAPORT

54  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
T-115 Dock Reconstruction
Status Snapshot Prior Report
Project:   C102451      Upgrade three areas of existing    Delayed Schedule 4Q 08
Budget: $31,541,577     1200 ft dock, upgrade Berth 1 and  Forecast Overrun 1Q 08
Phase: Construction     improve 15 acres of uplands for    29 Change Orders
Start: 7/2003            tug/barge cargo operations.       Total Change Orders Amount:
Completion: 12/31/2009                       $1,748,865
Budget/Costs Incurred
Significant Developments
31.6
Construction was completed in 2Q 2010. The Tenant began using     31.4
Berth 1 at the end of April 2010. Construction Management will        Millions31.2
31
negotiate the final Contract claims in 3Q 2010.                   30.8
30.6   Dollars in 30.4
Schedule                             30.2
Authorized Forecasted  Costs
Project is expected to close out by end of 4Q 2010.
Incurred
Budget
Construction Costs
No change this quarter.
30
Change Order                          Millions 25
20
A change order was approved for unexpected difficulties in driving
15
pipe and sheet pile caused by unanticipated underwater             10
obstructions. However, project is expected to stay within the          Dollars in  5
approved budget.                                    0
Initial  Change  Spent
Orders
Risks
None
Photo
Budget Transfers
None
Cost Growth of Construction
Underwater obstructions encountered during the dredging and pile
installation activities resulted in a change order that increased the
construction contract cost growth above ten percent.

SEAPORT
Port of Seattle 2Q 2010 Report  55

SECOND QUARTER REPORT, 2010
Terminal 30/Terminal 91 Program
Status Snapshot
Project: C800085     Redevelop Terminals 25/28/30 into one  On Schedule
Budget: $121,525,000  combined container facility. Relocation   On Budget
Phase: Construction  of the existing T-30 Cruise operations   129 Change Orders
Start: 10/2/07        into a new facility at T-91, and related    Total Change Orders
Completion: 4/30/11   facility improvements and berth       Amount: $6,581,000.
dredging.
Budget/Costs Incurred
Significant Developments
125
T-91: New canopy and canopy extension north of the cruise terminal
building was substantially completed and ready for use for the 2010    120
cruise season. New canopy structures, reconfigured Ground        Millions115
Transportation Center roadways, and other miscellaneous
110
improvements have been well received by the cruise lines and        Dollars in 105
Cruise Terminal of America. Cruise Terminal's art planner
Authorized  Forecasted Costs Incurred
completed art plan for terminal's public art.
Schedule
Construction Costs
T-91: Key components of work authorized under the December,
2009 Commission action have already been completed. Terminal's     100
public arts component is scheduled to be completed in 2011.
80
Millions  60
T-30: T-30 component of the project is in closeout and will no longer
40
be included as previously reported.
Dollars in   20
0
Budget
Initial  Change Orders  Spent
The budget remains stable. Current program budget is
$121,500,000 and the forecast is $115,900,000.
Photo
Change Order
There were no change orders this quarter. Major construction
contracts are in closeout.
Budget Transfers
There were no budget transfers in or out of the program.


56  Port of Seattle 2Q 2010 Report

Cost Growth of Construction
T-91 Cruise Terminal Upgrade  MC-0314783  The major
construction contract is in closeout. The cost growth of construction
remains as reported in 4Q 09.
T-30 Upgrade  MC-103326  The major construction contract is in
closeout. The cost growth of construction remains as reported in
4Q 09.
Risks
T-91: None. Facility is in operation.
T-30: None. Facility is in operation.








SEAPORT

Port of Seattle 2Q 2010 Report  57

SECOND QUARTER REPORT, 2010
P66 Bag. Corridor & Pass. Screening
Project:   C800114      Provide baggage and passenger    Status Snapshot Prior Report
Budget: $2,087,000      screening improvements at P66 to  Delayed Schedule 3Q 09
Phase: Construction     accommodate larger cruise vessels  On Budget
Start: 1/1/2008          with 300-400 more passengers per   No Change Orders
Completion: 12/31/2009   sailing.                Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Project was bid out for a fourth time June and received four bids
2.5
which were all deemed "non responsive". Bid documents have been
reviewed and project is scheduled to go back out to bid the second      2
week in August.                                     Millions 1.5
1
Schedule                            Dollars in 0.5
The cruise season has started, as such construction will be
0
postponed until 4Q 10.
Authorized  Forecasted Costs Incurred
Budget
None                                 Construction Costs
None
Change Order
None
Risks
The biggest risk is that we may not get responsive bids again but we
are mitigating this risk by reevaluating the bid documents and giving
the contractors ample time to purchase the materials and do the
construction. There is potential risk to the schedule with the rebid.
Budget Transfers
None


SEAPORT

58  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Terminal 18 South Fender Improvements
Status Snapshot Prior Report
Project: C800121        Replace 800' of deteriorated fender
Delayed Schedule 4Q 09
Budget: $3,300,000      system at the south end of
On Budget
Phase: Design        Terminal 18
0 Change Orders
Start: 3/26/08                                    Total Change Orders Amount:
Completion: 3/31/11                         $0
Significant Developments
Budget/Costs Incurred
Commission authorized construction funding for the replacement of
800' of the fender system.
3.5
Schedule
3
No change from last report. Construction is scheduled to start in       2.5
December 2010, with berth available for use in March 2011.          2
Millions
1.5
Budget                             Dollars in 1
0.5
Project within approved budget.                             0
Authorized  Forecasted Costs Incurred
Change Order
None this quarter
Construction Costs
Risks                               None
None this quarter
Photo
Budget Transfers
None




SEAPORT

Port of Seattle 2Q 2010 Report  59

SECOND QUARTER REPORT, 2010
T-5 Crane Spreader Replacement
Project:   C800123      To replace two crane cargo       Status Snapshot Prior Report
Budget: $525,000       spreader beams that are beyond   Delayed Schedule 1Q 10
Phase: Construction     their useful life. Spreader beams   On Budget
Start: 10/24/06          are terminal equipment used to     No Change Orders
Completion: 3/31/09     move containers to and from ships  Total Change Orders Amount:
and trucks.                   $0
Significant Developments                    Budget/Costs Incurred
Fabrication is currently in progress.
1.2
1
Schedule
Millions 0.8
Delivery is scheduled for August 2010.                        0.6
0.4
Budget                             Dollars in 0.2
0
Only two of the spreader beams will be installed due to the tenant
Authorized  Forecasted Costs Incurred
reprioritizing their needs. The forecast has been reduced
accordingly.
Construction Costs
Change Order
None                                   0.5
0.4
Risks                                 0.3
None                                   0.2
Millions
Budget Transfers                          Dollars in  0.1
0
None                                      Initial Change Orders Spent

Photo


SEAPORT

60  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
North Harbor Island Mooring Dolphins (4)
Project:   C800182      Replace four barge mooring      Status Snapshot
Budget: $500,000       dolphins at the north end of Harbor  On Schedule
Phase: Design        Island.                On Budget
Start: 07/05/09                                   0 Change Orders
Completion: 3/31/11                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Purchased preliminary design from Crowley Maritime. Executed
2.5
design contract for completion of bid package.
2
Schedule                             1.5
Millions
Project is still on schedule to be completed within the 2010-11 permit     1
fish window. Scheduled completion date extended to 3/31/10 based    Dollars in 0.5
on longer lead time for steel materials and design completion.
0
Commission construction authorization request expected 3rd quarter
Authorized  Forecasted Costs Incurred
of 2010.
Budget
Construction Costs
Revised construction estimate significantly higher than originally     None
estimated due mainly to increases in material cost estimates.
Construction funding request will reflect latest estimate.            Location
North Harbor Island
Change Order
None                                 Photo
Risks
None
Budget Transfers
None



SEAPORT
Port of Seattle 2Q 2010 Report  61

SECOND QUARTER REPORT, 2010
T-10 Interim Redevelopment
Status Snapshot Prior Report
Delayed Schedule 2Q 10
Project:   C800264   Funding is to develop full project scope    On Budget
Budget: $980,000    and design of utilities to support terminal  No Change Orders
Phase: Design     related activities. Primary focus is the    Total Change Orders Amount:
Start: 3/22/08       design of the storm water drainage system  $0
Completion: 11/30/09 and the paving, lighting and fencing.
Budget/Costs Incurred
Significant Developments
As noted previously, revised design and permit documents were
8
submitted to the City, State and Federal Agencies. During 2Q 2010,
staff received permit approval from several agencies. However,        6
permit review is progressing with the final approval needed from the    Millions
4
Department of Natural Resources. Additional funding, $180,000 was
approved to support the additional permit and design efforts. Their      Dollars in  2
approval is contingent on negotiating a use agreement with
0
Lockheed. Staff expects permits late in the 3Q 2010.
Authorized  Forecasted Costs Incurred
Schedule
Due to permit approval delays, completion is now scheduled to be
3Q 2011. This a nine-month delay from the previous report. Since   Construction Costs
the new outfall is in-water work the construction needs to be done    None
during the in-water-work season. The earliest opportunity to do this
work will be 3Q 2011.                                 Photo
Budget
Staff will return to Commission for additional construction
authorization 4Q 2010. The Project Cost forecast was increased
from $5,100,000 to $6,700,000 to reflect the addition of site lighting;
added ground and storm water collection/disposal costs during
construction, added soil disposal and additional costs related to
permits and associated design revisions.
Change Order
None
Risks
Schedule delays
Budget Transfers
None
SEAPORT
62  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
T-91 Mobile Gangway
Project:   C800273      Construct two mobile gangways    Status Snapshot
Budget: $6,460,000      and the associated support      On Schedule
Phase: Construction     infrastructures for the new T-91    On Budget
Start: 6/24/2008          Smith Cove Cruise Terminal       5 Change Orders
Completion: 4/30/2009                        Total Change Orders Amount:
$557,536
Significant Developments                    Budget/Costs Incurred
1Q 2010 modifications to the end of the vessel walkways are working
6.5
out well, allowing the walkways to be deployed/tucked under low
clearance areas on cruise ships.                           6.45
Millions 6.4
Schedule
6.35
Systems are under an 18 month warranty.                    Dollars in 6.3
6.25
Budget
Authorized  Forecasted Costs Incurred
Project is on budget.
Change Order                         Construction Costs
No change order issued during 2Q 2010.
7
Risks                                 6
5
None                                  Millions  4
3
Budget Transfers
Dollars in    2
None                                   1
0
InitialChange OrdersSpent

Photo


SEAPORT
Port of Seattle 2Q 2010 Report  63

SECOND QUARTER REPORT, 2010
T-91 Road Pavement Entry & Guard Shack
Project:   C800343                             Status Snapshot Prior Report
Budget: $138,000     Repave main entryway/intersections   Delayed Schedule 1Q 10
Phase: Design       west of the main guard shack.      On Budget
Start: 12/18/09                                   0 Change Orders
Completion: 5/1/2011                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Project design placed on hold during Q2 to better understand new
0.15
permit requirements and allow T-91 Watermain Project's design to
advance in order to better coordinate watermain crossing alignments
Millions 0.1                                                                                  and minimize construction impacts.
Schedule                            0.05
Dollars in 
Project design is being delayed one quarter to address new permit
0
requirements and new watermain alignments under the T-91
Authorized  Forecasted Costs Incurred
Watermain Project. Design will resume in Q3 with construction
scheduled right after 2010 cruise season.
Budget                            Construction Costs
None
Project is currently on budget.
Change Order
None
Risks
Paving is weather dependent and paving window is somewhat
limited after cruise season, before cold weather sets in.
Budget Transfers
None


SEAPORT

64  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
T46 Upgrade Yard Lighting
Status Snapshot
Project:   C800347      Purchase and Engineering support
Budget: $680,000       for installation of energy saving    On Budget
Phase: Design        yard lighting and equipment, as    0 Change Orders
Start: 08/25/09          part of T46 lease negotiation.      Total Change Orders Amount:
$0
Completion: 12/31/2010
Budget/Costs Incurred
Significant Developments
0.8
Initial advertisement yielded no responsive bidders. Package was rebid
and received multiple bids. After CPO evaluation, an award is      0.6
pending.                                        Millions
0.4
Schedule                            Dollars in 0.2
On schedule
0
Authorized  Forecasted Costs Incurred
Budget
No change
Construction Costs
Change Order                         None
None
Photo
Risks
Extended procurement could delay schedule
Budget Transfers
None




SEAPORT
Port of Seattle 2Q 2010 Report  65

SECOND QUARTER REPORT, 2010
T-5 Crane Cable Reels
Project:   C800349       Purchase Cable Reels for tenant   Status Snapshot
Budget: $3,500,000                         On Schedule
Phase: Design                            On Budget
Start: May 4, 2010                                0 Change Orders
Completion: March 31, 2011                    Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Commission approved funding for the Project on May 4, 2010.
Consultant is preparing performance specification for Request for       4
Quotation.
3
Schedule
2
in Millions
Not applicable
Dollars   1
Budget
0
Not applicable                                          Authorized Forecasted Costs Incurred
Change Order
Not applicable                                      Construction Costs
Risks                               Photo
Not applicable
Budget Transfers
Not applicable




SEAPORT

66  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
East Marginal Way Grade Separation
Status Snapshot Prior Report
Delayed Schedule 1Q 08
Project:   E 102007      FAST Corridor funded project;     Forecast Overrun  1Q 08
Budget: $49,000,000     FHWA, State, City with Port      12 Change Orders
Phase: Construction     commitment of $18,800,000. Scope  Total Change Orders Amount:
Start: 5/2006            is to construct grade separation in   $266,295
Completion: Q3 2011     vicinity of T5 and T18 to minimize
truck traffic/rail conflicts.           Budget/Costs Incurred
60
50
Significant Developments
Millions 40
Construction of structural earth embankment walls 90% complete.
30
Foundation shaft installations continue. Contaminated soils
20
discovered and required disposal.                          Dollars in  10
0
Schedule
Authorized  Forecasted Costs Incurred
Construction is underway and scheduled completion remains
September 1, 2011.
Construction Costs
Budget
Remains the same as reported in 4Q 09.                       60
50
Change Order                          Millions 40
12 change orders have been executed for a total net amount of         30
$266,295.                                        20
Dollars in   10
Risks                                 0
Construction change orders could occur, which could increase cost         InitialChange OrdersSpent
of construction.
Budget Transfers
New source of funds indicates that no budget transfers will be
required.


SEAPORT

Port of Seattle 2Q 2010 Report  67

SECOND QUARTER REPORT, 2010
Terminal 46 ZPMC Gearboxes
Project:   Expense      Implementation of contingency     Status Snapshot
103705,103706,103707    plans to keep the three port owned  On Schedule
Budget: $1,227,000      ZPMC cranes located at Terminal   On Budget
Phase: Construction     46 operating while          No Change Orders
Start: 8/22/2007          cause of the failing gearboxes is    Total Change Orders Amount:
investigated                  $0
Completion: 12/31/09
Budget/Costs Incurred
Significant Developments
1.4
No change. ZPMC acknowledged similar problems have occurred at
1.2
other ports and may begin arbitration process with manufacturer of      1
gearbox.                                        Millions 0.8
0.6
Schedule                            Dollars in 0.4
0.2
No change. Continue to work with the designer, consultants and
0
manufacturer to identify a solution.
Authorized  Forecasted Costs Incurred
Budget
Budget remains unchanged from the 1Q 10 Report.            Construction Costs
No Major Construction
Change Order                         Contracts
None this quarter
Risks                               Photo
Additional gearbox failures would result in further disruptions to
operations.
Budget Transfers
None


SEAPORT


68  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
T5/T18 Maintenance Dredging
Project:   Expense   Mechanically dredge up to 6,900 cy of   Status Snapshot
103835/103838      sediment along approximately 4,900' of  On Schedule
Budget: $2,937,000   berths at T18 and dispose of dredged   Under Budget
Phase: Construction  material at approved upland disposal   No Change Orders
Start: Feb 2008       sites; conduct environmental testing,    Total Change Orders Amount:
permitting, and design work for T5      $0
Completion: Feb 2011
maintenance dredging
Budget/Costs Incurred
Significant Developments                     3.5
T-18 WP#103838: This project has been completed and closed out.    3
This is the final report on this portion of the project.                 Millions 2.52  Dollars in 
1.5
T-5 WP#103835: Maintenance Dredging received Commission
1
authorization for construction on July 13th, and will be reported
0.5
separately beginning Q2 2010.
0
Authorized  Forecasted Costs Incurred
Schedule
T5: Completed 90% design and expect to advertise for bids in July.
Construction Costs
Budget                            None
No changes in Q2 2010.
Photo
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable


SEAPORT

Port of Seattle 2Q 2010 Report  69

SECOND QUARTER REPORT, 2010
Barge Layberth Improvements -- T25/P28/T46
Project: Expense 104011-3 Improvements to the fendering and  Status Snapshot
Budget: $338,000       terminal systems at Terminal 25,   On Schedule
Phase: Construction     Pier 28 and Terminal 46 to provide  On Budget
Start: 10/14/08          viable barge layberth use at these   No Change Orders
Completion: 4/1/10      sites.                 Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
All construction completed and berths returned to service. This will
0.35
be the final report.
0.34
0.33
Schedule                            Millions
0.32
Construction completed in February 2010.
0.31
Dollars in 0.3
Budget
0.29
All remaining work completed within budget.
Authorized  Forecasted Costs Incurred
Change Order
None this quarter                                    Construction Costs
No Major Construction
Risks                               Contracts
None
Budget Transfers                        Photo
None




SEAPORT

70  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Street Vacations T5,18,105
Status Snapshot
Project: Expense     Street vacation related real estate     On Schedule
104362, 104364, 104366 negotiations and agreements related to  On Budget
Budget: $1,500,000   T5, T18, and T105.            No Change Orders
Total Change Orders Amount: $0
Phase: Permitting
Start: June 2010                                 Budget/Costs Incurred
Completion: Feb 2012
2
1.5
Significant Developments                     Millions
1
Commission approved new budget on June 1, 2010. No significant
developments since June 1, 2010.                         Dollars in 0.5
0
Schedule
Authorized  Forecasted Costs Incurred
Not applicable
Budget                            Construction Costs
Not applicable                                     None
Change Order                         Photo
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable



SEAPORT

Port of Seattle 2Q 2010 Report  71

SECOND QUARTER REPORT, 2010
Water/Sewer Meter Upgrade
Project:   Expense      Upgrade existing water and sewer   Status Snapshot
Multiple work projects     meter to meet current Seattle      On Schedule
Budget: $373,000 in total  Public Utilities standards       On Budget
Phase: Planning                          0 Change Orders
Start: 09/13/09                                   Total Change Orders Amount:
$0
Completion: 12/23/2010
Budget/Costs Incurred
Significant Developments
0.4
Project priority order established. Advertising the Bid Package
resulted in no responsive bids, a revised internal procurement         0.3
strategy of requesting quotes was developed to request quotes. Six     Millions
0.2
firms submitted price sheets and four firms will be used to fill parts
needs.                                        Dollars in 0.1
Schedule                             0
Authorized  Forecasted Costs Incurred
Project is on schedule.
Budget
Construction Costs
Of the $373,000, approximately $123,000 is tenant reimbursable.    None at this time
Change Order                         Photo
None
Risks
POS and tenants will pay higher commercial sewer rates on meters
without upgraded technology.
Budget Transfers
None


SEAPORT

72  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
SBM Renewal and Replacement
Project:   C001706,      Redevelopment Shilshole Bay     Status Snapshot Prior Report
C001769, C001716      Marina docks, landside facilities,   On Schedule
Budget: $80,000,000     infrastructure and buildings.      On Budget
Phase: Construction                        149 Change Orders
Start: 1997                                     Total Change Orders Amount:
$6,299,064
Completion: 4/30/2010
Budget/Costs Incurred
Significant Developments
80.5
Construction of interim pad site flatwork and landscaping completed      80
in central marina area by PCS and Marine Maintenance crews.       Millions 79.5
79
78.5
Schedule
Dollars in   78
77.5
Interim Pad Site improvements and landscaping work completed.       77
Site is open for public access May 25, 2010.                       Authorized Forecasted  Cost
Incurred
Budget
No change this quarter.                                Construction Costs
60
Change Order
50
None this quarter                                       Millions 40
30
Risks                                 20
Dollars in  10
None identified this quarter.
0
Initial     Change     Spent
Orders
Budget Transfers
None
Location
Shilshole Bay Marina
Photo




Port of Seattle 2Q 2010 Report  73
REAL ESTATE

SECOND QUARTER REPORT, 2010
T 102 HVAC Renewal/Replacement
Project:   C800070      Replace HVAC System at all four   Status Snapshot Prior Report
Budget: $1,300,000      buildings at the Harbor Marina    Delayed Schedule 4Q 08
Phase: Construction     Conference Center          Forecast Overrun
Start: 10/2/2005                                  No Change Orders
Completion: 12/1/2008                        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Estimated costs have increased, putting the final estimated project
1.35
costs over budget by approximately $125,000.
1.3
Schedule                            1.25 Millions
Construction has been delayed by a few months and should be       1.2
completed in late summer, early fall of 2010.
1.15  Dollars in 
1.1
Budget
Authorized  Forecasted Costs Incurred
Project is over budget by $125,000 due to changes to the project
plan required by City of Seattle Department of Planning and
Development, HVAC design modifications, code changes, and      Construction Costs
increased costs of equipment, project management, procurement,
labor and contracting.                                     0.4
Change Order                           0.3
None                                   0.2
Millions
Risks                                Dollars in  0.1
Anchor tenant may not allow contractor to work in their space until        0
August 2011. If this occurs, the other 6 units would be installed in          Initial Change Orders Spent
2010 and the last unit would be installed next year.
Budget Transfers
None

REAL ESTATE

74  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
C15 Sewer Line Upgrades
Project:   C800125      Replace the failing sewer/drain     Status Snapshot Prior Report
Budget: $600,000       lines under the Fisherman's      Delayed Schedule 3Q 09
Phase: Construction     Terminal C-15 West Building     On Budget
Start: 4/1/2008                                   3 Change Orders
Completion: 3/31/2009                        Total Change Orders Amount:
$99,000
Significant Developments                    Budget/Costs Incurred
Project is complete. This will be the last report.
0.61
0.6
Schedule
0.59
No change this quarter                                 Millions
0.58
0.57
Budget
0.56  Dollars in 
No change this quarter
0.55
Authorized  Forecasted Costs Incurred
Change Order
None this quarter
Construction Costs
Risks                               None
None
Photo
Budget Transfers
None





REAL ESTATE
Port of Seattle 2Q 2010 Report  75

SECOND QUARTER REPORT, 2010
T-86 Grain Facility Modernization (Phase-1)
Project:   C800133      Modernize and replace aging grain   Status Snapshot Prior Report
Budget: $902,000       facility equipment/controls for $5M  On Schedule
Phase: Construction     by 12/31/2011 to maximize      On Budget
Start: 2/21/2010          operational efficiencies and allow    0 Change Orders
Completion: 11/30/2010   continuation of uninterrupted grain  Total Change Orders Amount:
terminal operations.             0
Budget/Costs Incurred
Significant Developments
Project has been advertised, bid and awarded. Contractor will begin     1
construction installation.                                    0.8
Millions 0.6
Schedule
0.4
None
Dollars in 0.2
Budget                             0
None                                     Authorized Forecasted Costs Incurred
Change Order
Construction Costs
None
None
Risks
Photo
Timely equipment delivery is required by tenant in order to make the
desired installation schedule.
Budget Transfers
None



REAL ESTATE

76  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
FT South Wall Reconstruction Phase IV
Project:   C800136      Completion of Fishermen's       Status Snapshot
Budget: $1,030,000      Terminal South Wall         On Schedule
Phase: Design        Reconstruction. Phase IV is located  On Budget
Start: 6/2009            along parcel currently leased by    No Change Orders
Completion: 6/2011      FVO.                 Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Permitting and engineering design complete pending final review
7
comments from the City of Seattle Building Department and the
6
Army Corps of Engineers.
Millions  5
4
Schedule                             3
No changes this quarter.                                Dollars in  2
1
0
Budget
Authorized  Forecasted Costs Incurred
No change this quarter.
Change Order                         Construction Costs
None this quarter                                    None at this time
Risks                               Photo
None this quarter
Budget Transfers
None



REAL ESTATE


Port of Seattle 2Q 2010 Report  77

SECOND QUARTER REPORT, 2010
MIC Central Seawall Replacement
Project:   C800175      Replacement of steel sheet pile    Status Snapshot
Budget: $410,000       seawall between West Pier and    On Schedule
Phase: Design        Central Pier at Maritime Industrial   On Budget
Start: 9/2008            Center.                    No Change Orders
Completion: 6/2011                          Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Permitting and design completed pending receipt of final review
2.5
comments from the City of Seattle Building Department and the
Army Corps of Engineers.                               2
Millions 1.5
Schedule
1
No changes this quarter.                                Dollars in 0.5
0
Budget
Authorized  Forecasted Costs Incurred
No change this quarter.
Change Order                         Construction Costs
None                                 None at this time
Risks                               Photo
None
Budget Transfers
None



REAL ESTATE


78  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
T-91 Watermain Replacement
Project:   C800298      Replace water main in the vicinity   Status Snapshot Prior Report
Budget: $700,000       of Magnolia Bridge and City      On Schedule
Phase: Design        Ice/Trident including various     On Budget
Start: 9/20/2009          buildings at T91              0 Change Orders
Completion: 12/30/2011                       Total Change Orders Amount:
0
Significant Developments                    Budget/Costs Incurred
Design is in progress. Ductile Iron Pipe will be used throughout the
5
project.
4
Schedule                            Millions 3
Dollars in 
On schedule                                     2
1
Budget
0
On budget
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
None
Risks
Contaminated material may be encountered throughout the        Photo
excavation process.
Budget Transfers
None



SEAPORT


Port of Seattle 2Q 2010 Report  79

SECOND QUARTER REPORT, 2010
FT NW Dock East Fender System Replacement
Project:   C800386      Replace existing timber fender     Status Snapshot
Budget: $580,000       system for the east section of the   On Schedule
Phase: Design        NW Dock at Fishermen's Terminal  On Budget
Start: January 2010       including all new steel piling and    No Change Orders
Completion: April 2011   associated fender system.       Total Change Orders Amount:
0
Significant Developments                    Budget/Costs Incurred
A hybrid fender system design was selected, which is based on
6
using new steel piles and timber above-water components; some
5
existing timber components may be re-used. 60% design level
4
drawings were completed and are in review. The permit application    Millions
3
was submitted.
2
Dollars in 
Schedule                             1
0
No change. Design will be completed during August 2010. Request
Authorized  Forecasted Costs Incurred
to Commission for construction funding will be in late August 2010.
Construction scheduled for approximately January through April
2011.
Construction Costs
Budget                            None
Total preliminary project budget range, including construction, is
$3,900,000 to $4,800,000. The final project budget will be revised
based on an updated construction cost estimate.
Change Order
There is no current construction contract.
Risks
In-water pile replacement work must be completed by April 15, 2011
to comply with anticipated permit requirements.
Budget Transfers
None

REAL ESTATE

80  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Flight Information System (FIMS) II
Project: C101117        Procure, develop, and implement a  Status Snapshot
Budget: $5,400,000      FIMS system that includes       On Schedule
Phase:Design         replacement monitors, an airport   On Budget
Start: 5/4/2010           resource management system, and  0 Change Orders
Completion: 12/30/2012    a flexible digital signage system    Total Change Orders Amount:
capable of displaying flight         $0
information, visual paging, and
Significant           notifications.
Developments                        Budget/Costs Incurred
Evaluating vendor proposals for a replacement resource
6
management system and for the monitor casework design. Planning
and architecture design in progress.                           5
Millions  4
Schedule                             3
2
On Schedule                                  Dollars in  1
Budget                             0
Authorized  Forecasted Costs Incurred
On Budget
Change Order
Construction Costs
None                                 Not applicable in this phase
Risks
Aircraft activity feeds will be requested from every airline in the new
industry standard format. There is a risk that not all airlines will
initially agree to this request causing a delay schedule delay.
Budget Transfers
None



CORPORATE

Port of Seattle 2Q 2010 Report  81

SECOND QUARTER REPORT, 2010
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule 3Q 09
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, add service desk module   0 Change Orders
Completion: 9/30/2010    and wireless handheld capabilities.  Total Change Orders Amount:
$0
Significant Developments
Service Management software deployed for ICT Service Desk in     Budget/Costs Incurred
December 2008. Legacy Ticket system decommissioned.
The design and development for Phase 2, upgrade and consolidation    4
of Marine Maintenance and Aviation Maintenance Maximo systems
3
is scheduled for completion in mid-September 2010.              Millions
2
Schedule
Dollars in   1
Prior Report - Delay of 9 months due to resource constraints and a
successful re-planning effort to mitigate potential vendor cost          0
overruns.                                             Authorized Forecasted Costs Incurred
Budget
On Budget                                  Construction Costs
Not Applicable
Change Order
None
Risks
While the majority of the project will be complete with the Upgrade
and Consolidation in September, some work will remain to complete
additional interfaces. There are potential resource constraints that
may delay the implementation of these interfaces.
Budget Transfers
None

CORPORATE

82  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Ground Transportation Management System
Project: C800227        Procure and implement a Ground   Status Snapshot
Budget: $840,000       Transportation Management      On Schedule
Phase: Planning        System for tracking and billing     On Budget
Start: 4/27/2010          ground transportation operators at   0 Change Orders
Completion: 6/30/2011    the airport.               Total Change Orders Amount:
$0
Significant Developments
Evaluating RFP proposals                            Budget/Costs Incurred
Schedule                             1
On Schedule                                   0.8
Millions 0.6
Budget
0.4
On Budget                                   Dollars in 0.2
Change Order                           0
Authorized  Forecasted Costs Incurred
None
Risks
Construction Costs
No significant risks.                                      Not Applicable
Budget Transfers
None




CORPORATE

Port of Seattle 2Q 2010 Report  83

SECOND QUARTER REPORT, 2010
Port of Seattle Internet Redesign
Project: C800319        Create a new Internet web site, and  Status Snapshot
Budget: $500,000       underlying infrastructure, with     Delayed Schedule
Phase:Planning        dynamic content and interactive    On Budget
Start: 1/6/2009           communication tools such as blogs,  0 Change Orders
Completion: 6/30/2011    video, podcasts, discussion forums  Total Change Orders Amount:
and interactive maps.           $0
Significant Developments                    Budget/Costs Incurred
In 2nd quarter 2010 a RFP was advertised for an implementation
0.6
vendor to assist with the design and development of the new Port of
Seattle website. Unfortunately, there were limited responses and the    0.5
Central Procurement Office is in the process of re-advertising the       0.4
procurement request.                                 0.3
in Millions
0.2
Schedule                            Dollars 0.1
The delay caused by the need to re-advertise the RFP for an          0
implementation vendor will delay the estimated completion to 2nd          Authorized Forecasted Costs Incurred
quarter 2011.
Budget                            Construction Costs
Not Applicable
On Budget
Change Order
None
Risks
Based on the limited response to the first RFP advertisement, there
is a continued risk that we will not receive a proposal matching our
requirements.
Budget Transfers
None

CORPORATE

84  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
External Sharepoint
Project: C800320        Implement External Microsoft     Status Snapshot Prior Report
Budget: $500,000       Sharepoint Services to support    Delayed Schedule     3Q 09
Phase:Design         application consolidation, customer  On Budget
Start: 1/6/2009           collaboration, and system        0 Change Orders
Completion: On-Hold     integration opportunities.       Total Change Orders Amount:
$0
Significant Developments
Project was put on hold by ICT Management to evaluate potential    Budget/Costs Incurred
security issues identified during architecture development. An interim      Dollars [Thousands)
600
solution utilizing a hosted sharepoint environment will be deployed to
500
meet the timeline for the Port Internet Redesign project.
400
Schedule                             300
On Hold                                      200
100
Budget                             0
Authorized    Forecasted   Costs incurred
On Budget
Change Order
Construction Costs
None
Not Applicable
Risks
New Technology
Budget Transfers
None



CORPORATE

Port of Seattle 2Q 2010 Report  85

SECOND QUARTER REPORT, 2010
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot Prior Report
Budget: $1,525,000      costing systems with a common    Delayed Schedule     4Q 09
Phase:Planning        enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: On-Hold                         Total Change Orders Amount:
$0
Significant Developments
Vendor did not deliver software per original contract and project was   Budget/Costs Incurred
put on-hold to evaluate alternatives. At this time a decision has been
made to continue with the Skire implementation and negotiations are     2
in progress to update agreement and finalize implementation plan.
1.5
Schedule                             Millions 1
On-hold
Dollars in 0.5
Budget                             0
None                                     Authorized Forecasted Costs Incurred
Change Order
Construction Costs
None                                 Not Applicable
Risks
See significant developments
Budget Transfers
None



CORPORATE

86  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot
Budget: $800,000       increase functionality, and lower   Delayed Schedule
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 5/30/2011    records and document        Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
Incorporating upgrade to Sharepoint 2010 because of significant
improvements in Records Management features.
1
Schedule                             0.8
Sharepoint 2010 implementation is dependent on the completion of     Millions 0.6
several infrastructure projects currently in progress. This will delay      0.4
the implementation of Sharepoint Records Center and full build out     Dollars in 0.2
of department sites until Spring 2011.
0
Authorized  Forecasted Costs Incurred
Budget
On Budget
Construction Costs
Change Order                         Not Applicable
None
Risks
Scope of Sharepoint 2010 upgrade may require additional funding to
complete migration activities.
Budget Transfers
None



CORPORATE
Port of Seattle 2Q 2010 Report  87

SECOND QUARTER REPORT, 2010
Business Continuity
Project: C800326        Acquire new backup and storage   Status Snapshot
Budget: $1,760,000      software and hardware that will    Delayed Schedule
Phase:Implementation    facilitate business continuity in the  On Budget
Start: 6/23/2009          event of a disaster            0 Change Orders
Completion: 4/30/2011                         Total Change Orders Amount:
$0
Significant Developments
Procurement and installation of backup system in Fisher Plaza Data   Budget/Costs Incurred
Center complete. Installation of the High Capacity Realtime Storage
for the Airport Data Center in progress.                         2
1.5
Schedule
Insufficient power in the data center required unplanned              1
in Millions
infrastructure upgrades for the new High Capacity Realtime Storage    Dollars 0.5
Device. The new device is estimated to be online in October 2010
and final project completion is estimated in April 2011, a 6 month        0
delay from the original schedule.                                Authorized  Forecasted Costs Incurred
Budget
Construction Costs
On Budget
Not Applicable
Change Order
None
Risks
No significant risks.
Budget Transfers
None


CORPORATE

88  Port of Seattle 2Q 2010 Report

SECOND QUARTER REPORT, 2010
Time Clock System
Project:C800387        Procure and implement a Time    Status Snapshot
Budget:$840,000       Clock System to accurately capture  On Schedule
Phase:Planning        and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion:7/30/2012     Aviation Security and Airport      Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
Negotiating contract with vendor selected through an RFP process.
0.4
Schedule                             0.3
On Schedule
Millions 0.2
Budget                             Dollars in 0.1
On Budget
0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
Cost of selected time clock system is greater than business case
estimate. There is a risk that contingency is not sufficient to cover
additional cost.
Budget Transfers
None


CORPORATE


Port of Seattle 2Q 2010 Report  89

SECOND QUARTER REPORT, 2010
Port Roster
Project: C800397      Develop and implement a single Port   Status Snapshot
Budget: $450,000     Roster & Bid System that replaces the  On Schedule
Phase: Design       functionality of three rosters, supports   On Budget
Start: 1/26/2010        new Central Procurement Office      0 Change Orders
Completion: 2/28/2011  processes , and simplifies the process  Total Change Orders Amount:
for Port vendors.                  $0

Significant Developments                    Budget/Costs Incurred
In Development                                  0.5
0.4
Schedule                            Millions 0.3
On Schedule                                  0.2
Budget                             Dollars in 0.1
0
On Budget                                      Authorized Forecasted Costs Incurred
Change Order
Construction Costs
None
Not Applicable
Risks
No significant risks
Budget Transfers
None




CORPORATE

90  Port of Seattle 2Q 2010 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.