7b report

Item Number: 7b_Report
Meeting Date: June 8, 2010


Commission Staff Brieng
Capital Improvement Projects
First Quarter Report 2010

This page intentionally left blank









ii  Port of Seattle 1Q 2010 Report

Port of Seattle
Capital Improvement Project ReporW
)LUVW Quarter 20 
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the statue of the Port's capital projects.
Background
During 2009 the Port plans to invest over $600 million to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 11 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
maritime transportation facilities and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 4Q 2009 Report  1Port of Seattle 1Q 2010 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................5 ........... 
C100266 et al .......Rental Car Facility ............................................... 6-7.......... ...............
C102030 ...............Stormwater Management Program .......................8 ........... .............................................................................. 
C102038 ...............Apron Pavement Rehabilitation 3 ........................9 ...........
C102163................Main Terminal Baggage Screening ................... 10-11 ........ ...................................
C102584 ...............Garage Floor Count ..............................................12 .......... ...............
C102744................2nd Floor Tenant Improvements ...........................13 .......... ...............
C800019 ...............Loading Bridge Utilities .........................................14 .......... ...............
C800020 ...............Trash Handling & Recycling System ....................15 ..........
C800034 ...............North Expressway Relocation ..............................16 .......... ...............
C800036 ...............Parking Garage 4th Floor Improvements .............17 ..........
C800042 ...............Aircraft Rescue Fire Fighting Station Upgrade ....18 .......... ...............
C800061 ...............Main Terminal South Sub Low Volt ......................19 .......... ...............
C800071 ...............Consolidated Warehouse .....................................20 .......... ...............
C800095 ...............Alaska Air 2 Step Ticket Counter..........................21 .......... ...............
C800105 ...............Airport Owned Gate Infrastructure .......................22 .......... ...............
C800107 ...............C4 UPS System Improvements ............................23 .......... ...............
C800109 ...............Garage Escalator & "A" Elevator Upgrade ...........24 ..........
C800112................Runway 16C/34C Panel/Joint Sealant .................25 ..........
C800144 ...............Security CCTV System Improvements.................26 .......... ...............
C800146 ...............RMU/Kiosk Concession Program ........................27 .......... ...............
C800147 ...............Concessions Renewal/Replacement ...................28 .......... ...............
C800148 ...............GML Arrivals Hall Concessions ...........................29 .......... ...............
C800157 ...............Concessions Flooring ...........................................30 .......... ...............
C800167 ...............Runway 16L/34R Reconstruction.........................31 ..........
C800170 ...............Connect C1 BHS to C88 BHS ..............................32 ..........
C800237 ...............Renew/Replace 42 Escalators .............................33 .......... ...............
C800238 ...............Central Plant Pre-Conditioned Air ........................34 .......... ...............
C800239 ...............Fire Piping .............................................................35 .......... .............................. ......................................
C800249 ...............2nd Floor HVAC ....................................................36 .......... ...............
C800254 ...............Aircraft RON Parking Post Ofce Site..................37 ..........
C800274 ...............8th Floor Weather Proong ..................................38 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......39 ..........
C800286 ...............South AOA Fence Replacement ..........................40 ..........
C800336 ...............South Satelite Delta Sky Club Extension .............41 ..........



2  Port of Seattle 1Q 2010 Report

Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C001338 ...............Fire Vehicles .........................................................42 ..........
C102396 ...............Fire Vehicles .........................................................43 ..........
C200007...............Highline School Noise Insulation ..........................44 .......... ...............
C200015 ...............3rd Runway Residential Acquisition .....................45 .........................
C200037 ...............FAR Part 150 Mobile Home Park Acquisition ......46 .......... ...............
C200042 ...............Highline Community College Noise Insulation .....47 .......... ...............
C200048 ...............Home Insulation Retrot .......................................48 .......... ...............
C200093 ...............Single Family Home Sound Insulation .................49 ..........
C800046 ...............Street Vacations  Des Moines Creek 1 ..............50 .......... ...............
C800150 ...............Burien Commercial Property Acquisition .............51 ..........
C800154 ...............Tenant Reimbursement ........................................52 ..........
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000579 ...............Alaskan Way St Vacation and Public Access ......53 .......... ...............
C102451 ................T-115 Dock Reconstruction...................................54 .......... ............... ....................
C800085 ...............T-30/T-91 Program ............................................55-56 ....... ............... ....................
C800114................P-66 Bag. Corridor & Pass. Screening ................57 .......... ...............
C800121 ...............T-18 S. Fendering .................................................58 .......... ...............
C800123 ...............T-5 Crane Spreader Replacement .......................59 .......... ...............
C800182 ...............NH Island Mooring Dolphins (4) ...........................60 ..........
C800264 ...............T-10 Interim Redevelopment.................................61 .......... ...............
C800273 ...............T-91 Mobile Gangways .........................................62 ..........
C800343 ...............T-91 RD Pavement Entry & Guard Shack ............63 .......... ..............................
C800347 ...............T-46 Upgrade Yard Lighting .................................64 ..........
WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................65 .......... ............... ....................
E103705 et al ........T-46 ZPMC Gearboxes ........................................66 ..........
E103835 et al ........T-5/T-18 Maintenance Dredging ...........................67 .......... ...................................
E104011 et al ........T-25/P-28/T-46 Barge Layberth Improvements ...68 ..........
Multiple Expense ..Water/Sewer Meter Upgrade ................................69 ..........



Port of Seattle 1Q 2010 Report  3

Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C001706 et al........SBM Renewal and Replacement .........................70 .......... ...............
C800070 ...............T-102 HVAC Renewal/Replacement ....................71 .......... ...............
C800125 ...............C15 Sewer Line Upgrades ....................................72 .......... .................................. 
C800133 .............. T-86 Grain Facility Modernization (Phase I) ........73 ..........
C800136 ...............FT South Wall Reconstruction Phase VI ..............74 ..........
C800175 ...............MIC Central SeaWall Replacement ......................75 ..........
C800298 ...............T-91 Watermain Replacement ..............................76 ..........
C800386 ...............FT NW Dock E. Fender System Replacement.....77 ..........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800003...............Maximo Enterprise Implementation......................78 ..........
C800066 ...............Parking System Consolidation .............................79 .......... ...............
C800119................Marine Domain Awareness ..................................80 .......... ...............
C800319............... Port of Seattle Internet Redesign.........................81 .......... .............................. 
C800320 ...............External Sharepoint ..............................................82 .......... .............................. 
C800321 ...............Enterprise Project Cost Management ..................83 .......... ...............
C800322 ...............Records and Document Management .................84 .......... ..............................
C800326 ...............Business Continuity ..............................................85 ..........
C800397 ...............Port Roster ............................................................86 ..........
Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
Previously Reported
No Diamond  On Budget or On Schedule



4  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
3rd Runway Program
Status Snapshot
Project: C000683,       The 3rd Runway Program will
C001138, C001175,      construct a new 8,500 foot long    On Schedule
C001331, C001751,      dependent runway, connecting    On Budget
4 Change Orders
C001760, C100172      taxiways, and related infrastructure.
When complete the 3rd Runway    Total Change Orders Amount:
Budget: $931,940,984
will significantly reduce weather-     $348,044.79
Phase: Construction    related delays.
Start: 05/27/1997                                Budget/Costs Incurred
Completion: 12/31/2011
1200
1000
Significant Developments
Millions800
The Pond M portion of the 2010 stormwater improvements has been
600
delayed until the 2011 construction season. Soil investigations
400
revealed the presence of organic and loose soils necessitating        Dollars in 200
additional design and analysis. Site preparation and utility work will
0
continue as planned.
Authorized  Forecasted  Costs Incurred
Schedule
The 2010 construction project was advertised in the first quarter with  Construction Costs
construction of the 2010 work to be completed in the fall.
5
Budget                              4
Reduced budget by $155,540,000 to the current budget of          Millions  3
$931,940,984. Two work projects were changed from an Asset to       2
an Expense totaling $25,942,000. To date, $615,388,000 of           1
construction has been completed on the overall program.
Dollars in   0
Initial   Change    Spent
Change Order                                Orders
Zero change orders have been executed during this period.
Photo
Risks
No risks were identified at this time.
Budget Transfers
To Expense                   $25,942,000

AIRPORT
Port of Seattle 1Q 2010 Report  5

FIRST QUARTER REPORT, 2010
Rental Car Facility
Project:   C100266,     The program will construct a       Status Snapshot Prior Report
C102167, C800032     consolidated rental car facility (RCF)  Delayed Schedule 4Q 08
Budget: $419,306,000   for all rental car companies at the    On Budget
Phase: Construction    airport, a bus maintenance facility    264 Change Orders
Start: 02/24/1998        (BMF), and mitigation with the off-site  Total Change Orders Amount:
roadway improvements (ORI), plus    $14,832,394
Completion: Spring 2012
purchase a fleet of buses.
Budget/Costs Incurred
Significant Developments
500
Construction is progressing well on every aspect of the RCF. The
concrete structure continues in four sections at various levels. One     400
section is complete to the fifth floor and work on the Customer        300
Service Building began. All but one retaining wall is complete.          Millions
200
Construction continues on all four quick turnaround areas (QTA's).
Dollars in
All utilities within the building footprint are complete. Averaging 230     100
workers daily, increasing to 260 workers for concrete work. Only one     0
conforming design change and seven suspension claims remain         Authorized Forecasted Costs Incurred
open. Completed the 100% design for the BMF and 90% for the
Compressed Natural Gas (CNG) facility, and completed the 100%
design for ORI and advertised for construction bids on March 10th.    Construction Costs
Schedule                             250
200
The program schedule remains on the revised track to be complete
spring 2012 as controlled by the BMF; delayed due to funding         Millions 150
addition of CNG Fuel Facility. ORI delayed slightly by late outside       100
agencies reviews, but completion remains on schedule.            Dollars in  50
0
Budget                                Initial Change Orders Spent
Customer Finance Charge (CFC) revenues continue to run lower
than planned due to the economy. The program forecast is within the
approved budget and authorization.
Photo
Change Order
91 change orders were issued this quarter in the amount of
$3,247,117.


6  Port of Seattle 1Q 2010 Report

Risks
For RCF, potential risks include timely resolution of larger suspension claims, stacking of trades,
quality issues, control of onsite stormwater and site congestion. Turner Construction recently
changed key staff positions; this will be managed carefully. For ORI, delay in review by other
agencies has impacted design completion and compressed the construction schedule. For BMF, sole
source and specification revisions will further delay schedule. Attempting to close the schedule "gap"
between completion of RCF and BMF projects for earlier opening.
Budget Transfers
None this quarter
Cost Growth of Construction
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32 million suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative change order percentage through
this quarter is 19.4%. Primary reason for changes is the removal of contaminated soils and
associated impacts. This work and the final contract reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  Cumulative change order percentage
through this quarter is 170.5%. Primary reasons for changes are for additional contractor
management, estimating, scheduling and bidding effort for cost estimate reconciliation,
constructability reviews and value engineering beyond the extent of the original scope to validate
project costs and support the rental car companies and the Port on final approval of the project. This
work and the final contract reconciliation is complete.





AIRPORT
Port of Seattle 1Q 2010 Report  7

FIRST QUARTER REPORT, 2010
Stormwater Management Program
Project:   C102030,    The program achieves permit       Status Snapshot
C800026, C800030     requirements and makes the Airport a  On Schedule
Budget: $58,447,234   leader in stormwater management by  Under Budget
Phase: Construction   construction of flow control, water    No Change Orders
Start: 06/11/2002       quality treatment and low stream flow   Total Change Orders Amount:
mitigation facilities.                  N/A
Completion: 12/31/2011
Significant Developments                    Budget/Costs Incurred
The stormwater program (C102030) is in its adaptive management
100
phase under which additional or upgraded water quality treatment
facilities are being implemented based on the stricter effluent          80
standards of the new stormwater National Pollutant Discharge        Millions 60
Elimination System (NPDES) permit. Water quality treatment
40
upgrades at three project sites are in the 90% design phase.         Dollars in  20
Schedule                             0
Authorized  Forecasted Costs Incurred
The new stormwater NPDES permit became effective April 1, 2009.
Adaptive management projects will be implemented during the 2010
to 2011 period, and possibly through 2014 depending on water
Construction Costs
quality monitoring results. The stormwater (C800026) and sanitary
No active construction
sewer (C800030) pipeliner projects, which are not part of adaptive
contract at this time.
management, have been deferred until later in 2010 or 2011.
Budget
The budget has been significantly reduced several times since
program inception in 2002 due to successful system optimization
measures. A $4,000,000 budget reduction was made in C102030 in
the first quarter, and an additional approximate $6,100,000 reduction
will be made in the second quarter.
Change Order
None.
Risks
Additional adaptive management facilities or upgrades may be
required beyond those currently being planned, depending upon
future water quality monitoring results.
Budget Transfers
To Savings                     $4,000,000
AIRPORT
8  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Apron Pavement Rehabilitation - 3
Status Snapshot
Project: C102038        Multiyear airfield pavement
Budget: $16,100,000     replacement program. This is a    On Schedule
On Budget
Phase: Construction    continuation of a program for the
removal and replacement of aged   No Change Orders
Start: 01/14/2003
airfield apron pavement started in    Total Change Orders Amount:
Completion: 12/31/2010
1994.                    N/A
Significant Developments                   Budget/Costs Incurred
Approximately 70 concrete panels will be replaced in the 2010
17
Apron Replacement Contract. Construction bids will be opened in
the second quarter of 2010.                               16
Millions 15
Schedule
14
The 2010 project is scheduled to start construction in Mid-May and     Dollars in  13
to be completed in July.
12
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                        Not applicable
None
Photo
Risks
No risks have been identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 1Q 2010 Report  9

FIRST QUARTER REPORT, 2010
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $230,538,762   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget   4Q 09
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
Significant Developments
235
The C-1 baggage handling/screening system has been placed into     230
revenue service for the Alaska Air Group. The only remaining work is    Millions 225
to relocate some fire sprinklers and to repair/replace fire proofing       220
material displaced from the main structural elements of the bagwell.     215
Dollars in 210
Schedule                             205
The project was delayed approximately two years from the original         Authorized  Forecasted Costs Incurred
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope
changes. Turner Construction demobilized on May 31st 2009. The   Construction Costs
GCCM construction contract with Turner Construction has been
200
closed. The remaining fire sprinkler and fire proofing work is
scheduled for completion by year end.                         150
Millions  100
Budget
50
The project forecast is within the approved budget and authorization.    Dollars in 
The project is anticipating a return of $8,954,000 of budget.             0
Initial  Change Orders  Spent
Change Order
665 Change Orders have been issued on this project.
Risks                               Photo
Risks include recent TSA changes in certification requirements and
whether they will be imposed retroactively.
Budget Transfers
None this quarter


10  Port of Seattle 1Q 2010 Report

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated as they were unable to meet the
project schedule requirements. The remaining work was rebid in the fall of 2006. Alaska Airlines
asked that we include the BHS work within the 2-step ticket counter project; which increased the
amount of BHS work in the bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.












AIRPORT

Port of Seattle 1Q 2010 Report  11

FIRST QUARTER REPORT, 2010
Garage Floor Count
Project:   C102584      This project is part of the Customer  Status Snapshot Prior Report
Budget: $4,087,371      Service initiative. The floor count   Delayed Schedule 3Q 09
Phase: Close Out      system will display information to   On Budget
Start: 08/06/2007         assist parking customers in finding   No Change Orders
Completion: 11/30/2009   parking spaces, especially at times  Total Change Orders Amount:
when the garage is near capacity.   N/A
Significant Developments                    Budget/Costs Incurred
The system is operational and in production. This will be the last
4.1
quarterly report for this project.
4.05
Schedule                            Millions 4
Project has been completed.                             3.95
Dollars in 3.9
Budget
3.85
The project forecast is within the approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.                                Photo
Budget Transfers
None this quarter




AIRPORT
12  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
2nd Floor Tenant Improvements
Project:   C102744      This project constructs a shell     Status Snapshot
Budget: $377,864       space for new tenant offices and   Delayed Schedule
Phase: Construction     provides utility pathways to the    On Budget
Start: 08/22/2006         shell space and makes code       No Change Orders
Completion: (See       improvements to adjacent lobby    Total Change Orders Amount:
and corridors.                 N/A
C800249)
Significant Developments                    Budget/Costs Incurred
Project construction activities are substantially complete except for
0.6
one project element, which is awaiting completion of tenant office
0.5
build out and relocation of current tenant offices. The remaining
0.4
portion of the work will be completed after the 2nd Floor HVAC
0.3
Upgrades project (C800249). The tenant has initiated the project to    in Millions
0.2
build out the office space.                                  Dollars 0.1
0
Schedule
Authorized  Forecasted Costs Incurred
The remaining work is now scheduled for late 2010.
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None.
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 1Q 2010 Report  13

FIRST QUARTER REPORT, 2010
Loading Bridge Utilities
Project:   C800019   This project will upgrade all Port-       Status Snapshot Prior Report
Budget: $9,385,000   owned loading bridges to the same     Delayed Schedule    2Q 09
Phase: Design     standards, including 400Hz power and   On Budget
potable water. It will reduce air
Start: 06/28/2007                                 No Change Orders
emissions, improve energy efficiency
Completion: TBD                           Total Change Orders Amount:
and save money for the airlines.        N/A
Budget/Costs Incurred
Significant Developments
The 100% design package was completed and submitted to the       10
Airport Building Department for review, and a permit was granted.       8
The project was then suspended.                         Millions 6
The project has been re-initiated and the design will be reviewed for      4
compliance with latest codes and changes to site conditions and       Dollars in  2
reissued as a 90% design review package.                     0
Authorized  Forecasted Costs Incurred
Schedule
The current schedule will be updated when the new contract is
finalized.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None.
Risks
The project budget could increase, due to the design being placed
on hold and restarting at 90% and potential increases in the
construction market.
Budget Transfers
None this quarter.


AIRPORT
14  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Trash Handling & Recycling System
Project:   C800020    To improve trash handling and       Status Snapshot
Budget: $1,612,000    recycling operations and to meet     On Schedule
Phase: Close Out    future trash volume demands;      On Budget
Start: 04/22/2008      decentralize tenant trash disposal and   9 Change Orders
Completion: 02/28/2010 recycling; and centralize airline trash   Total Change Orders Amount:
disposal and recycling.             $28,468
Significant Developments                    Budget/Costs Incurred
Project is now complete except for close out. All major airlines are
2
utilizing the six new sites. Each site has one trash and one recycling
compactor and all compactors are remotely monitored and emptied     1.5
when they are nearing 100% full.                           Millions
1
Schedule                            Dollars in 0.5
Project close out is under way.
0
Authorized  Forecasted Costs Incurred
Budget
The budget forecast indicates a savings will be realized at project
closeout.                                          Construction Costs
Change Order                           0.4
Southwest Airlines requested portable personal platforms between
0.3
their vehicle and the compactors at site Gate B4 before they would     Millions
commit to using the compactor program. This request was            0.2
completed in February 2010.                              0.1
Dollars in 
0
Risks
Initial  Change Orders  Spent
None identified at this time.
Budget Transfers                        Photo
None this quarter.
Cost of Construction Growth
Three electrical changes during construction affected the project's
costs. At Concourse D, the home run conduit proposed for re-use
did not exist in the field, so the project installed new conduit; the
Ethernet converters specified for the fiber conversion were changed
to analog to accommodate the Port's existing communication
system; and fusible disconnect switches were added at all twelve
trash compactors for safety and maintenance reasons.
AIRPORT
Port of Seattle 1Q 2010 Report  15

FIRST QUARTER REPORT, 2010
North Expressway Relocation
Project:   C800034
The project is a collaboration      Status Snapshot
Budget: $110,487,700    between the Port and Sound     Delayed Schedule
Phase: Construction     Transit. It will reconstruct the North  On Budget
Start: 07/27/2004         Airport Expressway and bring light   187 Change Orders
Completion: 03/31/2012   rail to the Airport.           Total Change Orders Amount:
$9,300,934
Significant Developments
Budget/Costs Incurred
The work in the main contract includes reconstruction of the North
Airport Expressway and included light rail transit components. This     115
work is complete, with only plant establishment remaining. The       110
intelligent transportation management system has been implemented   Millions105
and only an upgrade to resolve a server issue remains.             100
Advertisement occurred and award is pending for the final paving,
95
landscaping and reclamation contract.                        Dollars in  90
85
Schedule
Authorized  Forecasted Costs Incurred
The main contract received substantial completion in August 2008
and only plant establishment remains. A contract for final paving,
landscaping, and reclamation will be awarded in the second quarter,
and is planned to be complete in early 2011, followed by a first year   Construction Costs
plant establishment period to be complete in early 2012. This is a
delay from the original schedule due to a two month delay in the        150
advertisement process.
Millions  100
Budget
50
The project forecast is within the approved budget and authorization.
Dollars in 
0
Change Order
Initial  Change Orders  Spent
No change orders were issued this quarter.
Risks                               Photo
None identified at this time.
Budget Transfers
None this quarter.

AIRPORT
16  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Parking Garage 4th Floor Improvements
Project:   C800036
The project includes the design and  Status Snapshot
Budget: $8,991,000      construction of a pedestrian bridge  On Schedule
Phase: Construction     and a walkway from Sound      On Budget
Start: 02/14/2006         Transit's Airport Station to the      33 Change Orders
Completion: 12/31/2009   Terminal.               Total Change Orders Amount:
$275,128
Significant Developments
Budget/Costs Incurred
The project is being delivered in two contracts: the pedestrian bridge
between the Airport Station and the Parking Garage, and a walkway     10
on the 4th floor of the garage between the pedestrian bridge and
8
northernmost sky bridge to the main terminal. Both contracts were     Millions 6
substantially complete and opened in conjunction with the Sound
Transit's Airport Station on December 19, 2009.                   4
Dollars in   2
Schedule
0
Punch list work is complete for the walkway and the pedestrian           Authorized Forecasted Costs Incurred
bridge. MUFIDS (Multiple User Flight Information Display System)
will be installed in the second quarter of 2010. CUSS (Common Use
Self Service) units were installed during the first quarter of 2010.     Construction Costs
Budget                              4
The project forecast is within the approved budget and authorization.      3
2
Change Order
Millions
24 change orders were issued for the walkway this quarter in the         1
Dollars in 
amount of $146,206.                                   0
Initial  Change Orders  Spent
Risks
None
Photo
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 1Q 2010 Report  17

FIRST QUARTER REPORT, 2010
Aircraft Rescue & Fire Fighting Station Upgrade
Project:   C800042      Upgrade the Sea-Tac International   Status Snapshot Prior Report
Budget: $4,972,000      Airport Aircraft Rescue & Fire     Delayed Schedule 1Q 09
Phase: Close Out      Fighting (ARFF) station to meet    On Budget
Start: 06/13/2006         current Airport needs and comply    24 Change Orders
Completion: 01/31/2010   with current safety codes.       Total Change Orders Amount:
$148,871
Significant Developments                    Budget/Costs Incurred
The contractor and construction management team could not
5.2
negotiate a satisfactory credit for the waterproofing so that item has
5
been placed back on the punchlist.
Millions 4.8
4.6
Schedule
4.4
The project is substantially complete, but the punchlist will not be       Dollars in 4.2
resolved until Summer 2010.
4
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Five change orders were issued this quarter in the amount of
$20,571.                                          3
Risks                                 2
Contractor and Port costs to perform tower waterproofing may
Millions
1
exceed the amount orginally budgeted for this scope.
Dollars in 
0
Budget Transfers                             Initial Change Orders Spent
To C102066 (Art Pool)                   $28,000



AIRPORT

18  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Main Terminal South Sub Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
No Change Orders
Start: 06/28/2007      equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD    Main Terminal.
NA
Significant Developments
Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
and building codes, the design phase changed from 100% to 90%      2.5
complete. Port staff is in the process of reviewing the Consultant's
2
proposed Service Agreement and Service Directive, and should be
completed in the second quarter of 2010.                      Millions 1.5
1
Schedule                            Dollars in 0.5
The project was reactivated on June 24, 2009 and is in the process      0
of determining the scope of work, schedule and final design budget.
Authorized  Forecasted Costs Incurred
Expect to remobilize the Design Consultant late in the second
quarter of 2010.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None.
Photo
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area of the Main Terminal is a 24/7/365 operation and
sequencing of this work is critical and electrical power has to be
maintained without interruptions.
It is not known when the construction will proceed. There may be an
impact on project costs due to changes in market conditions at that
time.
Budget Transfers
None this quarter.
AIRPORT
Port of Seattle 1Q 2010 Report  19

FIRST QUARTER REPORT, 2010
Consolidated Warehouse
Project:   C800071      This project will construct a 50,000   Status Snapshot Prior Report
Budget: $9,300,000      square foot warehouse for storage  Ahead of Schedule    3Q 09
Phase: Close Out      and inventory management of     On Budget
Start: 06/27/2006         spare parts for the Aviation        30 Change Orders
Completion: 2/15/2010    Maintenance Department.       Total Change Orders Amount:
$790,565
Significant Developments                    Budget/Costs Incurred
Project is complete and in close out, with the building open for use
9.4
and in operation.
9.2
Schedule                            Millions 9
The project had several significant issues to resolve: Bill of Sale,       8.8
Permanent Easement and Right of Entry Agreement for the Highline    Dollars in 8.6
Water District; As- built drawings for the Midway Sewer District; and     8.4
final closeout of the project. Nearly all of these issues have been          Authorized  Forecasted Costs Incurred
resolved.
Budget                            Construction Costs
The project went to Commission for an additional authorization of
$300,000 in February. The project forecast is within the approved        6
budget and authorization.
Millions   4
Change Order
2
Seven change orders were issued this quarter in the amount of        Dollars in 
$68,517.                                          0
Initial  Change Orders  Spent
Risks
None
Photo
Budget Transfers
From C800152 (Non Aeronautical New Projects)   $300,000



20  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Alaska Air 2-Step Ticket Counter
Project:   C800095      This project provides Port of      Status Snapshot Prior Report
Budget: $10,707,000     Seattle support for Alaska Airlines'  Delayed Schedule 1Q 08
Phase: Close Out      2-step ticket counter projects (the   On Budget
Start: 04/11/2006         "Airport of the Future"). The work   No Change Orders
Completion: 02/13/2009   includes: asbestos abatement;    Total Change Orders Amount:
concessions relocations; and      N/A
related building modifications.
Budget/Costs Incurred
Significant Developments                     12
10
The onsite work is complete. The Port is meeting with Alaska
8
Airlines to reconcile the reimbursable amount.                   Millions
6
Schedule                             4
Dollars in   2
The project work is complete.
0
Authorized  Forecasted Costs Incurred
Budget
The project could incur additional costs over the current budget for
Port performed tasks which will be reimbursed by Alaska Airlines.
After reimbursement, the anticipated forecast is within the approved   Construction Costs
budget and authorization.                              Not Applicable
Change Order
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 1Q 2010 Report  21

FIRST QUARTER REPORT, 2010
Airport Owned Gate Infrastructure
Project:   C800105      This project purchases and
Status Snapshot
Budget: $6,000,000      replaces loading bridges at gates
Ahead of Schedule
Phase: Construction     throughout the airport.
On Budget
Start: 07/24/2007                                 No Change Orders
Completion: 3/31/2010                        Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
Installation of the two remaining loading bridges in this phase of the
project is complete.                                       7
6
Schedule                            Millions 5
4
The two remaining loading bridges were installed ahead of schedule.
3
Budget                             Dollars in  2
1
The project forecast is within the approved budget. The current        0
authorization is for $4,337,000. The remaining budget will be             Authorized  Forecasted Costs Incurred
authorized in a following phase to replace additional bridges and
make other gate improvements in the future.
Change Order                         Construction Costs
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

22  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
C4 UPS System Improvements
Project:   C800107    Project will replace existing UPS      Status Snapshot Prior Report
Budget: $2,336,000   System, including batteries, with a new  Delayed Schedule 1Q 09
Phase: Construction  new system located in the Airport     On Budget
Start: 06/28/2007      Combined Communications and       No Change Orders
Completion: TBD     Command Center (C4).          Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. Port staff is in the process of reviewing the Consultant's       2
proposed Service Agreement and Service Directive, and should be     Millions 1.5
completed in the second quarter of 2010.
1
Dollars in 0.5
Schedule
0
The project was reactivated on June 24, 2009 and is in the process
Authorized  Forecasted Costs Incurred
of determining the scope of work, schedule and final design budget.
Expect to remobilize the Design Consultant late in the second
quarter of 2010.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None.
Photo
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions.
It is not known when the construction will proceed as this is
specialized euipment and complex and requires rigorous testing
during the commissioning phase.
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 1Q 2010 Report  23

FIRST QUARTER REPORT, 2010
Garage Escalator & A-Bank Elevator Upgrade
Project:   C800109    This project renews and replaces     Status Snapshot
Budget: $7,315,000    aging elevators and escalators in the   On Schedule
Phase: Construction   Parking Garage to provide reliable    On Budget
Start: 09/11/2007       vertical transportation to customers for  13 Change Orders
Completion: 02/28/2011  years to come.              Total Change Orders Amount:
$95,477
Significant Developments                    Budget/Costs Incurred
A-Bank consists of seven elevators. Work on four elevators is
8
complete with three elevators in service and one elevator temporarily
out of service pending State inspection. Work on the remaining        6
three elevators is nearing completion. A sole source contractor       Millions
4
acquisition was approved for the garage escalator project with a
contract in preparation.                                   Dollars in  2
Schedule                             0
Authorized  Forecasted Costs Incurred
Substantial completion and in-service of all A-Bank elevator work is
scheduled for the end of May 2010. Change order work regarding
elevator electrical equipment is expected to occur in June. The      Construction Costs
garage escalator construction contract is expected to be executed in
late June 2010 with project duration of 8 months.                   2.5
2
Budget
Millions  1.5
The project forecast is within the approved budget and authorization.
1
Dollars in   0.5
Change Order
0
Four change orders have been issued this quarter in the amount of
Initial  Change Orders  Spent
$42,477.
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
24  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Runway 16C/34C Panel/Joint Sealant
Replacement
The scope of work will remove and   Status Snapshot
replace the pavement and joint seal  On Schedule
Project: C800112
in areas on Runway 16C-34C.     On Budget
Budget: $5,650,000                         No Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 02/26/2008                                 N/A
Completion: 12/31/2010
Budget/Costs Incurred
Significant Developments
6
Budget increased in December 2009 from $2,415,000 to $5,650,000    5
to replace 150 panels on Runway 16C-34C. The overall project      Millions 4
objective is to maintain the runway in an operational condition until      3
its planned reconstruction in 2016. Construction bids will be opened     2
in early second quarter.                                  Dollars in  1
0
Schedule
Authorized  Forecasted Costs Incurred
The 2010 project is scheduled to start construction in July and be
complete in September.
Construction Costs
Budget                           None
The project forecast is within the approved budget and authorization.
Change Order                        Photo
None
Risks
No risks have been identified at this time.
Budget Transfers
From C102166 (Aeronautical Renewal/Replacement)  $3,235,000


AIRPORT

Port of Seattle 1Q 2010 Report  25

FIRST QUARTER REPORT, 2010
Security CCTV System Improvements
Project:   C800144      This project will install          Status Snapshot Prior Report
Budget: $2,037,591      approximately 70 new cameras for  Delayed Schedule 3Q 09
Phase: Implementation   TSA and integrate existing Airport   On Budget
Start: 9/11/2007          camera networks which contain     No Change Orders
Completion: 03/31/2010   over 800 cameras.          Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The final cut overs are complete. The Port and TSA are evaluating
2.1
follow on work.
2.05
2
Schedule
1.95  Millions
Project completion occurred in March 2010.                    1.9
1.85  Dollars in 
Budget                             1.8
1.75
The project forecast is within the approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable.
Risks                               Construction Costs
None identified at this time.                                Not Applicable
Budget Transfers
None this quarter




AIRPORT
26  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
RMU/Kiosk Concession Program
Project:   C800146      The project will: Provide design and    Status Snapshot Prior Report
Budget: $1,209,000      fabrication of eight Retail        Delayed Schedule 4Q 09
Merchandising Units (RMUs); provide
Phase: Construction                        On Budget
power, communications, and data to
Start: 11/20/2007                                 No Change Orders
the sixteen RMU locations; and install
Completion: 2/29/2010                        Total Change Orders Amount:
floor-mounted receptacles for the
N/A
utilities to allow easy connection points
to the sixteen RMUs, as well as
flexibility for future utilization.          Budget/Costs Incurred
1.4
Significant Developments
1.2
All RMU installations are complete. Communications connections       1
are scheduled to be completed early April.                     Millions 0.8
0.6
Schedule                            Dollars in 0.4
0.2
The design phase has been restructured and the bid packages re-
0
sequenced, with the intent to maximize the timing for new
Authorized  Forecasted Costs Incurred
Concessions opportunities. The project was put on hold until the
prioritization decisions were made by the Port's Business
Development group, delaying the completion date by one month,
which was previously reported. The two existing communications
Construction Costs
connections have been delayed by coordination issues with the
Not Applicable
current tenant.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 1Q 2010 Report  27

FIRST QUARTER REPORT, 2010
Concessions Renewal/Replacement
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Design        previously vacated or slated to be   On Budget
Start: 08/26/2008         vacated to Port standards for use    No Change Orders
Completion: 06/30/2011   as specialty concession space.    Total Change Orders Amount:
N/A
Significant Developments
The project is in the permit planning review stage.               Budget/Costs Incurred
Schedule                             2.5
The schedule has slipped due to the economic climate. The sponsor     2
is re-evaluating the need to upgrades to all of the originally proposed    1.5
spaces. Project will return to Commission in late June or early July     Millions
1
for authorization to advertise and construct.
Dollars in 0.5
Budget                             0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order                         Construction Costs
Not Applicable
None.
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
28  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot  Prior Report
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule 4Q 09
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,000
project includes installing three      No Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      N/A
Completion: 12/31/2011   approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
1.2
The 100% design is complete.                            1
0.8
Schedule
Millions 0.6
The project completion has been pushed into 2011 to coordinate with    0.4
issuance of a Concessions Request for Proposal by the Aviation       Dollars in 0.2
Business Development Group.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                 Not applicable
Risks
Location
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 1Q 2010 Report  29

FIRST QUARTER REPORT, 2010
Concessions Flooring
Project:   C800157      This project replaces flooring in     Status Snapshot Prior Report
Budget: $2,182,000      North and South Satellite food    Delayed Schedule 2Q 09
Phase: Close Out      courts.                On Budget
Start: 07/24/2007                                 15 Change Orders
Completion: 08/05/2009                       Total Change Orders Amount:
$270,162
Budget/Costs Incurred
Significant Developments
All work is completed.                                   2.5
2
Schedule                            Millions 1.5
The project is complete.
1
Budget                             Dollars in 0.5
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
Four change orders issued this quarter closing out previously issued
Not to Exceed change orders resulted in a net decrease of $32,139.   Construction Costs
1.5
Risks
None identified at this time.                                  Millions  1
Budget Transfers                           0.5
None this quarter                                     Dollars in 
0
Initial  Change Orders  Spent
Cost of Construction Growth
Structural deficiencies were encountered during the demolition
phase. Changes in phasing and materials were required to expedite
curing and allow tenants to stay open during construction. Varying    Photo
site conditions required additional demolition, regulated materials
removal, and restoration of existing conditions.


AIRPORT
30  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Runway 16L/34R Reconstruction
Status Snapshot
Project: C800167        The scope of this project includes
the complete reconstruction of      On Schedule
Budget: $73,490,000
Phase: Close Out      Runway 16L/34R (the eastern     On Budget
Start: 02/26/2008        runway) and replacement of aging   26 Change Orders
infrastructure.                  Total Change Orders Amount:
Completion: 12/31/2009                       $604,117.41
Significant Developments                    Budget/Costs Incurred
Runway 16L/34R Reconstruction project includes reconstruction of    100
11,900 foot runway and portions of five taxiways. The construction
80
was completed on September 25, 2009 and re-opened on         Millions 60
September 26, 2009 on schedule.
40
Schedule                            Dollars in 20
0
The runway was re-opened on schedule on September 26, 2009
Authorized  Forecasted Costs Incurred
and contract closeout will continue through 2010.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
One work project was changed from an Asset to Expense totaling       60
$1,510,000.                                       50
Millions  40
Change Order                           30
20
Two change orders for a total of $74,661.11 have been executed      Dollars in  10
during this period. None involved extension of the contract time.
0
Initial  Change Orders  Spent
Risks
No risk have been identified at this time.
Photo
Budget Transfers
To Expense                     $1,510,000


AIRPORT

Port of Seattle 1Q 2010 Report  31

FIRST QUARTER REPORT, 2010
Connect C1 BHS to C88 BHS
Project:   C800170      This project connects the C1      Status Snapshot
Budget: $3,032,000      baggage handling system (BHS) to  On Schedule
Phase: Construction     the C88 BHS. It installs two High-  On Budget
Start: 8/30/2009          Speed Diverters plus additional     No Change Orders
Completion: 12/31/2010   baggage conveyor length that will   Total Change Orders Amount:
connect the two C1 sortation loops   N/A
to the C88 BHS.
Budget/Costs Incurred
Significant Developments
3.5
The 100% design is complete. The project received Commission
3
authorization for construction funding on March 23, 2010.
Millions 2.52   Dollars in 
Schedule                             1.5
Currently the project is on schedule.                           1
0.5
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Not Applicable                                     Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
From C102165 (Aeronautical New Projects)       $232,000




AIRPORT
32  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Renew/Replace 42 Escalators & 2 New
Escalators
This project will renew and replace   Status Snapshot  Prior Report
Project:   C800237      42 escalators in the Main Terminal,  Ahead of Schedule 3Q 09
Concourse B, and South Satellites.   On Budget
Budget: $55,000,000
In addition, two new escalators will   No Change Orders
Phase: Design        be installed at the South Satellite.   Total Change Orders Amount:
Start: 11/02/2007                                 N/A
Completion: 12/31/2013
Budget/Costs Incurred
Significant Developments
60
Design contract notice to proceed was issued in October 2009. The     50
project is utilizing a design-build contract method as part of an effort
to accelerate the overall project schedule.                      Millions 40
30
20
Schedule                            Dollars in 10
The schedule has been updated to reflect an expedited design-build
0
procurement as well as an accelerated construction duration with a
Authorized  Forecasted Costs Incurred
resultant tentative completion date in 2013. Commission approval to
advertise/request for qualification is scheduled for April 2010 with
advertisement in May 2010.                            Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested following the review of the proposal documents and
selection of a firm.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 1Q 2010 Report  33

FIRST QUARTER REPORT, 2010
Central Plant Pre-Conditioned Air
Project:   C800238     This project will provide a centralized  Status Snapshot Prior Report
Budget: $40,600,000    pre-conditioned air plant, associated  Delayed Schedule 3Q 09
Phase: Design       heating and cooling piping systems,   On Budget
Start: 06/15/2009       and jet bridge terminal air handling    No Change Orders
Completion: 12/10/2012  units to serve airplanes with heating   Total Change Orders Amount:
and cooling while at the gates.       N/A
Significant Developments
The Port of Seattle performed a Value Engineering process and     Budget/Costs Incurred
incorporated the design changes into the documents. The 90%
construction documents have been submitted.                  50
40
Schedule
30
The negotiation process took longer than anticipated and the project     Millions
20
is approximately two months behind for completing the construction     Dollars in 10
documents; however, coordination with the FAA is complete and the
project is on track for the current funding schedule. We anticipate       0
advertising for bids in June of 2010.                              Authorized  Forecasted Costs Incurred
Budget
The budget was increased to $40,600,000. The Port's commitment
Construction Costs
increased to $14,870,000. Authorization of construction funding and
Not applicable
authority to advertise for construction will be requested when the
design and bid documents are completed.
Change Order
None
Risks
The schedule is tied to Voluntary Airport Low Emissions (VALE)
funding.
Budget Transfers
From C102165 (Aeronautical New Projects)     $7,240,000


AIRPORT
34  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Fire Piping Upgrades - Main Terminal
Project:   C800239      This project will upgrade the Main   Status Snapshot Prior Report
Budget: $1,450,000      Terminal fire piping to restore     Ahead of Schedule    4Q 09
Phase: Close Out      system reliability and provide full   Under Budget   4Q 09
Start: 09/23/2008         monitoring capability with the fire    1 Change Orders
Completion: 03/24/2010   alarm system.             Total Change Orders Amount:
($10,000)
Significant Developments                    Budget/Costs Incurred
Project is complete and in close out. Substantial completion was
issued on March 24, 2010.                               2
1.5
Schedule                            Millions
The construction was completed ahead of schedule. The fire piping      1
contractor identified efficiencies and performed the work accordingly.
Dollars in 0.5
Budget                             0
The project forecast is within the approved budget and authorization.       Authorized Forecasted Costs Incurred
It is anticipated that this project will have a future savings of
approximately $700,000.
Change Order                         Construction Costs
None
0.3
Risks                                 0.2
Millions
None identified at this time.                                   0.1
0
Budget Transfers                          Dollars in     Initial Change Orders Spent
0.1
To C102166 (Aeronautical Renewal/Replace)      $50,000




AIRPORT
Port of Seattle 1Q 2010 Report  35

FIRST QUARTER REPORT, 2010
2nd Floor HVAC Upgrades
Project:   C800249      Construct a new Heating        Status Snapshot
Budget: $1,700,000      Ventilating and Air-Conditioning    Delayed Schedule
Phase: Construction     (HVAC) air supply duct system to   On Budget
Start: 03/25/2008         the north side of the second floor of  No Change Orders
Completion: 04/09/2010   the central main terminal       Total Change Orders Amount:
administration building and the      N/A
concessions located directly below
on the ticketing level.            Budget/Costs Incurred
Significant Developments
2
Construction is now scheduled to be complete April 9, 2010.
1.5
Schedule                            Millions
1
Construction contract was extended an additional two weeks to April
0.5
9, 2010 due to contractor's incorrect installation of structural          Dollars in 
supports. Deficiencies were found during the punchlist walkdown.      0
The contractor required additional time for fabrication, installation,          Authorized  Forecasted Costs Incurred
and re-insulating the affected areas.
Budget                            Construction Costs
Budget increase of $203,000 was approved by the Commission on
March 23, 2010.                                      1
0.8
Change Order                          Millions 0.6
None                                   0.4
Dollars in   0.2
Risks
0
None identified at this time.                                       Initial Change Orders Spent
Budget Transfers
From C102166 (Aeronautical Renewal/Replace)     $203,000


AIRPORT

36  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Aircraft RON Parking USPS Site
This project will prepare the site for   Status Snapshot
Project: C800254                               On Schedule
Budget: $43,900,000     the construction of Hardstands for
use as Remain Overnight parking   On Budget
Phase: Design                           No Change Orders
Start: 04/05/2009        of aircraft at the Air Mail Center
site.                            Total Change Orders Amount:
Completion: 06/30/2013                       N/A
Significant Developments                     Budget/Costs Incurred
This project completed the lease buyout negotiation with the USPS
50
and is scheduled for lease termination in 2010. A new one year
40
lease with Customs and Border Patrol (CBP) will extend into 2011.
Design efforts for the demolition of the Air Mail Center including the     Millions 30
design for minimal site improvements allowing for temporary uses      20
and amenities, and 15% design will start in Summer 2010.          Dollars in  10
0
Schedule
Authorized  Forecasted Costs Incurred
Abatement and demolition of the USPS Building is scheduled to
start second quarter of 2011. No current time frame for construction
of a permanent hardstand has been set.
Construction Costs
Budget                           Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested following the review of the proposal documents and
selection of a firm.
Change Order
None.
Risks
No risks identified at this time.
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 1Q 2010 Report  37

FIRST QUARTER REPORT, 2010
8th Floor Weatherproofing
Project:   C800274      This project includes removal and   Status Snapshot
Budget: $13,000,000     replacement of the floor covering   On Schedule
Phase: Planning       system on the 8th floor of the STIA  On Budget
Start: 03/23/2010         parking garage and repair or       No Change Orders
Completion: 03/31/2013   replacement of expansion joints    Total Change Orders Amount:
and flashings.                 N/A
Significant
Budget/Costs Incurred
Developments
Project notebook was completed and presented to the Investment      14
Committee. Commission approved moving to the design phase in     12
late March. Preparing Request for Qualifications for design services.    Millions 10
Current plan is to complete design in 2010, bid in first quarter 2011      8
Dollars in 
6
and construct during the spring/summer of 2011 and 2012.
4
2
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
None.                                    Construction Costs
Risks
Not Applicable
This is a weather-dependent project.
Budget Transfers
To C800153 (Non-Aero Renewal/Replacement)    $2,000,000




AIRPORT
38  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Common Use Equipment Expansion (CUSE)
Project:   C800276      This project installs flexible       Status Snapshot
Budget: $3,090,000      common use facilities at some    On Schedule
Phase: Design        South Satellite and Concourse A   On Budget
Start: 09/01/2009         gates, as well as at Delta's former   No Change Orders
Completion: 12/31/2011   (pre-NWA merger) ticket counters.  Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Procurement of the design consultant continues.
3.5
3
Schedule
The project is on schedule.                                Millions 2.52  Dollars in 
1.5
Budget                             1
0.5
The project forecast is within the approved budget. Authorization of
0
construction funding and authority to advertise for construction will
Authorized  Forecasted Costs Incurred
be requested when the design and bid documents are completed.
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 1Q 2010 Report  39

FIRST QUARTER REPORT, 2010

South AOA Fence Replacement
Status Snapshot
On Schedule
Project: C800286      This project provides new security
On Budget
Budget: $375,000     fencing around the south end of
No Change Orders
Phase: Close Out    Runway 34R that lies south of 188th
Total Change Orders Amount:
Start: 03/03/2009      street, meets current standards for
N/A
Completion: 11/30/2009 airfield security fence, and reduces the
number of coyotes on the airfield to
enhance aviation safety.
Budget/Costs Incurred
0.4
Significant Developments
0.3
Fence Replacement was completed in the Fall of 2009. This will be    Millions
the last quarterly report for this project.                          0.2
Schedule                            Dollars in 0.1
The project is complete. Contract closeout will be in mid 2010.        0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
0.2
None.
0.15
Risks                                Millions
0.1
No risks have been identified at this time.
Dollars in  0.05
Budget Transfers
0
None this quarter.                                          Initial Change Orders Spent



AIRPORT
40  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
South Satellite Delta Sky Club Expansion
Project:   C800336     Construction of a new 6,800 square   Status Snapshot
Budget: $5,440,000    foot Sky Club lounge on the roof of   On Schedule
Phase: Design       the South Satellite for Delta Air Lines.  On Budget
Start: July 2010                                  No Change Orders
Completion: April 2011                       Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
Tenant designer is developing 100% design and permit documents.
6
Schedule
5
Construction work is scheduled to begin in the Summer of 2010 and    Millions 4
to be complete by Spring 2011.                             3
2
Budget                             Dollars in  1
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
None.
Construction Costs
Risks                               Not Applicable
None identified at this time.
Budget Transfers
From C102165 (Aeronautical New Projects)      $1,440,000




AIRPORT

Port of Seattle 1Q 2010 Report  41

FIRST QUARTER REPORT, 2010
Fire Vehicles
Project:   C001338      Purchase of fire vehicles according  Status Snapshot
Budget: $2,242,000      to the Fire Department Vehicle    On Schedule
Phase: Implementation   Replacement Master Plan. Includes  On Budget
Start: 11/23/2008         Fire Pumper Vehicle purchase.     No Change Orders
Completion: 7/31/2009                        Total Change Orders Amount:
N/A
Significant Developments
The project is completed and has been closed out. This will be the   Budget/Costs Incurred
last quarterly report for this project.
2.244
Schedule                            2.243
2.242
The project is completed. The Fire Pumper (E-1) is in service.        2.241
Millions2.24
2.239
Budget
2.238   Dollars in
The project forecast is within the approved budget and authorization.   2.237
2.236
Change Order                            Authorized Forecasted Costs Incurred
None
Risks
Construction Costs
None identified at this time.                                Not Applicable
Budget Transfers
None





AIRPORT
42  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Fire Vehicles
Project:   C102396      Purchase of fire vehicles according  Status Snapshot
Budget: $1,369,000      to the Fire Department Vehicle    On Schedule
Phase: Implementation   Replacement Master Plan. Includes  On Budget
Start: 11/16/2008         purchase of an ARFF vehicle and   No Change Orders
Completion: 7/31/2009    medical aid unit vehicle.        Total Change Orders Amount:
N/A
Significant Developments
ARFF vehicle - Contract has been executed.                 Budget/Costs Incurred
Medical Aid Unit - Contract has executed, Aid vehicle in service        1.5
beginning July 2010.
1
Schedule                             Millions
Project is completed.                                    0.5
Dollars in
Budget                             0
The project forecast is within the approved budget.                   Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None




AIRPORT
Port of Seattle 1Q 2010 Report  43

FIRST QUARTER REPORT, 2010
Highline School Noise Insulation
Project:   C200007      Highline School Insulation        Status Snapshot Prior Report
Budget: $101,797,000    Agreement will provide funding for  Delayed Schedule 3Q 09
Phase: Construction     sound mitigation for 15 schools that  On Budget
Start: 03/23/1999         are impacted by aircraft noise from   No Change Orders
Completion: 11/30/2021   Sea-Tac Airport.            Total Change Orders Amount:
N/A

Budget/Costs Incurred
Significant Developments
The insulation of seven schools has been completed and no more     120
are scheduled until 2012.                                100
80
Schedule                             Millions 60
Port funding is authorized and will be available when the matching      40
Dollars in
funds are provided by the state and school district. The schedule for     20
state funding is not known. The district's schedule is also dependent     0
on obtaining general election bonds at various intervals.                Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable.
Not applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
44  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
3rd Runway Residential Acquisition
Project:   C200015    Acquire single/multi-family residences   Status Snapshot
Budget: $34,340,000   located in the noise-impacted 3rd     Delayed Schedule
Runway flight path in the City of Burien
Phase: Close Out                          On Budget
to comply with FAA noise exposure
Start: 05/27/1999                                 No Change Orders
and safety regulations.
Completion: TBD                           Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The final of three phases is complete. 56 of 59 properties have been
50
acquired and the residents relocated to quieter neighborhoods.
Three properties (two single family residences and one 16-unit        40
apartment complex) have been forwarded to our outside legal        Millions 30
counsel for acquisition via the condemnation process. Timing of the
20
remaining three properties is dependent on the legal process.         Dollars in  10
Demolition of vacant homes continues.
0
Schedule                               Authorized Forecasted Costs Incurred
The project end date is delayed due to the pending court cases and
dependent on the length of time the property condemnation process
takes to work through the legal system. This does not affect airport
Construction Costs
or 3rd Runway operations.
Not Applicable
Budget
The project forecast is within the approved budget and authorization.  Photo
Change Order
Not Applicable
Risks
No significant risks identified.
Budget Transfers
None


AIRPORT
Port of Seattle 1Q 2010 Report  45

FIRST QUARTER REPORT, 2010
FAR Part 150 Mobile Home Park Acquisition
Project:   C200037     Acquisition of mobile and         Status Snapshot
Budget: $52,306,110    manufactured home parks, and     Ahead of Schedule
Phase: Close Out     relocation of the tenants, to reduce   On Budget
Start: 02/12/2002       the number of people living in mobile   No Change Orders
homes within high noise areas.
Completion: 06/17/2010                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
All mobile home units have been purchased. Demolition and site
52.5
restoration continues. Approximately 50% complete. Regulated
52
materials sampling and testing on-going in preparation for a phased
51.5
Port Construction Services demolition schedule.                 Millions
51
Schedule                            50.5
Dollars in  50
All tenants have been successfully relocated to quieter
49.5
neighborhoods.
Authorized  Forecasted Costs Incurred
Budget
The total budget increases for the life of this program are
approximately 2.55% above the 2001 forecast for this Capital       Construction Costs
Improvement Project.                               Not Applicable
Change Order                         Photo
Not Applicable
Risks
Regulated materials abatement and demolition costs could be higher
than anticipated.
Budget Transfers
None this quarter.



AIRPORT
46  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $10,822,000     Insulation Agreement will provide   Delayed Schedule 1Q 08
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      No Change Orders
Completion: 10/01/2011   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
N/A
Significant Developments
Twelve of the 22 eligible buildings have been sound insulated by the  Budget/Costs Incurred
college.
12
Schedule                             10
Building #9 will be under construction during the summer of 2010       8
and is anticipated to be complete fall of 2010. The schedules for the     Millions 6
remaining buildings are dependent on state funding.                4
Dollars in  2
Budget                             0
The project forecast is within the approved budget. We will complete       Authorized  Forecasted Costs Incurred
noise audits on each of the remaining buildings that have not been
reconstructed to see if in the future any will be eligible for FAA grant
funds. Authorization of the remaining project budget of $4,567,070
will be requested for one building at a time from the Commission in   Construction Costs
the future when schedule is determined.                     Not Applicable.
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed. The Port is working with the College to determine
estimates for the remaining college buildings that have not been
completed.
Budget Transfers
None this quarter.

AIRPORT

Port of Seattle 1Q 2010 Report  47

FIRST QUARTER REPORT, 2010
Home Insulation Retrofit
Project:   C200048      This CIP includes two projects that   Status Snapshot Prior Report
Budget: $5,344,000      provide either re-insulation or repair  Delayed Schedule 4Q 09
Phase: Construction     of previously insulated homes due  On Budget
Start: 01/11/2005         to safety and condensation issues.   No Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
The Port is researching remaining eligible homes to continue with
insulation retrofit. The project is waiting on approval of a new           6
architectural service agreement with the Central Procurement Office.     5
4
Schedule                             Millions 3
The project will commence upon review of remaining homes and       2
having a new architectural service agreement to design the          Dollars in 1
construction.                                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable                                     Not Applicable.
Risks
There is potential liability associated with egress safety issues.
Budget Transfers
None



AIRPORT
48  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot
Budget: $2,450,000      that are within the 1998 65 decibel  On Schedule
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   No Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Seven homes are in process and there are 28 on the waiting list for
3
the next group.
2.5
Schedule                            Millions 2
Dollars in 
1.5
This project is on schedule.
1
0.5
Budget
0
The project forecast is within approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable
Construction Costs
Risks                               Not Applicable
The ability to accomplish the insulation is dependent on
homeowner's schedules, willingness to sign an aviation easement,
and structural integrity of the home.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 1Q 2010 Report  49

FIRST QUARTER REPORT, 2010
Street Vacations - Des Moines Creek 1
Project:   C800046    Purchase the City of Des Moines-      Status Snapshot
Budget: $3,850,000   owned streets in the Des Moines Creek  Delayed Schedule
Phase: Implementation Business Park site that are surrounded  On Budget
Start: 10/01/2008      by Port-owned property. This        No Change Orders
Completion: 12/31/2010 acquisition will enable the Port to     Total Change Orders Amount:
develop the business park site.        N/A
Significant Developments                    Budget/Costs Incurred
Per our agreement with the City of Des Moines, the amount owed
3.86
the City has been deposited into an escrow account pending
3.84
satisfaction of all the conditions required for closing.
3.82  Millions
Schedule                             3.8
Acquisition is expected to be completed by December 31, 2010. The   3.78  Dollars in 
Port is still negotiating the agreement with the City of Des Moines,
3.76
which we expect to complete before the end of the year.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Not applicable.
Risks
The original conditions required for closing--most notably, the Des
Moines City Council's approval of the developer's master plan--
cannot be met now that the developer selected for the project
withdrew from ground lease negotiations. The Port anticipates
revising its existing agreement with the City to reflect a new
approach to developing the site.
Budget Transfers
None


AIRPORT
50  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot
Budget: $3,000,000      along Des Moines Memorial Drive,  On Schedule
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that are surrounded by Port-  No Change Orders
Completion: 12/31/2010   owned properties.           Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The Burien Seventh Day Adventists Church and School were
3.5
acquired December 31, 2008. Next acquisitions are for the
3
Sunnydale Substation and a street vacation in Burien.
Millions 2.52   Dollars in 
Schedule                             1.5
Properties are purchased as Commission authorization is received.      1
Program expected to be completed in 2010.                   0.5
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 1Q 2010 Report  51

FIRST QUARTER REPORT, 2010
Tenant Reimbursement
Project:   C800154    Build out of spaces for new and      Status Snapshot
Budget: $4,709,577    existing tenants. If more than a "basic  On Schedule
finish" condition space is built for the    On Budget
Phase: Construction
tenant, the tenant is required to       No Change Orders
Start: 08/14/2007
reimburse the Port for the cost of the   Total Change Orders Amount:
Completion: 03/31/2010
work beyond this "basic finish". These   N/A
reimbursements are allowed under
the guidelines described in the       Budget/Costs Incurred
"Tenant Reimbursement Policy".
5
Significant Developments                      4
Port had no tenant reimbursement activity in the first Quarter of        Millions 3
2010.
2
Dollars in   1
Schedule
0
Schedules vary to meet the tenant's needs.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.              Construction Costs
Not Applicable.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
52  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Alaskan Way St Vacation and Public Access
Project:   C000579      Scope includes all public access    Status Snapshot Prior Report
Budget: $1,036,000      improvements at multiple sites and  Delayed Schedule 2Q 08
Phase: Planning       fees as required by the City of    On Budget
Start: 1996             Seattle in order to vacate Alaskan   No Change Orders
Completion: 2011       Way South at T30 site.        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
No changes this quarter.
1.2
1
Schedule
Millions 0.8                                                                                  No changes this quarter. Project continues to be on hold pending
0.6
closure of all other previous street vacations.
0.4
Dollars in 0.2
Budget
0
No changes this quarter. Plan is to get new authorizations for future       Authorized  Forecasted Costs Incurred
work pursuant to Resolution 3605.
Change Order                         Construction Costs
Not Applicable                                     None
Risks
Risks have not changed from 3rd Quarter 2008.
Budget Transfers
Not Applicable




SEAPORT
Port of Seattle 1Q 2010 Report  53

FIRST QUARTER REPORT, 2010
T-115 Dock Reconstruction
Project:   C102451      Upgrade three areas of existing    Status Snapshot Prior Report
Budget: $31,541,577     1200 ft dock, upgrade Berth 1 and  Delayed Schedule 4Q 08
Phase: Construction     improve 15 acres of uplands for    Forecast Overrun 1Q 08
Start: 7/2003            tug/barge cargo operations.       29 Change Orders
Completion: 12/31/2009                       Total Change Orders Amount:
$1,748,865
Significant Developments                    Budget/Costs Incurred
In-water construction was completed in 1Q 2010.
32
31.5
Schedule                             Millions 31
30.5
No change from 4Q 2009. Scheduled completion is 2Q 2010.        30
29.5
Budget                             Dollars in  29
28.5
No change this quarter.                                  28
Authorized  Forecasted    Costs
Incurred
Change Order
Change Order was approved for a tenant requested revision to the
Berth 1 Ramp Lifting System. Staff is expecting a claim for        Construction Costs
unexpected difficulties in driving pipe and sheet pile caused by
30
unanticipated underwater obstructions.
25
Risks                                Millions 20
15
Previous schedule risks were addressed. There is budget risk from
items associated with the unanticipated underwater obstruction        Dollars in  10
claim.                                                5
0
Budget Transfers                             Initial Change Spent
Orders
None



SEAPORT
54  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Terminal 30/Terminal 91 Program          Status Snapshot
On Schedule
On Budget
Project: C800085     Redevelopment of Terminals 25/28/30   129 Change Orders
Budget: $121,525,000  into one combined container facility.    Total Change Orders
Phase: Construction  Relocation of the existing T30 Cruise   Amount: $6,581,000.
Start: 10/2/07        operations into a new facility at T91, and
Completion: 4/30/11   related facility improvements and berth   Budget/Costs Incurred
dredging.
Significant Developments                     125
T91: The Commission authorized staff to proceed in December
120
2009 to construct new canopies and complete other improvements     Millions
utilizing remaining project budget. During this quarter, staff           115
completed canopies design and obtained building permit from City of
110
Seattle. Cruise terminal's building entry improvement is complete.      Dollars in 
Construction of canopies, Customs and Border Protection and other    105
improvements are underway by Port Construction Services and          Authorized Forecasted Costs Incurred
Seaport Maintenance. Cruise Terminal's art planner has completed
draft arts plan for terminal's public art.
Construction Costs
Schedule
100
T91: Targeting completing additional canopies north of the cruise
terminal before the 2010 cruise season. Instead of completing some     80
of the new authorized work right after the 2010 cruise season as       Millions  60
originally planned, staff will try to complete the work during early         40
cruise season. Terminal's public art component is scheduled to be
Dollars in   20
completed in 2011.
0
Initial  Change Orders  Spent
T30: Terminal became operational on August 3, 2009, as previously
reported. Per the Q4, 2009 report, T30 component of the project is
in closeout and will no longer be reported.                     Photos
Budget
The budget remains stable. Current program budget is
$121,500,000 and the forecast is $115,900,000.
Change Order
There were no change orders this quarter. Major construction
contracts are in closeout.

Port of Seattle 1Q 2010 Report  55

Budget Transfers
There were no budget transfers in or out of the program.
Cost Growth of Construction
T91 Cruise Terminal Upgrade  MC-0314783  The major
construction contract is in closeout. The cost growth of construction
remains as reported in 3Q, 09.
T30 Upgrade  MC-103326  The major construction contract is in
closeout. The cost growth of construction remains as reported in
4Q09.
Risks
T91: None. Facility is in operation.
T30: None. Facility is in operation.









SEAPORT
56  Port of Seattle 1Q 2010 Report

SECOND QUARTER REPORT, 2010
P66 Bag. Corridor & Pass. Screening
Project:   C800114      Provide baggage and passenger    Status Snapshot Prior Report
Budget: $2,087,000      screening improvements at P66 to  Delayed Schedule 3Q 09
Phase: Construction     accommodate larger cruise vessels  On Budget
Start: 1/1/2008          with 300-400 more passengers per   No Change Orders
Completion: 12/31/2009   sailing.                Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Three bids were received and all were determined to be non
2.5
responsive. The project will be rebid in 2010.
2
Schedule                            Millions 1.5
The cruise season has started, as such construction will be           1
postponed until 4Q 10.                                 Dollars in 0.5
0
Budget
Authorized  Forecasted Costs Incurred
None
Change Order                         Construction Costs
None                                 None
Risks
The biggest risk is that we may not get bids again but we are
mitigating this risk by reevaluating the bid documents and giving the
contractors ample time to purchase the materials and do the
construction. Potential risk to schedule with the rebid.
Budget Transfers
None



SEAPORT
Port of Seattle 1Q 2010 Report  57

FIRST QUARTER REPORT, 2010
Terminal 18 South Fender Improvements
Status Snapshot Prior Report
Project: C800121        Replace 800' of deteriorated fender
Delayed Schedule 4Q 09
Budget: $450,000       system at the south end of
On Budget
Phase: Design        Terminal 18
0 Change Orders
Start: 3/26/08                                    Total Change Orders Amount:
Completion: 3/31/10                         $0
Significant Developments
Budget/Costs Incurred
Commission authorized for the replacement of 800' of the fender
system.
3.5
Schedule
3
Construction is scheduled to start in December 2010 after the tribal     2.5
fishing activities are complete. The berth will be available for use in      2
Millions
March 2011.                                    1.5
Dollars in  1
0.5
Budget
0
Project within approved budget.                               Authorized Forecasted Costs Incurred
Change Order
None this quarter                                    Construction Costs
None
Risks
None this quarter
Budget Transfers
None




SEAPORT
58  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
T-5 Crane Spreader Replacement
Project:   C800123      To replace two crane cargo       Status Snapshot Prior Report
Budget: $525,000       spreader beams that are beyond   Delayed Schedule 1Q 10
Phase: Construction     their useful life. Spreader beams   On Budget
Start: 10/24/06          are terminal equipment used to     No Change Orders
Completion: 3/31/09     move containers to and from ships  Total Change Orders Amount:
and trucks.                   $0
Significant Developments                    Budget/Costs Incurred
After review of design submittals, some electrical and mechanical
1.2
changes were required to comply with code requirements and to
1
make the new spreaders compatible with some existing equipment.
0.8
Delivery was delayed until 3Q 2010.                        Millions
0.6
Schedule                             0.4
Dollars in 0.2
Delivery was delayed from 1Q 2010 to 3Q 2010.
0
Authorized  Forecasted Costs Incurred
Budget
Only two of the spreader beams will be installed due to the tenant
reprioritizing their needs. The forecast has been reduced           Construction Costs
accordingly.
0.5
Change Order
0.4
None                                  Millions 0.3
Risks                                 0.2
None                                  Dollars in  0.1
0
Budget Transfers                             Initial Change Orders Spent
None


SEAPORT

Port of Seattle 1Q 2010 Report  59

FIRST QUARTER REPORT, 2010
North Harbor Island Mooring Dolphins (4)
Project:   C800182      Replace four barge mooring      Status Snapshot
Budget: $1,900,000      dolphins at the north end of Harbor  On Schedule
Phase: Design        Island.                On Budget
Start: 07/05/09                                   0 Change Orders
Completion: 12/31/10                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Purchased preliminary design from Crowley Maritime. Executed
0.6
design contract for completion of bid package.
0.5
0.4
Schedule                            Millions
0.3
Project is still on schedule to be completed within the 2010-11 permit
0.2
fish window. Commission construction authorization request         Dollars in 0.1
expected in 2nd quarter of 2010.
0
Authorized  Forecasted Costs Incurred
Budget
Revised construction estimate significantly higher than originally
estimated due mainly to increases in material cost estimates. Staff is  Construction Costs
verifying estimates, and will verify financial performance with        Not applicable
investment committee before returning to Commission.
Change Order
None
Risks
None
Budget Transfers
None



SEAPORT
60  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
T-10 Interim Redevelopment
Project:   C800264      Funding is to develop full project    Status Snapshot Prior Report
Budget: $800,000       scope and design of utilities to    Delayed Schedule 1Q 10
Phase: Design        support terminal related activities.   On Budget
Start: 3/22/08           Primary focus is the design of the    No Change Orders
Completion: 11/30/09    storm water drainage system and   Total Change Orders Amount:
the paving, lighting and fencing.     $0
Significant Developments                    Budget/Costs Incurred
In 4Q 2009, submitted revised design and permit documents to the
City of Seattle, State and Federal Agencies. During 1Q 2010 staff
6
addressed questions from the agencies and continued work on
5
completing the design documents. Permit review is progressing and
4
staff expects permits late in the 2Q 2010.
Millions 3
Schedule                             2
Dollars in  1
Completion of the project, contingent on permit approval, is
0
scheduled for 4Q 2010. This a three month delay.
Authorized  Forecasted Costs Incurred
Budget
Staff will return to Commission for additional construction          Construction Costs
authorization 2Q 2010.                               None
Change Order
None
Risks
Schedule delays
Budget Transfers
None



SEAPORT
Port of Seattle 1Q 2010 Report  61

FIRST QUARTER REPORT, 2010
T91 Mobile Gangway
Project:   C800273      Construct two mobile gangways    Status Snapshot
Budget: $6,460,000      and the associated support      On Schedule
Phase: Construction     infrastructures for the new T91    On Budget
Start: 6/24/2008          Smith Cove Cruise Terminal       5 Change Orders
Completion: 4/30/2009                        Total Change Orders Amount:
$557,536
Significant Developments                    Budget/Costs Incurred
Successfully negotiated and executed vessel walkway retrofit
6.5
change order. Design and retrofit work is complete. Systems are
6.45
ready for the 2010 cruise season.
Millions 6.4
6.35
Schedule
6.3
Systems are under an 18 month warranty.
6.25  Dollars in 
6.2
Budget
Authorized  Forecasted Costs Incurred
Project is on budget.
Change Order                         Construction Costs
One change order issued during 1st Quarter 2010.
7
Risks                                 6
5
None                                  Millions  4
3
Budget Transfers
Dollars in    2
None                                   1
0
InitialChange OrdersSpent

Photo


SEAPORT
62  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
T91 RD Pavement Entry & Guard Shack
Project:   C800343      Repave main entryway/intersection  Status Snapshot
Budget: $138,000       west of the main guard shack.     Delayed Schedule
Phase: Design                            On Budget
Start: 12/18/09                                   0 Change Orders
Completion: 5/1/2011                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Project design is in progress.
0.15
Schedule
Millions 0.1                                                                                  Project design is being delayed to address new permit requirements.
Design will resume late spring with construction scheduled right after
0.05
2010 cruise season.                                  Dollars in 
0
Budget
Authorized  Forecasted Costs Incurred
Project is currently on budget.
Change Order                         Construction Costs
None                                 None
Risks
Paving is weather dependent and paving window is somewhat
limited after cruise season, before cold weather sets in.
Budget Transfers
None




SEAPORT
Port of Seattle 1Q 2010 Report  63

FIRST QUARTER REPORT, 2010
T46 Upgrade Yard Lighting
Project:   C800347      Purchase and Engineering support  Status Snapshot
Budget: $680,000       for installation of energy saving    On Schedule
Phase: Design        yard lighting and equipment, as    On Budget
Start: 08/25/09          part of T46 lease negotiation.      0 Change Orders
Completion: 12/31/2010                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Purchase package complete and ready for advertisement in Second
0.8
Quarter.
0.6
Schedule                            Millions
0.4
On schedule
Dollars in 0.2
Budget
0
No change
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
None
Risks
None this quarter
Budget Transfers
None




SEAPORT

64  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
East Marginal Way Grade Separation
Status Snapshot Prior Report
Delayed Schedule 1Q 08
Project:   E 102007      FAST Corridor funded project;     Forecast Overrun  1Q 08
Budget: $49,000,000     FHWA, State, City with Port      8 Change Orders
Phase: Construction     commitment of $18,800,000. Scope  Total Change Orders Amount:
Start: 5/2006            is to construct grade separation in   ($48,087) deductive
Completion: Q3 2011     vicinity of T5 and T18 to minimize
truck traffic/rail conflicts.           Budget/Costs Incurred
60
50
Significant Developments
Millions 40
Construction activities commenced January 2010 including
30
foundation excavations, seismic ground improvements, and
20
structural earth embankment walls.                         Dollars in  10
0
Schedule
Authorized  Forecasted Costs Incurred
Construction is underway and scheduled completion remains
September 1, 2011.
Construction Costs
Budget
Remains the same as reported in 4Q 09.                       60
50
Change Order                          Millions 40
Eight change orders have been executed for a total net amount of       30
negative $48,087.                                     20
Dollars in   10
Risks                                 0
Construction change orders could occur, which could increase cost         InitialChange OrdersSpent
of construction.
Budget Transfers
New source of funds indicates that no budget transfers will be
required.


SEAPORT
Port of Seattle 1Q 2010 Report  65

FIRST QUARTER REPORT, 2010
Terminal 46 ZPMC Gearboxes
Project:   Expense      Implementation of contingency     Status Snapshot
103705,103706,103707    plans to keep the three port owned  On Schedule
Budget: $1,227,000      ZPMC cranes located at Terminal   On Budget
Phase: Construction     46 operating while          No Change Orders
Start: 8/22/2007          cause of the failing gearboxes is    Total Change Orders Amount:
investigated                  $0
Completion: 12/31/09
Budget/Costs Incurred
Significant Developments
1.4
ZPMC acknowledged similar problems have occurred at other ports
1.2
and may begin arbitration process with manufacturer of gearbox.
Millions  1
0.8
Schedule                             0.6
No change from 2009 report. Continuing to work with the designer,     Dollars in 0.4
0.2
consultants and manufacturer to identify a solution.
0
Authorized  Forecasted Costs Incurred
Budget
Budget remains unchanged from the 2Q 09 Report.
Construction Costs
Change Order                         No Major Construction
None this quarter                                    Contracts
Risks
Additional gearbox failures would result in further disruptions to
operations.                                        Photo
Budget Transfers
None



SEAPORT
66  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
T5/T18 Maintenance Dredging
Project:   Expense   Mechanically dredge up to 6,900 cy of   Status Snapshot
103835/103838      sediment along approximately 4,900' of  On Schedule
Budget: $2,937,000   berths at T18 and dispose of dredged   Under Budget
Phase: Construction  material at approved upland disposal   No Change Orders
Start: Feb 2008       sites; conduct environmental testing,    Total Change Orders Amount:
permitting, and design work for T5      $0
Completion: Feb 2011
maintenance dredging
Budget/Costs Incurred
Significant Developments                     3.5
No changes from 4Q 09.                               3
Millions 2.5
Schedule                             2
1.5
No changes from 4Q 09.
Dollars in   1
0.5
Budget                             0
No changes from last quarter                                Authorized Forecasted Costs Incurred
Change Order
Construction Costs
N/A
None
Risks
N/A
Budget Transfers
N/A




SEAPORT
Port of Seattle 1Q 2010 Report  67

FIRST QUARTER REPORT, 2010
Barge Layberth Improvements -- T25/P28/T46
Project: Expense 104011-3 Improvements to the fendering and  Status Snapshot
Budget: $300,000       terminal systems at Terminal 25,   On Schedule
Phase: Construction     Pier 28 and Terminal 46 to provide  On Budget
Start: 10/14/08          viable barge layberth use at these   No Change Orders
Completion: 4/1/10      sites.                 Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
All construction completed and berths returned to service.
0.35
0.3
Schedule
0.25
Construction completed in February 2010.                    Millions 0.2
0.15
Budget                             0.1
0.05
Dollars in 
Project exceeded original budget due to higher than expected         0
overhead rates in January and February 2010. Commission            Authorized Forecasted Costs Incurred
authorization to increase budget approved April 27, 2010.
Change Order                         Construction Costs
None this quarter                                    No Major Construction
Contracts
Risks
None
Photo
Budget Transfers
None




SEAPORT
68  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Water/Sewer Meter Upgrade
Project:   Expense      Upgrade existing water and sewer   Status Snapshot
multiple work projects    meter to meet current Seattle      On Schedule
Budget: $373,000 in total  Public Utilities standards       On Budget
Phase: Planning                          0 Change Orders
Start: 09/13/09                                   Total Change Orders Amount:
$0
Completion: 12/23/2010
Budget/Costs Incurred
Significant Developments
0.4
Construction will take place as projects are created and design plans
established. Comprehensive purchase package is being prepared to    0.3
reflect the different types and sizes of replacement meters required     Millions
0.2
for each site.
Dollars in 0.1
Schedule
0
Project is on schedule.
Authorized  Forecasted Costs Incurred
Budget
$373,000, approximately $123,000 of which is tenant reimbursable   Construction Costs
None at this time
Change Order
None
Risks
POS and tenants will pay higher commercial sewer rates on meters
without upgraded technology
Budget Transfers
None



SEAPORT
Port of Seattle 1Q 2010 Report  69

FIRST QUARTER REPORT, 2010
SBM Renewal and Replacement
Project:   C001706,      Redevelopment Shilshole Bay     Status Snapshot Prior Report
C001769, C001716      Marina docks, landside facilities,   On Schedule
Budget: $80,000,000     infrastructure and buildings.      On Budget
Phase: Construction                        149 Change Orders
Start: 1997                                     Total Change Orders Amount:
Completion: 4/30/2010                        $6,299,064
Budget/Costs Incurred
Significant Developments
80.5
Construction of interim pad site flatwork and landscaping completed
80
April 2010.
Millions79.5
Schedule                             79
78.5
Interim Pad Site improvements and landscaping work completed.
Dollars in  78
Site to be open for public access June 1, 2010 after plant
77.5
establishment.
77
Authorized  Forecasted Cost Incurred
Budget
No change this quarter.
Construction Costs
Change Order
60
None this quarter
50
Risks
Millions 40
30
None identified this quarter.
Dollars in  20
10
Budget Transfers
0
None                                      Initial  Change  Spent
Orders




REAL ESTATE
70  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
T 102 HVAC Renewal/Replacement
Project:   C800070      Replace HVAC System at all four   Status Snapshot Prior Report
Budget: $1,300,000      buildings at the Harbor Marina    Delayed Schedule 4Q 08
Phase: Construction     Conference Center          On Budget
Start: 10/2/2005                                  No Change Orders
Completion: 12/1/2008                        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Will use Open Order Small Works contract to get the last 7 units
1.35
installed and are waiting for a proposal from the contractor.
Anticipate receiving a proposal from Open Order Small Works        1.3
contractor.                                            1.25  Millions
1.2
Schedule
1.15  Dollars in 
Construction schedule is for later this spring when weather is
1.1
optimum.
Authorized  Forecasted Costs Incurred
Budget
Project is on budget.                                   Construction Costs
Change Order                           0.4
None
0.3
Risks                                 0.2
Millions
Budget is very tight.
Dollars in   0.1
Budget Transfers                           0
Initial Change Orders Spent
None



REAL ESTATE
Port of Seattle 1Q 2010 Report  71

FIRST QUARTER REPORT, 2010
C15 Sewer Line Upgrades
Project:   C800125      Replace the failing sewer/drain     Status Snapshot Prior Report
Budget: $600,000       lines under the Fisherman's      Delayed Schedule 3Q 09
Phase: Construction     Terminal C-15 West Building     On Budget
Start: 4/1/2008                                   3 Change Orders
Completion: 3/31/2009                        Total Change Orders Amount:
$99,000
Significant Developments                    Budget/Costs Incurred
Project is complete. This will be the last report.
0.61
0.6
Schedule
0.59
Final closeout expected within Quarter 1, 2010.                  Millions
0.58
0.57
Budget
0.56  Dollars in 
Project was completed under budget by $30,000.
0.55
Authorized  Forecasted Costs Incurred
Change Order
None this quarter
Construction Costs
Risks                               None
None
Budget Transfers
None





REAL ESTATE
72  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
T-86 Grain Facility Modernization (Phase-1)
Project:   C800133      Modernize and replace aging grain   Status Snapshot
Budget: $800,000       facility equipment/controls for $5M  On Schedule
Phase: Design        by 12/31/2011 to maximize      On Budget
Start: 2/21/2010          operational efficiencies and allow    0 Change Orders
Completion: 11/30/2010   continuation of uninterrupted grain  Total Change Orders Amount:
terminal operations.             0
Significant Developments                    Budget/Costs Incurred
Project design has started.                                 3
2.5
Schedule
Millions  2
On schedule.                                     1.5
1
Budget                             Dollars in 0.5
On budget.                                       0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               None
Timely equipment delivery is required by tenant in order to make the
desired installation schedule.
Budget Transfers
None




REAL ESTATE
Port of Seattle 1Q 2010 Report  73

FIRST QUARTER REPORT, 2010
FT South Wall Reconstruction Phase IV
Project:   C800136      Completion of Fishermen's       Status Snapshot
Budget: $1,030,000      Terminal South Wall         On Schedule
Phase: Design        Reconstruction. Phase IV is located  On Budget
Start: 6/2009            along parcel currently leased by    No Change Orders
Completion: 6/2011      FVO.                 Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Permitting and engineering design completed to approximately 40%
7
and 60% levels respectively.
6
Schedule                            Millions 5
4
Dollars in 
No changes this quarter.                                 3
2
Budget                             1
0
No change this quarter.
Authorized  Forecasted Costs Incurred
Change Order
None this quarter                                    Construction Costs
None at this time
Risks
None this quarter
Budget Transfers
None





REAL ESTATE
74  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
MIC Central Seawall Replacement
Project:   C800175      Replacement of steel sheet pile    Status Snapshot
Budget: $410,000       seawall between West Pier and    On Schedule
Phase: Design        Central Pier at Maritime Industrial   On Budget
Start: 9/2008            Center.                    No Change Orders
Completion: 6/2011                          Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Permitting and design completed to approximately 35% and 60%
2.5
levels respectively.
2
Schedule                            Millions 1.5 Dollars in 
No changes this quarter.                                 1
0.5
Budget
0
No change this quarter.
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
None at this time
Risks
None
Budget Transfers
None





REAL ESTATE
Port of Seattle 1Q 2010 Report  75

FIRST QUARTER REPORT, 2010
T-91 Watermain Replacement
Project:   C800298      Replace water main in the vicinity   Status Snapshot
Budget: $700,000       of City Ice/Trident Building at T91   On Schedule
Phase: Design                            On Budget
Start: 9/20/2009                                  0 Change Orders
Completion: 12/30/2011                       Total Change Orders Amount:
0
Significant Developments                    Budget/Costs Incurred
Design has started. A decision analysis was performed to determine
0.8
the use of Ductile Iron Pipe for the project.
0.6
Schedule                            Millions
0.4
On schedule.
Dollars in 0.2
Budget
0
On budget.
Authorized  Forecasted Costs Incurred
Change Order
None.                                    Construction Costs
None
Risks
Contaminated material may be encountered throughout the
excavation process.
Budget Transfers
None.




REAL ESTATE
76  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
FT NW Dock E. Fender System Replacement
Project:   C800386      Replace existing timber fender     Status Snapshot
Budget: $580,000       system for the east section of the   On Schedule
Phase: Design        NW Dock at Fishermen's Terminal  On Budget
Start: January 2010       including all new steel piling and    No Change Orders
Completion: April 2011   associated fender system.       Total Change Orders Amount:
0
Significant Developments                    Budget/Costs Incurred
Commission authorized funds for the design, permit acquisition, and
0.7
project management. Design and permit acquisition work is in
0.6
progress.
0.5
0.4
Schedule
Millions
0.3
Design completion scheduled for July 2010, followed by return to      Dollars in 0.2
Commission requesting construction authorization and budget.        0.1
Construction scheduled for approximately January through April        0
2011.                                            Authorized Forecasted Costs Incurred
Budget
Construction Costs
Total current budget authorization for design, permit acquisition, and
None
project management is $580,000. Total preliminary project budget
range, including construction, is $3,900,000 to $4,800,000.
Change Order
None. There is no current construction contract.
Risks
In-water pile replacement work must be completed by April 15, 2011
to comply with anticipated permit requirements.
Budget Transfers
None


REAL ESTATE
Port of Seattle 1Q 2010 Report  77

FIRST QUARTER REPORT, 2010
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule 3Q 09
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, add service desk module   0 Change Orders
Completion: 9/30/2010    and wireless handheld capabilities.  Total Change Orders Amount:
$0
Significant Developments
Service Management software deployed for ICT Service Desk in     Budget/Costs Incurred
December 2008. Legacy Ticket system decommissioned.
The design and development for Phase 2, upgrade and consolidation    4
of Marine Maintenance and Aviation Maintenance Maximo systems,
3
is in progress.
2
in Millions
Schedule
Dollars   1
Prior Report - Delay of 9 months due to resource constraints and a
successful re-planning effort to mitigate potential vendor cost          0
overruns.                                             Authorized Forecasted Costs Incurred
Budget
On Budget
Change Order                         Construction Costs
Not Applicable
None
Risks
No significant risks
Budget Transfers
None



CORPORATE
78  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Parking System Consolidation
Project:C800066        Consolidate four separate       Status Snapshot Prior Report
Budget:$250,000       applications supporting different    Delayed Schedule     4Q 09
Phase:Close Out       parking programs into a single Port  On Budget
Start: 9/23/2008          Parking System.              0 Change Orders
Completion:4/30/2010                         Total Change Orders Amount:
$0
Significant Developments
System deployed on April 17, 2010.                       Budget/Costs Incurred
Schedule                            0.252
Prior Report: Project will require an additional three months to         0.25
complete testing and deployment activities for requirements change    0.248
to remove one application from scope.                        Millions
0.246
0.244   Dollars in
Budget
0.242
On Budget
Authorized   Forecasted  Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No significant risks
Budget Transfers
None




CORPORATE

Port of Seattle 1Q 2010 Report  79

FIRST QUARTER REPORT, 2010
Marine Domain Awareness
Project:   C800119     Implement a series of Seaport      Status Snapshot Prior Report
Budget: $7,130,000     Security projects, including video    Delayed Schedule 4Q 09
Phase: Close Out     monitoring, communication and     Under Budget   2Q 09
Start: 12/9/2007        access control.                0 Change Orders
Completion: 3/31/2009                        Total Change Orders Amount:
$0
Significant Developments
All five major components of this program have been completed:     Budget/Costs Incurred
x Dashboard showing real-time information from a variety of
operational sources.
x Wireless Infrastructure across all Seaport locations.               8
x TWIC infrastructure at Pier 66.                            7
6
x Video Surveillance deployed across multiple Seaport locations.       5
x T91 Fencing for TWIC areas                          Dollars in Millions 4
3
2
Schedule
1
0
Prior Report: Completion of Video Surveillance and T91 fencing
Budget     Forecast   Cost Incurred
delayed due to construction schedule and resource availability to
complete configuration.
Construction Costs
Budget
Project Budget Components include:
1.2
x Grant Reimbursement
1
x 25% Port funded match
Dollars in Millions 0.8
x Port funded, Non-Grant Eligible employee costs
0.6
We are anticipating a budget under run for the Grant Reimbursement     0.4
Budget Component of $1,400,000. The combined Port funded         0.2
components are on budget.                              0
Initial      Change      Spent
Orders
Change Order
None
Risks
No Significant Risks
Budget Transfers
None
CORPORATE
80  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Port of Seattle Internet Redesign
Project:C800319        Create a new Internet web site, and  Status Snapshot Prior Report
Budget:$500,000       underlying infrastructure, with     Delayed Schedule     1Q 09
Phase:Planning        dynamic content and interactive    On Budget
Start: 1/6/2009           communication tools such as blogs,  0 Change Orders
Completion:4/1/2011     video, podcasts, discussion forums  Total Change Orders Amount:
and interactive maps.           $0
Significant Developments                    Budget/Costs Incurred
Project taken off hold by Executive Team. Procurement is in process
0.6
for design and development services.
0.5
Schedule                             0.4
Project put on hold by Executive Team in early 2009 resulting in a       Millions 0.3
0.2
delay of 18 months.                                   Dollars in 0.1
Budget                             0
Authorized  Forecasted Costs Incurred
On Budget
Change Order
None                                 Construction Costs
Not Applicable
Risks

Budget Transfers
None




CORPORATE
Port of Seattle 1Q 2010 Report  81

FIRST QUARTER REPORT, 2010
External Sharepoint
Project:C800320        Implement External Microsoft     Status Snapshot Prior Report
Budget:$500,000       Sharepoint Services to support    Delayed Schedule     3Q 09
Phase:Design         application consolidation, customer  On Budget
Start: 1/6/2009           collaboration, and system        0 Change Orders
Completion:On-Hold     integration opportunities.       Total Change Orders Amount:
$0
Significant Developments
Project was put on hold by ICT Management to evaluate potential    Budget/Costs Incurred
security issues identified during architecture development. An interim      Dollars [Thousands)
600
solution utilizing a hosted sharepoint environment will be deployed to
500
meet the timeline for the Port Internet Redesign project.
400
Schedule                             300
On Hold                                      200
100
Budget                             0
Authorized    Forecasted   Costs incurred
On Budget
Change Order
Construction Costs
None
Not Applicable
Risks
New Technology
Budget Transfers
None



CORPORATE

82  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Enterprise Project Cost Management
Project:C800321        Replace the current construction   Status Snapshot Prior Report
Budget:$1,525,000       costing systems with a common    Delayed Schedule     4Q 09
Phase:Planning        enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion:On-Hold                        Total Change Orders Amount:
$0
Significant Developments
Vendor did not deliver software per contract and Notice to Cancel    Budget/Costs Incurred
has been sent. Legal is assisting in the negotiations. Project has
been put on-hold while alternatives are evaluated. A recomm-         2
endation will be complete in August 2010.
1.5
Schedule                             Millions 1
On-hold
Dollars in 0.5
Budget                             0
None                                     Authorized Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks
Not Applicable
See significant developments
Budget Transfers
None




CORPORATE
Port of Seattle 1Q 2010 Report  83

FIRST QUARTER REPORT, 2010
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot
Budget: $800,000       increase functionality, and lower   Delayed Schedule
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 5/30/2011    records and document        Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
Incorporating upgrade to Sharepoint 2010 because of significant
improvements in Records Management features.
1
Schedule                             0.8
Sharepoint 2010 implementation is dependent on the completion of     Millions 0.6
several infrastructure projects currently in progress. This will delay      0.4
the implementation of Sharepoint Records Center and full build out     Dollars in 0.2
of department sites until Spring 2011.
0
Authorized  Forecasted Costs Incurred
Budget
On Budget
Change Order                         Construction Costs
None                                 Not Applicable
Risks
Scope of Sharepoint 2010 upgrade may require additional funding to
complete migration activities.
Budget Transfers
None



CORPORATE
84  Port of Seattle 1Q 2010 Report

FIRST QUARTER REPORT, 2010
Business Continuity
Project:C800326        Acquire new backup and storage   Status Snapshot
Budget:$1,760,000       software and hardware that will    On Schedule
Phase:Implementation    facilitate business continuity in the  On Budget
Start: 6/23/2009          event of a disaster            0 Change Orders
Completion:8/30/2010                         Total Change Orders Amount:
$0
Significant Developments
Procurement and installation of backup system in Fisher Plaza Data   Budget/Costs Incurred
Center complete. Installation of the High Capacity Network Storage
for the Airport Data Center in progress.                         2
1.5
Schedule
On Schedule                                   Millions 1
Dollars in 0.5                                                                                      Budget
On Budget                                    0
Authorized  Forecasted Costs Incurred
Change Order
None
Risks
Construction Costs
No significant risks.                                      Not Applicable
Budget Transfers
None




CORPORATE
Port of Seattle 1Q 2010 Report  85

FIRST QUARTER REPORT, 2010
Port Roster
Project:C800397        Develop and implement a single    Status Snapshot
Budget:$450,000       Port Roster & Bid System that     On Schedule
Phase:Design         replaces the functionality of three   On Budget
Start: 1/26/2010          rosters, supports new Central      0 Change Orders
Completion:2/28/2011     Procurement Office processes ,    Total Change Orders Amount:
and simplifies the process for Port   $0
vendors.
Significant Developments                    Budget/Costs Incurred
In requirements and design phase.                         0.5
0.4
Schedule                            Millions 0.3
On Schedule                                  0.2
0.1
Budget                             Dollars in 
0
On Budget                                      Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No significant risks
Budget Transfers
None




CORPORATE
86  Port of Seattle 1Q 2010 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.