Item 10a Memo

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA                Item No.     10a 
Date of Meeting    March 10, 2009 
DATE:    February 20, 2009 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Mark Longridge, Capital Project Manager, Capital Development Division 
Melinda Miller, Director, Portfolio & Asset Management, Real Estate Div.
Darlene Robertson, Director, Harbor Services, Real Estate Division 
SUBJECT:  Authorization for design, permitting and construction of interim 
landscaping, flatwork improvements and lighting of the restaurant pad
area at Shilshole Bay Marina, at no increase to the previous $80,000,000
project authorization. 
ACTION REQUESTED
Request Port Commission approval for the Chief Executive Officer to: 
1.  Spend existing funds from the approved Shilshole Project budget for design,
permitting and construction of interim landscaping, flatwork improvements and
lighting at a currently unfinished gravel & dirt pad site of approximately 25,000
square feet located in the Central Plaza area at Shilshole Bay Marina in an amount not
to exceed $300,000. This amount would include: 
Design and permitting for the work using Port staff and consultants by entering 
into or amending existing service agreements by service directive. 
Purchase materials with long lead times. 
Construct improvements to this area to include landscaping, irrigation, lighting,
flatwork, and other amenities using Small Works contracts, Port labor, or a
combination of both. 
This work would complete the Shilshole Redevelopment. This-authorization of funds is
required due to the change from the original scope of work which is discussed below.
The original project budget included funding to complete permanent flatwork, utility and
lighting improvements around and up to the proposed restaurant building, and as such
this work can be accomplished within existing funding authorization, and no budget 
adjustment to the previously approved $80M capital budget for the overall Shilshole
Renewal and Replacement program is required.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
February 20, 2009 
Page 2 
SYNOPSIS 
There is one remaining improvement to be made to complete the Shilshole Bay Marina
Redevelopment Project. It currently is a rough graded, unfinished gravel and dirt pad site 
of approximately 25,000 square feet, surrounded by temporary construction fencing. It is
not suitable for public use in its current condition due to unfinished flatwork, exposed
rebar transitions, uneven loose gravel surfaces and inadequate lighting. The site in its
current configuration at the center of the Marina impedes access to/from some of the
docks to the parking areas, the Marina Building and to the other areas of the facility. 
The original plans approved by the Commission for this area incorporated a restaurant
pad site with the intent of Anthony's Restaurant ground leasing the area and building a
restaurant. Anthony's terminated lease negotiations last year and will not be building a
restaurant at Shilshole due to high construction costs and the deteriorating economic
situation. Therefore, the Port will need to remove the construction fencing and finish the
area. At some future point, when the market improves, we will reassess opportunities for 
another restaurant at Shilshole Bay Marina. 
Port staff requests approval of design, permitting and construction funding to complete 
paving, landscaping, lighting, irrigation and other work in the Central Plaza area at
Shilshole to make the area safe and available for use by Marina tenants, visitors and the
public. The current estimate to complete design, permitting and construction of this work
is an amount not to exceed $300,000. This re-authorization of funds is required due to
the change from the original scope of work.
The intent of this design will be to finish the area in such a way as to provide a useable,
safe, aesthetic space at a low cost, and without precluding the future use of the site for
functions such as the previously planned restaurant. Finishing this area will allow Marina
customers and visitors to use the area to more easily get to/from the parking lot to their
vessels as well as to other areas of the Marina and for the public to use the area when
visiting and transiting the Marina. Every effort will be made to minimize the cost of the
improvements. The design will also strive to incorporate materials which could be reused
in other parts of the Marina and/or any subsequent development wherever possible, and
minimize the use of materials that would need to be removed or demolished to develop
the site at some future point. 
PROJECT DESCRIPTION AND JUSTIFICATION: 
The pad site, approximately 25,000 square feet, southwest of the Marina Building
was originally slated for development as a restaurant. However, this development 
was delayed and subsequently cancelled, and will not happen in the foreseeable
future.
The site area is currently an unfinished gravel area, with no lighting, and surrounded
by construction fencing and is unsafe and not suitable for public use. As capital

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
February 20, 2009 
Page 3 
construction of the Renewal and Replacement projects at Shilshole are complete with
the exception of a few remaining small site improvements, this area remains the last
section of unfinished area at the site. 
In an effort to finish the area and improve accessibility to the docks & other areas of
the facility for Marina customers and the public, and precluding the immediate
development of the site, an interim solution needs to be designed, permitted, and
constructed as described above. This work needs to be completed this year so that the
area is finished before the next peak boating season. 
PROJECT SCOPE OF WORK AND SCHEDULE 
Project scope would include the design and construction of landscaping and flatwork
within the pad site, and lighting in the surrounding area, to provide an open finished
area for Marina customers and the public until such time the site can be developed as
originally planned. 
The authorization amount also includes funds to pre-purchase any long lead items, 
such as light poles, in order to complete the work on the proposed schedule. 
The work will emphasize the economic use of materials which could be relocated or
reused if the pad site is developed at some future date. The current palette of
materials and plantings will be used, where possible, to integrate this area into the rest
of the Marina. Low maintenance materials will also be used. 
Project schedule:
Design completed in June 2009 
Planting completed in the fall of 2009, and 
Construction completed by December 31, 2009 or earlier. 
STRATEGIC OBJECTIVES 
While it is possible to leave the site area as described above in an unfinished state, it
would not be safe or useable by the Marina customers, their visitors and the public. The
completion of this work will provide the tenants, public and the community with a fully
accessible site, that is safe and well lit and a finished area that increases the general
appeal of the Marina and something that blends with the rest of the redeveloped site. 
BUSINESS PLAN OBJECTIVES 
Proceeding with this project will complete construction and redevelopment of Shilshole 
Bay Marina, without precluding the future use of the approximately 25,000 square foot
area and will minimize demolition costs of future development.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
February 20, 2009 
Page 4 
FINANCIAL ANALYSIS 
Budget/Authorization Summary 
Original Budget (Shilshole Renewal and Replacement program)         $80,000,000 
Budget Used                                        $78,298,119 
Remaining Budget Authorization                            $1,701,881 
Current project request  Reauthorization due to change in scope           $300,000 
Project Cost Breakdown 
Construction costs                                          $182,000 
Sales tax                                                   $18,000 
Outside professional services                                    $45,000 
Project & Construction Management                            $25,000 
Other (estimated pre-purchase)                                  $30,000 
Total (not to exceed)                                         $300,000 
Source of Funds 
The funds for this project were included in the 2009 Draft Plan of Finance under
committed CIP C001716 SBM Infrastructure, Buildings, Site Improvements.
This project will be funded from existing 2007 Revenue Bonds proceeds.
Financial Analysis Summary 
CIP Category             Renewal/Enhancement 
Project Type              Renewal & Replacement 
Risk adjusted Discount rate     7.5% 
Key risk factors             An opportunity to develop the site into a restaurant comes up
within the foreseeable future and some of the current requested
project investment is not moveable or re-useable.
Project cost for analysis        $300,000 
Business Unit (BU)          Portfolio Management  SBM Uplands

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
February 20, 2009 
Page 5 

Effect on business performance  Assuming an expected useful life of 10 years prior to
redevelopment of the area into a restaurant, this project will
increase Depreciation Expense by $30,000 per year for 2011 
through 2019 and decrease Net Operating Income After
Depreciation by the same amount. 
If the site is redeveloped into a restaurant anytime prior to the 10- 
year horizon, the un-depreciated balance of the improvement 
would be written off as a non-operating loss. 
IRR/NPV             Since this project neither creates incremental revenue nor preserves
existing revenue, the net present value of this project is negative
($300K). 
SUSTAINABILITY AND LIFE CYCLE COSTS 
The proposed course of action preserves the option of future development of this pad,
while minimizing the interim capital investment required to finish the site and provide
a usable area for customers and the public. 
The design will look for opportunities to use environmentally low impact materials,
minimize site runoff and use low water native planting materials. The design will
also look at the use of low maintenance materials and possible methods for reuse of
these materials as well as plantings in any future site development. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS 
Do nothing alternative.  The pad site is approximately 25,000 square feet and is
currently a rough graded, unfinished gravel & dirt area surrounded by construction
fencing. The site is not suitable for public use in its current condition due to
unfinished flatwork, exposed rebar transitions, uneven loose gravel surfaces and
inadequate lighting. It could be left in its current condition for the foreseeable future
at little or no cost. This, however, would leave an unsafe area and preclude the use of
the area by Marina customers, their visitors and the public in the Central Plaza area as
it impedes access to/from some of the docks to the parking areas, the Marina Building 
& to other areas of the Marina. This alternative is not recommended. 
Permanent paving and development.  The site could be developed to a finished state
using concrete paving and plantings similar to other flatwork areas at the Marina.
This option carries a higher cost for more substantial development, and the risk of
needing to demolish & remove the new work if an agreement is reached to develop
the site as originally intended. This is not a cost-effective use of funds. 
Interim development.  This level of design and construction would strive to reopen a
currently unusable area and install interim landscaping, complete flatwork and add
lighting so that it is open, safe and usable by Marina customers, their visitors and the

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
February 20, 2009 
Page 6 
public, without either precluding future development options or requiring the
demolition of significant assets to complete that development. The design would
look for low-cost and "low-impact" methods such as landscaping, grass and movable
planters to provide the most efficient interim development of the site. - This is the
recommended alternative. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
On August 26, 2003, Commission approved project-wide authorization for the
Shilshole Bay Marina Renewal and Replacement Project in the amount of
$78,500,000. 
On February 8, 2005, Commission authorized $1,500,000 to replace the north-end
restroom building, bringing the total project authorization to $80,000,000. 
On September 25, 2007, Commission authorized the execution of a fifty (50) year
land lease with Mad Anthony's Inc., for construction and operation of a new
restaurant at Shilshole Bay Marina.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.