Item 6a attach

Item No.:    6a_attach 
Date of Meeting:  January 27, 2009 
ATTACHMENT A 
TODAY'S BRIEFING FOR January 27, 2009 
Upcoming Commission Actions 
Request Commission approval for the following: 
Bus Maintenance Facility CNG Design Additional Funding  February 10, 2009 
RCF Acquisitions (Cemetery)  April, 2009 
RCF Property Acquisitions (WSDOT)  April, 2009 
Bus Maintenance Facility Construction  Suspended 
Off-Site Roadway Improvements Construction  Suspended 
Developments Since Last Update: 
Main Contract: 
Turner shut down all work from December 18, 2008 through January 7, 2009 
Construction suspended except for all necessary work to close the site for up to one year 
Dewatered flooded excavations and treated a significant amount of Stormwater without issue 
Continuing construction of only those building footings and columns formed with reinforcing
steel set in Area B 
Continuing construction only on retaining walls that could become unstable or that will likely
be damaged by sitting through the suspension. 
Continuing construction to complete the Detention Vault and get the Building Permit signed
off 
Continuing installation of only those underground utilities that support the site shutdown or
that could be damaged or impacted during the suspension 
Conducted site walks and determined critical work needed to suspend site construction for up
to one year 
Turner reduced staff to eleven, laying off seven employees January 9th and reassigned others
to active Turner projects 
Continuing review of conforming change orders for each subcontractor 
Design: 
Completed review of 60% design of the Bus Maintenance Facility and working on 90% 
90% design of the Off-Site Road Improvements estimated to be complete in January 2009 
Signed contract for the Consultant providing replacement Project Management staff 
Continuing to analyze additional after-the-fact design services claims 
Issued 10 Design Change Notices to date, four of which were issued after the last
Commission update. 
Continuing to review Contractor submittals and request for information (RFI) that were
submitted before the authorization to suspend construction.
Industry: 
Technical and Industry meetings held January 14 to discuss an update on Bus Maintenance
Facility project, specifically the CNG station addition 
Industry updated on current status and on going work 
Advantage has pulled out of the Seattle rental car market.

Change Orders Processed 
17 change orders have been processed (4 Initial Contract, 13 Main Contract) for
$2,225,484.00. $4,035,399.67 Construction Contingency remains 
21 Serial letters issued for $10,197,794.50 of Negotiated Support Services and $7,355,763.50
remains 
11 Design Change Notices are in various stages of development, some being submitted to
Turner for pricing 
OVERALL PROJECT SCHEDULE AND BUDGET 
Project Schedule 
The completion date for the Consolidated Rental Car Program is unknown due to suspension 
Rental Car Facility is unknown due to suspension 
Bus Maintenance Facility is unknown due to suspension. The addition of the CNG fueling
facilities has delayed the design schedule resulting in a construction schedule that supports a
Fall 2011 opening of the Rental Car Facility assuming funding is secured in the next six
months. 
Off-Site Roadway Improvements is unknown due to suspension. Multiple design delays have
resulted in a construction schedule that supports a Fall 2011 opening of the Rental Car
Facility assuming funding is secured in the next six months. 
The Port is continuing with the procurement of Port-provided electrical equipment. 
Project Budget 
Refining cash flow and accrual projections to ensure CFC plus the $20 million is not
exceeded during the suspension 
Continue updating CFC actual collections and projections through 2009 
Turner has spent less money that forecasted for November and December 
The Project Management Group has also reduced projected monthly spending 
Current Turner contract value including all change orders is now $229,637,853.00 
The projected program budget likely no longer remains at $382,451,000 and the $29.9M
unauthorized remaining budget will be needed to cover delay claims and cost of the
suspension 
The Off-Site Roadways Improvements budget remains the same 
The Bus Maintenance Facility requires an additional budget estimated to be $4,455,000 to
accommodate the design and construction of CNG fueling facilities to support the busing
operation. Recent procurement changes necessitate the change in approach for providing the
CNG fueling facilities 
Financing  Exit Strategy 
Finance team continues exploring options for financing. Finance staff will provide a status
report.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.