6c memo

COMMISSION 
AGENDA MEMORANDUM                Item No.       6c 
ACTION ITEM                   Date of Meeting     January 9, 2018 
DATE:    December 31, 2017 
TO:     Dave Soike, Interim Executive Director 
FROM:   Michael Ehl, Director Airport Operations 
Wayne Grotheer, Director Aviation Project Management Group 
SUBJECT:  Zone 3 Common Use Ticket Counter Conversion Project (CIP #C800925) 
Amount of this request:          $1,650,000 
Total estimated project cost:       $1,700,000 
ACTION REQUESTED 
Request a single Commission authorization for the Executive Director to: (1) proceed with
design and construction of the Zone 3 Common Use Ticket Counter project at Seattle-Tacoma
International Airport; (2) execute a contract to purchase common use equipment; and (3) use
Port crews to complete the project. This single authorization is for a total cost of $1,700,000. 
EXECUTIVE SUMMARY 
This project responds to the continued growth in Airport traffic and airline operations. It
improves the efficiency and flexibility of the ticket lobby, and thus improves the passenger
experience at the Airport. This project is necessary to provide additional common use ticket
counters for new airline entrants that have announced the start of service to Seattle beginning
the summer of 2018. There is currently not enough capacity at the current common use ticket
counters to accommodate these new airlines as these counters are fully subscribed at peak
times. 
The project adds common use ticketing capacity in the Zone 3 Ticket Lobby between Delta Air
Lines and Southwest Airlines creating 10 new common use ticket counter positions. It also adds
8 Common Use Self Service (CUSS) kiosks in the lobby area. Zone 3 is located adjacent to the
passenger security checkpoint that provides the most direct access to international departure
gates. Virgin America, Inc., through the merger with Alaska Airlines, will be vacating the space
in April 2018. 
This single authorization request will allow the project team to proceed quickly as this project
has been deemed a "hot project." Airline operations are impacted by the current lack of ticket
counter capacity that this project will address. 


Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. _6c___                     Page 2 of 4 
Meeting Date: January 9, 2018 
JUSTIFICATION 
This project supports the Century Agenda Goal to advance this region as a leading tourism
destination and business gateway: make Sea-Tac Airport the West Coast "Gateway of Choice" 
for international travel and double the number of international flights and destinations. 
DETAILS 
This project will add common use ticketing capacity in the Zone 3 Ticket Lobby between Delta
Air Lines and Southwest Airlines creating 10 new common use ticket counter positions. It also
adds up to 8 Common Use Self Service (CUSS) kiosks in the lobby area. Total project costs are
estimated to be $1,700,000. Recurring hardware license and maintenance costs will be
budgeted within the Aviation Maintenance department's operating budget. 
Scope of Work 
This project adds ticketing capacity in Zone 3 by creating 10 new common use ticket counter
positions and adding 8 CUSS kiosks. 
(1) Repurpose 6 existing Virgin America ticket counter positions for common use 
(2) Add 4 ticket counter positions in Zone 3 
(3) Add 6 new bag scales to replace previous proprietary scales 
(4) Purchase and install Common Use (CUSE) ticket counter equipment, including bag scales
and overhead display monitors required for 10 positions 
(5) Purchase and install 8 Common Use Self Service (CUSS) kiosks 
Schedule 
Activity 
Design start                        2018 Quarter 1 
Construction start                    2018 Quarter 1 
In-use date                        2018 Quarter 3 
Cost Breakdown                         This Request       Total Project 
Design                                   $276,000          $276,000 
Procurement                            $722,000         $722,000 
Construction                               $701,000          $701,000 
Total                                      $1,700,000          $1,700,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Lease the vacated Virgin America ticket counters to another airline 
Cost Implications: $0 
Pros: 
(1)   This is the least expensive option. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6c___                     Page 3 of 4 
Meeting Date: January 9, 2018 
Cons: 
(1)   This option does not provide the common use capacity needed to support new
entrant carriers. 
This is not the recommended alternative. 
Alternative 2  Replicate the adjacent Delta Air Lines flow-through ticket counter "islands" by
building out a third check-in island as a Port sponsored capital project using the vacated Virgin
America ticket counters along with the next door vacant former airline ticket office space to
create 17 flow-through passenger check-in positions (8 common use positions, 9 common use
kiosks). 
Cost Implications: $4,300,000 
Pros: 
(1)   Additional common use check-in counters for new entrants would be established. 
(2)   Passenger queueing and circulation in Zone 3 would see improvement. 
Cons: 
(1)   This alternative will not meet the timeline required for new entrants in summer of
2018. 
(2)   This alternative would cost more than Alternative 3. 
This is not the recommended alternative. 
Alternative 3 Convert Virgin America's existing check-in counters to 10 common use positions.
Purchase and install 8 CUSS kiosks. 
Cost Implications: $1,700,000 
Pros: 
(1)   Allows flexibility with 10 common use positions which can be configured to meet
airline needs on-demand. 
(2)   Can be constructed to meet summer deadline for new entrant carriers. 
Cons: 
(1)   Location of construction area will have some impact on Delta operations; will require
coordination with Delta to mitigate impacts. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary          Capital      Expense        Total 
COST ESTIMATE 
Original estimate                      $1,700,000          $0    $1,700,000 
AUTHORIZATION 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6c___                     Page 4 of 4 
Meeting Date: January 9, 2018 
Previous authorizations                    $50,000          $0      $50,000 
Current request for authorization           $1,650,000          $0    $1,650,000 
Total authorizations, including this request     $1,700,000          $0    $1,700,000 
Remaining amount to be authorized              $0          $0          $0 
Annual Budget Status and Source of Funds 
The Zone 3 Common Use Ticket Counter Conversion (CIP# C800925) was not included in the
2018-2022  capital budget and plan of Finance. The budget was transferred from the
Aeronautical Allowance (CIP #C800753), resulting in no net change to the capital budget. The
funding source for this project will be future revenue bonds. 
Financial Analysis and Summary 
Project cost for analysis         $1,700,000 
Business Unit (BU)            Terminal Building 
Effect on business performance   NOI after depreciation will increase 
(NOI after depreciation) 
IRR/NPV (if relevant)           N/A 
CPE Impact                Less than $0.01 in 2018 
Future Revenues and Expenses (Total cost of ownership) 
The space will continue to be used as ticket counter space. The capital cost of this project will
be incorporated into the airline rate base and recovered through terminal rents and common
use fees. 
ATTACHMENTS TO THIS REQUEST 
Presentation slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None 






Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.