Delta Lounge Tenant Reimbursement Agreement

INTERNAL AUDIT REPORT 
OPERATIONAL AUDIT 
DELTA LOUNGE - TENANT REIMBURSEMENT AGREEMENT 

September 2015- January 2018 

ISSUE DATE: March 9, 2018 
REPORT NO. 2017-27



Delta Lounge - Tenant Reimbursement Agreement                                          INTERNAL AUDIT 
September 2015- January 2018 



TABLE OF CONTENTS 

EXECUTIVE SUMMARY ................................................................................................................................................. 3 
BACKGROUND .............................................................................................................................................................. 4 
AUDIT SCOPE AND METHODOLOGY ........................................................................................................................... 5 
SCHEDULE OF FINDINGS AND RECOMMENDATIONS............................................................................................... 6 
APPENDIX A: RISK RATINGS ........................................................................................................................................ 8 
APPENDIX B: ADDITIONAL DETAIL  MANAGEMENT RESPONSE ........................................................................... 9 











2

Delta Lounge - Tenant Reimbursement Agreement 
September 2015- January 2018 
EXECUTIVE SUMMARY 
Internal Audit (IA) completed an audit of the Aviation Delta Lounge Tenant Improvement Reimbursement
for the period September 2015 - January 2018. The objectives of this audit were to determine whether
Port staff followed policies, procedures, and the Tenant Reimbursement Agreement  (Agreement)
requirements. 
Delta Airlines (Delta) is the largest global carrier at the Seattle-Tacoma International Airport and has more
than tripled their flights at its Seattle hub since 2012. To accommodate the growth, the Port and Delta
entered into an agreement to construct a 23,000 square foot lounge for its members and guests. While
Delta was responsible for the cost of completing the interior, the Agreement required the Port to
reimburse Delta for the cost to construct the shell (exterior) and core utilities. 
Port Commission approved a project budget of $13.7 million. Construction began in October 2015 and
was completed and fully functional in October 2016. As of January 2018, total construction costs were
$24 million, of which $13.2 million was paid by the Port. 
In general, Port staff effectively managed the project. Port staff frequently discussed project deliverables
with Delta, reviewed change orders, and verified compliance to the Agreement. As a result, Port
management did not allow certain charges that reduced the amount paid by the Port. 
The Agreement, however, provided Delta with broad decision making and oversight authority. The Port
frequently structures these agreements, relying significantly on external resources for expertise and
project oversight. The downside with using this approach is that it inherently limits the perceived or actual
influence of Port management. Nonetheless, the Port is still responsible for financial overruns and
maintains public accountability to complete the project on time. 
We identified the following issue: 
1) The Tenant Reimbursement Agreement was not written to give Port staff broad oversight authority of
decisions made by external parties. However, the Port remained financially responsible for the majority of
costs from these decisions. Delegating decision to external parties is not designed to facilitate financial
accountability and sound stewardship of public funds. 
We extend our appreciation to Port management and staff for their assistance and cooperation during the
audit. 


Glenn Fernandes, CPA 
Director, Internal Audit 
RESPONSIBLE MANAGEMENT TEAM 
Ralph Graves, Sr. Director of Capital Development 
Wayne Grotheer, Director Aviation Project Management Group 
Jim Schone, Director Aviation Business Development 
Jason Olson, Sr. Controls Manager, Aviation Project Management Group 
Alan Olson, Capital Project Manager, Aviation Project Management Group 
James Jennings, Sr. Manager, Aviation Properties 

3

Delta Lounge - Tenant Reimbursement Agreement 
September 2015- January 2018 

BACKGROUND 

Delta Air Lines, Inc. (Delta) is the largest global carrier at the Seattle-Tacoma International Airport and
has more than tripled their flights at its Seattle hub since 2012. To accommodate this growth, the Port and
Delta entered into a Tenant Reimbursement Agreement (Agreement) to construct a 21,000 square foot
lounge for Delta's members and guests. 
Revised  Code  of  Washington  14.08.120  allows  Ports  to  reimburse  airport  tenants  for  tenant
improvements to their leased premises, if the reimbursement is paid solely out of funds fully collected
from airport tenants. These agreements create a unique contractual relationship between the Port, a
government agency, and Delta, a private entity, leveraging the skills and assets of each. 
Port Commission approved a budget of $13.7 million and construction began in October 2015. The
project was completed and fully functional in October 2016 at a total cost of $24 million. The Port
reimbursed Delta $13.2 million to construct the building shell and core utilities. Delta constructed the
interior using its own funding. 
PCL Construction was selected as the general contractor; ECH Architecture was used to design the
structures exterior and interior; Jacobsen Daniels Associates provided project management, and Airport
and Aviation Professionals provided financial services. 
The lounge interior features wood, water, and movement to create a Pacific Northwest feel. The lounge
features 30-foot ceilings with curved paneling and a mezzanine level with an art gallery showcasing
artwork from emerging artists and local galleries. 
The lounge is situated where the A and B Concourses intersect and on clear days offers views of Mount
Rainier. The lounge  offers conference tables for dining or meetings, a full-service bar, self-service
individual work stations for computing or reading, and a self-service buffet with both cold and hot food
options. 







4

Delta Lounge - Tenant Reimbursement Agreement 
September 2015- January 2018 

AUDIT SCOPE AND METHODOLOGY 
We conducted this performance audit in accordance with Generally Accepted Government Auditing
Standards and the International Standards for the Professional Practice of Internal Auditing. Those
standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide
a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the
evidence obtained provides a reasonable basis for our findings and conclusions based on our audit
objectives. 
The period audited was September 2015 - January 2018. We utilized a risk-based approach from the
planning phase to the testing phase of our audit. We gathered information through document requests,
research, interviews, observations, and analytical procedures. We assessed significant risks and
identified controls to mitigate those risks. Our audit included the following procedures: 
Design Development Allowance 
Obtained an understanding of the design development allowance and how it was applied. 
Reviewed supporting documentation on expenses charged to the design development allowance
for reasonableness, accuracy, and allowability. 
Reviewed project files to determine whether price increases were reasonable, accurate, and
included a final "true-up". 
Determined if add or deduct change order(s) were executed for differences between budgeted
and actual costs. 
Construction Contingency 
Obtained an understanding of the construction contingency and how it was applied. 
Reviewed supporting documentation on expenses charged to the construction contingency for
reasonableness, accuracy, and allowability. 
General Contractor Self-Performed Work 
Obtained an understanding of Port monitoring of the general contractor's self-performed work. 
Reviewed project files to evaluate the bid process of self-performed work. 
Determined if an agreement, similar to agreements with subcontractors, was established. 
Budget Allocation 
Obtained an understanding of the Port's monitoring of payment allocations. 
Re-calculated expenses of tenant reimbursements and non-tenant reimbursements and agreed
the charges to PeopleSoft. 
Compared actual tenant reimbursement and non-tenant reimbursement charges to the authorized
budget. 



5

Delta Lounge - Tenant Reimbursement Agreement 
September 2015- January 2018 
SCHEDULE OF FINDINGS AND RECOMMENDATIONS 
1) RATING: HIGH 
THE TENANT REIMBURSEMENT AGREEMENT WAS NOT WRITTEN TO GIVE PORT
STAFF BROAD OVERSIGHT AUTHORITY FOR DECISIONS MADE BY EXTERNAL
PARTIES. 
The Agreement does not give Port management the authority or ability to be included in the selection
process of contractors. However, the Port remained financially responsible for the majority of costs from 
these decisions. Delegating decisions to external parties, while still maintaining financial responsibility, is
not designed to facilitate accountability and sound stewardship of public funds. Below are examples that
reflect decisions made externally and the resulting financial impact to the Port. 
1.  Delta received three bids for design services and selected ECH as the architect, with a bid of
$317,245. ECH revised their bid to approximately $900,000; however, Port management questioned
their request which resulted in a revised lower estimate of approximately $623,000. Internal Audit
estimated that the Port incurred an additional $190,000 as a result of the cost overrun. 
Although not required by the Agreement, Delta did not retain documentation of the two bids that were
not selected. Retaining this documentation would have allowed IA and Port Management to assess if
other bidders might have anticipated any later changes in their bids. 
2. Delta did not follow sound practices and allowed PCL, the general contractor, to review bids, including
their own. PCL selected themselves as the successful bidder of "self-performed" work. 
General Contractors may have information, such as budgeted costs and contingency funds that other
bidders don't have, giving them an unfair advantage. General Contractors may also claim that they
can perform the work at a more reasonable cost than a subcontractor, because they have a more
comprehensive understanding of the project.  Therefore, implementing strong internal controls is
critical to make sure the bidding process is equitable and the successful bidder is accountable for their
bid. 
PCL's conceptual estimate for self-performed concrete work was $203,473. However, the revised
estimate was $450,536. Internal Audit was not able to determine the additional cost derived from the
initial and final estimate. 
3. The Agreement included a contingency fund of $912,000 to absorb budget overruns. Although the full
contingency fund was expended, the Port was not given an opportunity to assess if it aligned to the
original scope of the project or to determine the reasonableness of the charges until after the work
had been completed. 
Recommendation: 
Management should reexamine the Port's Tenant Reimbursement Agreements to assure that the Port's
interests are met.  Additionally, Tenant Reimbursement Agreements should be written in a manner that 
gives Port management broad authority when decisions are made that impact the Port financially. 



6

Delta Lounge - Tenant Reimbursement Agreement 
September 2015- January 2018 
Management Response/Action Plan: 
The Tenant Reimbursement Agreement (TRA) process has become an important tool to more quickly and
cost effectively deliver projects that tenants request at SEA. Without these types of agreements, the Port
would not have been able to deliver this project, as well as many others; in a time frame that met the
tenant's needs (Specific responses to audit findings and recommendations are at Appendix B). Yet when
public funds are spent, an appropriate level of oversight and documentation is needed. 
Although already reflected as a TRA requirement, management recognizes and agrees with the
importance of enforcing the requirement for the tenant and their contractor to provide the Port with timely
notification of change orders in advance of actual construction. Although there is often tremendous
pressure  to keep  a  project  moving forward,  to  this  end  Properties,  AVPMG  and  Construction
Management are taking steps to adjust existing procedures to better support this timely review and
approval of change orders and release of contingency funds in the future. 
While we welcome the suggestions by this audit for "broad authority" and contractor oversight in TRA
projects, we believe that placing additional requirements on the Public Private Partnership process begins
to erode the benefits of the mechanism as a nimble and cost effective project delivery method, as well as
introduces new liability and risk to the Port for work performed by tenants and their contractors that we
are currently shielded from.  There is a balance to be struck between the inherent efficiency of tenant
administration of the work and Port exercise of detailed control. 
By the end of 2018, management will reexamine tenant reimbursement policy to confirm the Port's
interests and risks are appropriately reflected in TRA documents and policies.  Policy review will also
consider documentation requirements and procedures to ensure cost reasonableness. 










7

Delta Lounge - Tenant Reimbursement Agreement 
September 2015- January 2018 

APPENDIX A: RISK RATINGS 
Findings identified during the course of the audit are assigned a risk rating, as outlined in the table below. The
risk rating is based on the financial, operational, compliance or reputational impact the issue identified has on
the Port. Items deemed "Low Risk" will be considered "Exit Items" and will not be brought to the final report. 
Port Commission/
Rating        Financial         Internal Controls         Compliance           Public 
Management 
Large financial
impact                                    Noncompliance
High probability
with applicable                               Important 
Missing, or inadequate                         for external audit
Remiss in                                 Federal, State,
HIGH                       key internal controls                        issues and/or
responsibilities                                   and Local Laws,                           Requires immediate
negative public
of being a                                    or Port Policies                               attention 
perception 
custodian of
public trust 
Partial controls             Inconsistent          Potential for      Relatively important 
compliance with      external audit
Moderate
MEDIUM                  Not adequate to identify    Federal, State,     issues and/or     May or may not
financial impact 
noncompliance or       and Local Laws,     negative public     require immediate
misappropriation timely      or Port Policies         perception            attention 
Generally
Internal controls in place                            Low probability
complies with
but not consistently                             for external audit
Federal, State and                       Lower significance 
Low financial       efficient or effective                              issues and/or
LOW/                                         Local Laws or Port
impact                                                         negative public
Exit Items                                                  Policies, but some                         May not require
Implementing/enhancing                         perception 
minor                          immediate attention 
controls could prevent
discrepancies
future problems 
exist 
Efficiency    An efficiency opportunity is where controls are functioning as intended; however, a modification would make
Opportunity                                        the process more efficient 








8

Delta Lounge - Tenant Reimbursement Agreement 
September 2015- January 2018 
APPENDIX B: ADDITIONAL DETAIL  MANAGEMENT RESPONSE 
The following reflects specific responses to the examples (1-3) referenced in the finding on Page 6: 
1. Regarding the three bids referenced in Example 1, the design scope increased substantially as a result
of two significant design changes that were within the project scope authorized by Commission and
directed by the Port during the 15% design review. These Port-directed scope changes were financially
consequential, but are not referenced in Internal Audit's finding. 
Existing HVAC equipment located nearby did not have sufficient capacity to serve the new
SkyClub as was originally planned. This resulted in a protracted design investigation by ECH and
their sub-consultants to determine whether the required HVAC equipment could be installed on 
the roof of the new lounge. It was then discovered that the existing lounge building structure
couldn't support the weight of the new HVAC equipment, which led to a further investigation to
identify other suitable locations. No fewer than 16 different options were explored before the final
site was chosen. This effort lasted over 2 months. 
Major components of the electrical infrastructure for the lounge also needed to be moved from
their original location in order to accommodate work being completed for two other projects, one of
which was already in advanced design. 
2. Regarding the sound practice concern referenced in Example 2, the scope and complexity of the
concrete work that Delta's contractor self-performed also increased significantly between their original bid
at 30% design and when the Preliminary Guaranteed Maximum Price (PGMP) for the project was
determined at 60% design. This change was due to unforeseen site conditions related to an operationally
constrained work site. The added costs due to actual site conditions were not noted in Internal Audit's
assessment. 
3. Regarding the contingency fund referenced in Example 3, it is standard practice for all construction
projects to have a similar contingency fund to deal with change orders and unforeseen conditions.  It is
important to note that Delta was not able to utilize these funds until after Port staff determined them to be
the financial responsibility of the Port. Although Management does not refute the delayed timing of the
Port's review, each Additional Service Request and Change Order Request (ASR/COR) on this project
was subjected to the same rigorous review and approval processes that are in place for Port controlled
Major Works/Capital Projects. Internal Audit confirmed through their review of the detailed project
documentation that many ASR/CORs were found to have no merit by Delta and/or the Port and were
rejected in whole, while the final cost of many other ASR/CORs was significantly reduced.




9

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.